CN110759222A - Take quick hoist device of PC wallboard of counter weight - Google Patents

Take quick hoist device of PC wallboard of counter weight Download PDF

Info

Publication number
CN110759222A
CN110759222A CN201911213445.7A CN201911213445A CN110759222A CN 110759222 A CN110759222 A CN 110759222A CN 201911213445 A CN201911213445 A CN 201911213445A CN 110759222 A CN110759222 A CN 110759222A
Authority
CN
China
Prior art keywords
steel
steel beam
wallboard
hoisting
counterweight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911213445.7A
Other languages
Chinese (zh)
Inventor
王佳蓓
张宏
梁熊
代保明
陈文玉
吴云孝
冯苛钊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201911213445.7A priority Critical patent/CN110759222A/en
Publication of CN110759222A publication Critical patent/CN110759222A/en
Priority to PCT/CN2020/132177 priority patent/WO2021109932A1/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/18Implements for finishing work on buildings for setting wall or ceiling slabs or plates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a rapid hoisting device for a PC wallboard with a counterweight, which has the structure that an I-shaped steel beam and a counterweight steel beam are respectively welded at two ends of a balance main steel beam, steel lifting lugs I are respectively symmetrically welded at two sides of the middle part above the balance main steel beam, steel lifting lugs II are respectively symmetrically welded at two sides of the end part of the counterweight steel beam above the balance main steel beam, a hole for hoisting is arranged on each steel lifting lug II, and a counterweight block is arranged below the counterweight steel beam; four steel wire ropes are respectively connected with the two steel lifting lugs I and the two steel lifting lugs II and then are gathered into a whole to be connected with an external truck crane. The PC wallboard is fixed to a hoisting point of a hoisting I-shaped steel beam, the balancing weight is installed on the other side of the cantilever steel beam, the balancing weight section and the lifting lug at the middle section of the balance main steel beam are connected through the steel wire rope, and the truck crane is connected with the steel wire rope and can be hoisted and installed to the installation position of the PC wallboard with the cantilever structure at one time. The invention has the characteristics of simple, convenient and quick construction, safety and reliability, and effectively solves the problem of installation of the PC wallboard under the cantilever structure.

Description

Take quick hoist device of PC wallboard of counter weight
Technical Field
The invention belongs to the field of constructional engineering, and particularly relates to a rapid hoisting device for a PC (polycarbonate) wallboard with a balance weight.
Background
The precast concrete structure has the advantages of improving construction efficiency, improving construction quality of building engineering, reducing environmental pollution and the like, and has wide development prospect in China. In the construction process, the hoisting of the prefabricated parts is a life line of site construction and is also an important factor influencing the construction progress.
When the prefabricated wall panel is generally required to be hoisted under an overhanging structure, a hole needs to be formed in a floor above the corresponding position of the wall panel, the prefabricated wall panel is firstly hoisted by a truck crane to the wall edge to be erected and leaned on the completed structure, then a chain block is put down from the hole of the upper floor panel, a worker needs to climb to the top of the inner wall panel to unhook and change the hook into a hook on the chain block, and then the prefabricated inner wall panel is installed. The hoisting of the prefabricated inner wall is influenced by other indoor structures, and when the upper-layer structure is a cantilever beam or a cantilever plate, the operation space at the upper end of the prefabricated inner wall can be very limited, so that the construction difficulty is brought.
Disclosure of Invention
The invention aims to overcome the problems and the defects in the prior art and provide a rapid hoisting device for a PC wallboard with a counterweight. The device solves the difficult problem of hoisting the prefabricated wallboard under the cantilever structure, adopts the lifting appliance to directly hoist and install, has high field hoisting speed, and avoids digging a floor slab.
The technical scheme of the invention is as follows:
the utility model provides a take quick hoist device of PC wallboard of counter weight, includes I-steel roof beam, balanced main girder steel, counter weight girder steel, two steel lugs I, two steel lugs II, balancing weight, four wire rope, its characterized in that: the balance main steel beam is welded with an I-shaped steel beam and a balance weight steel beam at two ends respectively, steel lugs I are symmetrically welded at two sides of the middle part above the balance main steel beam respectively, steel lugs II are symmetrically welded at two sides of the end part of the balance weight steel beam above the balance main steel beam respectively, a hole for lifting is formed in each steel lug II, and a balancing weight is installed below the balance weight steel beam; four steel wire ropes are respectively connected with the two steel lifting lugs I and the two steel lifting lugs II and then are gathered into a whole to be connected with an external truck crane.
A plurality of holes for hoisting are formed in the I-shaped steel beam, and suitable holes are conveniently selected to serve as hoisting points according to the size of the PC wallboard.
A plurality of holes for hoisting are formed in the steel lifting lug I, and suitable holes of the steel lifting lug I can be conveniently selected to serve as hoisting points according to actual conditions on site.
The balancing weight is a steel balancing weight.
The invention designs a balanced hoisting device by utilizing a lever principle (similar to a hoisting balance principle of a tower crane). One end of the hoisting device is an I-shaped steel beam for hoisting a PC wall, a plurality of PC wallboard hoisting holes are formed in the I-shaped steel beam, the other end of the I-shaped steel beam is a balancing weight, and the weight of the balancing weight is comprehensively considered according to whether the heaviest weight of the PC wallboard and the total length of the hoisting beam are beneficial to construction. In the hoisting process, the PC wallboard is firstly fixed to the installation position of the PC wallboard of the balance main steel beam, the balancing weight is installed at the other end of the balance main steel beam, and the balancing weight block section and the plurality of hoisting holes in the middle section of the overhanging hoisting device are connected through the steel wire rope. And the truck crane is connected with the steel wire rope, so that the truck crane can be successfully lifted at one time and is installed to the installation position of the PC wallboard of the cantilever structure.
Compared with the hoisting of the prefabricated part under the traditional overhanging structure, the invention directly adopts mechanical hoisting, personnel only adjust the wall plate, secondary hoisting installation is not needed, holes do not need to be formed on the second floor, in the whole installation process, all loads directly act on a crane, no influence is generated on the second floor, and the danger of cracking and collapsing of the floor is eliminated.
Drawings
Fig. 1 is a schematic elevation view of the present invention.
Fig. 2 is a plan view of the present invention.
Fig. 3 is a schematic view of the installation of the present invention.
Fig. 4 is a schematic diagram of the present invention.
Detailed Description
The invention is described in detail below with reference to the attached drawing figures:
as shown in fig. 1, 2 and 3, the invention comprises an i-shaped steel beam 1, a balance main steel beam 2, a counterweight steel beam 3, two steel lifting lugs i 4, two steel lifting lugs ii 5, a steel counterweight block 6 and four steel wire ropes 7, wherein the i-shaped steel beam 1 and the counterweight steel beam 3 are respectively welded at two ends of the balance main steel beam 2, a plurality of holes for lifting are arranged on the i-shaped steel beam 1, the steel lifting lugs i 4 are respectively symmetrically welded at two sides of the middle part above the balance main steel beam 2, the steel lifting lugs i 4 are respectively provided with a plurality of holes for lifting, the steel lifting lugs ii 5 are respectively symmetrically welded at two sides of the end part of the counterweight steel beam 3 above the balance main steel beam 2, one hole for lifting is arranged on the steel lifting lugs ii 5, and the steel counterweight block 6; four wire ropes 7 are respectively connected with two steel lifting lugs I4 and two steel lifting lugs II 5 and then are gathered into a whole to be connected with an external truck crane.
As shown in FIG. 4, the method for hoisting PC wallboard according to the invention comprises the following steps: the method comprises the following steps of selecting a proper steel balancing weight according to the weight of a PC wallboard and installing the proper steel balancing weight to a counterweight steel beam 3, selecting a hoisting point on an I-shaped steel beam 1 according to the size of the PC wallboard and the actual situation on site, selecting a proper hoisting point of a steel lifting lug I4 on a balance main steel beam 2 according to the actual situation on site, and reliably connecting the steel lifting lug I4 and a steel lifting lug II 5 by using a steel wire rope 7. The truck crane hoists the PC wallboard through the steel wire rope 7, and horizontal movement to PC wallboard installation position, PC wallboard pause slightly about 500mm high apart from the mounted position top, and constructor can hand the wallboard, control wallboard whereabouts direction, and prefabricated link plate descends slowly here. And after the position 20mm away from the top of the embedded steel bar is reached, aligning the steel bar with the reserved corrugated blind hole by using the reflector, and slowly descending the wallboard to enable the wallboard to be stably positioned after the position of the corrugated blind hole at the bottom of the prefabricated hanging plate is aligned with the position of the ground embedded steel bar. After the prefabricated PC wallboard is in place, the bolt is installed on the PC steel beam and is not pre-tightened. According to the previous control line, the level, the vertical and the elevation of the prefabricated part are adjusted, the bolt is fastened to the design requirement after the prefabricated part is adjusted to be within the error range, and the bolt is screwed to the design requirement.

Claims (4)

1. The utility model provides a take quick hoist device of PC wallboard of counter weight, includes I-steel roof beam, balanced main girder steel, counter weight girder steel, two steel lugs I, two steel lugs II, balancing weight, four wire rope, its characterized in that: the balance main steel beam is welded with an I-shaped steel beam and a balance weight steel beam at two ends respectively, steel lugs I are symmetrically welded at two sides of the middle part above the balance main steel beam respectively, steel lugs II are symmetrically welded at two sides of the end part of the balance weight steel beam above the balance main steel beam respectively, a hole for lifting is formed in each steel lug II, and a balancing weight is installed below the balance weight steel beam; four steel wire ropes are respectively connected with the two steel lifting lugs I and the two steel lifting lugs II and then are gathered into a whole to be connected with an external truck crane.
2. The rapid hoisting device of PC wallboard with counterweight of claim 1, characterized in that: and a plurality of holes for hoisting are arranged on the I-shaped steel beam.
3. The rapid hoisting device for PC wallboard with counterweight according to claim 1 or 2, characterized in that: a plurality of holes for hoisting are formed in the steel lifting lug I.
4. The rapid hoisting device of PC wallboard with counterweight of claim 3, characterized in that: the balancing weight is a steel balancing weight.
CN201911213445.7A 2019-12-02 2019-12-02 Take quick hoist device of PC wallboard of counter weight Pending CN110759222A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201911213445.7A CN110759222A (en) 2019-12-02 2019-12-02 Take quick hoist device of PC wallboard of counter weight
PCT/CN2020/132177 WO2021109932A1 (en) 2019-12-02 2020-11-27 Counterweight-equipped device for quick hoisting of pc wall panel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911213445.7A CN110759222A (en) 2019-12-02 2019-12-02 Take quick hoist device of PC wallboard of counter weight

Publications (1)

Publication Number Publication Date
CN110759222A true CN110759222A (en) 2020-02-07

Family

ID=69340761

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911213445.7A Pending CN110759222A (en) 2019-12-02 2019-12-02 Take quick hoist device of PC wallboard of counter weight

Country Status (1)

Country Link
CN (1) CN110759222A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111517221A (en) * 2020-03-27 2020-08-11 海洋石油工程(青岛)有限公司 Pipe fitting hoisting and assembling method
CN111608402A (en) * 2020-05-23 2020-09-01 成都市天柱建筑工程有限公司 Connecting device for prefabricated house and connecting method thereof
CN112061341A (en) * 2020-08-13 2020-12-11 沪东中华造船(集团)有限公司 Tilting bucket tool and using method thereof
WO2021109932A1 (en) * 2019-12-02 2021-06-10 中建三局第二建设工程有限责任公司 Counterweight-equipped device for quick hoisting of pc wall panel

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021109932A1 (en) * 2019-12-02 2021-06-10 中建三局第二建设工程有限责任公司 Counterweight-equipped device for quick hoisting of pc wall panel
CN111517221A (en) * 2020-03-27 2020-08-11 海洋石油工程(青岛)有限公司 Pipe fitting hoisting and assembling method
CN111608402A (en) * 2020-05-23 2020-09-01 成都市天柱建筑工程有限公司 Connecting device for prefabricated house and connecting method thereof
CN112061341A (en) * 2020-08-13 2020-12-11 沪东中华造船(集团)有限公司 Tilting bucket tool and using method thereof

Similar Documents

Publication Publication Date Title
CN110759222A (en) Take quick hoist device of PC wallboard of counter weight
CN201411900Y (en) Hydraulic die lifter for chimneys
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN205387439U (en) Mast hoisting accessory
CN105692470A (en) Internal climbing tower crane and operating method thereof
CN101566005B (en) Chimney hydraulic mould lifting device
CN103352576A (en) Externally expanding, assembling, converting and lifting method for medium/small span steel structure roof net rack
CN201068371Y (en) Self-hoisting tower crane
CN211169496U (en) Take quick hoist device of PC wallboard of counter weight
CN105540446A (en) Interior-climbing type lifting platform
CN104989111A (en) Construction method for steel structure high-rise hoisting
CN201102883Y (en) Steel cable sliding and lifting device
WO2021109932A1 (en) Counterweight-equipped device for quick hoisting of pc wall panel
CN210763974U (en) Be suitable for reverse construction method to get soil mouthful and pass suspension type electric hoist for material
CN110606435B (en) Suspension type electric hoist suitable for reverse construction method soil taking port transferring materials
CN113802858A (en) Reverse hanging construction method for steel structure roof tile
CN111893898A (en) Suspension splicing bridge building system with pier hoisting and transportation splicing separated and construction method thereof
CN201649667U (en) Reinforcement cage immersion guide frame
CN218912360U (en) Basement reinforced structure
CN212953807U (en) Large-span high-altitude steel trestle segmentation unit integral hoisting device
CN217378638U (en) Splicing seam adjusting device for mounting prefabricated box channel and box culvert
CN211714320U (en) Roof structure of tubular high-rise building
CN209369372U (en) A kind of overhanging hanging beam
CN220642173U (en) Hoistway construction elevator platform
CN219279306U (en) Single-machine lifting ground wall-connected reinforcement cage device in narrow space

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination