CN111042161A - Slope collapse high slope flexible processing structure and construction method thereof - Google Patents

Slope collapse high slope flexible processing structure and construction method thereof Download PDF

Info

Publication number
CN111042161A
CN111042161A CN202010015712.6A CN202010015712A CN111042161A CN 111042161 A CN111042161 A CN 111042161A CN 202010015712 A CN202010015712 A CN 202010015712A CN 111042161 A CN111042161 A CN 111042161A
Authority
CN
China
Prior art keywords
slope
steel pipe
anchor
grouting
processing structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010015712.6A
Other languages
Chinese (zh)
Inventor
徐建军
殷亮
魏海宁
黄熠辉
么伦强
段伟锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202010015712.6A priority Critical patent/CN111042161A/en
Publication of CN111042161A publication Critical patent/CN111042161A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Abstract

The invention relates to a flexible processing structure for a collapse slope high slope and a construction method thereof. The invention aims to provide a collapse slope volume high slope flexible treatment structure and a construction method thereof, so as to reduce the treatment difficulty, accelerate the construction progress, improve the adaptive deformation capacity and reduce the excavation and environmental pollution. The technical scheme of the invention is as follows: the structure is provided with side slopes excavated from top to bottom in grades, and a berm is arranged corresponding to each grade of side slope; arranging a plurality of steel pipe piles along the berm, wherein the lower ends of the steel pipe piles penetrate through the unconformity boundary line of the stratum, the upper ends of the steel pipe piles are exposed out of the berm, a capping beam combined with the steel pipe piles is poured on the berm, a sash beam is arranged on the slope surface of the side slope, and the lower part of the sash beam is connected with the capping beam on the berm below through an anchoring plate; the anchor plate is fixed on the side slope through a plurality of prestressed anchor cables, and the lattice beam is fixed on the side slope through a plurality of mortar anchor rods. The invention is suitable for civil engineering collapse slope high slopes such as water conservancy, hydropower and traffic.

Description

Slope collapse high slope flexible processing structure and construction method thereof
Technical Field
The invention relates to a flexible processing structure for a collapse slope high slope and a construction method thereof. The method is suitable for slope collapse high slopes of civil engineering such as water conservancy, hydropower and traffic.
Background
The collapse volume is a bad geological phenomenon frequently encountered during side slope excavation, the deformation and the stability of the collapse volume are one of key problems in the field of engineering geology, and particularly in water conservancy and hydropower engineering, the stability of the collapse volume is often the key for construction and safe operation of the engineering.
The high slope of collapse slope product is usually treated by excavating, anti-slide piles, lattice beams and the like:
the excavation scheme has the problems of great environmental damage, difficult stacking of discarded slag and the like, particularly for high slopes and large-volume slope collapse volumes, the disturbance of large-area excavation on the slope collapse volumes is great, construction risks exist in the excavation process, a large amount of slag can form a new artificial slope stability problem, and secondary treatment is needed;
the anti-slide pile scheme is difficult to construct, the construction period is long, the construction safety risk is prominent, when the covering layer is thick, the anti-slide pile is difficult to root, and the rigid anti-slide pile has poor deformation adaptability to the flexible slope collapse body and is easy to crack;
the sash beam can only solve the problem of slope surface shallow layer stability, when collapsing the integrated height of slope, the sash beam is not only difficult to construct, but also the self stability problem is outstanding, and during rainy season, the soil body at the bottom of the sash beam is easy to be emptied and collapsed, and the local stability problem occurs.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: aiming at the existing problems, the collapse slope high slope flexible treatment structure and the construction method thereof are provided to reduce the treatment difficulty, accelerate the construction progress, improve the adaptive deformation capacity and reduce the excavation and environmental pollution.
The technical scheme adopted by the invention is as follows: the utility model provides a collapse slope volume high slope flexible processing structure which characterized in that: the side slope is excavated from top to bottom in grades, and a berm is arranged corresponding to each grade of side slope;
arranging a plurality of steel pipe piles along the berm, wherein the lower ends of the steel pipe piles penetrate through the unconformity boundary line of the stratum, the upper ends of the steel pipe piles are exposed out of the berm, a capping beam combined with the steel pipe piles is poured on the berm, a sash beam is arranged on the slope surface of the side slope, and the lower part of the sash beam is connected with the capping beam on the berm below through an anchoring plate;
the anchor plate is fixed on the side slope through a plurality of prestressed anchor cables, and the lattice beam is fixed on the side slope through a plurality of mortar anchor rods.
The steel pipe pile is divided into two-sequence pile jumping construction, pipe following drilling is adopted, and the rock entering depth is greater than or equal to 1/3 steel pipe pile length.
4 grouting holes are drilled in the steel pipe pile along the pipe length direction, the steel pipe pile is arranged in a quincunx mode, and 1 anchor bar bundle 328 with the length L equal to 12m and 1 grouting pipe with the diameter phi of 20mm are placed inside the steel pipe pile.
The steel pipe pile is grouted by a hole bottom grout returning method, the distance between the end part of the steel pipe pile and the hole bottom of a pile hole is 10cm, grouting is diluted firstly and then concentrated, the water cement ratio is adjusted according to the grout absorption amount, finally, the hole is sealed by thick grout, the plugging length is generally 10cm, grouting materials are M30 cement mortar, the sand-lime ratio is 1:1, the water cement ratio is 0.38-0.45, the grouting pressure is 0.3-0.5 MPa, the grout shielding pressure is 0.5MPa, and the pressure is stabilized for 5-10 min.
The prestressed anchor cables are connected to the central line of the anchor plate and are arranged at intervals in length, the length of the prestressed anchor cables is controlled according to 8-10 m of anchoring into bedrock, and the prestressed anchor cables are adjusted according to the actual thickness of a covering layer on site.
And grouting, tensioning and locking the prestressed anchor cable, and tensioning the prestressed anchor cable according to 50% of the designed tensioning force.
The mortar anchor rod is arranged at the node of the lattice beam.
And the frame beam, the anchor plate, the capping beam and the steel pipe pile are poured into a whole.
And a drain hole I is reserved on the anchor pulling plate.
A construction method of a collapse slope high slope flexible processing structure comprises the following steps:
excavating the side slope from top to bottom in a grading manner, and protecting the side slope after excavating the side slope for the first time;
arranging steel pipe piles along the pavement direction;
grouting the steel pipe pile;
an anchor cable hole, a mortar anchor rod and a side slope drainage hole II are formed in the slope surface of the side slope, and a prestressed anchor cable is arranged in the anchor cable hole;
pouring a capping beam, an anchor plate and a lattice beam, wherein the capping beam, the anchor plate and the lattice beam are connected to form a whole;
and grouting, tensioning and locking the prestressed anchor cable.
The invention has the beneficial effects that: the flexible treatment structure for the slope collapse high slope adopted by the invention has the advantages that the treatment difficulty is reduced, the construction progress is accelerated, the adaptive deformation capability of the structure is improved, and the environmental pollution is reduced.
Drawings
Fig. 1 is a schematic structural diagram of the embodiment.
Fig. 2 is a schematic structural view of the steel pipe pile in the embodiment.
FIG. 3 is a schematic cross-sectional view of a steel pipe pile according to an embodiment.
Detailed Description
As shown in fig. 1, the present embodiment is a collapse slope flexible processing structure for a high slope, which has side slopes 8 excavated from top to bottom in stages, and a berm 11 is provided corresponding to each stage of side slope 8.
In the embodiment, a plurality of steel pipe piles 1 are arranged along the pavement 11, the lower ends of the steel pipe piles 1 penetrate through the stratum unconformity boundary line 12, and the upper ends of the steel pipe piles 1 are exposed out of the pavement 11. And a capping beam 2 combined with the steel pipe pile 1 is poured on the berm 11, a lattice beam 4 is arranged on the slope surface of the side slope 8, and the lower part of the lattice beam 4 is connected with the capping beam 2 on the berm 11 below through an anchor plate 3.
In this example, a drain hole I9 is reserved on the anchor plate 3 corresponding to the side slope 8. The anchor plate 3 is fixed on a side slope 8 through a plurality of prestressed anchor cables 5, the prestressed anchor cables 5 are arranged on the central line of the anchor plate 3, the length is arranged at intervals, and the length of each anchor cable can be adjusted according to the actual thickness of a covering layer on site. The lattice beam 4 is arranged on the excavation side slope 8 above the anchor pulling plate 3, the anchor pulling plate 3 is poured with the lattice beam 4 as a bottom beam of the lattice beam 4 to form a whole, and a mortar anchor rod 7 is arranged at the node of the lattice beam 4 in a system mode.
The construction method of the embodiment is as follows:
a. and excavating from top to bottom in stages, excavating each stage of side slope 8 to the designed slope ratio of 1: i, and protecting one stage after excavating one stage.
b. Two rows of steel pipe piles 1 are arranged along the direction of a packway 11, the distance is 0.6m, the row distance is 0.5m, the steel pipe piles are arranged in a quincunx shape, the lower ends of the steel pipe piles penetrate through a stratum unconformity boundary line 12, and the rock penetration depth is not less than 1/3 pile lengths. The steel pipe pile 1 is divided into two-sequence pile jumping construction to avoid mutual influence of adjacent hole sites, and pipe following drilling is adopted to prevent collapse in the hole.
As shown in figures 2 and 3, the steel pipe pile 1 is provided with a steel pipe with an outer diameter phi of 108mm and a wall thickness of 4.5mm, 4 grouting holes 16 are drilled in the steel pipe along the length direction of the steel pipe, the distance between the grouting holes is 0.5m, the diameter phi of the steel pipe is 20mm, the grouting holes are arranged in a quincunx manner, the holes are distributed at a distance of 0.5m from the bottom of the steel pipe, and 1 bundle of grouting holes is placed in the steel pipe pile
Figure BDA0002358795280000041
12m anchor bar bundles 13 and 1 grouting pipe 14 with the diameter of 20 mm.
c. The steel pipe pile 1 adopts a hole bottom slurry return method for grouting, a 10cm deep gap 17 is reserved between a steel pipe and the bottom of a pile hole, grouting is performed first on the dilute side and then on the concentrated side, the water cement ratio is adjusted according to the slurry absorption amount, and finally, the hole is sealed by using concentrated slurry, so that the grouting is compact, and the plugging length can be adjusted according to the actual pressure. The grouting material adopts M30 cement mortar 15 (the ratio of lime to sand is 1:1), the water-cement ratio is 0.38-0.45, the grouting pressure is 0.3-0.5 MPa, the screen grouting pressure is 0.5MPa, and the pressure is stabilized for 5-10 min.
d. Anchor cable holes 6 of the prestressed anchor cables 5, mortar anchor rods 7 and side slope drain holes II10 are arranged on the slope surface. In order to prevent the holes from collapsing, the anchor cable holes 6 are drilled by following pipes; mortar anchor rods 7 are arranged at the nodes of the frame beams 4,
Figure BDA0002358795280000042
(L is 9m/6m), and the direction of the anchor rod is vertical to the slope surface; cloth 1m above the horse way 11Arranging a row of side slope drainage holes II10 phi 100, wherein L is 10m @3m, penetrating out of the anchor plate 3 through a reserved drainage hole I9, excavating a slope system above the anchor plate 3 to arrange side slope drainage holes II10 phi 100, L is 10m @4m multiplied by 4m, upward inclining all the drainage holes by 10 degrees, interpolating phi 75 drainage flower pipes, and arranging reverse filtration;
e. and integrally pouring the capping beam 2 and the anchor plate 3 at the top of the steel pipe pile 1 along the direction of the berm 11, arranging a structural joint every 12m, wherein the width of the joint is 2cm, and filling asphalt boards in the joint.
And (3) pouring the lattice beams 4 on the excavation side slope 8 above the anchor pulling plate 3, pouring the anchor pulling plate 3 as a bottom beam of the lattice beams 4 and the lattice beams 4 to form a whole, arranging a structural joint at intervals of 12m on the lattice beams 4, and filling asphalt boards in the joints.
f. Grouting, tensioning and locking the prestressed anchor cable 5, performing under-tensioning on the prestressed anchor cable 5 according to 50% of designed tensioning force, and performing compensation tensioning in due time according to the condition of the tensioning force loss of the anchor cable.

Claims (10)

1. The utility model provides a collapse slope volume high slope flexible processing structure which characterized in that: the device is provided with side slopes (8) excavated from top to bottom in a grading way, and a pavement (11) is arranged corresponding to each grade of side slope (8);
a plurality of steel pipe piles (1) are arranged along the packway (11), the lower ends of the steel pipe piles (1) penetrate through a stratum unconformity boundary line (12), the upper ends of the steel pipe piles (1) are exposed out of the packway (11), a capping beam (2) combined with the steel pipe piles (1) is poured on the packway (11), a frame beam (4) is arranged on the slope surface of the side slope (8), and the lower part of the frame beam (4) is connected with the capping beam (2) on the packway (11) below through an anchor plate (3);
the anchor plate (3) is fixed on a side slope (8) through a plurality of prestressed anchor cables (5), and the lattice beam (4) is fixed on the side slope (8) through a plurality of mortar anchor rods (7).
2. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: the steel pipe pile (1) is constructed by two-step pile jumping, pipe following drilling is adopted, and the rock-entering depth is greater than or equal to 1/3 steel pipe pile length.
3. The method of claim 1Collapse slope volume high side slope flexible processing structure, its characterized in that: the steel pipe pile (1) is drilled with 4 grouting holes (16) along the pipe length direction, the grouting holes are arranged in a quincunx manner, and 1 bundle of 3 grouting holes are placed inside the steel pipe pile
Figure FDA0002358795270000011
12m anchor bar bundles (13) and 1 grouting pipe (14) with the diameter of 20 mm.
4. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: the steel pipe pile (1) is grouted by a hole bottom grout returning method, the distance between the end part of the steel pipe pile and the hole bottom of a pile hole is 10cm, grouting is performed first in a diluted mode and then in a concentrated mode, the water cement ratio is adjusted according to the grout absorption amount, finally, hole sealing is performed by using concentrated grout, the blocking length is generally 10cm, grouting materials are M30 cement mortar (15), the sand-lime ratio is 1:1, the water cement ratio is 0.38-0.45, the grouting pressure is 0.3-0.5 MPa, the grout shielding pressure is 0.5MPa, and the pressure is stabilized for 5-10 min.
5. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: the prestressed anchor cables (5) are connected to the center line of the anchor pulling plate (3) and are arranged at intervals in length, the length is controlled within the range of 8-10 m of the anchoring-in bedrock, and the prestressed anchor cables are adjusted according to the actual thickness of a covering layer on site.
6. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: and grouting, tensioning and locking the prestressed anchor cable (5), and tensioning the prestressed anchor cable (5) according to 50% of the designed tensioning force.
7. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: the mortar anchor rod (7) is arranged at a node of the lattice beam (4).
8. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: the frame beam (4), the anchor plate (3), the capping beam (2) and the steel pipe pile (1) are poured to form a whole.
9. The collapsing slope area high slope flexible processing structure according to claim 1, characterized in that: and a drain hole I (9) is reserved on the anchor pulling plate (3).
10. A construction method of the collapse slope high slope flexible processing structure according to any one of claims 1 to 9 comprises the following steps:
excavating the side slope (8) from top to bottom in a grading manner, and protecting the side slope after excavating the side slope for one grade;
arranging the steel pipe piles (1) along the direction of the packway (11);
grouting the steel pipe pile (1);
an anchor cable hole (6), a mortar anchor rod (7) and a side slope drain hole II (10) are arranged on the slope surface of the side slope (8), and a prestressed anchor cable (5) is arranged in the anchor cable hole (6);
pouring a capping beam (2), an anchor plate (3) and a lattice beam (4), wherein the capping beam (2), the anchor plate (3) and the lattice beam (4) are connected to form a whole;
and (3) grouting, tensioning and locking the prestressed anchor cable (5).
CN202010015712.6A 2020-01-07 2020-01-07 Slope collapse high slope flexible processing structure and construction method thereof Pending CN111042161A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010015712.6A CN111042161A (en) 2020-01-07 2020-01-07 Slope collapse high slope flexible processing structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010015712.6A CN111042161A (en) 2020-01-07 2020-01-07 Slope collapse high slope flexible processing structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN111042161A true CN111042161A (en) 2020-04-21

Family

ID=70244020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010015712.6A Pending CN111042161A (en) 2020-01-07 2020-01-07 Slope collapse high slope flexible processing structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN111042161A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687361A (en) * 2021-12-09 2022-07-01 中国铁建大桥工程局集团有限公司 Construction method for preventing landslide of side slope at inlet of flood discharge tunnel
US20230009242A1 (en) * 2021-07-09 2023-01-12 Fujian Geological Engineering Survey Institute Construction Method of Fast-setting Polymer Grouting for Rapid Control of Slope Erosion and Landslide

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20230009242A1 (en) * 2021-07-09 2023-01-12 Fujian Geological Engineering Survey Institute Construction Method of Fast-setting Polymer Grouting for Rapid Control of Slope Erosion and Landslide
CN114687361A (en) * 2021-12-09 2022-07-01 中国铁建大桥工程局集团有限公司 Construction method for preventing landslide of side slope at inlet of flood discharge tunnel

Similar Documents

Publication Publication Date Title
CN205742213U (en) Foundation pit supporting construction
CN104110038A (en) Construction method for large-area pit support structure in deep-sludge type soft soil area
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN112554198B (en) Construction method of deep foundation pit protection structure adjacent to high-rise building
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN203213136U (en) Caisson and pile combined foundation of consolidated subsoil
CN105525627A (en) Two-way anchorage plate retaining wall and construction method thereof
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN114575355A (en) Soil protection and descent construction method
CN113669073B (en) Construction method for controlling adjacent building deformation of water-rich sandy stratum by tunneling before station
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN103015430A (en) Long auger pressure filling steel reinforced cement-soil pile foundation pit water-resisting and supporting method
CN213329051U (en) Collapse slope accumulation high slope flexible processing structure
CN216194845U (en) Pebble covering layer steel sheet pile cofferdam system
CN112813984B (en) Deep foundation pit construction method under complex geological condition
CN211447015U (en) H-shaped anti-slide pile plate wall
CN214573978U (en) Deep foundation pit protection structure next to high-rise building
CN203034465U (en) Core soil reserved double-buttress inclined inner support foundation pit supporting and protecting device
CN214061635U (en) Support-before-dig bored pile and inclined hollow square pile enclosure
CN110258621B (en) Assembled retaining wall convenient to quick construction
CN216839459U (en) Vertical variable cross-section structure adjacent to deep and shallow foundation pit in foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination