CN206693641U - The irregular alien invasion glass curtain wall positioning apparatus of high-rise building - Google Patents

The irregular alien invasion glass curtain wall positioning apparatus of high-rise building Download PDF

Info

Publication number
CN206693641U
CN206693641U CN201720394354.8U CN201720394354U CN206693641U CN 206693641 U CN206693641 U CN 206693641U CN 201720394354 U CN201720394354 U CN 201720394354U CN 206693641 U CN206693641 U CN 206693641U
Authority
CN
China
Prior art keywords
curtain wall
glass curtain
alien invasion
irregular
rise building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720394354.8U
Other languages
Chinese (zh)
Inventor
王志强
桑明辉
石建彬
徐建陇
薛德民
贺凯
李冠宇
赵晶文
秦帅
李龙鑫
柳世军
郭利红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Original Assignee
Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd filed Critical Construction and Installation Engineering Co Ltd of China Railway No 3 Engineering Group Co Ltd
Priority to CN201720394354.8U priority Critical patent/CN206693641U/en
Application granted granted Critical
Publication of CN206693641U publication Critical patent/CN206693641U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model is a kind of irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method, solve in the construction of high-rise building unit glass curtain wall, cost performance is low and the problem of security is poor when being transported using tower crane or construction elevator, including perpendicular lifting apparatus and horizontal sliding device, a kind of irregular alien invasion glass curtain wall construction method in place of high-rise building, the shaped form alien invasion horizontal sliding construction method that the shaped form alien invasion vertical-lift construction method and glass curtain wall unit body changed including glass curtain wall unit body along irregular multi-angle changes along irregular multi-angle.The utility model ensure that horizontal transport construction of the glass curtain wall unit body in the case where being helped without tower crane, meets construction needs, ensure that construction safety.

Description

The irregular alien invasion glass curtain wall positioning apparatus of high-rise building
Technical field
It is sliding along the vertical-lift of shaped form alien invasion and level that the utility model belongs to high-rise building glass curtain wall unit body Move the technical field of construction, specially a kind of irregular alien invasion glass curtain wall positioning apparatus of high-rise building.
Technical background
With social development, high-rise building is more and more, and the pursuit in building height can not meet people's need Ask, and the profile for more starting to pursue building is beautiful, novel and beautiful design, this causes curtain wall into high-end building Standard configuration, it is seen that curtain wall construction becomes an important node in whole engineering.No matter curtain wall plate is aluminum-pinch, glass curtain wall Plate or other materials, have size it is larger, from great, auxiliary installation can only be carried out by equipment during installation, particularly with super With greater need for the lifting in view of being brought by building height and variable topographies is difficult and the problem such as security difference for skyscraper.
The lifting of conventional ultra high layer building glass curtain wall is mainly transported using construction elevator in place, while also can be in tower Hang and carry out auxiliary lifting using tower crane in the case of not removing, lifting one piece of block of needs in place using tower crane is carried out, and lifting is in place The man-hour of tower crane can greatly be wasted;When being transported using construction elevator, it is contemplated that construction elevator needs periodic inspection and cost Problem, one or two only generally is set in the outside of building, can not meet that curtain wall transports at all, while into construction elevator Transport glass curtain wall block and from construction elevator to needing position transport to be mounted to be required to carry out secondary transhipment, not only waste people Power, it is often more important that the damage of glass curtain wall plate is only easily caused by manual handling and transport.
Patent CN106121255A discloses a kind of Super High Ou Li curtain walls installation apparatus, including thanks to steel wire, tiltedly Pull bar, the pre-buried wall-connecting piece on multi-layer cavity, support connecting bolt, driven hanging basket, cantilever supporting frame and wherein electronic calabash Reed, the both ends of cantilever supporting frame connect undermost pre-buried wall-connecting piece and support connecting bolt respectively, and oblique pull steel wire is connected to support Between connecting bolt and the pre-buried wall-connecting piece of the superiors, brace is connected to support connecting bolt and the pre-buried wall-connecting piece in intermediate layer Between, driven hanging basket and wherein electric block are connected on the i-beam track on cantilever supporting frame.The utility model is by glass curtain wall Vertical lifting and horizontal sliding both be attached on electric block, although can improve curtain wall work comfort level and operation effect Rate, but it is easy to use for the building of rule only for alien invasion, and the curtain wall installation to irregular alien invasion, which easily produces, is rebuffed Phenomenon, and because track is that each side is separately provided, can not solve the lifting problem in place for building corner location.
It can be seen that a kind of high performance-price ratio and being adapted to the high-rise building glass curtain wall dress in place of different alien invasion structures Put and just seem particularly important with construction method.
The content of the invention
The utility model utilizes tower crane to solve in the irregular alien invasion unit glass curtain wall construction of high-rise building Or construction elevator when transporting cost performance it is low and the problem of security is poor, there is provided a kind of irregular alien invasion glass of high-rise building Glass curtain wall positioning apparatus.
The utility model is achieved by the following technical solution:A kind of irregular alien invasion glass curtain wall of high-rise building Positioning apparatus, including perpendicular lifting apparatus and horizontal sliding device, perpendicular lifting apparatus carry including being arranged on the multiple of concrete flooring Gun carriage is risen, lifting gun carriage includes base, and base leading portion is provided with four vehicle frame bars, a fixation branch is connected at the top of four vehicle frame bars Point, electric hoist is provided with fixed pivot, base stage casing is provided with winch, and base back segment is provided with counterweight, and winch is connected with steel Cord, steel wire rope are connected with electric hoist;
Horizontal sliding device includes multiple support meanss, and support meanss include vertical connection and are anchored at the support of concrete flooring Column and support rail, support drawstring, one end of support rail are connected with by otic placode respectively between support post and support rail Concrete flooring edge is stretched out, support rail bottom is connected with track, coaster is provided with track.
It is 1 that gun carriage, which is lifted, in the quantity that building concrete flooring is set per side, and is separately positioned on the center on each side of concrete flooring Position.Lifting gun carriage is mainly used as vertical-lift, and one is set per side center in building concrete flooring, can ensure carrying Meet each side lifting demand in the case of rising gun carriage minimum number, after gun carriage lifts glass curtain wall unit to respective storey, It is accurately positioned again by switching the realization of horizontal sliding device.
Track is set perpendicular to support rail, and track connects along concrete flooring in closure.The rail set along each side of concrete flooring Road connects in closure, is advantageous to its firm stress, improves the security in hoisting process.
Minimum range of the track away from outside vertical surface of building is 300 millimeters.Facade is curve irregular structure, to protect Card glass curtain wall unit during horizontal sliding will not collide damage with outside vertical surface of building, it is desirable to ensure track away from building The distance for building beyond the region of objective existence facade is not less than 300 millimeters.
Minimum perpendicular distance of the electric hoist away from outside vertical surface of building is 300 millimeters.Facade is that curve is irregularly tied Structure, to ensure that in lift-off process glass curtain wall unit will not collide damage with outside vertical surface of building, it is desirable to ensure Distance of the electric hoist away from outside vertical surface of building is not less than 300 millimeters.
A kind of irregular alien invasion glass curtain wall construction method in place of high-rise building, including glass curtain wall unit body is not along The shaped form alien invasion vertical-lift construction method and glass curtain wall unit body of regular multi-angle change become along irregular multi-angle The shaped form alien invasion horizontal sliding construction method of change.
The shaped form alien invasion vertical-lift construction method that glass curtain wall unit body changes along irregular multi-angle include with Lower step:
S1, equipment are inspected for acceptance;Special messenger is responsible for checking that the machineries such as lifting gun carriage, steel wire rope, cable rope, dolly, fork truck are set It is standby;
S2, using fork truck glass curtain wall unit body is transported in push trolley;Cell cube is transported from place is stacked using fork truck To the push trolley of fabricating yard;
S3, inspection cleaning is carried out to glass curtain wall unit body;The dust and rubbish cleared up on glass curtain wall unit body, and examine Look into whether accessory is complete, whether installation is firm;
S4, installation lifting shoulder pole, worry messenger;The steel shoulder pole girder of lifting is connected with the upper end of glass curtain wall unit body Firmly;Pull rope is installed in cell cube lower end simultaneously, to carry out the position control of cell cube in hoisting process;
S5, vertical-lift glass curtain wall unit body extremely away from 50-100cm of ground and install horizontal cable rope;Lifted for the first time It need to ensure that it is completely vertical with ground to glass curtain wall unit body, and leave ground 50-100cm, then horizontal cable rope is installed. Horizontal cable rope one end is fixed in cell cube, and the other end is fixed on vertical steel and made on cable rope;
S6, lifting glass curtain wall unit body to setting height(from bottom).After cable rope fixation, start lifting gun carriage and play lifting Put, setting height(from bottom) is arrived in the lifting of glass curtain wall unit body, is then converted to horizontal sliding device, further passes through level Slide device is transported to appropriate installation site and constructed.
The shaped form alien invasion horizontal sliding construction method that glass curtain wall unit body changes along irregular multi-angle is included such as Lower step:
F1, equipment are inspected for acceptance;Special messenger is responsible for support post, support beam, support drawstring, the rail of inspection AQL sliding The plant equipment such as road, coaster and shoulder pole girder;
F2, the glass curtain wall unit body after vertical transport is transformed on coaster and pull rope is installed;Work as glass curtain wall After cell cube is transported to setting height(from bottom), the steel wire rope on horizontal sliding device is connected with steel shoulder pole girder, further removed vertical The pull rope set when steel wire rope on lifting device and vertical-lift, while the traction of horizontal sliding and installation in place is installed Rope;
F3, the accurate location for installing curtain wall unit body horizontal sliding to it along track using coaster, complete glass curtain wall Unit works in place.Glass curtain wall unit body is moved horizontally to installation site along track, further under the traction of pull rope just Position installation.
The utility model has the advantages that compared with the prior art:
1)The shaped form alien invasion perpendicular lifting apparatus and construction method that glass curtain wall unit body changes along irregular multi-angle
Employ shaped form alien invasion perpendicular lifting apparatus and the construction that glass curtain wall unit body changes along irregular multi-angle Method, vertical transport construction of the glass curtain wall unit body in the case where being helped without tower crane, construction elevator is ensure that, accelerates construction speed Degree, ensure that construction safety.
2)The shaped form alien invasion horizontal sliding device and construction party that glass curtain wall unit body changes along irregular multi-angle Method
Employ the shaped form alien invasion horizontal sliding device and apply that glass curtain wall unit body changes along irregular multi-angle Work method, horizontal transport construction of the glass curtain wall unit body in the case where being helped without tower crane is ensure that, construction needs is met, ensure that Construction safety.
Brief description of the drawings
Fig. 1 is integral hoisting positioning structure schematic diagram of the present utility model;
Fig. 2 is Support bracket of the present utility model and track structure schematic diagram;
Fig. 3 is lifting gun carriage schematic diagram of the present utility model;
Fig. 4 is lifting gun carriage top view of the present utility model.
In figure:1- concrete floorings, 2- support meanss, 2.1- support posts, 2.2- support rails, 2.3- support drawstrings, 2.4- Otic placode, 3- lifting gun carriages, 3.1- bases, 3.2- vehicle frame bars, 3.3- electric hoists, 3.4- steel wire ropes, 3.5- counterweights, 3.6- winches, 4- tracks, 5- coasters.
Embodiment
The utility model is described further with reference to Fig. 1-Fig. 4, a kind of irregular alien invasion glass curtain of high-rise building Wall positioning apparatus, including perpendicular lifting apparatus and horizontal sliding device, perpendicular lifting apparatus include being arranged on the multiple of concrete flooring Gun carriage 3 is lifted, lifting gun carriage 3 includes base 3.1, and the leading portion of base 3.1 is provided with four vehicle frame bars 3.2, and four vehicle frame bars 3.2 push up Portion is connected to a fixed pivot, and electric hoist 3.3 is provided with fixed pivot, and the stage casing of base 3.1 is provided with winch 3.6, base 3.1 Back segment is provided with counterweight 3.5, and winch 3.6 is connected with steel wire rope 3.4, and steel wire rope 3.4 is connected with electric hoist 3.3;
Horizontal sliding device includes multiple support meanss 2, and support meanss 2 include vertical connection and are anchored at concrete flooring 1 Support post 2.1 and support rail 2.2, support is connected between support post 2.1 and support rail 2.2 by otic placode 2.4 respectively The edge of concrete flooring 1 is stretched out in drawstring 2.3, one end of support rail 2.2, and the bottom of support rail 2.2 is connected with track 4, set on track 4 Coaster 5 is equipped with, minimum range of the track 4 away from outside vertical surface of building is 300 millimeters, and minimum of the electric hoist away from outside vertical surface of building is hung down Straight distance is 300 millimeters.
It is 1 that gun carriage 3, which is lifted, in the quantity that building concrete flooring 1 is set per side, and is separately positioned in 1 each side of concrete flooring Heart position.Track 4 is set perpendicular to support rail 2.2, and track 4 connects along concrete flooring 1 in closure.
