CN113802858A - Reverse hanging construction method for steel structure roof tile - Google Patents

Reverse hanging construction method for steel structure roof tile Download PDF

Info

Publication number
CN113802858A
CN113802858A CN202111014852.2A CN202111014852A CN113802858A CN 113802858 A CN113802858 A CN 113802858A CN 202111014852 A CN202111014852 A CN 202111014852A CN 113802858 A CN113802858 A CN 113802858A
Authority
CN
China
Prior art keywords
roof
purline
steel structure
construction
cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111014852.2A
Other languages
Chinese (zh)
Inventor
刘斌
闫显亮
杨振
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202111014852.2A priority Critical patent/CN113802858A/en
Publication of CN113802858A publication Critical patent/CN113802858A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D15/00Apparatus or tools for roof working
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D15/00Apparatus or tools for roof working
    • E04D15/04Apparatus or tools for roof working for roof coverings comprising slabs, sheets or flexible material

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a reverse hanging construction method of a steel structure roof tile, which comprises the following steps of 1, pressing and forming a roof ceiling board in a factory building; step 2, manufacturing a suspension cage; step 3, finishing the installation of the roof purline; step 4, locking the special suspension cage on the mounted purline during construction; and 5: the constructor pulls the hoisting bottom plate to the installation height through a fixed pulley rope by ground personnel in the suspension cage, and then fixes the roof bottom plate on the purline by the suspension cage personnel; and 6, completing the construction of the roof suspended ceiling plate by the sliding mode in the same way. According to the lifting cage and the operation method thereof, the problem that the steel structure roof tiles can be constructed and reversely lifted in the light steel structure industrial factory building without a portal crane is solved, and compared with the traditional construction mode of erecting a scaffold and fully laying and erecting the scaffold on the bottom surface, the construction period is greatly shortened, and the economic cost is reduced.

Description

Reverse hanging construction method for steel structure roof tile
Technical Field
The invention relates to the technical field of construction of steel structures, in particular to a reverse hoisting construction method for steel structure roof tiles.
Background
At present, according to the energy-saving requirement, most domestic industrial plants with light steel structures do not use a gantry crane, but according to the construction experience of the conventional steel structure roof ceiling tiles, a scaffold is erected on a travelling trolley of the gantry crane to finish the construction of the roof ceiling tiles through the travelling of the bridge crane, but the method needs the gantry crane, and the construction is difficult for the industrial plants with light steel structures without the gantry crane.
Disclosure of Invention
The invention aims to overcome the defects and provides a method for carrying out reverse hoisting operation on a construction steel structure roof tile in a light steel structure industrial factory building under the condition of no portal crane.
In order to achieve the above object, the present invention is realized by:
the reverse hanging construction method of the steel structure roof tile comprises
Step 1, pressing and forming a roof ceiling board in a factory building;
step 2, manufacturing a suspension cage;
step 3, finishing the installation of the roof purline;
step 4, locking the special suspension cage on the mounted purline during construction;
and 5: the constructor pulls the hoisting bottom plate to the installation height through a fixed pulley rope by ground personnel in the suspension cage, and then fixes the roof bottom plate on the purline by the suspension cage personnel;
and 6, completing the construction of the roof suspended ceiling plate by the sliding mode in the same way.
According to the steel structure roof tile reverse-hanging construction method, the hanging cage comprises the operation platform, the ladder stand and the hanging arm, the operation platform and the hanging arm are respectively arranged at the top and the bottom of the ladder stand, the operation platform, the ladder stand and the hanging arm are all made of steel pipes, and the side projection of the hanging arm is the same as the section of the purline.
According to the lifting cage and the operation method thereof, the problem that the steel structure roof tiles can be constructed and reversely lifted in the light steel structure industrial factory building without a portal crane is solved, and compared with the traditional construction mode of erecting a scaffold and fully laying and erecting the scaffold on the bottom surface, the construction period is greatly shortened, and the economic cost is reduced.
Drawings
Fig. 1 is a schematic structural view of the suspension cage of the present invention.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in figure 1, the reverse hanging construction method of the steel structure roof tile comprises the following steps
Step 1, pressing and forming a roof ceiling board in a factory building;
step 2, manufacturing a suspension cage 1;
step 3, finishing the installation of the roof purline 2;
step 4, buckling the special lifting cage lock 3 on the mounted purline during construction;
and 5: in the suspension cage 1, a constructor pulls the suspension bottom plate to the installation height through a fixed pulley rope by a ground operator, and then fixes the roof bottom plate on the purline by the suspension cage operator;
and 6, completing the construction of the roof suspended ceiling plate by the sliding mode in the same way.
According to the steel structure roof tile reverse-hanging construction method, the hanging cage comprises the operation platform, the ladder stand and the hanging arm, the operation platform and the hanging arm are respectively arranged at the top and the bottom of the ladder stand, the operation platform, the ladder stand and the hanging arm are all made of steel pipes, and the side projection of the hanging arm is the same as the section of the purline.
According to the lifting cage and the operation method thereof, the problem that the steel structure roof tiles can be constructed and reversely lifted in the light steel structure industrial factory building without a portal crane is solved, and compared with the traditional construction mode of erecting a scaffold and fully laying and erecting the scaffold on the bottom surface, the construction period is greatly shortened, and the economic cost is reduced.

