CN109881659A - A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability - Google Patents

A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability Download PDF

Info

Publication number
CN109881659A
CN109881659A CN201910239761.5A CN201910239761A CN109881659A CN 109881659 A CN109881659 A CN 109881659A CN 201910239761 A CN201910239761 A CN 201910239761A CN 109881659 A CN109881659 A CN 109881659A
Authority
CN
China
Prior art keywords
foundation
pipe pile
steel pipe
offshore wind
protection against
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910239761.5A
Other languages
Chinese (zh)
Inventor
戴国亮
高鲁超
万志辉
龚维明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201910239761.5A priority Critical patent/CN109881659A/en
Publication of CN109881659A publication Critical patent/CN109881659A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability, belongs to marine wind electric field field of foundation treatment.This method mainly includes building stabilization zone, bed course and scour protection layer, and the preferred the method for mixing cement and soil into pile of reinforcement means, bed course and scour protection layer use jackstone method;The vertical equal length of cement mixing pile or elongated degree arrangement, horizontal direction have a variety of arrangement forms such as radiant type, circular ring type;By pile peripheral earth property, suitable foundation stabilization range B and reinforcement depth H is determined;Top is laid with bed course and scour protection layer, has certain protection against erosion ability.Offshore wind power foundation reinforcement means provided by the invention can be effectively improved shallow-layer soil body physico mechanical characteristic, increase resistance of soil, achieve the purpose that improve pile foundation level bearing capacity, reduce foundation pile horizontal displacement and reduce engineering cost.

Description

A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability
Technical field
The invention belongs to soft clay area stiffening basic ground fields under complicated marine environment, and in particular to one kind has erosion control The offshore wind farm steel pipe pile foundation foundation reinforcement method of brush ability.
Background technique
Large diameter steel pipe pile foundation is a kind of offshore wind farm facility protection against erosion commonly base form, in complicated marine environment Under, the influence of the factors such as wind-engaging, wave, stream causes steel pipe pile foundation to generate biggish horizontal bearing capacity and horizontal displacement, in threat The safety of portion's blower.Large diameter steel pipe pile cost of manufacture is higher, and construction technology, construction equipment are more demanding in addition, constrains sea The development of upper wind-powered electricity generation industry.Pile foundation level bearer properties are affected by the shallow-layer soil body, are controlled by top Pile side soil body drag, shallowly For layer soil body mostly based on mud, silt, soil property is relatively poor.It is improved in Practical Project by using the method for increasing stake diameter Pile foundation level bearing capacity, causes steel-pipe pile cost of manufacture to increase, and difficulty of construction improves significantly.
Therefore, steel-pipe pile horizontal bearing characteristic how is effectively improved, engineering cost is reduced, is a problem to be solved.
Summary of the invention
To solve the above problems, the invention discloses a kind of offshore wind farm steel pipe pile foundation ground with protection against erosion ability Reinforcement means can effectively improve pile foundation level bearing capacity, reduce pile foundation level displacement by improving pile peripheral earth characteristic.
In order to achieve the above objectives, technical scheme is as follows:
A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability, comprising the following steps:
(1) before foundation stabilization, by live coring and laboratory test, soil cement physico mechanical characteristic is determined, and then determine cement The parameter of mixing pile;
(2) stabilization zone is built up on the outside of steel-pipe pile,
(3) bed course and scour protection layer are laid on stabilization zone top using jackstone method;
(4) power transmission cable protective layer is constructed.
Further, laboratory test described in step (1) includes unconfined compression strength test, triaxial consolidation not Drainage Shear Cut test, conventional one-dimensional consolidation test, specific gravity test, water content test, liquid model limitation test etc.;Determined mechanics index of physics packet Include unconfined compressive strength value, Shear Strength Index, compression modulus, soil cement severe, relative density, infiltration coefficient, Atterberg Limit Deng.
Further, step (2) combines factors, the stabilization zones such as geological conditions, the construction equipment condition of steel-pipe pile preferentially to adopt Use Deep Mixing Method.
Further, step (2) bed course uses cobble, rubble or the broken concrete of 1-5cm.
Further, step (2) scour protection layer uses the block stone or concrete block of 10-50cm.
Further, one layer of geotextiles are laid between step (2) bed course and scour protection layer.
Further, reserved cable installation seam when upper protective layer is washed away in step (4) laying, after cable installation, Protective layer is filled in the installation is stitched.
A kind of offshore wind farm steel pipe pile foundation ground with protection against erosion ability, including stabilization zone, bed course and scour protection Layer three parts;Pile foundation level bearing capacity is improved for improving Pile side soil bulk properties in stabilization zone;Bed course and scour protection layer play anti- Souring, the stabilization zone are arranged on the outside of steel pipe pile foundation, and stabilization zone top is laid with bed course and scour protection layer.
Further, determine reinforcing scope: steel-pipe pile stake diameter be D, stabilization zone depth H be 3 ~ 4D, reinforce sector width B be 5 ~ 10D;Vertical reinforcement form is equal length or becomes length fashion, and horizontal direction reinforcement form has the forms such as radiant type or circular ring type.
The beneficial effects of the present invention are:
A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability of the present invention, pile peripheral earth support Anti- pile foundation level bearing capacity plays an important role, and consolidated subsoil soil can improve the physico mechanical characteristic of foundation soil, improves steel pipe Stake horizontal bearing capacity, reduces steel-pipe pile horizontal distortion;It can reduce offshore wind farm engineering cost, improve engineering efficiency, it is ensured that wind Machine whole structural stability.
Detailed description of the invention
Fig. 1 is sectional view of the invention.
Fig. 2 is the top view of the first arrangement form (radiant type) of cement mixing pile.
Fig. 3 is the top view of second of arrangement form of cement mixing pile (circular ring type).
Specific embodiment
With reference to the accompanying drawings and detailed description, the present invention is furture elucidated, it should be understood that following specific embodiments are only For illustrating the present invention rather than limiting the scope of the invention.
As shown in Figure 1, the present invention devises a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method, including reinforce 4 three parts of area 2, bed course 3 and scour protection floor;Wherein, stabilization zone is vertically equal length or elongated degree arrangement, and reinforcement depth H is 3 ~ 4D, reinforcing width B are 5 ~ 10D, and D is 1 diameter of steel-pipe pile;Stabilization zone top is followed successively by bed course 3 and scour protection layer 4.
As shown in Figure 1, cobble, rubble or broken concrete of the bed course 3 using 1-5cm, erosion control brush layer 4 use 10-50cm Stone or concrete block, 4 thickness of erosion control brush layer be greater than 3 thickness of bed course;It is laid with reserved cable installation seam when protective layer, to electricity After cable installation, protective layer is filled in the installation is stitched.
Such as the arrangement form that Fig. 2 to Fig. 3 is cement mixing method, respectively radiant type and circular ring type;It needs to carry out before reinforcing Laboratory test determines the cement mixed ratio, the ratio of mud, grouting pressure of cement mixing pile using the mechanics index of physics of soil cement Etc. parameters.Wherein, laboratory test includes unconfined compression strength test, triaxial consolidation undrained shear test, routinely unidirectionally consolidates Tie test, specific gravity test, water ratio test, liquid model limitation test etc..
According to marine environment feature and water level depth, suitable cement mixing pile workboat and construction machinery are selected;It is adjacent Mixing pile uses mutual lap joint form, determines the suitable lap of splice.
The technical means disclosed in the embodiments of the present invention is not limited only to technological means disclosed in above embodiment, further includes Technical solution composed by arbitrarily being improved by the above technical characteristic.

Claims (9)

1. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability, it is characterised in that: including following Step:
(1) before foundation stabilization, by live coring and laboratory test, soil cement physico mechanical characteristic is determined, and then determine cement The parameter of mixing pile;
(2) round stabilization zone is built up on the outside of steel-pipe pile,
(3) bed course and scour protection layer are laid on stabilization zone top using jackstone method;
(4) power transmission cable protective layer is preset on scour protection layer.
2. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: laboratory test described in step (1) includes unconfined compression strength test, triaxial consolidation undrained shear examination It tests, conventional one-dimensional consolidation test, specific gravity test, water content test, liquid model limitation test;Determined mechanics index of physics includes no side Limit compression strength value, Shear Strength Index, compression modulus, soil cement severe, relative density, infiltration coefficient, Atterberg Limit.
3. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: step (2) combines the geological conditions of steel-pipe pile, construction equipment condition, stabilization zone uses Deep Mixing Method.
4. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: step (2) bed course uses cobble, rubble or the broken concrete of 1-5cm.
5. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: step (2) scour protection layer uses the block stone or concrete block of 10-50cm.
6. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: being laid with one layer of geotextiles between step (2) bed course and scour protection layer.
7. a kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability according to claim 1, It is characterized by: step (4) is laid with reserved cable installation seam when top scour protection layer, after cable installation, described Interior fill concrete protective layer is stitched in installation.
8. a kind of offshore wind farm steel pipe pile foundation ground with protection against erosion ability, it is characterised in that: including stabilization zone, bed course and Scour protection layer three parts;The stabilization zone is arranged on the outside of steel pipe pile foundation, and stabilization zone top is laid with bed course and scour protection Layer.
9. a kind of offshore wind farm steel pipe pile foundation ground with protection against erosion ability according to claim 8, feature exist In: stabilization zone depth is 3-4 times of steel-pipe pile stake diameter, reinforces 5-10 times that sector width is steel-pipe pile stake diameter;Vertical reinforcement form For equal length or become length fashion, horizontal direction reinforcement form has radiant type or circular ring type form.
CN201910239761.5A 2019-03-27 2019-03-27 A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability Pending CN109881659A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910239761.5A CN109881659A (en) 2019-03-27 2019-03-27 A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910239761.5A CN109881659A (en) 2019-03-27 2019-03-27 A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability

Publications (1)

Publication Number Publication Date
CN109881659A true CN109881659A (en) 2019-06-14

Family

ID=66934780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910239761.5A Pending CN109881659A (en) 2019-03-27 2019-03-27 A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability

Country Status (1)

Country Link
CN (1) CN109881659A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110439020A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with sand pile reinforcing ground
CN110439023A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with foundation reinforcement high pressure grouting pile
CN110439021A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with Reinforcement with Cement-mixed Piles ground
CN110439022A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with compacting grouting and reinforcing ground
CN110512638A (en) * 2019-08-27 2019-11-29 东南大学 Offshore wind farm steel pipe pile foundation Anti-scouring structure and its construction method
CN112663668A (en) * 2021-01-15 2021-04-16 中国能源建设集团浙江省电力设计院有限公司 Disc type composite single-pile fan foundation suitable for soft soil seabed and construction method
CN112814008A (en) * 2021-02-09 2021-05-18 中交路桥建设有限公司 Steel pipe pile structure of steel box girder and construction method
CN113174990A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile
CN113175004A (en) * 2021-04-25 2021-07-27 中国长江三峡集团有限公司 Anti-scouring device and method for offshore wind power single-pile foundation
CN113174992A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile
CN113718820A (en) * 2021-08-20 2021-11-30 都城伟业集团有限公司 Offshore wind power steel pipe pile combined reinforcing device and reinforcing method
WO2022037707A1 (en) * 2021-03-08 2022-02-24 中国长江三峡集团有限公司 Monopile foundation using cemented vibroflotation pile to reinforce soft soil foundation for use in offshore wind power generation, and construction method
CN114753414A (en) * 2022-04-13 2022-07-15 中交三航局第三工程有限公司 Intelligent anti-scouring device and method for annular grid type fluidized soil steel pipe pile

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5729726A (en) * 1980-07-31 1982-02-17 Nippon Kokan Kk <Nkk> Filling method for space below foundation
CN101838996A (en) * 2010-05-17 2010-09-22 中国海洋石油总公司 Sea gravity type pile foundation combined fan foundation
CN103835306A (en) * 2014-03-13 2014-06-04 中国水电顾问集团中南勘测设计研究院有限公司 Draught fan foundation applicable to liquefaction soft foundation and construction method thereof
CN104480961A (en) * 2014-11-19 2015-04-01 华电重工股份有限公司 Anti-scouring construction method for single-pile foundations of offshore wind power
CN106013204A (en) * 2016-05-30 2016-10-12 上海电力设计院有限公司 Method for applying gravity-type foundation to offshore wind power engineering in sea area with soft-soil seabed

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5729726A (en) * 1980-07-31 1982-02-17 Nippon Kokan Kk <Nkk> Filling method for space below foundation
CN101838996A (en) * 2010-05-17 2010-09-22 中国海洋石油总公司 Sea gravity type pile foundation combined fan foundation
CN103835306A (en) * 2014-03-13 2014-06-04 中国水电顾问集团中南勘测设计研究院有限公司 Draught fan foundation applicable to liquefaction soft foundation and construction method thereof
CN104480961A (en) * 2014-11-19 2015-04-01 华电重工股份有限公司 Anti-scouring construction method for single-pile foundations of offshore wind power
CN106013204A (en) * 2016-05-30 2016-10-12 上海电力设计院有限公司 Method for applying gravity-type foundation to offshore wind power engineering in sea area with soft-soil seabed

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110439023A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with foundation reinforcement high pressure grouting pile
CN110439021A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with Reinforcement with Cement-mixed Piles ground
CN110439022A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with compacting grouting and reinforcing ground
CN110439020A (en) * 2019-08-22 2019-11-12 上海勘测设计研究院有限公司 Marine single-pile foundation with sand pile reinforcing ground
CN110512638A (en) * 2019-08-27 2019-11-29 东南大学 Offshore wind farm steel pipe pile foundation Anti-scouring structure and its construction method
CN112663668A (en) * 2021-01-15 2021-04-16 中国能源建设集团浙江省电力设计院有限公司 Disc type composite single-pile fan foundation suitable for soft soil seabed and construction method
CN112814008A (en) * 2021-02-09 2021-05-18 中交路桥建设有限公司 Steel pipe pile structure of steel box girder and construction method
WO2022037707A1 (en) * 2021-03-08 2022-02-24 中国长江三峡集团有限公司 Monopile foundation using cemented vibroflotation pile to reinforce soft soil foundation for use in offshore wind power generation, and construction method
GB2609841B (en) * 2021-03-08 2024-04-03 China Three Gorges Corp Monopile foundation using cemented vibroflotation pile to reinforce soft soil foundation for use in offshore wind power generation, and construction method
GB2609841A (en) * 2021-03-08 2023-02-15 China Three Gorges Corp Monopile foundation using cemented vibroflotation pile to reinforce soft soil foundation for use in offshore wind power generation, and construction method
CN113175004A (en) * 2021-04-25 2021-07-27 中国长江三峡集团有限公司 Anti-scouring device and method for offshore wind power single-pile foundation
CN113175004B (en) * 2021-04-25 2022-06-07 中国长江三峡集团有限公司 Anti-scouring device and method for offshore wind power single-pile foundation
CN113174992A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Comprehensive treatment and reinforcement method for collapse of stratum around marine deep-water inclined pile
CN113174990B (en) * 2021-04-29 2023-05-23 福建永强岩土股份有限公司 Rotary spraying reinforcement method for pile periphery collapse foundation of ocean deep water inclined pile
CN113174990A (en) * 2021-04-29 2021-07-27 福建永强岩土股份有限公司 Rotary spraying reinforcement method for foundation around subsidence of ocean deep water inclined pile
CN113718820A (en) * 2021-08-20 2021-11-30 都城伟业集团有限公司 Offshore wind power steel pipe pile combined reinforcing device and reinforcing method
CN114753414A (en) * 2022-04-13 2022-07-15 中交三航局第三工程有限公司 Intelligent anti-scouring device and method for annular grid type fluidized soil steel pipe pile
CN114753414B (en) * 2022-04-13 2023-07-14 中交三航局第三工程有限公司 Intelligent anti-scouring device and method for annular grid type fluidized soil steel pipe pile

Similar Documents

Publication Publication Date Title
CN109881659A (en) A kind of offshore wind farm steel pipe pile foundation foundation reinforcement method with protection against erosion ability
CN107938676B (en) Pile foundation construction method for penetrating through full-filling karst cave
CN101250868B (en) Precipitation prepressing association motive power induration deep densification method
CN108560542B (en) Waste tire coated building slag bidirectional reinforcement and construction method thereof
CN101634143A (en) Method for treating spiral oil-extruding filling pile composite foundation in stratum containing soft clay
CN105464074B (en) A kind of artificial digging pile high polymer grouting safeguard structure and its construction method
CN203393530U (en) Anti-floating lightweight high-fill embankment structure
CN105200973A (en) Comprehensive treatment method of soft foundation
CN105735232A (en) Collapsible loess wellpoint presoaking dynamic compaction replacement method
CN109853608A (en) A kind of offshore wind turbine gravity type foundation composite foundation and its processing method
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN110453699B (en) Drainage slide-resistant pile structure of &#39;rice&#39; -shaped pile core and construction method thereof
CN114045808A (en) Deep soft soil foundation reinforcement treatment structure formed by combining concrete lattice walls and discrete material piles and construction method
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN117574504A (en) Reinforced parameter determination method for expansive soil cut slope flexible supporting structure
CN209652954U (en) GCL bentonite waterproof pad combines TGXG grouting water-tight and reinforces powdery soil slope
CN217378957U (en) Miniature pile supporting arrangement structure for reinforcing slag pile body side slope
CN116289862A (en) Construction method of soft soil vibroflotation gravel pile composite foundation with upper open mountain layer and lower horizontal soft soil
CN100396854C (en) Column-hammer strong-tamper displacing base kit supporting construction method
CN215976663U (en) Excavation area composite foundation treatment structure crossing under high-voltage line
CN113863076B (en) Sinking road construction method under sand bridge
CN103015438A (en) Collapsible loess subgrade landslide treatment method
CN206052770U (en) A kind of use cast-in-situ bored pile combines the retaining wall of compaction grouting
CN213926284U (en) Foundation pit supporting and foundation treatment synergistic structure
CN212248171U (en) Offshore artificial island structure suitable for silt foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190614

RJ01 Rejection of invention patent application after publication