CN201406678Y - Linkage structure of gravity dam and unfavorable geological bank slope - Google Patents

Linkage structure of gravity dam and unfavorable geological bank slope Download PDF

Info

Publication number
CN201406678Y
CN201406678Y CN2009201200300U CN200920120030U CN201406678Y CN 201406678 Y CN201406678 Y CN 201406678Y CN 2009201200300 U CN2009201200300 U CN 2009201200300U CN 200920120030 U CN200920120030 U CN 200920120030U CN 201406678 Y CN201406678 Y CN 201406678Y
Authority
CN
China
Prior art keywords
bank slope
dam
gravity dam
pile
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009201200300U
Other languages
Chinese (zh)
Inventor
涂祝明
叶建群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina East China Engineering Corp
Original Assignee
Hydrochina East China Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina East China Engineering Corp filed Critical Hydrochina East China Engineering Corp
Priority to CN2009201200300U priority Critical patent/CN201406678Y/en
Application granted granted Critical
Publication of CN201406678Y publication Critical patent/CN201406678Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model relates to a linkage structure of a gravity dam and an unfavorable geological bank slope, and aims to solve the technical problem through providing the linkage structure of a gravitydam and an unfavorable geological bank slope. An active support manner is used for improving the stressed state of an unfavorable geological bank slope and ensuring the stability of bank slope. The technical scheme for solving the problem is as follows: the linkage structure of a gravity dam and an unfavorable geological bank slope is characterized in that a set of skidproof stakes are uniformlyarranged at the connection part of the gravity dam and the unfavorable bank slope, an inter-state plate is arranged on a slope surface between every two contiguous skidproof states, the upper part ofthe stake body of each skidproof stake is provided with a prestress anchor rope, and a water stop slot is formed between the dam body and the skidproof stakes connected with the dam body. The utilitymodel is mainly used in hydraulic and hydro-power engineering.

Description

The draw bail of a kind of gravity dam and unfavorable geology bank slope
Technical field
The utility model relates to the draw bail of a kind of gravity dam and unfavorable geology bank slope.Be mainly used in the Hydraulic and Hydro-Power Engineering.
Background technology
Gravity dam is one of important dam type that extensively adopts in the Hydraulic and Hydro-Power Engineering, because the western complicated topographic and geologic condition and the operating characteristic of gravity dam itself, gravity dam high slope and superelevation side slope often occur with connecting of two sides bank slope, when the bank slope geological conditions is unfavorable, often cause the stability of slope problem.
At present, the engineering that has is by engineering measures such as employing anchor arm-ties, solved the articulation issues of indivedual gravity dams and the bad bank slope of geology, but because the restriction of this structure construction program and design feature, there are shortcomings such as slope retaining is untimely, the construction safety problem is outstanding in this passive retaining structure.
Summary of the invention
The technical problems to be solved in the utility model is: provide the draw bail of a kind of gravity dam and unfavorable geology bank slope at the problem of above-mentioned existence, with the form of active support, improve the stress of unfavorable geology bank slope, guarantee the stability of side slope.
The technical scheme that the utility model adopted is: the draw bail of a kind of gravity dam and unfavorable geology bank slope, it is characterized in that: one group of antislide pile evenly is set in the junction of gravity dam and unfavorable geology bank slope, on domatic between adjacent each antislide pile plate between stake is set, described antislide pile pile body top is provided with prestress anchorage cable, between dam body and the antislide pile that is attached thereto water stopping trough is set.
Described antislide pile is divided into a preface antislide pile and two preface antislide piles, and a preface antislide pile and the dislocation of two preface antislide piles are arranged.
The plate top is provided with the contact beam between described stake.
The beneficial effects of the utility model are: the utility model is by calculating the excavation slope residual pushing force, plate and anchor cable between reasonable Arrangement antislide pile, stake, form anchor cable reinforced concrete pile board wall, realize the positive connection of dam and bank slope, effectively reduce unfavorable geological condition bank slope engineering slope height simultaneously, improved the stress of unfavorable geology bank slope, improved working security, guarantee the engineering slope safe operation, saved construction investment.
Description of drawings
Fig. 1 is a front view of the present utility model.
Fig. 2 is the lateral view of Fig. 1.
The specific embodiment
As shown in Figure 1 and Figure 2, present embodiment evenly is provided with one group of antislide pile in the junction of gravity dam and unfavorable geology bank slope, remain basically stable with dam crest road surface 6 in the stake top, and the pile body diameter that is connected with dam outline line 9 is big than other pile body diameters, for guaranteeing bank stability, each pile body all need pass completely through severely-weathered fracture area 8 and go deep into the weak-weathered rock body and be no less than 1/4 pile body length.For guaranteeing stake well excavation safety, adopt the steel concrete supporting around the stake well, on domatic between adjacent each antislide pile plate 3 between stake is set, prevent domatic local buckling between stake, described antislide pile pile body top is provided with prestress anchorage cable 4, to reduce pile body deformation and to improve pile body and the stress condition of side slope, for preventing antislide pile and dam body binding site generation seepage, between dam body and the antislide pile that is attached thereto sealing 10 is set, plate 3 tops are provided with contact beam 5 between described stake.
The job practices of present embodiment is:
A, in order to prevent from the work progress to take place the landslide phenomenon, adopt branch preface excavation in the work progress, build antislide pile stake well, in this example, at first excavation is built a preface antislide pile 1, after treating that its concrete strength reaches requirement, excavation is built two preface antislide piles 2 between each preface antislide pile 1, and stake well excavation construction needs the supporting while excavating, excavation is promptly built pile concrete after finishing, and with antislide pile that dam body is connected on reservation sealing 10 grooves;
B, treat that the antislide pile concrete pouring construction is finished, after concrete strength of pile reaches requirement, press excavation line 7 beginning stage excavation dam foundation foundation ditches, plate 3 between the stake of excavation one deck construction one deck according to the bank slope geological conditions;
C, wait to be excavated to the anchor cable design altitude, stop excavation, construction anchor cable, anchor cable prestressing force lock value need and antislide pile later stage displacement coupling;
D, treat that anchor cable construction is finished after, continue construction according to step b, plate between stage excavation dam foundation foundation ditch, construction stake is until being excavated to design altitude;
E, cleaning foundation plane are built dam concrete, and are buried sealing 10 underground at the pile body preformed groove, in case the seepage phenomenon takes place.

Claims (3)

1, the draw bail of a kind of gravity dam and unfavorable geology bank slope, it is characterized in that: one group of antislide pile evenly is set in the junction of gravity dam and unfavorable geology bank slope, on domatic between adjacent each antislide pile plate between stake (3) is set, described antislide pile pile body top is provided with prestress anchorage cable (4), between dam body and the antislide pile that is attached thereto water stopping trough (10) is set.
2, the draw bail of gravity dam according to claim 1 and unfavorable geology bank slope is characterized in that: described antislide pile is divided into a preface antislide pile (1) and two preface antislide piles (2), and a preface antislide pile and the dislocation of two preface antislide piles are arranged.
3, the draw bail of gravity dam according to claim 1 and 2 and unfavorable geology bank slope is characterized in that: plate (3) top is provided with contact beam (5) between described stake.
CN2009201200300U 2009-05-12 2009-05-12 Linkage structure of gravity dam and unfavorable geological bank slope Expired - Fee Related CN201406678Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009201200300U CN201406678Y (en) 2009-05-12 2009-05-12 Linkage structure of gravity dam and unfavorable geological bank slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009201200300U CN201406678Y (en) 2009-05-12 2009-05-12 Linkage structure of gravity dam and unfavorable geological bank slope

Publications (1)

Publication Number Publication Date
CN201406678Y true CN201406678Y (en) 2010-02-17

Family

ID=41677609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009201200300U Expired - Fee Related CN201406678Y (en) 2009-05-12 2009-05-12 Linkage structure of gravity dam and unfavorable geological bank slope

Country Status (1)

Country Link
CN (1) CN201406678Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102864761A (en) * 2012-10-11 2013-01-09 黄河勘测规划设计有限公司 Connection method of water inlet, gravity dam and deep covering layer bank slope
CN101565940B (en) * 2009-05-12 2013-03-06 中国水电顾问集团华东勘测设计研究院 Coupling structure of gravity dam and unfavorable geological bank slope and the construction method thereof
CN103953009A (en) * 2014-05-05 2014-07-30 黄河勘测规划设计有限公司 Arrangement structure of multi-functional dam with deep soft foundation and high water head

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565940B (en) * 2009-05-12 2013-03-06 中国水电顾问集团华东勘测设计研究院 Coupling structure of gravity dam and unfavorable geological bank slope and the construction method thereof
CN102864761A (en) * 2012-10-11 2013-01-09 黄河勘测规划设计有限公司 Connection method of water inlet, gravity dam and deep covering layer bank slope
CN103953009A (en) * 2014-05-05 2014-07-30 黄河勘测规划设计有限公司 Arrangement structure of multi-functional dam with deep soft foundation and high water head
CN103953009B (en) * 2014-05-05 2016-03-09 黄河勘测规划设计有限公司 The arrangement on the multi-functional dam of deep soft foundation high water head

Similar Documents

Publication Publication Date Title
CN103321241B (en) Deep water open type combination foundation harbour and construction method thereof
CN101644041B (en) Face rockfill dam toe board structure constructed on completely weathered bed rock and construction method thereof
CN207633352U (en) A kind of slope reinforcement structure for rapid rescue construction
CN205934908U (en) Concrete precast pile and manger plate fender building structure for soil
CN101565940B (en) Coupling structure of gravity dam and unfavorable geological bank slope and the construction method thereof
CN201406678Y (en) Linkage structure of gravity dam and unfavorable geological bank slope
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN210151660U (en) Embedded concrete antiskid tenon grout stone retaining wall
CN103966981B (en) Force transferring structure and the construction method thereof of arch dam is built on weathering rock mass
CN201502065U (en) Anchor rod joint excavation compound basis
CN107503354A (en) A kind of tower crane goes along with sb. to guard him bracing reinforcement and excavation method
CN109555129A (en) One kind is quickly met an urgent need diagonal brace and construction method for salvage of foundation pits
CN113279374B (en) Rock-fill dam top earthquake-resistant wave-proof structure and construction method
CN212404803U (en) Tunnel inverted arch combined type cableway bridge abutment
CN202000306U (en) All-straight-pile wharf structure
CN201411707Y (en) Tower cane foundation
CN209760245U (en) Multistage supporting construction of pier foundation ditch
CN207079600U (en) A kind of flat pressure dispersing anchorage cable wall retaining structure of rock matter cut slope
CN207176696U (en) A kind of buttress type supporting and protecting row pile pit structure
CN201495554U (en) Anchor bolt combination excavating compound base
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN216787170U (en) Supporting construction with lean on formula barricade and anchor rope lattice roof beam
CN204875703U (en) A cross adfluxion sediment weir for hydraulic and hydroelectric engineering
CN217923677U (en) Foundation anti-impact structure
CN216787169U (en) Vertical anchor rope bracket formula sheet pile wall supporting construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100217