Claims (2)

1. The steel structure roof tile reverse hanging construction method is characterized in that: comprises that
Step 1, pressing and forming a roof ceiling board in a factory building;
step 2, manufacturing a suspension cage;
step 3, finishing the installation of the roof purline;
step 4, locking the special suspension cage on the mounted purline during construction;
and 5: the constructor pulls the hoisting bottom plate to the installation height through a fixed pulley rope by ground personnel in the suspension cage, and then fixes the roof bottom plate on the purline by the suspension cage personnel;
and 6, completing the construction of the roof suspended ceiling plate by the sliding mode in the same way.
2. The steel structure roof tile reverse-hanging construction method as claimed in claim 1, wherein: the cage comprises an operating platform, a ladder stand and a suspension arm, wherein the operating platform and the suspension arm are respectively arranged at the top and the bottom of the ladder stand, the operating platform, the ladder stand and the suspension arm are all made of steel pipes, and the side projection of the suspension arm is the same as the section of a purline.
CN202111014852.2A 2021-08-31 2021-08-31 Reverse hanging construction method for steel structure roof tile Pending CN113802858A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111014852.2A CN113802858A (en) 2021-08-31 2021-08-31 Reverse hanging construction method for steel structure roof tile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111014852.2A CN113802858A (en) 2021-08-31 2021-08-31 Reverse hanging construction method for steel structure roof tile

Publications (1)

Publication Number Publication Date
CN113802858A true CN113802858A (en) 2021-12-17

Family

ID=78894430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111014852.2A Pending CN113802858A (en) 2021-08-31 2021-08-31 Reverse hanging construction method for steel structure roof tile

Country Status (1)

Country Link
CN (1) CN113802858A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115387611A (en) * 2022-09-30 2022-11-25 中国建筑第五工程局有限公司 Construction method of 360-degree vertical rubber-sandwiched lockstitch light steel roof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2255468Y (en) * 1996-05-23 1997-06-04 余鹏 External hanging basket for building construction
CN105735624A (en) * 2016-02-17 2016-07-06 浙江远大钢构实业有限公司 Cage for installing roof ceiling sheet
CN105986664A (en) * 2016-07-20 2016-10-05 中国建筑局(集团)有限公司 Hanging basket and roof reverse-hanging plate work platform including same
CN108190808A (en) * 2018-02-13 2018-06-22 黑龙江省建筑安装集团有限公司 The anti-furred ceiling high-altitude slide apparatus of color steel and anti-ceiling construction engineering method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2255468Y (en) * 1996-05-23 1997-06-04 余鹏 External hanging basket for building construction
CN105735624A (en) * 2016-02-17 2016-07-06 浙江远大钢构实业有限公司 Cage for installing roof ceiling sheet
CN105986664A (en) * 2016-07-20 2016-10-05 中国建筑局(集团)有限公司 Hanging basket and roof reverse-hanging plate work platform including same
CN108190808A (en) * 2018-02-13 2018-06-22 黑龙江省建筑安装集团有限公司 The anti-furred ceiling high-altitude slide apparatus of color steel and anti-ceiling construction engineering method
CN108468433A (en) * 2018-04-12 2018-08-31 陈年康 A kind of construction tool of workshop metal Roof inner panel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115387611A (en) * 2022-09-30 2022-11-25 中国建筑第五工程局有限公司 Construction method of 360-degree vertical rubber-sandwiched lockstitch light steel roof
CN115387611B (en) * 2022-09-30 2023-10-20 中国建筑第五工程局有限公司 Construction method of 360-degree vertical glue-clamping seam-locking light steel roof

Similar Documents

Publication Publication Date Title
CN201411900Y (en) Hydraulic die lifter for chimneys
CN102979313B (en) Steel truss upper air installing construction method that conversion layer is overweight
CN102877637B (en) Method for implementing operating platform in bottom wall construction of cantilever beam
CN101566005B (en) Chimney hydraulic mould lifting device
CN110562868B (en) Hoisting construction method for unit type glass curtain wall of super high-rise building
CN106948604A (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
CN110759222A (en) Take quick hoist device of PC wallboard of counter weight
CN114182647B (en) Construction method for lifting and turning weak arch
CN113802858A (en) Reverse hanging construction method for steel structure roof tile
CN205637622U (en) Perpendicular unit glass curtain wall hoist and mount system
CN102888894A (en) Structure and construction method for steel frame building with inner cylinder, outer frame and shape like Chinese character 'hui'
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN113062584A (en) Multipoint elevator shaft construction lifting platform and construction method
CN102677907A (en) Method for manually installing steel beam at top of silo
CN108468433A (en) A kind of construction tool of workshop metal Roof inner panel
CN206693641U (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building
CN216865633U (en) Super large glass curtain wall mounting structure
WO2023070257A1 (en) Intelligent hoisting robot
CN201770429U (en) Portal type framework used for hoisting and slipping
CN211169496U (en) Take quick hoist device of PC wallboard of counter weight
CN211143319U (en) Building structure composed of beam column framework for multi-layer steel structure building
CN210366717U (en) Be applied to console mode and from climbing formula whole construction work platform
CN112377672A (en) Old factory dust removal pipeline reconstruction and installation method and special pipeline moving and hoisting device thereof
CN220056126U (en) Curtain wall hoisting and installing system
CN221031318U (en) Movable construction platform for steel structure installation roof bottom plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20211217