A kind of irregular alien invasion glass curtain wall construction method in place of high-rise building, including glass curtain wall unit body is not along The shaped form alien invasion vertical-lift construction method and glass curtain wall unit body of regular multi-angle change become along irregular multi-angle The shaped form alien invasion horizontal sliding construction method of change.
The shaped form alien invasion vertical-lift construction method that glass curtain wall unit body changes along irregular multi-angle include with Lower step:
S1, equipment are inspected for acceptance;
S2, using fork truck glass curtain wall unit body is transported in push trolley;
S3, inspection cleaning is carried out to glass curtain wall unit body;
S4, installation lifting shoulder pole, worry messenger;
S5, vertical-lift glass curtain wall unit body extremely away from 50-100cm of ground and install horizontal cable rope;
S6, lifting glass curtain wall unit body to setting height(from bottom).
The shaped form alien invasion horizontal sliding construction method that glass curtain wall unit body changes along irregular multi-angle is included such as Lower step:
F1, equipment are inspected for acceptance;
F2, the glass curtain wall unit body after vertical transport is transformed on coaster and pull rope is installed;
F3, the accurate location for installing curtain wall unit body horizontal sliding to it along track using coaster, complete glass curtain wall Unit works in place.
Embodiment:
Zhong Tiesanju research and development centres building alien invasion is irregular, changeable curved surface, and the outside linear dimension of each floor is equal Differ, one layer is octagon, and 38 layers are quadrangle.Corner size tapers into, and the 13.5m by one layer becomes 2.4m, Positive facade size becomes larger;Differed per floor outer edge, wherein 14 layers of construction area maximum(1667m2), 38 Layer construction area is minimum(140 2m2).The positive angle between facade and horizontal plane in east, south, west, north four is:96°(1-4 layers) →90°(13-16 layers)→85°(35-38 layers);Angle between four corner facades and horizontal plane is:96°(1-4 layers)→93° (13-16 layers)→90°(35-38 layers).
The various installation to curtain wall unit body of change of alien invasion brings great difficulty, particularly vertical transport, horizontal fortune Defeated, in place, windproof, fall arrest etc..
Adopt the following technical scheme that realization:
1)The shaped form alien invasion perpendicular lifting apparatus and apply that a kind of glass curtain wall unit body changes along irregular multi-angle Work method, its feature and step are as follows:
Constructing device:Lifting device(Gun carriage), wind-proof device(Cable rope), ground transport device(Fork truck, push trolley), lead Leading-in device(Pull rope)Deng composition.
Construction method:Equipment inspects for acceptance → and fork truck is transported to cell cube in push trolley → inspection cleaning → peace of cell cube Load and hang shoulder pole, to worry messenger → be promoted to curtain wall unit body vertical(And leave ground 50-100cm), installation cable rope → carry Cell cube is risen to setting height(from bottom) → conversion to horizontal sliding device
The first step:Equipment is inspected for acceptance
Special messenger is responsible for having checked the plant equipment such as the gun carriage of lifting, steel wire rope, cable rope, dolly, fork truck.
Second step:Fork truck is transported to cell cube in push trolley
Cell cube is transported in the push trolley of fabricating yard from place is stacked using fork truck.
3rd:Inspection cleaning is carried out to cell cube
The dust and rubbish cleared up in cell cube, and check whether accessory is complete, whether installation is firm.
4th step:Installation lifting shoulder pole, worry messenger
The firm shoulder pole of lifting and the upper end of cell cube are connected firmly;The pull rope of lower end is installed simultaneously, to hang The position control of cell cube is carried out during dress.
5th step:It is vertical to be promoted to curtain wall unit body(Leave ground 50-100cm), the horizontal cable rope of installation
It is completely vertical that glass curtain wall unit body is promoted to for the first time, and leaves ground 50-100cm, and then installation level is pulled Wind rope.Horizontal cable rope one end is fixed in cell cube, and the other end is fixed on vertical steel cable rope.
6th step:Lift unit body is to setting height(from bottom)
After cable rope fixation, start lifting finishing, setting height(from bottom), Ran Houzhuan are arrived in the lifting of glass curtain wall unit body Shift on horizontal sliding device.Specific installation site is transported to by horizontal sliding device to be installed.
2)The shaped form alien invasion horizontal sliding device and apply that a kind of glass curtain wall unit body changes along irregular multi-angle Work method, its feature and step are as follows:
Constructing device:Encorbelment device(Girder steel), rail set(Rail), horizontal sliding device(Electric hoist), draw-gear (Pull rope)Deng composition.
Construction method:Equipment inspects for acceptance → cell cube on vertical transferring apparatus is transformed on horizontal transporter, In place installation of the pull rope → horizontal sliding to the specific installation site → cell cube of curtain wall unit body is installed
The first step:Equipment is inspected for acceptance
Special messenger is responsible for the plant equipment such as the cantilever steel girder of inspection AQL sliding, rail, electric hoist, steel wire rope, shoulder pole.
Second step:Cell cube on vertical transferring apparatus is transformed on horizontal transporter, pull rope is installed
After glass curtain wall unit body is transported to setting height(from bottom), the steel wire rope on horizontal sliding device is connected with steel shoulder pole Connect, remove the steel wire rope on vertical transportation machinery;Pull rope during vertical transport is removed simultaneously, and horizontal transport and peace in place are installed The pull rope of dress.
3rd step:Horizontal sliding is to the specific installation site of curtain wall unit body
Glass curtain wall unit body is moved horizontally to installation site along slide rail, and then installation in place is solid under the traction of pull rope It is fixed.
Finally it should be noted that:Above example is only to illustrate the technical solution of the utility model, rather than it is carried out Limitation, although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art is to foregoing reality Apply the technical scheme described in example to modify, including partly or entirely technical characteristic of the present utility model is equally replaced Change, the essence of its appropriate technical solution is without departing from the scope of protection of the utility model.

Claims (5)

1. a kind of irregular alien invasion glass curtain wall positioning apparatus of high-rise building, including perpendicular lifting apparatus and horizontal sliding dress Put, it is characterised in that:Perpendicular lifting apparatus includes the multiple lifting gun carriages for being arranged on concrete flooring(3), lift gun carriage(3)Including Base(3.1), base(3.1)Leading portion is provided with four vehicle frame bars(3.2), four vehicle frame bars(3.2)Top is connected to a fixation Fulcrum, electric hoist is provided with fixed pivot(3.3), base(3.1)Stage casing is provided with winch(3.6), base(3.1)Back segment is set It is equipped with counterweight(3.5), winch(3.6)It is connected with steel wire rope(3.4), steel wire rope(3.4)With electric hoist(3.3)Connection;
Horizontal sliding device includes multiple support meanss(2), support meanss(2)Including vertical connection and it is anchored at concrete flooring(1) Support post(2.1)And support rail(2.2), support post(2.1)And support rail(2.2)Between pass through otic placode respectively (2.4)It is connected with support drawstring(2.3), support rail(2.2)One end stretch out concrete flooring(1)Edge, support rail(2.2)Bottom Portion is connected with track(4), track(4)On be provided with coaster(5).
2. the irregular alien invasion glass curtain wall positioning apparatus of high-rise building according to claim 1, it is characterised in that:Carry Rise gun carriage(3)In building concrete flooring(1)The quantity set per side is 1, and is separately positioned on concrete flooring(1)The centre bit on each side Put.
3. the irregular alien invasion glass curtain wall positioning apparatus of high-rise building according to claim 1, it is characterised in that:Rail Road(4)Perpendicular to support rail(2.2)Set, track(4)Along concrete flooring(1)Connected in closure.
4. the irregular alien invasion glass curtain wall positioning apparatus of high-rise building according to claim 1 or 3, its feature exist In:Track(4)Minimum range away from outside vertical surface of building is 300 millimeters.
5. the irregular alien invasion glass curtain wall positioning apparatus of high-rise building according to claim 1, it is characterised in that:Electricity Cucurbit(3.3)Minimum perpendicular distance away from outside vertical surface of building is 300 millimeters.
CN201720394354.8U 2017-04-16 2017-04-16 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building Active CN206693641U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720394354.8U CN206693641U (en) 2017-04-16 2017-04-16 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720394354.8U CN206693641U (en) 2017-04-16 2017-04-16 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building

Publications (1)

Publication Number Publication Date
CN206693641U true CN206693641U (en) 2017-12-01

Family

ID=60444944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720394354.8U Active CN206693641U (en) 2017-04-16 2017-04-16 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building

Country Status (1)

Country Link
CN (1) CN206693641U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948604A (en) * 2017-04-16 2017-07-14 中铁三局集团建筑安装工程有限公司 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
WO2021012971A1 (en) * 2019-07-22 2021-01-28 中建三局集团有限公司 Integral lifting construction method for ultra-large hyperbolic integrated unit aluminium plate curtain walls

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106948604A (en) * 2017-04-16 2017-07-14 中铁三局集团建筑安装工程有限公司 The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
WO2021012971A1 (en) * 2019-07-22 2021-01-28 中建三局集团有限公司 Integral lifting construction method for ultra-large hyperbolic integrated unit aluminium plate curtain walls

Similar Documents

Publication Publication Date Title
CN106948604A (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building and construction method
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN206722429U (en) A kind of roofing color corrugated sheet steel transportation system
CN206591432U (en) Pipe installing job platform
CN107060349A (en) A kind of large-span steel girder upper air installing system in place and its construction
CN106698208A (en) Hoisting equipment and hoisting method for external transportation of super high-rise building
CN111395730A (en) Curtain wall construction system and method suitable for high-rise building with special-shaped giant columns
CN206562264U (en) A kind of hanging device for transport outside high-rise building
CN206693641U (en) The irregular alien invasion glass curtain wall positioning apparatus of high-rise building
CN103086276B (en) Construction method for hoisting bridge type crane in high-rise well tower type building
CN107575032A (en) A kind of bolt-ball net frame roofing installation method
CN205637622U (en) Perpendicular unit glass curtain wall hoist and mount system
CN210002838U (en) Device for mounting steel structure vestibule color plate
CN116853963A (en) Hoisting device and hoisting method for main girder of cable-stayed bridge
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN214942249U (en) Novel indoor wall construction device
CN214329956U (en) Ring rail hoisting device for curtain wall installation
CN203257106U (en) Multifunctional power-driven walking type walking system
CN206346500U (en) Compact simplified arm extending type straddle truck
CN110593582A (en) High-rise curtain wall installation auxiliary assembly with safety facility
CN113802858A (en) Reverse hanging construction method for steel structure roof tile
CN210286499U (en) Hoisting trolley mechanism walking on wide-flange H-shaped steel beam at top of factory building
CN206917297U (en) A kind of large-span steel girder upper air installing system in place
CN209567730U (en) A kind of small-sized lattice dead man steel construction
CN103291078B (en) A kind of steel girder erection equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant