CN113431060B - Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method - Google Patents
Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method Download PDFInfo
- Publication number
- CN113431060B CN113431060B CN202110674509.4A CN202110674509A CN113431060B CN 113431060 B CN113431060 B CN 113431060B CN 202110674509 A CN202110674509 A CN 202110674509A CN 113431060 B CN113431060 B CN 113431060B
- Authority
- CN
- China
- Prior art keywords
- tree root
- self
- bag
- slope
- pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 45
- 238000000034 method Methods 0.000 title claims abstract description 14
- 239000004568 cement Substances 0.000 claims abstract description 47
- 239000002002 slurry Substances 0.000 claims abstract description 43
- 239000012528 membrane Substances 0.000 claims abstract description 29
- 239000002689 soil Substances 0.000 claims abstract description 27
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 14
- 239000000945 filler Substances 0.000 claims abstract description 4
- 239000010410 layer Substances 0.000 claims description 39
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 22
- 238000010276 construction Methods 0.000 claims description 21
- 229910000831 Steel Inorganic materials 0.000 claims description 16
- 239000010959 steel Substances 0.000 claims description 16
- 239000011440 grout Substances 0.000 claims description 12
- 239000003864 humus Substances 0.000 claims description 11
- 238000005553 drilling Methods 0.000 claims description 10
- 239000002344 surface layer Substances 0.000 claims description 9
- 239000003795 chemical substances by application Substances 0.000 claims description 8
- 239000010881 fly ash Substances 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 7
- 239000000654 additive Substances 0.000 claims description 5
- 239000003337 fertilizer Substances 0.000 claims description 5
- 230000002787 reinforcement Effects 0.000 claims description 5
- 238000003860 storage Methods 0.000 claims description 5
- 238000009412 basement excavation Methods 0.000 claims description 4
- 238000004364 calculation method Methods 0.000 claims description 4
- 239000004927 clay Substances 0.000 claims description 4
- 238000005336 cracking Methods 0.000 claims description 4
- 239000002657 fibrous material Substances 0.000 claims description 4
- 239000004746 geotextile Substances 0.000 claims description 4
- 230000003993 interaction Effects 0.000 claims description 4
- 239000000203 mixture Substances 0.000 claims description 4
- 239000004576 sand Substances 0.000 claims description 4
- 238000004140 cleaning Methods 0.000 claims description 3
- 238000005520 cutting process Methods 0.000 claims description 3
- 238000009434 installation Methods 0.000 claims description 3
- 238000005516 engineering process Methods 0.000 abstract description 9
- 230000000694 effects Effects 0.000 abstract description 5
- 230000008595 infiltration Effects 0.000 abstract description 5
- 238000001764 infiltration Methods 0.000 abstract description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000009991 scouring Methods 0.000 description 3
- 238000004873 anchoring Methods 0.000 description 2
- 230000007423 decrease Effects 0.000 description 2
- 230000002708 enhancing effect Effects 0.000 description 2
- 230000014759 maintenance of location Effects 0.000 description 2
- 235000015097 nutrients Nutrition 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 238000004458 analytical method Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 239000011405 expansive cement Substances 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000011159 matrix material Substances 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
- 238000009424 underpinning Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/12—Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/202—Securing of slopes or inclines with flexible securing means
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
本发明提供了变截面树根桩和膜袋混凝土联合排水绿化护坡结构及方法,自应力膨胀树根桩埋设在边坡土体内部,进而通过自应力膨胀树根桩与边坡土体的相互作用,在边坡土体的表层铺设有土工膜袋,所述土工膜袋的内部填充有膜袋填充物;所述土工膜袋通过固定在自应力膨胀树根桩顶部固定台座进行固定;所述自应力膨胀树根桩上等间距设置有刚性约束盘,所述自应力膨胀树根桩之间填充有普通水泥浆和自应力膨胀水泥浆。通过将普通树根桩改进为变截面自应力膨胀树根桩,提高了树根桩自身的抗拔力,结合膜袋混凝土技术,即可对边坡进行绿化,又能防止雨水的入渗,极大的降低了雨水下渗的能力,增强了边坡的稳定性。
The invention provides a structure and method for combined drainage and greening of variable cross-section tree root piles and membrane bag concrete. effect, laying a geomembrane bag on the surface of the slope soil, the inside of the geomembrane bag is filled with a film bag filler; the geomembrane bag is fixed by fixing the pedestal on the top of the self-stress expansion tree root pile; Rigid confinement discs are arranged at equal intervals on the self-stress expansion tree root piles, and ordinary cement slurry and self-stress expansion cement slurry are filled between the self-stress expansion tree root piles. By improving the ordinary tree root piles into variable cross-section self-stress expansion tree root piles, the pullout resistance of the tree root piles is improved. Combined with membrane bag concrete technology, the slope can be greened and the infiltration of rainwater can be prevented. It greatly reduces the ability of rainwater to infiltrate and enhances the stability of the slope.
Description
技术领域technical field
本发明属于岩土工程领域设施,特别是涉及一种变截面树根桩和膜袋混凝土联合排水绿化护坡结构及方法,应用于边坡支护、地质灾害防护等工程。The invention belongs to facilities in the field of geotechnical engineering, and in particular relates to a variable-section tree root pile and membrane bag concrete combined drainage and greening slope protection structure and method, which are applied to slope support, geological disaster protection and other projects.
背景技术Background technique
树根桩类似一种摩擦桩,它既可以承担竖向荷载,同时也可以承担水平荷载,通过压力注浆可以使桩的外侧与土体紧密结合,使其获得更大的承载力。常用于地基基础托换、软土地基加固等工程,在边坡工程中运用较少,主要原因在于树根桩的桩径较小,不能提供足够的抗拔力。Tree root piles are similar to friction piles, which can bear both vertical loads and horizontal loads. Pressure grouting can make the outside of the piles closely bonded to the soil to obtain greater bearing capacity. It is often used in foundation underpinning, soft soil foundation reinforcement and other projects, but it is rarely used in slope engineering. The main reason is that the pile diameter of tree root piles is small and cannot provide sufficient pullout resistance.
针对边坡支护治理,除了要对其进行支护以外,另一方面,还需重视降雨入渗对边坡的影响,强降雨落到边坡表面时,一部分水分在表面形成径流,对边坡造成了冲刷作用,带走了边坡表面的土体颗粒;另一部分水分入渗到边坡内部。雨水的入渗使边坡非饱和区上部的含水量逐渐增大,基质吸力逐渐降低,导致土体抗剪强度降低,减小了边坡阻滑力,使边坡的稳定性下降。For slope support treatment, in addition to supporting it, on the other hand, it is also necessary to pay attention to the impact of rainfall infiltration on the slope. When heavy rainfall falls on the surface of the slope, part of the water will form runoff on the surface, which will affect the slope. The slope causes erosion, taking away the soil particles on the surface of the slope; another part of the water infiltrates into the interior of the slope. The infiltration of rainwater gradually increases the water content in the upper part of the unsaturated area of the slope, and the matrix suction gradually decreases, resulting in a decrease in the shear strength of the soil, reducing the sliding resistance of the slope, and reducing the stability of the slope.
边坡稳定问题在工程建设中具有极其重要的地位。为防止边坡失稳,保证工程建设的顺利进行和人们的财产安全,对不稳定和具有潜在危险的边坡必须采取一定的加固和防治措施;尤其是针对需要对边坡进行快速支护、治理的抢险救灾工程,目前的边坡支护治理技术有很多种:挡土墙、网格梁、框格锚杆和锚喷混凝土,人字骨架边坡等方式,这些成熟的技术虽能对边坡进行支护,但施工成本较高,工期长,对于需抢险救灾的工程边坡并不适用,且都不具备绿化边坡的作用;目前较为常用的植被混凝土技术虽能绿化边坡,但不能兼顾对滑坡进行治理,因此急需研发一种能达到快速施工、成本较低,又能兼顾绿化边坡、对滑坡进行治理的集成技术尤为重要。The slope stability problem has an extremely important position in engineering construction. In order to prevent slope instability, ensure the smooth progress of engineering construction and the safety of people's property, certain reinforcement and prevention measures must be taken for unstable and potentially dangerous slopes; especially for rapid support, There are many kinds of slope support and treatment technologies for emergency rescue and disaster relief projects: retaining walls, grid beams, lattice anchors, anchor shotcrete, herringbone skeleton slopes, etc. Although these mature technologies can The side slope is supported, but the construction cost is high and the construction period is long. It is not suitable for the engineering slope that needs emergency rescue and disaster relief, and it does not have the effect of greening the slope; although the more commonly used vegetation concrete technology can green the slope, However, landslide control cannot be taken into account, so it is urgent to develop an integrated technology that can achieve rapid construction, low cost, and can also take into account the greening of slopes and the control of landslides.
发明内容Contents of the invention
为解决上述问题,本发明提供一种改进式变截面树根桩和膜袋混凝土联合排水绿化护坡方法,利用改进式自应力膨胀树根桩和膜袋混凝土进行边坡绿化和支护治理;通过将普通树根桩改进为变截面自应力膨胀树根桩,提高了树根桩自身的抗拔力,结合膜袋混凝土技术,即可对边坡进行绿化,又能防止雨水的入渗,极大的降低了雨水下渗的能力,增强了边坡的稳定性,该方法可有效解决常规边坡支护技术施工工期长,施工成本高,在支护边坡的同时,不能兼顾边坡绿化的问题。In order to solve the above problems, the present invention provides an improved variable-section tree root pile and membrane bag concrete joint drainage and greening slope protection method, which uses the improved self-stress expansion tree root pile and membrane bag concrete to carry out slope greening and support management; The ordinary tree root pile is improved into a variable cross-section self-stress expansion tree root pile, which improves the pullout resistance of the tree root pile itself. Combined with the membrane bag concrete technology, the slope can be greened and the infiltration of rainwater can be prevented. It greatly reduces the ability of rainwater to infiltrate and enhances the stability of the slope. This method can effectively solve the long construction period and high construction cost of the conventional slope support technology. While supporting the slope, it cannot take into account the slope greening The problem.
为了实现上述的技术特征,本发明的目的是这样实现的:变截面树根桩和膜袋混凝土联合排水绿化护坡结构,它包括多组自应力膨胀树根桩,所述自应力膨胀树根桩埋设在边坡土体内部,进而通过自应力膨胀树根桩与边坡土体的相互作用,使其由边坡普通锚杆或单桩的单独受力变为树根桩与土共同受力,提高边坡抗滑性能;在边坡土体的表层铺设有土工膜袋,所述土工膜袋的内部填充有膜袋填充物;所述土工膜袋通过固定在自应力膨胀树根桩顶部固定台座进行固定;所述自应力膨胀树根桩上等间距设置有刚性约束盘,所述自应力膨胀树根桩之间填充有普通水泥浆和自应力膨胀水泥浆。In order to realize above-mentioned technical characterictic, the object of the present invention is achieved like this: variable cross-section tree root pile and membrane bag concrete joint drainage greening slope protection structure, it comprises multiple groups of self-stress expansion tree root pile, described self-stress expansion tree root pile Buried inside the slope soil, and through the interaction between the self-stressed expansion tree root pile and the slope soil, it changes from the single force of the ordinary anchor rod or single pile of the slope to the joint force of the tree root pile and the soil , to improve the anti-skid performance of the slope; a geomembrane bag is laid on the surface of the slope soil, and the inside of the geomembrane bag is filled with a film bag filler; the geomembrane bag is fixed on the top of the self-stress expansion tree root pile The pedestal is fixed; the self-stress expansion tree root piles are equidistantly provided with rigid restraint plates, and the self-stress expansion tree root piles are filled with ordinary cement slurry and self-stress expansion cement slurry.
所述自应力膨胀树根桩直径为100~300mm,自应力膨胀树根桩采用中空锚杆作为钢筋材料,中空锚杆上钻有注浆孔,注浆管能够插入中空锚杆中进行注浆。The diameter of the self-stressing expansion tree root pile is 100-300 mm, and the self-stressing expansion tree root pile adopts a hollow anchor rod as a reinforcement material, and a grouting hole is drilled on the hollow anchor rod, and the grouting pipe can be inserted into the hollow anchor rod for grouting .
所述刚性约束盘以0.3~1m的间距固定在自应力膨胀树根桩的钢筋上,相间隔的两个刚性约束盘之间分别充填普通水泥浆和自应力膨胀水泥浆,使自应力膨胀树根桩的桩身呈“糖葫芦”状,以提高桩体的边界摩阻力。The rigid confinement disks are fixed on the steel bars of the self-stress expansion tree root pile at a distance of 0.3-1 m, and the two spaced apart rigid confinement disks are filled with ordinary cement slurry and self-stress expansion cement slurry respectively, so that the self-stress expansion tree The pile body of the root pile is in the shape of "candied haws" to improve the boundary friction of the pile body.
所述固定台座与土工膜袋之间安装有钢制面板,所述固定台座的下表面设置一块承压板,避免固定螺母与土工膜袋接触面太小而破坏膜袋混凝土,并均匀分散来自锚杆的拉力。A steel panel is installed between the fixed pedestal and the geomembrane bag, and a pressure-bearing plate is arranged on the lower surface of the fixed pedestal to prevent the contact surface between the fixing nut and the geomembrane bag from being too small to damage the concrete of the membrane bag, and evenly disperse the concrete from the geomembrane bag. Anchor tension.
所述自应力膨胀水泥浆由5%~30%的膨胀剂、水泥以及粉煤灰添加剂组成,添加粉煤灰来改善自应力膨胀水泥浆的流动度和强度,添加5%~30%的膨胀剂后,能够使水泥浆液具有自应力膨胀的性能。The self-stress expansion cement slurry is composed of 5% to 30% expansion agent, cement and fly ash additives, adding fly ash to improve the fluidity and strength of the self-stress expansion cement slurry, adding 5% to 30% expansion After adding agent, it can make the cement slurry have the performance of self-stress expansion.
所述土工膜袋由土工织物缝制而成,厚度为20~50cm,膜袋内部为多层结构,层数和每层的厚度按照膜袋的实际厚度和工程实际的需要设置,底层充填混凝土层,防止雨水渗入,混凝土层的混凝土中添加有纤维材料,减小混凝土的开裂;中层为储水保肥层,由陶粒、木屑保水材料组成;膜袋表层充填植被腐质充填物,为植被生长提供植生土壤。The geomembrane bag is sewn from geotextile with a thickness of 20-50cm. The inside of the geomembrane bag is a multi-layer structure. The number of layers and the thickness of each layer are set according to the actual thickness of the membrane bag and the actual needs of the project. The bottom layer is filled with concrete layer to prevent rainwater from infiltrating, the concrete of the concrete layer is added with fiber materials to reduce the cracking of concrete; the middle layer is a water storage and fertilizer layer, which is composed of ceramsite and sawdust water-retaining materials; Provide vegetative soil.
所述植被腐质充填物由植物种子、腐殖土、黏土、砂土、水泥、水组成,其组成比例为1:1:1:1.5:2.5:3拌合而成。The vegetation humus filling is composed of plant seeds, humus, clay, sand, cement, and water, and its composition ratio is 1:1:1:1.5:2.5:3.
所述膜袋表层采用粗麻布编制而成,表面有细小的透气孔洞,此外,表层粗麻布还设有直径0.5~1cm的孔洞,以增加植被的出土率。The surface layer of the film bag is made of burlap, which has small air-permeable holes on the surface. In addition, the surface burlap is also provided with holes with a diameter of 0.5-1 cm to increase the excavation rate of vegetation.
变截面树根桩和膜袋混凝土联合排水绿化护坡结构的施工方法,包括以下步骤:The construction method of the variable-section tree root pile and membrane bag concrete combined drainage and greening slope protection structure includes the following steps:
步骤一,清理坡表:在铺设土工膜袋施工前,先将边坡表面整平,防止出现尖锐石头割破、刺穿膜袋;
步骤二,树根桩的设计:对于加固边坡土体的网状结构自应力膨胀树根桩设计,首先必须进行自应力膨胀树根桩的布置,再按布置情况验算受力模式,对内力和外力进行计算分析;其内力计算公式如下:Step 2: Design of tree root piles: For the design of self-stressed expansion tree root piles with reticular structure to reinforce the slope soil, the arrangement of self-stressed expansion tree root piles must be carried out first, and then the force mode shall be checked and calculated according to the layout situation. The calculation and analysis of the internal force and the external force are carried out; the calculation formula of the internal force is as follows:
其中:FR为每根树根桩上作用的拉力,单位为kN;P为避免发生圆弧滑动而需增加的抵抗力,单位为kN/m;S1为单位宽度1m中树根桩根数;β为树根桩与竖直方向的夹角;α为滑动力作用方向与水平线夹角;f为变截面树根桩桩身膨胀摩擦系数;Among them: F R is the pulling force acting on each tree root pile, the unit is kN; P is the resistance that needs to be increased to avoid arc sliding, the unit is kN/m; S 1 is the root of the tree root pile with a unit width of 1m β is the angle between the tree root pile and the vertical direction; α is the angle between the direction of the sliding force and the horizontal line; f is the expansion friction coefficient of the tree root pile with variable cross-section;
步骤三,钻孔:采用套管跟进法,钻机转速为200~220r/min,液压力为1.5~2.5MPa,配套供水压力为0.1~0.3MPa,钻孔到设计标高后必须清孔,控制供水压力的大小,直至孔口一处流出清水为止;
步骤四,吊放钢筋和注浆管:应尽可能一次吊放带有刚性约束盘的钢筋,避免对孔壁造成影响,注浆管采用无缝铁管,在接头处采用内缩节,使外管壁光滑,便于拔出;
步骤五,桩体分段注浆:应有两台机器进行注浆,一台注普通水泥浆,另一台注自应力膨胀水泥浆,注浆时应计算好两根注浆管的提升长度,以区别开相邻段注浆浆液,同时应控制好注浆压力,使浆液均匀上冒注浆管能够在注浆过程中随注随拔,注浆管一定要埋在水泥浆中2~3m,以保证浆体质量;Step 5: Segmented grouting of pile body: There should be two machines for grouting, one for ordinary grouting and the other for self-stress expansion grouting. When grouting, the lifting length of the two grouting pipes should be calculated , to distinguish the grouting grout in adjacent sections, and at the same time, the grouting pressure should be well controlled so that the grout rises up evenly and the grouting pipe can be pulled out as it is injected during the grouting process. The grouting pipe must be buried in the grout for 2~ 3m to ensure the quality of the slurry;
步骤六,铺设膜袋:按照自应力膨胀树根桩布置的间距,在土工膜袋上预留好对应的安装孔,然后将土工膜袋从上至下铺设在边坡表面,使得土工膜袋上的预留孔与树根桩对齐;
步骤七,膜袋底面注浆:膜袋铺设完成后,将拌制好的水泥浆液注入第一层膜袋中;
步骤八,膜袋表层植被腐质物充填:底层的水泥浆液初凝后,再进行膜袋表层的植被腐质物充填,充填时遇到拥堵的情况时,采用脚踩挤压的方式疏通。
本发明有如下有益效果:The present invention has following beneficial effect:
1、本发明所述自应力膨胀树根桩直径为100~300mm,刚性约束盘以0.3~1m的间距固定在树根桩的钢筋上,相间隔的两个刚性约束盘之间分别充填普通水泥浆和自应力膨胀水泥浆,可使树根桩的桩身呈“糖葫芦”状,可提高桩体的边界摩阻力,进而提高变截面自应力膨胀树根桩的抗拔力,其中刚性约束盘的作用可使膨胀水泥浆的轴向应力受到约束,使得其膨胀应力朝径向发展。1. The diameter of the self-stressing expansion tree root pile described in the present invention is 100-300 mm, and the rigid restraint discs are fixed on the steel bars of the tree root pile at intervals of 0.3-1 m, and ordinary cement is respectively filled between the two spaced apart rigid restraint discs Slurry and self-stress expansion cement slurry can make the pile body of the root pile take the shape of "candied haws", which can increase the boundary friction resistance of the pile body, thereby improving the pullout resistance of the self-stress expansion tree root pile with variable cross-section. The effect of can restrain the axial stress of the expansive cement slurry, so that the expansion stress develops radially.
2、本发明中通过采用树根桩对边坡进行支护,由于直径较小,使用的钻机功率液较小,故所需施工场地较小,从而减小了施工时对边坡的扰动。2. In the present invention, tree root piles are used to support the slope. Due to the smaller diameter, the power fluid of the drilling rig used is smaller, so the required construction site is smaller, thereby reducing the disturbance to the slope during construction.
3、本发明所述固定台座与凸形土工膜袋混凝土之间安装有钢制面板,所述固定台座的上表面与固定螺母之间设置一块承压板,避免固定螺母与土工膜袋接触面太小而破坏膜袋混凝土,可均匀分散来着锚杆的拉力。3. A steel panel is installed between the fixed pedestal of the present invention and the convex geomembrane bag concrete, and a pressure-bearing plate is arranged between the upper surface of the fixed pedestal and the fixing nut to avoid contact between the fixing nut and the geomembrane bag. Too small to destroy the membrane bag concrete, which can evenly disperse the pulling force of the anchor rod.
4、本发明所述自应力膨胀水泥浆主要由5%~30%的膨胀剂、水泥以及粉煤灰等添加剂组成,添加粉煤灰可改善自应力膨胀水泥浆的流动度和强度,添加5%~30%的膨胀剂后,可使水泥浆液具有自应力膨胀的性能,从而增强了树根桩的抗拔力。4. The self-stress expansion cement slurry of the present invention is mainly composed of 5% to 30% expansion agent, cement and fly ash and other additives. Adding fly ash can improve the fluidity and strength of the self-stress expansion cement slurry. Add 5 % to 30% of the expansion agent can make the cement slurry have the performance of self-stress expansion, thereby enhancing the pullout resistance of the tree root pile.
5、本发明所述土工膜袋由土工织物缝制而成,厚度为20~50cm,膜袋内部为多层结构,层数和每层的厚度按照膜袋的实际厚度和工程实际的需要设置,底层充填混凝土,可防止雨水渗入边坡,有效减小了降雨对边坡的冲刷作用,增强了边坡自身的稳定性,混凝土中添加有纤维材料,以减小混凝土的开裂,提高混凝土自身稳定性。5. The geomembrane bag of the present invention is sewn from geotextile, with a thickness of 20 to 50 cm. The inside of the film bag is a multi-layer structure. The number of layers and the thickness of each layer are set according to the actual thickness of the film bag and the actual needs of the project. , the bottom layer is filled with concrete, which can prevent rainwater from seeping into the slope, effectively reduce the scouring effect of rainfall on the slope, and enhance the stability of the slope itself. Fiber materials are added to the concrete to reduce the cracking of the concrete and improve the concrete itself. stability.
6、本发明所述中层为储水保肥层,主要以陶粒、木屑等吸水、保水材料组成;可有效吸收一部分入渗水体,并为植被的生长提供养分。6. The middle layer of the present invention is a water storage and fertilizer retention layer, which is mainly composed of water-absorbing and water-retaining materials such as ceramsite and sawdust; it can effectively absorb a part of infiltrating water and provide nutrients for the growth of vegetation.
7、本发明所述的膜袋表层充填植被腐质充填物,可为植被生长提供植生土壤。充填物主要由植物种子、腐殖土、黏土、砂土、水泥、水等其他添加剂组成,其组成比例为1:1:1:1.5:2.5:3拌合而成,提高植被腐质充填物的可泵性。7. The surface layer of the film bag of the present invention is filled with vegetation humus fillings, which can provide vegetation soil for vegetation growth. The filling is mainly composed of plant seeds, humus, clay, sand, cement, water and other additives, and its composition ratio is 1:1:1:1.5:2.5:3. pumpability.
8、本发明所述的膜袋表层,采用粗麻布编制而成,表面有细小的透气孔洞,此外,表层粗麻布还设有直径0.5~1cm的孔洞,以增加植被的出土率。8. The surface layer of the film bag according to the present invention is made of burlap, and has small air-permeable holes on the surface. In addition, the surface burlap is also provided with holes with a diameter of 0.5-1 cm to increase the excavation rate of vegetation.
9、本发明将普通树根桩改进为变截面自应力膨胀树根桩,提高了树根桩自身的抗拔力,结合膜袋混凝土技术,即可对边坡进行绿化,又能防止雨水的入渗,极大的降低了雨水下渗的能力,增强了边坡的稳定性,该方法可有效解决常规边坡支护技术施工工期长,施工成本高,在支护边坡的同时,不能兼顾边坡绿化的问题。9. The present invention improves ordinary tree root piles into variable cross-section self-stress expansion tree root piles, which improves the pullout resistance of the tree root piles themselves. Combined with membrane bag concrete technology, the slope can be greened and rainwater can be prevented. Infiltration greatly reduces the ability of rainwater to infiltrate and enhances the stability of the slope. This method can effectively solve the problem of long construction period and high construction cost of conventional slope support technology. While supporting the slope, it cannot Taking into account the problem of slope greening.
附图说明Description of drawings
下面结合附图和实施例对本发明作进一步说明。The present invention will be further described below in conjunction with drawings and embodiments.
图1为本发明树根桩结构示意图。Fig. 1 is a schematic diagram of the structure of the root pile of the present invention.
图2为本发明树根桩结合膜袋混凝土作用于堤坝结构示意图。Fig. 2 is a schematic diagram of the action of the tree root pile combined with membrane bag concrete on the embankment structure of the present invention.
图3为本发明树根桩结合膜袋混凝土支护边坡示意图。Fig. 3 is a schematic diagram of a slope supported by tree root piles combined with membrane bag concrete according to the present invention.
图中:自应力膨胀树根桩1、固定台座2、刚性约束盘3、自应力膨胀水泥浆4、土工膜袋5、膜袋填充物6、注浆孔7、钢制面板8、固定螺母9、承压板10、混凝土层11、储水保肥层12、膜袋表层13、透气孔洞14、中空锚杆15、普通水泥浆16。In the figure: self-stress expansion
具体实施方式Detailed ways
下面结合附图对本发明的实施方式做进一步的说明。Embodiments of the present invention will be further described below in conjunction with the accompanying drawings.
实施例1:Example 1:
参见图1-3,变截面树根桩和膜袋混凝土联合排水绿化护坡结构,它包括多组自应力膨胀树根桩1,所述自应力膨胀树根桩1埋设在边坡土体内部,进而通过自应力膨胀树根桩1与边坡土体的相互作用,使其由边坡普通锚杆或单桩的单独受力变为树根桩与土共同受力,提高边坡抗滑性能;在边坡土体的表层铺设有土工膜袋5,所述土工膜袋5的内部填充有膜袋填充物6;所述土工膜袋5通过固定在自应力膨胀树根桩1顶部固定台座2进行固定;所述自应力膨胀树根桩1上等间距设置有刚性约束盘3,所述自应力膨胀树根桩1之间填充有普通水泥浆16和自应力膨胀水泥浆4。通过采用上述结构的护坡结构,其通过自应力膨胀树根桩1与边坡土体的相互作用,使其由边坡普通锚杆或单桩的单独受力变为树根桩与土共同受力,提高边坡抗滑性能;同时利用土工膜袋5混凝土进行护坡和绿化,防止雨水对边坡冲刷、入渗,减小滑坡出现的几率,提高边坡稳定性。Referring to Fig. 1-3, variable cross-section tree root piles and membrane bag concrete combined drainage and greening slope protection structure, which includes multiple sets of self-stress expansion
进一步的,所述自应力膨胀树根桩1直径为100~300mm,自应力膨胀树根桩1采用中空锚杆15作为钢筋材料,中空锚杆15上钻有注浆孔7,注浆管能够插入中空锚杆15中进行注浆。通过采用上述的中空锚杆15能够用于后续对树根桩进行注浆,进而增强锚杆与土体之间的锚固力。Further, the diameter of the self-stressing expansion
进一步的,所述刚性约束盘3以0.3~1m的间距固定在自应力膨胀树根桩1的钢筋上,相间隔的两个刚性约束盘3之间分别充填普通水泥浆16和自应力膨胀水泥浆4,使自应力膨胀树根桩1的桩身呈“糖葫芦”状,以提高桩体的边界摩阻力。通过采用上述的锚杆注浆工艺提高了锚杆的锚固力,可提高桩体的边界摩阻力,进而提高变截面自应力膨胀树根桩的抗拔力,其中刚性约束盘的作用可使膨胀水泥浆的轴向应力受到约束,使得其膨胀应力朝径向发展。Further, the
进一步的,所述固定台座2与土工膜袋5之间安装有钢制面板8,所述固定台座2的下表面设置一块承压板10,避免固定螺母9与土工膜袋5接触面太小而破坏膜袋混凝土,并均匀分散来自锚杆的拉力。通过采用上述结构的钢制面板8的能够增强土工膜袋5的抗压能力,进而有效防止其被压坏。Further, a
进一步的,所述自应力膨胀水泥浆4由5%~30%的膨胀剂、水泥以及粉煤灰添加剂组成,添加粉煤灰来改善自应力膨胀水泥浆4的流动度和强度,添加5%~30%的膨胀剂后,能够使水泥浆液具有自应力膨胀的性能。通过采用上述的自应力膨胀水泥浆4形成局部膨胀部,进而增强了自应力膨胀树根桩1的抗拉拔力。Further, the self-stressing
进一步的,所述土工膜袋5由土工织物缝制而成,厚度为20~50cm,膜袋内部为多层结构,层数和每层的厚度按照膜袋的实际厚度和工程实际的需要设置,底层充填混凝土层11,防止雨水渗入,混凝土层11的混凝土中添加有纤维材料,减小混凝土的开裂;中层为储水保肥层12,由陶粒、木屑保水材料组成;膜袋表层13充填植被腐质充填物,为植被生长提供植生土壤。通过采用上述结构的土工膜袋5,在填充了混凝土层11之后增强了其表层的防冲刷性能。通过充填植被腐质充填物保证了植被的正常生长。Further, the
进一步的,所述植被腐质充填物由植物种子、腐殖土、黏土、砂土、水泥、水组成,其组成比例为1:1:1:1.5:2.5:3拌合而成。通过采用上述的植被腐质充填物能够为植物的生产提供足够的养分,进而保证了制备的正常生长。Further, the vegetation humus filling is composed of plant seeds, humus, clay, sand, cement, and water, and its composition ratio is 1:1:1:1.5:2.5:3. By using the above-mentioned vegetation humus filling, sufficient nutrients can be provided for the production of plants, thereby ensuring the normal growth of the preparation.
进一步的,所述膜袋表层13采用粗麻布编制而成,表面有细小的透气孔洞14,此外,表层粗麻布还设有直径0.5~1cm的孔洞,以增加植被的出土率。通过上述的透气孔洞14能够便于土工膜袋5的透气,进而保证了制备的生长。Further, the
实施例2:Example 2:
变截面树根桩和膜袋混凝土联合排水绿化护坡结构的施工方法,包括以下步骤:The construction method of the variable-section tree root pile and membrane bag concrete combined drainage and greening slope protection structure includes the following steps:
步骤一,清理坡表:在铺设土工膜袋5施工前,先将边坡表面整平,防止出现尖锐石头割破、刺穿膜袋;
步骤二,树根桩的设计:对于加固边坡土体的网状结构自应力膨胀树根桩1设计,首先必须进行自应力膨胀树根桩1的布置,再按布置情况验算受力模式,对内力和外力进行计算分析;其内力计算公式如下:
其中:FR为每根树根桩上作用的拉力,单位为kN;P为避免发生圆弧滑动而需增加的抵抗力,单位为kN/m;S1为单位宽度1m中树根桩根数;β为树根桩与竖直方向的夹角;α为滑动力作用方向与水平线夹角;f为变截面树根桩桩身膨胀摩擦系数;Among them: F R is the pulling force acting on each tree root pile, the unit is kN; P is the resistance that needs to be increased to avoid arc sliding, the unit is kN/m; S 1 is the root of the tree root pile with a unit width of 1m β is the angle between the tree root pile and the vertical direction; α is the angle between the direction of the sliding force and the horizontal line; f is the expansion friction coefficient of the tree root pile with variable cross-section;
步骤三,钻孔:采用套管跟进法,钻机转速为200~220r/min,液压力为1.5~2.5MPa,配套供水压力为0.1~0.3MPa,钻孔到设计标高后必须清孔,控制供水压力的大小,直至孔口一处流出清水为止;
步骤四,吊放钢筋和注浆管:应尽可能一次吊放带有刚性约束盘3的钢筋,避免对孔壁造成影响,注浆管采用无缝铁管,在接头处采用内缩节,使外管壁光滑,便于拔出;
步骤五,桩体分段注浆:应有两台机器进行注浆,一台注普通水泥浆16,另一台注自应力膨胀水泥浆4,注浆时应计算好两根注浆管的提升长度,以区别开相邻段注浆浆液,同时应控制好注浆压力,使浆液均匀上冒注浆管能够在注浆过程中随注随拔,注浆管一定要埋在水泥浆中2~3m,以保证浆体质量;Step 5: Segmented grouting of the pile body: two machines should be used for grouting, one for
步骤六,铺设膜袋:按照自应力膨胀树根桩1布置的间距,在土工膜袋5上预留好对应的安装孔,然后将土工膜袋5从上至下铺设在边坡表面,使得土工膜袋5上的预留孔与树根桩对齐;
步骤七,膜袋底面注浆:膜袋铺设完成后,将拌制好的水泥浆液注入第一层膜袋中;
步骤八,膜袋表层植被腐质物充填:底层的水泥浆液初凝后,再进行膜袋表层的植被腐质物充填,充填时遇到拥堵的情况时,采用脚踩挤压的方式疏通。
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110674509.4A CN113431060B (en) | 2021-06-17 | 2021-06-17 | Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110674509.4A CN113431060B (en) | 2021-06-17 | 2021-06-17 | Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113431060A CN113431060A (en) | 2021-09-24 |
CN113431060B true CN113431060B (en) | 2022-11-22 |
Family
ID=77756342
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110674509.4A Active CN113431060B (en) | 2021-06-17 | 2021-06-17 | Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113431060B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114016466B (en) * | 2021-12-09 | 2023-05-05 | 山东科技大学 | Slope protection system for anchoring geomembrane bag and construction method thereof |
CN116752554B (en) * | 2023-06-27 | 2023-11-14 | 中国铁道科学研究院集团有限公司 | High slope support system and implementation method based on controlled cement grouting |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3681902B2 (en) * | 1998-07-31 | 2005-08-10 | 日特建設株式会社 | Seismic ground reinforcement method |
JP3740341B2 (en) * | 1999-12-24 | 2006-02-01 | 天龍工業株式会社 | Protective greening structure on slopes, walls, shores, etc. |
CN109024607A (en) * | 2018-07-16 | 2018-12-18 | 三峡大学 | Expand the device and method that head effect reinforces deep rock mass difference rupture zone using swelling agent |
CN110258591A (en) * | 2019-06-14 | 2019-09-20 | 神华包神铁路集团有限责任公司 | The ruggedized construction and reinforced construction method of loess slope |
-
2021
- 2021-06-17 CN CN202110674509.4A patent/CN113431060B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN113431060A (en) | 2021-09-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107503257B (en) | One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method | |
CN106677797A (en) | U-shaped steel composite support structure for deep dynamic pressure soft rock roadway and construction method of U-shaped steel composite support structure | |
CN113431060B (en) | Variable cross-section root pile and film bag concrete combined drainage greening slope protection structure and method | |
CN114703872B (en) | Maintenance system for soil slope in permafrost region and construction method | |
CN207109475U (en) | It is close to mountain high-filled subgrade stabilization and Deformation control structure | |
CN206220105U (en) | A kind of double-deck Frozen Soil Cylinder anchoring soil nailed wall retaining structure system | |
CN107642041A (en) | Super large diameter hollow pile group anchorage | |
CN106759133A (en) | The mixing structure of dam type and construction method of a kind of homogeneous earth and rockfill dam and rock | |
CN112431213A (en) | Ecological comprehensive treatment structure for semi-rigid support of artificial slope and construction method thereof | |
CN107288120A (en) | A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash | |
CN101029490B (en) | Method for preventing and managing rock/upper side slope | |
CN112081155A (en) | A method for strengthening and lifting of strip or box-shaped foundation buildings | |
CN211143046U (en) | Water-blocking and draining anti-floating construction structure | |
CN211200426U (en) | Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall | |
CN108914954A (en) | Slope support method of the pre support in conjunction with permanent support | |
CN107178077A (en) | Overburden layer grouting and reinforcing structure and its design method on a kind of karst area solution cavity | |
CN111441372A (en) | Landslide foundation treatment embankment structure and construction method | |
CN111622240A (en) | Trapezoidal toe-added drainage slide-resistant pile and construction method thereof | |
CN102518136A (en) | Flexible reinforced combined protection structure for preventing and treating humidifying damage of soft rock strongly weathered zone | |
CN207032212U (en) | A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash | |
CN207484290U (en) | The hollow clump of piles anchorage of super-large diameter | |
CN102828534A (en) | Inclination rectification reinforcing method for disaster damage diseased deep pile foundation building | |
KR20020022446A (en) | Repairing method of earth-fill dam | |
Perry | Innovative methods for levee rehabilitation | |
CN102425179B (en) | Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240731 Address after: 230000 b-1018, Woye Garden commercial office building, 81 Ganquan Road, Shushan District, Hefei City, Anhui Province Patentee after: HEFEI WISDOM DRAGON MACHINERY DESIGN Co.,Ltd. Country or region after: China Address before: 443002 No. 8, University Road, Xiling District, Yichang, Hubei Patentee before: CHINA THREE GORGES University Country or region before: China |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20241223 Address after: Store 7, Building 2, Phase 1, Mengxi Sunshine Lishe B Area, Haibowan District, Wuhai City, Inner Mongolia Autonomous Region 016000 Patentee after: Inner Mongolia Youyuan Construction Engineering Co.,Ltd. Country or region after: China Address before: 230000 b-1018, Woye Garden commercial office building, 81 Ganquan Road, Shushan District, Hefei City, Anhui Province Patentee before: HEFEI WISDOM DRAGON MACHINERY DESIGN Co.,Ltd. Country or region before: China |
|
TR01 | Transfer of patent right |