CN115370052B - Aluminum pipe small ceramic brick curtain wall system and construction method thereof - Google Patents

Aluminum pipe small ceramic brick curtain wall system and construction method thereof Download PDF

Info

Publication number
CN115370052B
CN115370052B CN202211088482.1A CN202211088482A CN115370052B CN 115370052 B CN115370052 B CN 115370052B CN 202211088482 A CN202211088482 A CN 202211088482A CN 115370052 B CN115370052 B CN 115370052B
Authority
CN
China
Prior art keywords
mounting
ceramic tile
curtain wall
clamping
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202211088482.1A
Other languages
Chinese (zh)
Other versions
CN115370052A (en
Inventor
吴锡良
任伟
张康
吴继华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Lingyun Hongda Curtain Wall Engineering Co ltd
Original Assignee
Beijing Lingyun Hongda Curtain Wall Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Lingyun Hongda Curtain Wall Engineering Co ltd filed Critical Beijing Lingyun Hongda Curtain Wall Engineering Co ltd
Priority to CN202211088482.1A priority Critical patent/CN115370052B/en
Publication of CN115370052A publication Critical patent/CN115370052A/en
Application granted granted Critical
Publication of CN115370052B publication Critical patent/CN115370052B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • E04B2/967Details of the cross-section of the mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/02Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
    • E04C2/04Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
    • E04C2/041Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres composed of a number of smaller elements, e.g. bricks, also combined with a slab of hardenable material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2/30Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by the shape or structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2002/001Mechanical features of panels
    • E04C2002/004Panels with profiled edges, e.g. stepped, serrated
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C2/00Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
    • E04C2002/005Appearance of panels
    • E04C2002/007Panels with the appearance of a brick wall

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Finishing Walls (AREA)

Abstract

The application relates to an aluminum pipe small ceramic brick curtain wall system and a construction method thereof, belonging to the technical field of ceramic brick curtain walls, wherein the system comprises unit ceramic bricks and mounting pipes, the mounting pipes are arranged on the outer side of a main body structure along the vertical direction in an array manner, and the unit ceramic brick arrays are arranged between adjacent mounting pipes; the two ends of the unit ceramic brick are respectively provided with a connecting component; the connecting component comprises a clamping seat, mounting grooves are formed in two ends of the unit ceramic bricks, and the clamping seat slides in the mounting grooves and is used for matching with the subsequent mounting of the unit ceramic bricks; the unit ceramic tile is installed on the installation tube in a left-right sleeving and inserting mode, and the clamping seats are adjusted in a sliding mode, so that adjacent clamping seats on two sides of the installation tube are buckled on the installation tube and are connected on the installation tube through bolts.

Description

Aluminum pipe small ceramic brick curtain wall system and construction method thereof
Technical Field
The application relates to the technical field of ceramic brick curtain walls, in particular to an aluminum pipe small ceramic brick curtain wall system and a construction method thereof.
Background
The ceramic tile curtain wall has the characteristics of difficult fading, smooth surface, strong natural smell, no pollution and the like, and is favored in house construction engineering.
At present, a ceramic brick curtain wall is mainly constructed by a construction method of dry hanging the curtain wall, specifically, after a dry hanging connecting piece is pre-buried on a main body structure outer wall, a mounting frame is arranged on the main body structure outer wall and comprises a plurality of vertical keels and a plurality of horizontal keels, the horizontal keels are connected on the vertical keels through bolts, and the vertical keels are connected on the dry hanging connecting piece through bolts. And then the ceramic tile curtain wall units are sequentially installed on the horizontal keels through bolts in a construction sequence from top to bottom or from bottom to top.
However, in the above prior art, if the ceramic tile curtain wall unit is damaged during use, the ceramic tile curtain wall unit needs to be installed on the horizontal keel of the installation frame, and the interval between the adjacent ceramic tile curtain wall units in the vertical direction after installation is too small, so that the ceramic tile curtain wall unit is not easy to disassemble and replace.
Disclosure of Invention
In order to facilitate the disassembly and replacement of the ceramic brick curtain wall unit when the ceramic brick curtain wall unit is damaged in the use process, the application provides an aluminum pipe small ceramic brick curtain wall system and a construction method thereof.
In a first aspect, the application provides an aluminum pipe small ceramic tile curtain wall system, which adopts the following technical scheme:
an aluminum pipe small ceramic brick curtain wall system comprises unit ceramic bricks and mounting pipes, wherein the mounting pipes are arranged on the outer side of a main body structure along the vertical direction in an array manner, and the unit ceramic brick arrays are arranged between adjacent mounting pipes; the two ends of the unit ceramic brick are respectively provided with a connecting component; the connecting component comprises a clamping seat, mounting grooves are formed in two ends of the unit ceramic bricks, and the clamping seat slides in the mounting grooves and is used for matching with the subsequent mounting of the unit ceramic bricks; the unit ceramic tile is installed on the installation tube in a left-right sleeve inserting mode, and the clamping seats are adjusted in a sliding mode, so that adjacent clamping seats on two sides of the installation tube are buckled on the installation tube and are connected on the installation tube through bolts.
By adopting the technical scheme, the connecting component is moved on the mounting groove, the unit ceramic bricks are mounted on the mounting pipe in a left-right sleeving manner, adjacent clamping seats on two sides of the mounting pipe are buckled on the mounting pipe, and the connecting component is connected on the mounting pipe through bolts, so that the unit ceramic bricks are easier to mount; meanwhile, when the unit ceramic bricks are damaged in the use process, as the unit ceramic bricks are not required to be connected with the horizontal structure through bolts after being overlapped on the horizontal structure, operators can detach the bolts on the mounting pipes outdoors and indoors, the unit ceramic bricks can be detached through the operation flow opposite to the left and right sleeve insertion, and when the unit ceramic bricks are replaced, only the installation flow is required to be operated again, so that the damaged unit ceramic bricks are easy to detach and replace.
Optionally, the fastener is fixed with on the cassette, is located the fastener on the adjacent cassette of mounting tube both sides, and one side is C type spare, and the opposite side is the splint piece, and C type spare lock is on the mounting tube, splint piece lock on C type spare, and the bolt runs through splint piece and C type spare respectively after with mounting tube threaded connection.
Through adopting above-mentioned technical scheme, because the fastener on the adjacent cassette of mounting tube both sides is C type spare and presss from both sides the board piece respectively for C type spare is in the mounting tube lock back, presss from both sides the board piece and can directly centre gripping C type spare outside, and installs the fastener combination on the mounting tube through the bolt, makes coupling assembling more easily connect the installation on the mounting tube.
Optionally, the connecting assembly further comprises a lapping plate, wherein the lapping plate is installed at the upper end and the lower end of the clamping seat through bolts and respectively and slidably lapped at the upper side and the lower side of the unit ceramic tile.
Through adopting above-mentioned technical scheme, the setting of strap can be spacing to the cassette in the mounting groove in vertical direction, avoids the cassette to deviate from the unit ceramic tile by vertical direction, simultaneously because the strap passes through the bolt to be connected with the cassette for strap and cassette can dismantle the replacement on the unit ceramic tile.
Optionally, be fixed with the stopper on the unit ceramic tile, the stopper is located the notch department of mounting groove, and when the cassette was slided to the mounting groove notch, cassette and stopper butt.
Through adopting above-mentioned technical scheme, the setting of stopper can be to carrying out spacingly along the gliding cassette of unit pottery brick length trend in the mounting groove, avoids the cassette to deviate from the unit pottery by the horizontal direction and changes.
Optionally, a first clamping groove is formed in the mounting tube, the first clamping groove is formed in the vertical direction, and a bolt penetrating through the buckling piece is in threaded connection with the mounting tube through the first clamping groove.
Through adopting above-mentioned technical scheme, the setting of first draw-in groove for the bolt that runs through the buckling piece can receive the direction when carrying out threaded connection with the installation pipe, is convenient for bolt and installation pipe connection.
Optionally, the buckling piece is provided with a mounting protrusion, the mounting protrusion is located on the inner side of the C-shaped piece, and when the C-shaped piece is buckled on the mounting tube, the mounting protrusion is clamped and embedded in the first clamping groove.
Through adopting above-mentioned technical scheme, because the inboard installation arch is when C type fastener lock on the installation tube on the C type fastener, can inlay in first draw-in groove for C type fastener can more stable install on the installation tube.
Optionally, be provided with the second draw-in groove on the lock piece, the second draw-in groove corresponds with installation protruding position, and sets up in the outside of C type spare, runs through C type spare and installation pipe threaded connection through the second draw-in groove after the bolt runs through the splint piece.
Through adopting above-mentioned technical scheme, the setting of second draw-in groove for the bolt that runs through splint buckling piece can receive the direction when carrying out threaded connection with the installation pipe, and the bolt of being convenient for is connected with C type buckling piece.
Optionally, the unit ceramic tile is a hollow ceramic tile.
By adopting the technical scheme, because the unit ceramic bricks are hollow ceramic bricks, the whole dead weight of the aluminum pipe small ceramic brick curtain wall system can be reduced, and the load applied to the main body structure is reduced.
Optionally, the mounting tube is an aluminum alloy tube with a surface rust-proof treatment.
In a second aspect, the application provides a construction method of an aluminum pipe small ceramic tile curtain wall system, which adopts the following technical scheme:
a construction method of an aluminum pipe small ceramic brick curtain wall system comprises the following steps:
s1, arranging mounting pipes on the outer side of a main body structure in an array mode;
s2, installing a connecting assembly on the unit ceramic tile;
s3, mounting the unit ceramic bricks between adjacent mounting pipes;
s4, mounting the connecting assembly on the mounting tube through bolts;
s5, repeating the steps S3-S4 until the aluminum pipe small ceramic tile curtain wall system is completely installed on the main body structure.
In summary, the present application includes at least one of the following beneficial technical effects:
1. the connecting assembly is moved on the mounting groove, the unit ceramic bricks are mounted on the mounting pipe in a left-right sleeving manner, after adjacent clamping seats on two sides of the mounting pipe are buckled on the mounting pipe, the connecting assembly is connected on the mounting pipe through bolts, and the unit ceramic bricks are easy to mount; meanwhile, when the unit ceramic bricks are damaged in the use process, as the unit ceramic bricks are not required to be connected with the horizontal structure through bolts after being overlapped on the horizontal structure, operators can detach the bolts on the mounting pipes outdoors and indoors, the unit ceramic bricks can be detached through the operation flow opposite to the left and right sleeve insertion, and when the unit ceramic bricks are replaced, only the mounting flow is required to be operated again, so that the damaged unit ceramic bricks are easy to detach and replace;
2. because the buckling pieces on the adjacent clamping seats at the two sides of the mounting pipe are respectively a C-shaped piece and a clamping piece, after the C-shaped piece is buckled on the mounting pipe, the clamping piece can directly clamp the outer side of the C-shaped piece and the buckling pieces are assembled and mounted on the mounting pipe through bolts, so that the connecting component is easier to connect and mount on the mounting pipe;
3. because the unit ceramic bricks are hollow ceramic bricks, the whole dead weight of the aluminum pipe small ceramic brick curtain wall system can be reduced, and therefore the load applied to the main body structure is reduced.
Drawings
FIG. 1 is a schematic overall structure of an embodiment of the present application;
FIG. 2 is an exploded view showing the connection assembly;
FIG. 3 is a top cross-sectional view showing the mounting of the fastener on the mounting tube;
FIG. 4 is an exploded view showing the attachment of the connector assembly to the mounting tube in conjunction with the fastener.
Reference numerals illustrate: 1. a unit ceramic brick; 11. a mounting groove; 12. a limiting block; 2. installing a pipe; 21. a first clamping groove; 3. a connection assembly; 31. a clamping seat; 32. a lapping plate; 4. a fastener; 41. mounting the bulge; 42. and a second clamping groove.
Detailed Description
The application is described in further detail below with reference to fig. 1-4.
The embodiment of the application discloses an aluminum pipe small ceramic brick curtain wall system.
Referring to fig. 1, an aluminum pipe small ceramic tile curtain wall system comprises a plurality of groups of unit ceramic tiles 1 and a plurality of installation pipes 2, wherein the installation pipes 2 are all arranged along the vertical direction, and the array is installed outside a main structure. Each group of unit ceramic bricks 1 are respectively installed between adjacent installation pipes 2, single unit ceramic bricks 1 are attached to the outer wall of the main body structure along the horizontal direction, and unit ceramic bricks 1 in the single group are arranged along the length direction of the installation pipes 2 in an array mode.
Referring to fig. 2, in this embodiment, the unit ceramic tile 1 may be a hollow ceramic tile with a plurality of cavities formed along its length direction in an array, and the use of the hollow ceramic tile can reduce the overall dead weight of the aluminum pipe small ceramic tile curtain wall system, thereby reducing the load applied to the main structure. The mounting groove 11 has been seted up respectively at the both ends along its length trend of unit pottery brick 1, all be provided with coupling assembling 3 in the mounting groove 11, every coupling assembling 3 comprises 1 cassette 31 and 2 bridging plates 32, cassette 31 slides in mounting groove 11 along the length trend of unit pottery brick 1, bridging plates 32 are located the upper and lower both ends of cassette 31 respectively, bridging plates 32 are the metal plate that the middle part was sunken towards cassette 31, and the sunken lateral wall of bridging plates 32 passes through bolt threaded connection with the cassette 31 lateral wall that corresponds, after bridging plates 32 and cassette 31 are connected, bridging plates 32 both ends overlap joint is on the notch of mounting groove 11 along vertical direction. The setting of the lapping plate 32 can limit the clamping seat 31 in the mounting groove 11 in the vertical direction, so that the clamping seat 31 is prevented from being separated from the unit ceramic tile 1 in the vertical direction.
Referring to fig. 2 and 3, limiting blocks 12 are fixed at the notch of the mounting groove 11 along the length direction of the unit ceramic tile 1, the limiting blocks 12 are arranged in the vertical direction, and the axis of the unit ceramic tile 1 is used as a symmetrical axis to be symmetrically arranged on the notch of the mounting groove 11. The setting of stopper 12 can carry out the spacing to the cassette 31 that slides along unit pottery brick 1 length trend in mounting groove 11, avoids cassette 31 to deviate from the unit pottery by the horizontal direction when sliding the regulation in mounting groove 11.
Referring to fig. 3 and 4, in the present embodiment, the installation tube 2 may be a hollow aluminum alloy tube, and the outer surface is coated with an epoxy zinc-rich rust-proof layer. The outer wall of the installation tube 2 is provided with 4 first clamping grooves 21, the first clamping grooves 21 are all arranged along the length direction of the installation tube 2, and on the cross section of the installation tube 2, the 4 first clamping grooves 21 are arranged at equal intervals along the circumferential direction of the installation tube 2. When the installation tube 2 is installed outside the main structure, in the cross section of the installation tube 2, 2 first clamping grooves 21 are arranged along the diameter of the cross section of the installation tube 2, and the connecting lines are perpendicular to the outer wall of the main structure in the horizontal direction. Each clamping seat 31 is fixedly provided with a buckling piece 4, and the buckling piece 4 is positioned on the side wall of the clamping seat 31 facing the limiting block 12. The buckling piece 4 on the unit ceramic tile 1 positioned on one side of the same horizontal plane of the installation tube 2 is a C-shaped piece, and the buckling piece 4 on the unit ceramic tile 1 positioned on the other side is a sandwich piece. The C-shaped buckling piece 4 is buckled on the outer wall of the mounting pipe 2, the clamping plate buckling piece 4 clamps the outer wall of the C-shaped buckling piece 4, and after bolts respectively penetrate through the clamping plate buckling piece 4 and the C-shaped buckling piece 4, the bolts are connected with the mounting pipe 2 through the first clamping groove 21 which is close to the bolts in a threaded mode.
Referring to fig. 3 and 4, the inner wall of the C-shaped fastener 4 is fixed with mounting protrusions 41, the mounting protrusions 41 are in one-to-one correspondence with the first clamping grooves 21, and the mounting protrusions 41 are all arranged along the length trend of the first clamping grooves 21, when the C-shaped fastener 4 is fastened on the mounting pipe 2, the mounting protrusions 41 are connected with the first clamping grooves 21 in a clamping manner, so that the C-shaped fastener 4 can be stably mounted on the mounting pipe 2, the end parts of the unit ceramic bricks 1 provided with the C-shaped fastener 4 can be stably mounted, and the adjacent unit ceramic bricks 1 can be stably mounted on the C-shaped fastener 4 when being mounted on the mounting pipe 2. The outer wall of the C-shaped buckling piece 4 is provided with second clamping grooves 42, the second clamping grooves 42 are in one-to-one correspondence with the mounting protrusions 41, and the second clamping grooves 42 are arranged along the length direction of the first clamping grooves 21. After the clamp plate fastener 4 is clamped on the C-shaped fastener 4, the bolt penetrates the clamp plate fastener 4 and can be guided through the second clamping groove 42 to penetrate the C-shaped fastener 4.
The implementation principle of the aluminum pipe small ceramic brick curtain wall system provided by the embodiment of the application is as follows: after the installation pipe 2 is installed outside the main structure, the connecting components 3 in the installation groove 11 are adjusted in a sliding mode, so that the unit ceramic tile 1 is arranged on the installation pipe 2 in a left-right sleeving mode, the connecting components 3 are adjusted in a sliding mode, the buckling pieces 4 on the connecting components 3 on two sides of the installation pipe 2 are buckled on the installation pipe 2, and the installation of the aluminum pipe small ceramic tile curtain wall outside the main structure is realized by connecting the buckling pieces on the installation pipe 2 through bolts. When the unit ceramic tile 1 is damaged in the use process, an operator can detach the bolts on the mounting pipe 2 outdoors and indoors, and can detach the unit ceramic tile 1 through the operation flow opposite to the left and right sleeve insertion, and when the unit ceramic tile 1 is replaced, the installation flow only needs to be operated again.
The embodiment of the application also discloses a construction method of the aluminum pipe small ceramic brick curtain wall system.
The method comprises the following steps:
s1, arranging mounting tubes 2 in an array manner outside a main body structure;
the mounting pipes 2 are respectively arranged on the outer wall surface of the main body structure in an array manner, and the mounting pipes 2 are connected with dry hanging pieces preset on the outer wall surface of the main body structure.
S2, installing a connecting component 3 on the unit ceramic tile 1;
the clamping seats 31 are respectively arranged in the mounting grooves 11 at the two ends of the unit ceramic tile 1, the buckling pieces 4 on the clamping seat 31 at one end are C-shaped pieces, the buckling pieces 4 on the clamping seat 31 at the other end are clamping plate pieces, and then the lap plates 32 are arranged at the upper side and the lower side of the clamping seat 31, so that the lap plates 32 can drive the clamping seat 31 to slide in the mounting grooves 11.
S3, mounting the unit ceramic bricks 1 between adjacent mounting pipes 2;
the adjusting connection assembly 3 moves in the installation groove 11 along the direction towards the inside of the unit ceramic tile 1, the unit ceramic tile 1 is arranged between the adjacent installation pipes 2 in a left-right sleeving manner, the connection assembly 3 with the C-shaped buckling piece 4 is slid to be buckled on the adjacent installation pipe 2, and the installation protrusions 41 are clamped and embedded in the first clamping groove 21. And then the unit ceramic tile 1 is installed on the other side of the installation pipe 2 where the C-shaped fastener 4 is positioned, and the connecting component 3 with the clamping plate fastener 4 is slid so as to be clamped on the adjacent C-shaped fastener 4.
S4, mounting the connecting component 3 on the mounting tube 2 through bolts;
the bolts respectively penetrate through the clamping plate buckling piece 4 and the C-shaped buckling piece 4 from the inside and the outside of the main body structure and are connected with the mounting pipe 2 through threads.
S5, repeating the steps S3-S4 until the aluminum pipe small ceramic tile curtain wall system is completely installed on the main body structure.
The embodiments of the present application are all preferred embodiments of the present application, and are not intended to limit the scope of the present application in this way, therefore: all equivalent changes in structure, shape and principle of the application should be covered in the scope of protection of the application.

Claims (10)

1. An aluminum pipe little ceramic tile curtain system, its characterized in that: the unit ceramic tile comprises unit ceramic tiles (1) and mounting pipes (2), wherein the mounting pipes (2) are arranged on the outer side of a main structure along the vertical direction in an array manner, and the unit ceramic tiles (1) are arranged between adjacent mounting pipes (2) in an array manner;
the two ends of the unit ceramic brick (1) are respectively provided with a connecting component (3);
the connecting assembly (3) comprises a clamping seat (31), mounting grooves (11) are formed in two ends of the unit ceramic bricks (1), and the clamping seat (31) slides in the mounting grooves (11) and is used for being matched with subsequent mounting of the unit ceramic bricks (1);
the unit ceramic bricks (1) are arranged on the mounting pipe (2) in a left-right sleeving manner, the clamping seats (31) are slidably adjusted, so that adjacent clamping seats (31) on two sides of the mounting pipe (2) are buckled on the mounting pipe (2), and the unit ceramic bricks are connected on the mounting pipe (2) through bolts;
the clamping seat (31) is fixedly provided with buckling pieces (4), the buckling pieces (4) are positioned on the two sides of the mounting pipe (2) and adjacent to the clamping seat (31), one side of each buckling piece is a C-shaped piece, the other side of each buckling piece is a clamping plate, the C-shaped pieces are buckled on the mounting pipe (2), and the clamping plate is buckled on the C-shaped pieces.
2. An aluminum pipe small ceramic tile curtain wall system as recited in claim 1, wherein: the bolts penetrate through the clamping plate and the C-shaped piece respectively and then are connected with the mounting pipe (2) in a threaded mode.
3. An aluminum pipe small ceramic tile curtain wall system as recited in claim 2, wherein: the connecting assembly (3) further comprises a lapping plate (32), wherein the lapping plate (32) is installed at the upper end and the lower end of the clamping seat (31) through bolts, and the lapping plate is respectively and slidably lapped on the upper side and the lower side of the unit ceramic tile (1).
4. An aluminum pipe small ceramic tile curtain wall system according to claim 3, wherein: a limiting block (12) is fixed on the unit ceramic tile (1), the limiting block (12) is located at the notch of the mounting groove (11), and when the clamping seat (31) slides to the notch of the mounting groove (11), the clamping seat (31) is abutted to the limiting block (12).
5. An aluminum pipe small ceramic tile curtain wall system as recited in claim 4, wherein: the mounting pipe (2) is provided with a first clamping groove (21), the first clamping groove (21) is arranged in the vertical direction, and a bolt penetrating through the buckling piece (4) is connected with the mounting pipe (2) through the first clamping groove (21) in a threaded mode.
6. An aluminum pipe small ceramic tile curtain wall system as recited in claim 5, wherein: the buckling piece (4) is provided with a mounting protrusion (41), the mounting protrusion (41) is located on the inner side of the C-shaped piece, and when the C-shaped piece is buckled on the mounting pipe (2), the mounting protrusion (41) is clamped and embedded in the first clamping groove (21).
7. An aluminum pipe small ceramic tile curtain wall system as recited in claim 6, wherein: the buckling piece (4) is provided with a second clamping groove (42), the second clamping groove (42) corresponds to the installation protrusion (41) in position and is arranged on the outer side of the C-shaped piece, and when a bolt penetrates through the clamping piece, the second clamping groove (42) penetrates through the C-shaped piece to be in threaded connection with the installation tube (2).
8. An aluminum pipe small ceramic tile curtain wall system as recited in claim 1, wherein: the unit ceramic bricks (1) are hollow ceramic bricks.
9. An aluminum pipe small ceramic tile curtain wall system as recited in claim 8, wherein: the mounting pipe (2) is an aluminum alloy pipe with the surface subjected to rust prevention treatment.
10. A construction method of an aluminum pipe small ceramic brick curtain wall system is characterized by comprising the following steps: the method comprises the following steps:
s1, arranging mounting pipes (2) on the outer side of a main body structure in an array manner;
s2, installing a connecting component (3) on the unit ceramic tile (1);
s3, mounting the unit ceramic bricks (1) between adjacent mounting pipes (2);
s4, mounting the connecting component (3) on the mounting pipe (2) through bolts;
s5, repeating the steps S3-S4 until the aluminum pipe small ceramic tile curtain wall system is completely installed on the main body structure.
CN202211088482.1A 2022-09-07 2022-09-07 Aluminum pipe small ceramic brick curtain wall system and construction method thereof Active CN115370052B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211088482.1A CN115370052B (en) 2022-09-07 2022-09-07 Aluminum pipe small ceramic brick curtain wall system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211088482.1A CN115370052B (en) 2022-09-07 2022-09-07 Aluminum pipe small ceramic brick curtain wall system and construction method thereof

Publications (2)

Publication Number Publication Date
CN115370052A CN115370052A (en) 2022-11-22
CN115370052B true CN115370052B (en) 2023-09-22

Family

ID=84072486

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211088482.1A Active CN115370052B (en) 2022-09-07 2022-09-07 Aluminum pipe small ceramic brick curtain wall system and construction method thereof

Country Status (1)

Country Link
CN (1) CN115370052B (en)

Citations (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9000835U1 (en) * 1990-01-26 1990-04-05 Schüco International GmbH & Co, 4800 Bielefeld Fixing and adjusting device for the flat structural elements of a curtain wall of a building with vertical posts
CN203385065U (en) * 2013-05-29 2014-01-08 福建省乐普陶板制造有限公司 Recycled constant temperature ceramic floor integrated system
CN104727466A (en) * 2014-05-16 2015-06-24 蒋卫国 Bolt type and steel bar type curtain wall brick outer wall
CN204609073U (en) * 2015-05-18 2015-09-02 东亚装饰股份有限公司 Vertical hanged type ceramic plate curtain wall mounting structure
WO2016082765A1 (en) * 2014-11-25 2016-06-02 应家荣 Base module, component, preparing mould, and construction method of earthenware brick stone wall
CN205577165U (en) * 2016-02-15 2016-09-14 黄佳财 Light compartment earthenware brick of green building materials
DE102015121728A1 (en) * 2015-12-14 2017-06-14 Hagemeister GmbH & Co. KG, Ziegelwerk Masonry Association for energy production
CN107882330A (en) * 2017-10-27 2018-04-06 上海市建筑装饰工程集团有限公司 The construction method of concrete brick curtain wall
KR101891092B1 (en) * 2018-03-13 2018-08-23 이명진 Truss Coupling Device for Curtain Wall
CN108756018A (en) * 2018-08-30 2018-11-06 刘晓峰 A kind of attachment device and building brick curtain wall of building brick
CN110130550A (en) * 2019-05-31 2019-08-16 中建东方装饰有限公司 The dried hanging hang structure and its construction method of assembled hollow out earthenware brick curtain wall
CN110158864A (en) * 2019-07-02 2019-08-23 山东天元装饰工程有限公司 A kind of staged profile aluminium plate curtain wall system
CN211080720U (en) * 2019-08-22 2020-07-24 中建八局第二建设有限公司 Hyperbolic aluminum curtain wall fossil fragments installation device and hyperbolic aluminum keel structure
CN111485651A (en) * 2020-06-02 2020-08-04 北京港源幕墙有限公司 Hollow trapezoidal glass brick dry-hanging curtain wall system
CN211229305U (en) * 2019-08-21 2020-08-11 浙江亚厦装饰股份有限公司 Penetrating type ceramic tile quick dry hanging component
CN211312985U (en) * 2019-11-06 2020-08-21 江阴市华德幕墙有限公司 Ceramic brick curtain wall with built-in aluminum alloy keels
CN212358753U (en) * 2020-02-26 2021-01-15 南京城镇建筑设计咨询有限公司 Curtain wall plate with pipeline framework
CN212405635U (en) * 2020-09-24 2021-01-26 中建八局装饰工程有限公司 Connecting structure for double-layer curved curtain wall
CN213572541U (en) * 2020-10-14 2021-06-29 北京德沅门窗幕墙工程有限公司 Three-dimensional adjustable curtain wall connecting piece
CN213979482U (en) * 2020-12-18 2021-08-17 贵州工业职业技术学院 Architectural decoration curtain wall
CN214006116U (en) * 2020-12-14 2021-08-20 湖北万泉建设工程有限公司 High-strength heat-insulating building block masonry wall
CN113293899A (en) * 2021-06-18 2021-08-24 浙江亚厦幕墙有限公司 Mounting structure and mounting method of artificial brick curtain wall
CN113431237A (en) * 2021-05-17 2021-09-24 中国建筑第七工程局有限公司 Green brick grid curtain wall system and construction method thereof
CN214329500U (en) * 2021-03-09 2021-10-01 中国中建设计集团有限公司 Outer decoration pottery rod and curtain wall connecting structure
CN214466598U (en) * 2021-03-23 2021-10-22 天保建设集团有限公司 Water pipe fixing frame used in engineering
CN215211744U (en) * 2021-03-23 2021-12-17 中建海峡建设发展有限公司 Clamp type glass curtain wall mounting structure
CN215368096U (en) * 2021-01-12 2021-12-31 中建铁路投资建设集团有限公司 Dry-hanging ceramic brick system bracket for decoration
CN113882565A (en) * 2021-11-08 2022-01-04 广州珠江装修工程有限公司 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof
CN215716384U (en) * 2021-04-22 2022-02-01 浙江亚厦幕墙有限公司 Connecting structure of stay cable ceramic brick curtain wall
CN114197712A (en) * 2021-12-28 2022-03-18 上海世微智能科技有限公司 Integrated structure combining extrusion type hollow outer wall cement board and light steel wall
CN216075781U (en) * 2021-10-28 2022-03-18 北京城建设计发展集团股份有限公司 Improved structure of hollow ceramic brick curtain wall
CN114293694A (en) * 2021-12-02 2022-04-08 中建八局第二建设有限公司 Zigzag unit aluminum plate curtain wall mounting system
CN216405860U (en) * 2021-11-19 2022-04-29 中亿丰(苏州)绿色建筑发展有限公司 Dry-hanging type hollow ceramic brick curtain wall system
CN216475772U (en) * 2021-11-08 2022-05-10 广州珠江装修工程有限公司 Curtain is decorated to building outer wall
CN216840100U (en) * 2022-01-25 2022-06-28 南京亦川建设发展有限公司 Installation mosaic structure that engineering curtain was used
CN216892988U (en) * 2022-02-21 2022-07-05 江西娉林建筑工程有限公司 House building partition wall integrating prefabricated constructional columns
CN217151026U (en) * 2022-03-18 2022-08-09 中建八局第三建设有限公司 Zipper component for decorating ceramic tiles outside curtain wall
CN217150836U (en) * 2022-03-10 2022-08-09 中海建筑有限公司 Assembled aluminum plate curtain wall
CN217811831U (en) * 2022-08-04 2022-11-15 北京凌云宏达幕墙工程有限公司 Angle-adjustable ceramic brick curtain wall system
CN217924311U (en) * 2022-08-04 2022-11-29 北京凌云宏达幕墙工程有限公司 Aluminum pipe framework for ceramic brick installation

Patent Citations (40)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE9000835U1 (en) * 1990-01-26 1990-04-05 Schüco International GmbH & Co, 4800 Bielefeld Fixing and adjusting device for the flat structural elements of a curtain wall of a building with vertical posts
CN203385065U (en) * 2013-05-29 2014-01-08 福建省乐普陶板制造有限公司 Recycled constant temperature ceramic floor integrated system
CN104727466A (en) * 2014-05-16 2015-06-24 蒋卫国 Bolt type and steel bar type curtain wall brick outer wall
WO2016082765A1 (en) * 2014-11-25 2016-06-02 应家荣 Base module, component, preparing mould, and construction method of earthenware brick stone wall
CN204609073U (en) * 2015-05-18 2015-09-02 东亚装饰股份有限公司 Vertical hanged type ceramic plate curtain wall mounting structure
DE102015121728A1 (en) * 2015-12-14 2017-06-14 Hagemeister GmbH & Co. KG, Ziegelwerk Masonry Association for energy production
CN205577165U (en) * 2016-02-15 2016-09-14 黄佳财 Light compartment earthenware brick of green building materials
CN107882330A (en) * 2017-10-27 2018-04-06 上海市建筑装饰工程集团有限公司 The construction method of concrete brick curtain wall
KR101891092B1 (en) * 2018-03-13 2018-08-23 이명진 Truss Coupling Device for Curtain Wall
CN108756018A (en) * 2018-08-30 2018-11-06 刘晓峰 A kind of attachment device and building brick curtain wall of building brick
CN110130550A (en) * 2019-05-31 2019-08-16 中建东方装饰有限公司 The dried hanging hang structure and its construction method of assembled hollow out earthenware brick curtain wall
CN110158864A (en) * 2019-07-02 2019-08-23 山东天元装饰工程有限公司 A kind of staged profile aluminium plate curtain wall system
CN211229305U (en) * 2019-08-21 2020-08-11 浙江亚厦装饰股份有限公司 Penetrating type ceramic tile quick dry hanging component
CN211080720U (en) * 2019-08-22 2020-07-24 中建八局第二建设有限公司 Hyperbolic aluminum curtain wall fossil fragments installation device and hyperbolic aluminum keel structure
CN211312985U (en) * 2019-11-06 2020-08-21 江阴市华德幕墙有限公司 Ceramic brick curtain wall with built-in aluminum alloy keels
CN212358753U (en) * 2020-02-26 2021-01-15 南京城镇建筑设计咨询有限公司 Curtain wall plate with pipeline framework
CN111485651A (en) * 2020-06-02 2020-08-04 北京港源幕墙有限公司 Hollow trapezoidal glass brick dry-hanging curtain wall system
CN212405635U (en) * 2020-09-24 2021-01-26 中建八局装饰工程有限公司 Connecting structure for double-layer curved curtain wall
CN213572541U (en) * 2020-10-14 2021-06-29 北京德沅门窗幕墙工程有限公司 Three-dimensional adjustable curtain wall connecting piece
CN214006116U (en) * 2020-12-14 2021-08-20 湖北万泉建设工程有限公司 High-strength heat-insulating building block masonry wall
CN213979482U (en) * 2020-12-18 2021-08-17 贵州工业职业技术学院 Architectural decoration curtain wall
CN215368096U (en) * 2021-01-12 2021-12-31 中建铁路投资建设集团有限公司 Dry-hanging ceramic brick system bracket for decoration
CN214329500U (en) * 2021-03-09 2021-10-01 中国中建设计集团有限公司 Outer decoration pottery rod and curtain wall connecting structure
CN214466598U (en) * 2021-03-23 2021-10-22 天保建设集团有限公司 Water pipe fixing frame used in engineering
CN215211744U (en) * 2021-03-23 2021-12-17 中建海峡建设发展有限公司 Clamp type glass curtain wall mounting structure
CN215716384U (en) * 2021-04-22 2022-02-01 浙江亚厦幕墙有限公司 Connecting structure of stay cable ceramic brick curtain wall
CN113431237A (en) * 2021-05-17 2021-09-24 中国建筑第七工程局有限公司 Green brick grid curtain wall system and construction method thereof
CN113293899A (en) * 2021-06-18 2021-08-24 浙江亚厦幕墙有限公司 Mounting structure and mounting method of artificial brick curtain wall
CN216075781U (en) * 2021-10-28 2022-03-18 北京城建设计发展集团股份有限公司 Improved structure of hollow ceramic brick curtain wall
CN113882565A (en) * 2021-11-08 2022-01-04 广州珠江装修工程有限公司 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof
CN216475772U (en) * 2021-11-08 2022-05-10 广州珠江装修工程有限公司 Curtain is decorated to building outer wall
CN216405860U (en) * 2021-11-19 2022-04-29 中亿丰(苏州)绿色建筑发展有限公司 Dry-hanging type hollow ceramic brick curtain wall system
CN114293694A (en) * 2021-12-02 2022-04-08 中建八局第二建设有限公司 Zigzag unit aluminum plate curtain wall mounting system
CN114197712A (en) * 2021-12-28 2022-03-18 上海世微智能科技有限公司 Integrated structure combining extrusion type hollow outer wall cement board and light steel wall
CN216840100U (en) * 2022-01-25 2022-06-28 南京亦川建设发展有限公司 Installation mosaic structure that engineering curtain was used
CN216892988U (en) * 2022-02-21 2022-07-05 江西娉林建筑工程有限公司 House building partition wall integrating prefabricated constructional columns
CN217150836U (en) * 2022-03-10 2022-08-09 中海建筑有限公司 Assembled aluminum plate curtain wall
CN217151026U (en) * 2022-03-18 2022-08-09 中建八局第三建设有限公司 Zipper component for decorating ceramic tiles outside curtain wall
CN217811831U (en) * 2022-08-04 2022-11-15 北京凌云宏达幕墙工程有限公司 Angle-adjustable ceramic brick curtain wall system
CN217924311U (en) * 2022-08-04 2022-11-29 北京凌云宏达幕墙工程有限公司 Aluminum pipe framework for ceramic brick installation

Also Published As

Publication number Publication date
CN115370052A (en) 2022-11-22

Similar Documents

Publication Publication Date Title
CN114535855B (en) Heat supply pipeline butt welding tool
CN115370052B (en) Aluminum pipe small ceramic brick curtain wall system and construction method thereof
CN209990064U (en) Fixing assembly for building outer wall body decorative plate
CN209954603U (en) Large-diameter PCCP pipeline installer
CN215185659U (en) High-strength light energy-saving bridge convenient to assemble and disassemble
CN217000204U (en) Steel construction reinforcing apparatus that stability is strong
CN215803166U (en) A wooden template for civil engineering construction easy to assemble and disassemble
CN113202205B (en) Assembly type building assembly
CN210979243U (en) Modular support
CN210342331U (en) Assembled hard mounting wall structure
CN220598908U (en) Building steel column
CN216587150U (en) Assembled building wall component
CN217812558U (en) Prefabricated floor strutting arrangement
CN219451056U (en) Steel structure reinforcing apparatus
CN218842888U (en) Splicing apparatus of steel construction for bridge construction
CN220247183U (en) I-steel stand electromechanical device and pipeline installing support
CN211712459U (en) Guide rail connecting clamp
CN218990581U (en) A quick mounting structure for curtain design
CN219011521U (en) Pre-buried subassembly of concrete steel construction
CN220955022U (en) Color steel mounting and supporting structure
CN210623072U (en) Iron shell mechanism for water pump protection
CN214657793U (en) Hook for connecting steel structure in wall for building
CN218970438U (en) Overlength shear force wall reinforcing bar fixing fixture
CN209907207U (en) Prefabricated bridge deck system embedded steel bar clamping fixture
CN219794243U (en) Wallboard mounting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant