Summary of the invention
The object of the invention is to propose a kind of online management method of project progress plan, the method is based on a remote interaction platform, mutual and data-switching by submitting to a higher level for approval or revision between end microcomputer device, audit end microcomputer device and server end computer system has realized drafting online the tracking of project progress plan, project progress performance, reflection and the processing of project progress abnormal conditions.Issue OO operation interface by server computer system, data are stored in database server, data sharing is used the operating personnel of this interaction platform to all, by locking and authorization control operating right, controlled again version and can not arbitrarily change when guaranteeing real-time property.It is abnormal that server computer system automatic-prompting progress falls behind, and when abnormality processing was untimely, system can be core automatically to other supervisor of construction of higher one-level.
The objective of the invention is to be achieved through the following technical solutions: a kind of online management method of project progress plan, described method comprise that information acquisition is carried out in planning, plan and three parts are processed in plan execution tracking;
described planning: integrated third party's plug-in unit gantt.js does the displaying of schedule, WEB pagefile jap or jspx load the gantt.js file, utilize javaScript to trigger the update of plug-in data, the operator pulls the progress taskbar on gantt.js, promotedemote, set up operation associated after, click and preserve, page data is formed the XML form be transferred to logical layer by AJAX, logical layer becomes available form according to the XML format analysis, call the AM logic data are saved in database, planning has strict audit and lock function, when planning is completed, the responsible official will submit to a higher level for approval or revision and examine to the related personnel, when audit by the time plan to lock,
Information acquisition is carried out in described plan: comprise actual the end input on work day and the input of actual performance, design two main man-machine interfaces, for user's typing data, logic is saved in database to the information of typing, and according to business rule, the data that are associated are saved in related tables of data, realize data sharing and real-time update;
Described plan is carried out to follow the tracks of and is processed: computer system start by set date program, inspection has a few thing task, and this goes into operation, perhaps actual progress falls behind, according to the grading throw exception job information that falls behind to the related personnel, the related personnel must process this job information, at the relevant property of processing page check box, modification of schedule, plan can the automatic unlocking schedule be revised for the responsible official by system.
Purpose of the present invention can also be achieved through the following technical solutions: a kind of online management method of project progress plan, mutual personnel carry out information interchange according to a remote interaction platform, and described remote interaction platform comprises a server end computer system, submits to a higher level for approval or revision and hold microcomputer device, audit end microcomputer device; Described server end computer system, the end microcomputer device of submitting to a higher level for approval or revision, audit end microcomputer device are in a wan environment and realize that network connects, described wan environment is based on the net territory environment of INTERNET, and described server end computer system comprises database server, web application server and the software that is complementary with described server end computer system; The described end microcomputer device of submitting to a higher level for approval or revision, audit end microcomputer device mates respectively that corresponding management software is arranged; The step of described online management is:
I, draft the project progress plan
A, the project director sends an engineering project query requests by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the engineering project query requests that receives, calling the engineering of the applicable this project project of search in the engineering coded data table of AM method from described database server encodes and generates engineering coding schedule monofile, record a plurality of sub-project code in this project project in described engineering coding schedule monofile, a plurality of operational codes, described web application server sends to the described end microcomputer device of submitting to a higher level for approval or revision with described engineering coding schedule monofile,
B, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, input successively the schedule data of every operation according to the operational code in described engineering coding schedule monofile, the gantt.js plug-in unit converts the schedule data of input to the Gantt chart graph data in real time; The schedule data of every operation comprise operational code, ps, plan completion date, duration, and the linking relationship between the schedule data of every operation, the priority level of every operation are set;
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision the schedule data of every operation are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method schedule data in the XML formatted file are saved in schedule tables of data in described database server;
D, project director send the request of submitting to a higher level for approval or revision by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified schedule data from described database server, and schedule data composition XML formatted file is sent to described audit end microcomputer device;
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the schedule data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, and described web application server is called the AM method schedule tables of data in described database server is locked;
The tracking of II, project progress performance
A, project director send an engineering project query requests by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the engineering project query requests that receives, call the AM method and select qualified project progress planning data from described database server, and project progress planning data composition XML formatted file is sent to the described end microcomputer device of submitting to a higher level for approval or revision;
B, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, and input successively the actual progress data of every operation, and the gantt.js plug-in unit converts the actual progress data of input to the Gantt chart graph data in real time; The actual progress data of every operation comprise operational code, actual starting date, actual Percent Complete of current period, actual finish date;
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision the actual progress data of every operation are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method actual progress data in the XML formatted file are saved in actual progress tables of data in described database server;
D, project director hold microcomputer device to the request of submitting to a higher level for approval or revision of described web application server by described submitting to a higher level for approval or revision, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified actual progress data from described database server, and actual progress data composition XML formatted file is sent to described audit end microcomputer device;
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the actual progress data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, and described web application server is called the AM method actual progress tables of data in described database server is locked;
III, project progress abnormal response and processing
A, described web application server regularly start the project progress scrutiny program, check the actual progress abnormal conditions of every operation, namely the actual progress location point drops on the left side of check data location point in the Gantt chart graph data, sends abnormal job information to the described end microcomputer device of submitting to a higher level for approval or revision according to the abnormal alert level that arranges;
B, project director receive abnormal job information by the described end microcomputer device of submitting to a higher level for approval or revision, calling the gantt.js plug-in unit checks abnormal job information, the project director is by the described end microcomputer device input progress abnormality processing data of submitting to a higher level for approval or revision, and described progress abnormality processing data comprise the progress declaration of exception, intend treatment measures, upgrade ps, upgrade the plan completion date;
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision described progress abnormality processing data are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method progress abnormality processing data in the XML formatted file are saved in progress abnormality processing tables of data in described database server;
D, project director hold microcomputer device to the request of submitting to a higher level for approval or revision of described web application server by described submitting to a higher level for approval or revision, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified progress abnormality processing data from described database server, and progress abnormality processing data composition XML formatted file is sent to described audit end microcomputer device;
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the progress abnormality processing data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, described web application server is called the AM method ps in the schedule tables of data in described database server is revised as the renewal ps, will be revised as the plan completion date to upgrade the plan completion date.
The present invention compared with prior art has following advantage:
1, the present invention is based on a remote interaction platform, mutual and data-switching by submitting to a higher level for approval or revision between end microcomputer device, audit end microcomputer device and server end computer system has realized drafting online the tracking of project progress plan, project progress performance, reflection and the processing of project progress abnormal conditions.
2, the present invention is by the OO operation interface of server end computer system issue, data are stored in database, data sharing is used the operator of this interaction platform to all, by locking and authorization control operating right, controlled again version and can not arbitrarily change when guaranteeing real-time property.
3, the present invention is by the backward abnormal information of server end computer system automatic-prompting progress, and when untimely to the abnormal processing of progress, the server end computer system can be core automatically to other supervisor of construction of higher one-level.
4, the present invention has realized the online management of project progress, make the project progress plan establishment, examine, consult, feed back all and be achieved on the internet, business is more real-time, more convenient with urging; Guarantee simultaneously upgrading in time and sharing of project progress information, make the project progress information data more unified, more accurate.
Below in conjunction with drawings and Examples, the present invention is made a detailed description.
Embodiment
Embodiment one:
Referring to Fig. 1, the online management method of project progress plan of the present invention, described method comprise that information acquisition is carried out in planning, plan and three parts are processed in plan execution tracking;
Described planning: integrated third party's plug-in unit gantt.js does the displaying of schedule, WEB pagefile jap or jspx load the gantt.js file, utilize javaScript to trigger the update of plug-in data, when the operator pulls the progress taskbar on gantt.js, promotedemote, after setting up the operation such as association, when clicking preservation, page data is formed the XML form be transferred to logical layer by AJAX, logical foundation XML format analysis becomes available form, call the AM logic data are saved in database, planning has strict audit and lock function.When planning was completed, the responsible official will submit to a higher level for approval or revision to related personnel audit, when audit by the time plan to lock;
Information acquisition is carried out in described plan: comprise actual the end input on work day and the input of actual performance, design two main man-machine interfaces, for user's typing data, logic is saved in database to the information of typing, and according to business rule, the data that are associated are saved in related tables of data, realize data sharing and real-time update;
Described plan is carried out to follow the tracks of and is processed: computer system start by set date program, whether inspection has a few thing task, and this has gone into operation, has perhaps actual progress fallen behind? according to the grading throw exception job information that falls behind to the related personnel, the related personnel must process this job information, at the relevant property of processing page check box, modification of schedule whether, when the operator selected to be, plan can the automatic unlocking schedule be revised for the responsible official by system.
The below further describes the present embodiment:
1. schedule establishment, at a plurality of selection buttons of page setup, inquiry, interpolation task, deletion task, foundation link, cancel link, hide front forward line, hide linkage lines, confirm to submit to a higher level for approval or revision.
The button explanation:
Inquiry: press the querying condition screening after clicking.
The interpolation task: select any one engineering, can be before it after click a newly-built engineering.Select newly-built task in left side picture frame click right, in the end a newly-built engineering; As select any one engineering, click right select after newly-built task can be before it newly-built engineering.
The deletion task: select any one engineering, deletion after clicking, and message notifying " is deleted successfully ".
Preserve: preserve the schedule of establishment, after click is preserved, message notifying " is preserved successfully ".
Set up link: select wantonly two engineerings, click this button and can set up association line, the association line of foundation will meet logic.Drag between two gunter drawings, also can set up association line.As revise the progress duration, association line also will change simultaneously, and will meet logic.
Cancel link: select wantonly two engineerings, click this button and can delete association line.Also can click association line in right side gunter drawing zone, eject dialog box and revise incidence relation or association line is deleted.
Hide front forward line: click should be with progress forward line concealing or demonstration.
Hide linkage lines: click should be hidden the progress linkage lines or Display and Print: the print screen content.
Confirmation is submitted to a higher level for approval or revision: deliver person approving's examination, and can not be to submitting to a higher level for approval or revision and examining the progress gunter drawing that passes through and modify.
Drafting progress gunter drawing:
A. after entering the page, drop-down single choice select the project place company, click after project name
Button selects wish to set up the project of engineering project in selecting of ejection frame, left mouse button double-click is chosen, and then clicks inquire button.If do not work out in the past plan, below the countless certificates of left-hand line bezel, cluster, if worked out plan, below the left-hand line bezel, cluster in shown the engineering name of working out progress.If do not choose the engineering name of working out progress, click " line increment " button, can increase the blank input frame of delegation newly in list box bottom.If choose scheduling engineering name, then click " line increment ", can be at the blank input frame of the newly-increased delegation in the top of this project title.
B. double-click mouse in the blank option field of newly-increased engineering name, the engineering coding of the project division of passing through has been reported in ejection to a higher authorities for approval, and selection will be worked out the engineering coding of gunter drawing, after clicking confirmation.Add at engineering name and engineering coding automatic powder adding the data of choosing, select operational code with drop-down folk prescription formula in the operational code field, then click start time and deadline input frame, select planning start time and plan deadline in the dat frame that ejects, input at last responsible official's job number of this project title operation, if the gunter drawing of setting up is mission critical, also to choose the square frame of mission critical field, after all input is completed, left mouse button is clicked " preservation " button, has just set up data.
C. repeating step 1 and step 2 are set up the gunter drawing of all-work title, click " confirmation is submitted to a higher level for approval or revision " button and are submitted to audit screen.
Set up the connection relation:
A. after entering page queried for items, wish on the left of left mouse button is clicked is set up one of them engineering name of connection relation, pin " ctrl " key, select to set up with it another engineering name of connection relation, click " connecting " button, just set up the connection relation at the gunter drawing of two engineering names and (or clicked one of them gunter drawing, pin left mouse button, drag to wish and set up the gunter drawing of connection, also can set up the connection relation at the gunter drawing of two engineering names).
B. system is according to the gunter drawing position, the connection relation that acquiescence is set up is " beginning-beginning " and " complete-begin " two kinds of connection relations, if will revise this connection relation, namely sets up other connection relation, click the arrow of this linkage lines, modify in the modification frame that ejects.
C. repeat above step, can set up a plurality of connection relations, after foundation is completed, left mouse button is clicked " preservation " button.
Modification progress gunter drawing
If a. this schedule is not submitted to a higher level for approval or revision, during operation gunter drawing under a certain engineering name of wish deletion, select the data of this journey, click " deletion task ", then click and preserve, just the data of this journey have been deleted from schedule.
If wish increases gunter drawing, with the step of drafting progress gunter drawing.
2. information acquisition is carried out in plan, i.e. the actual beginning of engineering overall progress, deadline input;
The button explanation:
Inquiry: press the querying condition screening after clicking
Preserve: preserve the information of current input, after preserving, message notifying " is preserved successfully ".
By examining: after confirming under handler's line, the input actual date is clicked and is filed.
Input actual start time or physical end time:
A. after entering the page, drop-down single choice select the project place company, click after bullets
Button, in selection wish input actual starting date or the project on physical end date in frame selected that ejects, left mouse button double-click is chosen.After clicking inquire button, show every work data of all division engineerings of this project that the login people is responsible in the downside list.
Click after actual start time or physical end time field
Button ejects dat frame, selects Start Date or the actual target date of this operation reality, and left mouse button is clicked " preservation " button, then clicks " by audit " button, just these data has been kept in system.
3. plan is carried out to follow the tracks of and is processed, be i.e. engineering corporate plan actual performance input;
The button explanation:
Inquiry: press the querying condition screening after clicking
Preserve: preserve the information of current input, after preserving, message notifying " is preserved successfully ".
Confirmation is submitted to a higher level for approval or revision: deliver person approving's examination, and can not be to submitting to a higher level for approval or revision and examining the capable data of passing through and modify.
Input actual completion rate of current period
A. after entering the page, drop-down single choice select the project place company, click after bullets
Button, in the project of selecting the actual completion rate of wish input in frame of selecting that ejects, left mouse button double-click is chosen.After clicking inquire button, show every work data of all division engineerings of this project that the login people is responsible in the downside list.
B. input actual Percent Complete rate in field actual completing of current period, and the situation explanation that the input current period completes in the progress summary, then left mouse button click " preservation " button is clicked " confirmation is submitted to a higher level for approval or revision " button and is submitted to audit screen.
4. progress abnormal response and processing input;
The button explanation:
Inquiry: press the querying condition screening after clicking
Preserve: the information of preserving current input
Close a case: the responsible official can process according to the treatment measures of drafting according to this to not revising the abnormal of progress or contract duration, closes a case after implementing.Extremely should fall behind number of days according to progress for what need were revised progress or contract duration, be core by authority setting, check and approve and process according to handling suggestion afterwards, close a case after implementing.
Progress is submitted to a higher level for approval or revision extremely
A. after entering the page, drop-down single choice select the project place company, click after project name
Button, in the project of selecting the lander to participate in frame of selecting that ejects, left mouse button double-click is chosen, and then clicks inquire button, below the left-hand line bezel, cluster in shown that each progress of engineering that project is divided falls behind the project under construction that operation or progress fall behind.
B. choose the data line of appointing of the left list, after the analysis situation, input progress declaration of exception and plan treatment measures.Click the progress of whether revising, revise as need, after the operation that click plan is adjusted begins day or completes day field, option date.Whether click variation on contract, as the need change, click and intend the adjustment contract and complete after day field, option date.Left mouse button is clicked " preservation " button, has just completed extremely and has filed.
C. for progress fall behind number of days exceed 7 days extremely should deliver audit, input is submitted to a higher level for approval or revision after suggestion, clicks " submitting to a higher level for approval or revision " button, and these data are delivered audit.
Recall the audit of delivering:
D. after entering the page, drop-down single choice select the project place company, click after project name
Button, in the project of recalling of wanting of selecting lander's participation in frame of selecting that ejects, left mouse button double-click is chosen, and then clicks inquire button, chooses in the downside list and wants to recall abnormal data, clicks " recalling " button, and these data are recalled.Can update information after recalling and preserve.
Examine the progress abnormal data
A. after entering the page, drop-down single choice select the project place company, click project name after, the selection wish examination and approval project in frame of selecting that is ejecting, left mouse button double-click is chosen, then click inquire button, below the left-hand line bezel, cluster in shown pending trial progress fall behind the project under construction that operation or progress fall behind, after the input audit opinion, click " agreement " or " disagreeing with " button, examine this data.After selection was disagreed with, the operating personnel can update information and submit to a higher level for approval or revision.
Progress is closed a case extremely
After entering the page, drop-down single choice select the project place company, click after project name
Button, the project of selecting the lander to participate in frame of selecting that is ejecting, left mouse button double-click is chosen, then click inquire button, below the left-hand line bezel, cluster in shown that each progress of engineering that project is divided falls behind the project under construction that operation or progress fall behind, for examining the abnormal data that passes through or need not submit to a higher level for approval or revision, if implemented treatment Countermeasures, click " closing a case " button, forward these data to the backstage storage.
Embodiment two:
Referring to Fig. 2, in the present embodiment, a kind of online management method of project progress plan, mutual personnel carry out information interchange according to a remote interaction platform, and described remote interaction platform comprises a server end computer system, submits to a higher level for approval or revision and hold microcomputer device, audit end microcomputer device; Described server end computer system, the end microcomputer device of submitting to a higher level for approval or revision, audit end microcomputer device are in a wan environment and realize that network connects, described wan environment is based on the net territory environment of INTERNET, and described server end computer system comprises database server, web application server and the software that is complementary with described server end computer system; The described end microcomputer device of submitting to a higher level for approval or revision, audit end microcomputer device mates respectively that corresponding management software is arranged.
A preferred disposition of the computer installation that uses in the present embodiment, is as follows:
Server end computer system-rack-mount server:
More than CPU frequency double-core 3000 megahertzes;
More than internal memory 1G;
More than SCSI hard disk 60GB;
Network interface capabilities 1000M.
The end microcomputer device of submitting to a higher level for approval or revision:
More than CPU frequency 1500 megahertzes;
Internal memory is more than 512,000,000;
More than SATA hard disk 40GB;
Network interface capabilities 100M;
128,000,000 display cards.
Audit end microcomputer device:
More than CPU frequency 1500 megahertzes;
Internal memory is more than 512,000,000;
More than SATA hard disk 40GB;
Network interface capabilities 100M;
128,000,000 display cards.
In the present embodiment, in the described end microcomputer device of submitting to a higher level for approval or revision, audit end microcomputer device, Management of engineering schedule software is installed all, according to the login account logon server end computer system of distributing, the server end computer system is verified according to the login account number, and is given corresponding use identity and operating right.
In the present embodiment, the server end computer system designs based on multistage server architecture, has the characteristics such as across a network, distributed, dynamic equalization, data distribution, can stable operation on Windows or Linux platform, by expansion servers, allow endless user online.Because the server end computer system adopts server cluster, have the characteristics such as fault recovery, Dynamic Thermal backup, thereby can provide round-the-clock continual service for the user.
Server end computer system in the present embodiment adopts distributed server architecture, support tree type and netted two kinds of servers to set up structure, fault-tolerant by multilevel distributed master, multipoint communication service device Hot Spare, effectively avoided because of the separate unit server failure whole system that causes paralysis on structure.
Referring to Fig. 5, in the present embodiment, engineering project all is based on unified coding rule and carries out structure analysis, depth requirements according to the management and control of actual progress target, selection meets the hierarchical structure of progress control, and give unique engineering coding according to rule with each level schedule objective simultaneously, generate engineering coded data table and be saved in database server.The engineering of passing through of reporting to a higher authorities for approval that in described engineering coded data table, storage is all is encoded.The next stage of each engineering project comprises a plurality of sub-engineerings, and the next stage of every sub-engineering comprises again multi-mode operation.
Referring to Fig. 2 to Fig. 5, in the present embodiment, the step of described online management is:
I, draft the project progress plan
A, the project director sends an engineering project query requests by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the engineering project query requests that receives, calling the engineering of the applicable this project project of search in the engineering coded data table of AM method from described database server encodes and generates engineering coding schedule monofile, record a plurality of sub-project code in this project project in described engineering coding schedule monofile, a plurality of operational codes, described web application server sends to the described end microcomputer device of submitting to a higher level for approval or revision with described engineering coding schedule monofile.
In the present embodiment, described engineering project query requests is an XMLHttpRequest request that sends by the AJAX program in the end microcomputer device of submitting to a higher level for approval or revision, and is independent of browser and interaction platform; The AJAX program is a kind of for creating web application better faster and that interactivity is stronger, pass through AJAX, JavaScript can come directly and the server end computer system communicates with the XMLHttpRequest object of JavaScript, and JavaScript can be at not situation and the server end computer system swap data of the heavily loaded page.
In the present embodiment, record all engineering codings of applicable this project project in described engineering coding schedule monofile; The inquiry of described engineering project can be to inquire about by the Business Name under this project project and engineering project title.
B, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, input successively the schedule data of every operation according to the operational code in described engineering coding schedule monofile, the gantt.js plug-in unit converts the schedule data of input to the Gantt chart graph data in real time; The schedule data of every operation comprise operational code, ps, plan completion date, duration, and the linking relationship between the schedule data of every operation, the priority level of every operation are set; At first the project director selects operational code from engineering coding schedule monofile, then select input ps, plan completion date by keyboard or from the calendar list, the end microcomputer device of submitting to a higher level for approval or revision calculates the duration automatically according to ps and plan completion date.
In the present embodiment, by the gantt.js plug-in unit can input every operation the schedule data, the milestone operation is set, the priority of every operation is set, and the linking relationship between the schedule data of every operation, and show on Gantt chart.After carrying out hold-over command, can export the XML formatted file.Linking relationship between the schedule data of described every operation comprises: two operations need to go into operation simultaneously, i.e. " beginning-beginning " linking relationship; An operation could begin another operation after completing, and namely " completes-begin " linking relationship; Two operations need to be completed simultaneously, namely " complete-complete " linking relationship.
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision the schedule data of every operation are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method schedule data in the XML formatted file are saved in schedule tables of data in described database server; As shown in Figure 4.
In the present embodiment, the servlet container is a kind of java application of server end, has the characteristic that is independent of platform and agreement, can generate the dynamic Web page.It takes on the middle layer of client requests (Web browser or other Http CLIENT PROGRAM) and server response (database on the Http server or application program).
D, project director send the request of submitting to a higher level for approval or revision by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified schedule data from described database server, and schedule data composition XML formatted file is sent to described audit end microcomputer device.
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the schedule data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, and described web application server is called the AM method schedule tables of data in described database server is locked.
The tracking of II, project progress performance
A, project director send an engineering project query requests by the described end microcomputer device of submitting to a higher level for approval or revision to described web application server, servlet container in described web application server is resolved the engineering project query requests that receives, call the AM method and select qualified project progress planning data from described database server, and project progress planning data composition XML formatted file is sent to the described end microcomputer device of submitting to a higher level for approval or revision.
B, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, and input successively the actual progress data of every operation, and the gantt.js plug-in unit converts the actual progress data of input to the Gantt chart graph data in real time; The actual progress data of every operation comprise operational code, actual starting date, actual Percent Complete of current period, actual finish date.
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision the actual progress data of every operation are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method actual progress data in the XML formatted file are saved in actual progress tables of data in described database server.
D, project director hold microcomputer device to the request of submitting to a higher level for approval or revision of described web application server by described submitting to a higher level for approval or revision, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified actual progress data from described database server, and actual progress data composition XML formatted file is sent to described audit end microcomputer device.
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the actual progress data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, and described web application server is called the AM method actual progress tables of data in described database server is locked; Simultaneously, the actual progress data in the actual progress tables of data can be synchronized in the schedule tables of data.
III, project progress abnormal response and processing
A, described web application server regularly start the project progress scrutiny program, check the actual progress abnormal conditions of every operation, namely the actual progress location point drops on the left side of check data location point in the Gantt chart graph data, sends abnormal job information to the described end microcomputer device of submitting to a higher level for approval or revision according to the abnormal alert level that arranges; Can set alert level in the project progress scrutiny program, when the actual progress of operation falls behind to a certain extent, web application server can send to abnormal job information audit end microcomputer device automatically.
B, project director receive abnormal job information by the described end microcomputer device of submitting to a higher level for approval or revision, calling the gantt.js plug-in unit checks abnormal job information, the project director is by the described end microcomputer device input progress abnormality processing data of submitting to a higher level for approval or revision, and described progress abnormality processing data comprise the progress declaration of exception, intend treatment measures, upgrade ps, upgrade the plan completion date; Described abnormal job information comprises: operational code, ps, plan completion date, abnormal prompt date, not completion rate, progress abnormal cause, above-mentioned abnormal job information is provided by the server end computer system.
C, project director call the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision described progress abnormality processing data are preserved into the XML formatted file and sent to described web application server, servlet container in described web application server is resolved the XML formatted file, calls the AM method progress abnormality processing data in the XML formatted file are saved in progress abnormality processing tables of data in described database server;
D, project director hold microcomputer device to the request of submitting to a higher level for approval or revision of described web application server by described submitting to a higher level for approval or revision, servlet container in described web application server is resolved the request of submitting to a higher level for approval or revision that receives, call the AM method and select qualified progress abnormality processing data from described database server, and progress abnormality processing data composition XML formatted file is sent to described audit end microcomputer device;
E, auditor call the gantt.js plug-in unit by described audit end microcomputer device the progress abnormality processing data in the XML formatted file are examined, the auditor holds microcomputer device will examine the information of passing through by audit and sends to described web application server, described web application server is called the AM method ps in the schedule tables of data in described database server is revised as the renewal ps, will be revised as the plan completion date to upgrade the plan completion date.
Embodiment three:
The present embodiment will be made more detailed explanation to the online management step in embodiment two.
I, draft the project progress plan
Referring to Fig. 6, in the present embodiment, the project director enters by the end microcomputer device of submitting to a higher level for approval or revision the operation interface of drafting the project progress plan, and then the company at option place, project name from drop-down list are clicked inquire button the schedule data of this project are inquired about.
In the present embodiment, the project director calls the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, and clicks " interpolation operation " button, can increase delegation's space record in following data form newly.Double-click mouse in newly-increased project code hurdle, eject and reported the engineering coding that the project passed through is divided to a higher authorities for approval, selection will be worked out the engineering coding of gunter drawing.Select operational code in the mode of drop-down list in the operational code hurdle, then click ps and plan completion date input frame, select planning Start Date and plan completion date in the dat frame that ejects, input at last project director's job number of this operation, after all input is completed, click " preservation " button, just set up the schedule data of an operation.The schedule data of All Jobs are completed in input, click " confirmation is submitted to a higher level for approval or revision " button and are submitted to audit screen.
In the present embodiment, can modify or delete the schedule data of this project at any time before submitting to a higher level for approval or revision, the mode of revising has two kinds: a kind of is Update Table in data form, and another kind is directly the Gantt chart graph data on data form right side to be modified.
The tracking of II, project progress performance
Referring to Fig. 7, in the present embodiment, the project director enters the operation interface of the tracking of project progress performance by the end microcomputer device of submitting to a higher level for approval or revision, and then the company at option place, project name from drop-down list are clicked inquire button the schedule data of this project are inquired about.
In the present embodiment, the project director calls the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, the gantt.js plug-in unit loads the XML formatted file of the record project progress planning data that is sent by web application server, and the form of project progress planning data with chart is presented on the display of the end microcomputer device of submitting to a higher level for approval or revision; Click actual starting date and actual finish date input frame, select actual starting date, actual Percent Complete of current period, actual finish date in the dat frame that ejects, input at last project director's job number of this operation, after all input is completed, click " preservation " button, just set up the actual progress data of an operation.The actual progress data of All Jobs are completed in input, click " confirmation is submitted to a higher level for approval or revision " button and are submitted to audit screen.
In the present embodiment, can modify to the actual progress data of this project at any time before submitting to a higher level for approval or revision, the mode of modification has two kinds, and a kind of is Update Table in data form, and another kind is directly the Gantt chart graph data on data form right side to be modified.Actual progress data and the schedule data expression mode in Gantt chart has two kinds: a kind ofly show the schedule data with the progress bar frame table, represent the actual progress data with the progress bar that is filled in this progress bar frame; Another kind of progress bar with two kinds of different colours represents respectively schedule data and actual progress data.
III, project progress abnormal response and processing
Referring to Fig. 8, in the present embodiment, the project director enters the operation interface of project progress abnormal response and processing by the end microcomputer device of submitting to a higher level for approval or revision, and then the company at option place, project name from drop-down list are clicked inquire button the schedule data of this project are inquired about.
In the present embodiment, the project director calls the gantt.js plug-in unit by the described end microcomputer device of submitting to a higher level for approval or revision, the gantt.js plug-in unit loads the XML formatted file of the abnormal job information of record that is sent by web application server, and the form of project progress planning data with chart is presented on the display of the end microcomputer device of submitting to a higher level for approval or revision, after the project director analyzes abnormal job information, input progress declaration of exception and plan treatment measures, if the selection modification of schedule also needs input upgrade ps and upgrade the plan completion date.Input at last project director's job number of this operation, after all input is completed, click " preservation " button, just set up the progress abnormality processing data of an operation.The progress abnormality processing data of All Jobs are completed in input, click " confirmation is submitted to a higher level for approval or revision " button and are submitted to audit screen.Can modify to the progress abnormality processing data in this project at any time before submitting to a higher level for approval or revision.
In the present embodiment, the auditor holds microcomputer device to call the gantt.js plug-in unit by audit, and the gantt.js plug-in unit loads the XML formatted file of the record progress abnormality processing data that sent by web application server and shows; The auditor examines progress abnormality processing data, the input audit opinion.The audit opinion by audit will not feed back to the end microcomputer device of submitting to a higher level for approval or revision of submitting audit to, and progress abnormality processing data be updated and will submit to a higher level for approval or revision by the end microcomputer device of submitting to a higher level for approval or revision by the project director.The project director checks and writes off the progress abnormality processing data of also implementing the operation of processing by audit by the end microcomputer device of submitting to a higher level for approval or revision.