CN113379195A - Management system of project under construction based on wisdom building - Google Patents

Management system of project under construction based on wisdom building Download PDF

Info

Publication number
CN113379195A
CN113379195A CN202110528441.9A CN202110528441A CN113379195A CN 113379195 A CN113379195 A CN 113379195A CN 202110528441 A CN202110528441 A CN 202110528441A CN 113379195 A CN113379195 A CN 113379195A
Authority
CN
China
Prior art keywords
task
project
management
construction
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110528441.9A
Other languages
Chinese (zh)
Inventor
王建杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Intelligent Building Research Institute Co ltd
Original Assignee
Nanjing Intelligent Building Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Intelligent Building Research Institute Co ltd filed Critical Nanjing Intelligent Building Research Institute Co ltd
Priority to CN202110528441.9A priority Critical patent/CN113379195A/en
Publication of CN113379195A publication Critical patent/CN113379195A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063114Status monitoring or status determination for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a management system of a project under construction based on an intelligent building, which comprises a basic capability layer, a business association layer and a management layer under construction, wherein the basic capability layer is used for managing basic data including users, project data and archive data in the system, the business association layer accesses the data of the basic capability layer and associates the newly-built data with the existing data in the basic capability layer, and the management layer under construction is used for managing construction planning tasks and tracking progress. The invention has simple structure and convenient operation, reduces the labor intensity and improves the working efficiency.

Description

Management system of project under construction based on wisdom building
Technical Field
The invention belongs to the technical field of intelligent buildings, and particularly relates to a management system for projects under construction based on an intelligent building.
Background
The project management system under construction on the market at present mainly comprises the following functions: setting up management, and creating a management project; managing drawings, namely managing the drawings required in construction; contract management, which manages various contracts used in construction; managing progress, namely managing the completion condition of the construction task; fund management, namely managing the investment condition of construction fund; monitoring quality, and managing construction safety quality; a user of the system inputs information into the system through the modules, and then the system can manage the input information so as to realize real-time follow-up and data management of project construction conditions.
Currently, like products do not perform deep management on recorded information content, and only process data from a single module view angle after data is recorded in each module, for example: the general project management platform can input a construction responsible person in a project and can also input a contact person in unit management, but if the construction responsible person is an existing user in a unit and the user is also responsible for other projects, the system cannot know the project and the management view angle is narrow. Meanwhile, the existing products are provided for a single project management enterprise to manage own projects, and the purpose of simultaneously managing all projects in the park for the view of the park party cannot be achieved.
The problems existing in the prior art are as follows: the prior art is mainly used for recording construction project information and reprocessing recorded information, but the mutual relation among the information is not reflected, the recorded data is inconsistent before and after the information is used inevitably, the inconsistent condition is difficult to verify, and meanwhile, the existing similar technology is oriented to a construction manager and lacks an intelligent system for managing a park in a macroscopic view.
Disclosure of Invention
The invention aims to provide a management system for a project under construction based on an intelligent building, which is simple in structure and convenient to operate.
The invention provides the following technical scheme: a management system of a project under construction based on an intelligent building comprises a basic capability layer, a business association layer and a management layer under construction, wherein the basic capability layer is used for managing basic data including users, project data and archive materials, the business association layer accesses the data of the basic capability layer and associates newly-built data with existing data in the basic capability layer, and the management layer under construction is used for managing construction planning tasks and tracking progress.
Preferably, the basic capability layer includes a system management module and a profile management module, the system management module is used for creating new users, recording units and departments to which each person belongs, and limiting data permissions of the users, and the profile management module is used for managing related data of the engineering project.
Preferably, the system management module comprises an organization management unit, a personnel management unit and a role management unit, wherein the organization management unit is used for creating units and departments, the personnel management unit is used for creating platform users, all the users must belong to an organization, and the role management unit is used for managing the functional authority of the users; the file management module comprises a contract center and a data center and is used for carrying out classified management on all contracts and other data of the engineering project.
Preferably, the business association layer comprises a project management module, and the project management module is used for creating a project, associating the project with a personnel file created in the system, and managing a construction plan of the project.
Preferably, the project management module comprises a project creating unit, a mission plan creating unit and an association module, the association module comprises a profile association unit and a user association unit, and the association module realizes information interaction between a basic capability layer and a business association layer.
Preferably, the under-construction management layer comprises a task management module and a progress tracking module, wherein the task management module is used for managing the construction task plan, and the progress tracking module is used for tracking the evolution of the construction task.
Preferably, the task management module comprises a task approval unit, a task change unit and a task acceptance unit, and is used for respectively approving, changing and accepting the construction task plan, and the progress tracking module is used for managing and tracking the construction task plan and synchronizing information into the system in time when the construction task is completed, accepted or changed.
Preferably, the organization recorded into the system in the organization management unit must provide a uniform credit code and can be created in the system only by auditing under a line, and the organization management unit can be divided into 6 levels at most, and the first level of the organization is a unit; one user in the role management unit has at most ten roles, and the union of the functional authorities of all the roles is used as the real functional authority of the user.
Preferably, the construction plan task management comprises the following steps:
a1, creating a new task by the user in the project management module;
a2, if the created new task passes the audit of the task audit module, the progress tracking module tracks the progress of the task; if the created new task does not pass the audit, the new task is resubmitted after the relevant materials are supplemented;
a3, submitting and checking the completed task, and withdrawing the check when the task is in a state to be checked; if the submitted acceptance task fails to be accepted, the acceptance task needs to be improved and then submitted again; if the acceptance passes, the acceptance is finished;
a4, when the construction planning tasks of the proceeding stage, the stage to be checked and accepted and the checking and accepting completion stage are changed, repeating the steps A1-A3.
Preferably, the association of the newly created project with the personnel records already created in the system and the management of the construction plan of the project comprise the following working steps:
b1, logging in the system by the user;
b2, if a new organization and a user need to be created, entering a system management module to create an organization user, then adding an administrator, and associating the newly added administrator with the existing project in the system by the user association unit; if a new project needs to be created, entering a project management module to create the new project, then tracking the project progress by a progress tracking module, and associating relevant contracts and other materials in a file management module with the project by a file association module;
and B3, entering a task management module to examine, approve, change and check the construction plan task, and tracking the construction plan task by a progress tracking module.
The invention has the beneficial effects that:
1. the invention carries out standardized management on all assets, behaviors and seniors related to the project, so that all people, events and objects in the system have uniqueness, and then establishes an association relation on the data with the uniqueness. And then, data processing is carried out, so that the data in the platform are accurate and correct, and meanwhile, deep data processing and analysis are carried out on all data transactions in the platform according to the uniqueness of the transactions. For example: while managing a project, all the persons participating in the project in the system can be known, and then the information of all the projects that the persons have been subjected to, the tasks that have been performed, the current states of the persons, the current departments of the units, and the like can be continuously checked. Therefore, the project can be controlled more clearly and accurately.
2. On the other hand, the system can clearly reflect all currently-under-construction projects of a park, each under-construction project is respectively responsible for what unit, and to what degree each project is currently developed, which related data documents are available, and the like, so that an all-around viewing angle is provided.
3. The invention can display the data which can be inquired according to the user authority, and has good protection effect on the data.
Drawings
The accompanying drawings, which are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description serve to explain the principles of the invention and not to limit the invention. In the drawings:
FIG. 1 is a diagram of the management system architecture of the present invention;
FIG. 2 is a construction planning task management flow diagram;
FIG. 3 is a flow chart of the association of the modules of the system.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments, and not all of the embodiments. Other embodiments, which can be derived by those skilled in the art from the embodiments given herein without inventive faculty, are within the scope of the invention.
The first embodiment is as follows:
as shown in the figure, the present invention provides a technical solution: a management system of project under construction based on intelligent building comprises a basic capability layer, a business association layer and a management layer under construction, wherein the basic capability layer is used for managing basic data including users, project data and archive materials in the system, the basic capability layer comprises a system management module and an archive management module, the system management module is used for creating new users, recording units and departments to which each person belongs and limiting data authority of the users, and the archive management module is used for managing related materials of project under construction;
the business association layer accesses data of the basic capability layer and associates newly-built data with existing data in the basic capability layer, the business association layer comprises a project management module, and the project management module is used for creating a project, associating the project with a personnel file created in a system and managing a construction plan of the project;
the on-building management layer is used for managing and tracking progress of the construction plan tasks, and comprises a task management module and a progress tracking module, wherein the task management module is used for managing the construction task plans, and the progress tracking module is used for tracking the evolution of the construction tasks.
Example two:
as shown in the figure, the present invention provides a technical solution: a management system of project under construction based on intelligent building comprises a basic capability layer, a business association layer and a management layer under construction, wherein the basic capability layer is used for managing basic data including users, project data and archive materials in the system, the basic capability layer comprises a system management module and an archive management module, the system management module is used for creating new users, recording units and departments to which each person belongs and limiting data authority of the users, and the archive management module is used for managing related materials of project under construction; the system management module comprises an organization management unit, a personnel management unit and a role management unit, wherein the organization management unit is used for creating units and departments, the organization management unit can be divided into 6 levels at most, the first level of the organization is the unit, the organization entering the system in the organization management unit can be created in the system only by checking under line and providing a uniform credit agency code, personnel needing to enter the system in the corresponding organization must be provided by the organization firstly, and the information can be entered into the system only after checking under line to ensure no error; the personnel management unit is used for creating platform users, all the users must belong to an organization, the role management unit is used for managing the function authorities of the users, one user in the role management unit has at most ten roles, and the union of the function authorities of all the roles is used as the real function authority of the user, so that the data safety in engineering projects is ensured. The archive management module comprises a contract center and a data center, and is used for carrying out classification management on all contracts of the engineering project and other data, wherein the other data comprise design, research, investigation and acceptance reports related to the engineering project, when materials are uploaded on the archive management module, the project needs to be marked, corresponding users can also directly submit the materials in the project, and the submitted materials can be automatically synchronized to the archive center so as to ensure that the users with access rights under the corresponding project can access the materials.
The business association layer accesses data of the basic capability layer and associates newly-created data with existing data in the basic capability layer, the management layer under construction is used for managing construction plan tasks and tracking progress, wherein a newly-created project is associated with a personnel file created in a system and a construction plan of the project is managed as shown in fig. 3, and the management comprises the following working steps:
b1, logging in the system by the user;
b2, if a new organization and a user need to be created, entering a system management module to create an organization user, then adding an administrator, and associating the newly added administrator with the existing project in the system by the user association unit; if a new project needs to be created, entering a project management module to create the new project, then tracking the project progress by a progress tracking module, and associating relevant contracts and other materials in a file management module with the project by a file association module;
b3, entering a task management module to examine, approve, change and check the construction plan task, and tracking the construction plan task by a progress tracking module;
the business association layer comprises a project management module, wherein the project management module is used for creating a project, associating the project with a personnel file created in the system and managing a construction plan of the project so as to ensure the authenticity of the project and related data; the project management module comprises a project creating unit, a task plan creating unit and an association module, the association module comprises a file association unit and a user association unit, and the association module realizes information interaction between a basic capability layer and a business association layer.
The under-construction management layer comprises a task management module and a progress tracking module, the task management module is used for managing a construction task plan, the progress tracking module is used for tracking the evolution of the construction task, the task management module comprises a task approval unit, a task change unit and a task acceptance unit, and the task approval unit, the task change unit and the task acceptance unit are respectively used for approving, changing and accepting the construction task plan, wherein the construction task management comprises the following steps:
a1, creating a new task by the user in the project management module;
a2, if the created new task passes the audit of the task audit module, the progress tracking module tracks the progress of the task; if the created new task does not pass the audit, the new task is resubmitted after the relevant materials are supplemented;
a3, submitting and checking the completed task, and withdrawing the check when the task is in a state to be checked; if the submitted acceptance task fails to be accepted, the acceptance task needs to be improved and then submitted again; if the acceptance passes, the acceptance is finished;
a4, when the construction planning tasks of the proceeding stage, the stage to be checked and accepted and the checking and accepting completion stage are changed, repeating the steps A1-A3.
The progress tracking module manages and tracks the construction task plan and synchronizes information to the system in time when the construction task is completed, accepted or changed.
The invention takes three major elements of assets, behaviors and seniority as cores, aims at the standard requirements, intelligent management and control and intelligent scheduling based on the three major elements, takes big data application as drive and takes full-process consultation as a novel working mode, comprehensively improves the informatization level of project management, realizes refined process management and precise budget management and control on the execution process of the project, effectively avoids the capital risk of excessive project cost, further thoroughly promotes the transition of enterprises from passive management to active intervention, and comprehensively improves the project management level of the enterprise and the core competitiveness of the enterprise by visual data decision.
Although the invention has been described in terms of the above specific embodiments, the inventive idea of the invention is not limited to this invention, and any modification applying the inventive idea is intended to be included in the scope of protection of the patent claims.

Claims (10)

1. The utility model provides a management system in project under construction based on wisdom building which characterized in that: the construction planning system comprises a basic capability layer, a business association layer and an under-construction management layer, wherein the basic capability layer is used for managing basic data including users, project data and archive data in the system, the business association layer accesses the data of the basic capability layer and associates newly-built data with existing data in the basic capability layer, and the under-construction management layer is used for managing construction planning tasks and tracking progress.
2. The system of claim 1, wherein the system comprises: the basic capability layer comprises a system management module and a file management module, wherein the system management module is used for creating new users, recording units and departments to which each person belongs and limiting data authority of the users, and the file management module is used for managing related data of engineering projects.
3. The system of claim 2, wherein the system comprises: the system management module comprises an organization management unit, a personnel management unit and a role management unit, wherein the organization management unit is used for creating units and departments, the personnel management unit is used for creating platform users, all the users must belong to an organization, and the role management unit is used for managing the functional authority of the users; the file management module comprises a contract center and a data center and is used for carrying out classified management on all contracts and other data of the engineering project.
4. The system of claim 1, wherein the system comprises: the business association layer comprises a project management module, and the project management module is used for creating a project, associating the project with a personnel file created in the system and managing a construction plan of the project.
5. The system of claim 4, wherein the system comprises: the project management module comprises a project creating unit, a task plan creating unit and an association module, the association module comprises a file association unit and a user association unit, and the association module realizes information interaction between a basic capability layer and a business association layer.
6. The system of claim 1, wherein the system comprises: the under-construction management layer comprises a task management module and a progress tracking module, wherein the task management module is used for managing a construction task plan, and the progress tracking module is used for tracking the evolution of the construction task.
7. The system of claim 6, wherein the system comprises: the task management module comprises a task approval unit, a task change unit and a task acceptance unit and is used for respectively approving, changing and accepting the construction task plan, and the progress tracking module is used for managing and tracking the construction task plan and synchronizing information into the system in time when the construction task is completed, accepted or changed.
8. The system of claim 3, wherein the system comprises: the organization which is input into the system in the organization management unit must provide a uniform credit agency code and can be established in the system only by auditing under a line, the organization management unit can be divided into 6 levels at most, and the first level of the organization is a unit; one user in the role management unit has at most ten roles, and the union of the functional authorities of all the roles is used as the real functional authority of the user.
9. The intelligent building-based project under construction management system of claim 6, wherein the construction planning task management comprises the following steps:
a1, creating a new task by the user in the project management module;
a2, if the created new task passes the audit of the task audit module, the progress tracking module tracks the progress of the task; if the created new task does not pass the audit, the new task is resubmitted after the relevant materials are supplemented;
a3, submitting and checking the completed task, and withdrawing the check when the task is in a state to be checked; if the submitted acceptance task fails to be accepted, the acceptance task needs to be improved and then submitted again; if the acceptance passes, the acceptance is finished;
a4, when the construction planning tasks of the proceeding stage, the stage to be checked and accepted and the checking and accepting completion stage are changed, repeating the steps A1-A3.
10. The intelligent building-based project under construction management system of claim 4, wherein the association of the newly created project with the personnel files already created in the system for managing the project construction plan comprises the following steps:
b1, logging in the system by the user;
b2, if a new organization and a user need to be created, entering a system management module to create an organization user, then adding an administrator, and associating the newly added administrator with the existing project in the system by the user association unit; if a new project needs to be created, entering a project management module to create the new project, then tracking the project progress by a progress tracking module, and associating relevant contracts and other materials in a file management module with the project by a file association module;
and B3, entering a task management module to examine, approve, change and check the construction plan task, and tracking the construction plan task by a progress tracking module.
CN202110528441.9A 2021-05-14 2021-05-14 Management system of project under construction based on wisdom building Pending CN113379195A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110528441.9A CN113379195A (en) 2021-05-14 2021-05-14 Management system of project under construction based on wisdom building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110528441.9A CN113379195A (en) 2021-05-14 2021-05-14 Management system of project under construction based on wisdom building

Publications (1)

Publication Number Publication Date
CN113379195A true CN113379195A (en) 2021-09-10

Family

ID=77570952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110528441.9A Pending CN113379195A (en) 2021-05-14 2021-05-14 Management system of project under construction based on wisdom building

Country Status (1)

Country Link
CN (1) CN113379195A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103136618A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for project progress plan
CN107291330A (en) * 2016-06-13 2017-10-24 湖南鸿扬家网电子商务有限公司 A kind of construction project supervising device and its method
CN107506898A (en) * 2017-07-28 2017-12-22 山东科技大学 A kind of ecological management project information dynamic management system and method
CN108446895A (en) * 2018-03-26 2018-08-24 郑州大学 A kind of engineering construction project intelligent management system
CN109840737A (en) * 2018-12-29 2019-06-04 武汉神谕科技有限公司 A kind of mine materials management system
CN110598298A (en) * 2019-09-04 2019-12-20 北京华科软科技有限公司 Design and construction integrated visual management working platform based on BIM
CN111144836A (en) * 2019-12-12 2020-05-12 中建八局第二建设有限公司 Smart building integrated collaborative big data platform
CN111815168A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project quality management system
CN111950975A (en) * 2020-07-08 2020-11-17 广州中建亿信科技有限公司 BIM technology-based multi-organization coordination management cloud platform for construction engineering project
CN212569860U (en) * 2020-03-03 2021-02-19 河北建设集团股份有限公司 Construction progress management system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103136618A (en) * 2011-11-29 2013-06-05 北京建龙重工集团有限公司 On-line management method for project progress plan
CN107291330A (en) * 2016-06-13 2017-10-24 湖南鸿扬家网电子商务有限公司 A kind of construction project supervising device and its method
CN107506898A (en) * 2017-07-28 2017-12-22 山东科技大学 A kind of ecological management project information dynamic management system and method
CN108446895A (en) * 2018-03-26 2018-08-24 郑州大学 A kind of engineering construction project intelligent management system
CN109840737A (en) * 2018-12-29 2019-06-04 武汉神谕科技有限公司 A kind of mine materials management system
CN110598298A (en) * 2019-09-04 2019-12-20 北京华科软科技有限公司 Design and construction integrated visual management working platform based on BIM
CN111144836A (en) * 2019-12-12 2020-05-12 中建八局第二建设有限公司 Smart building integrated collaborative big data platform
CN212569860U (en) * 2020-03-03 2021-02-19 河北建设集团股份有限公司 Construction progress management system
CN111950975A (en) * 2020-07-08 2020-11-17 广州中建亿信科技有限公司 BIM technology-based multi-organization coordination management cloud platform for construction engineering project
CN111815168A (en) * 2020-07-09 2020-10-23 北京中百信信息技术股份有限公司 Information system engineering supervision project quality management system

Similar Documents

Publication Publication Date Title
US20190220936A1 (en) Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN104992308A (en) Enterprise informatization management system
CN102096886A (en) Credit levying business system
CN111898853A (en) Engineering construction fine management system
CN110223048A (en) Special fund declares comprehensive management platform system
CN113487172A (en) Project supervision method
Guo et al. Research and design of electric power engineering project management system bsed on blockchain technology
Murpratiwi et al. Design of Enterprise Information System with TOGAF Framework (Case Study: STD Bali)
RU2480830C2 (en) Method for automated data processing for making managerial decisions on project or project portfolio
CN112991121A (en) Information-based construction management system and method for colleges and universities
CN102096855A (en) Method for business processing before credit granting based on credit checking and granting business system
CN116739208A (en) Unified management system for power supply service
CN113379195A (en) Management system of project under construction based on wisdom building
CN110826923A (en) Enterprise management comprehensive evaluation system
CN102063688A (en) Mechanism credit providing business processing method based on credit investigating and providing business system
CN109377155A (en) The loan information measures and procedures for the examination and approval and device
Guo [Retracted] Design of University Financial Information System Based on Data Mining Technology and IoT
CN114254908A (en) Risk perception and supervision platform for regional financial non-bank financial institution
CN113554408A (en) Capital efficiency supervision big data platform
Khusna et al. Information technology governance in a sharia microfinance institution: an evaluation based on COBIT 5 framework
CN102096854A (en) Method for processing services during credit extension on the basis of levy credit extension service system
Ho et al. Establishment Process of the Secondary Development Platform of Diversified Role Management-A Study of the Cloud Building Construction Management System
CN114707964A (en) Enterprise management system
Zhang et al. Research on the Construction of Internal Control Management System with Geoscience Documentation Center. CGS as an Example
Yadav Employee leave management in SAP

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination