CN212569860U - Construction progress management system - Google Patents

Construction progress management system Download PDF

Info

Publication number
CN212569860U
CN212569860U CN202020244965.6U CN202020244965U CN212569860U CN 212569860 U CN212569860 U CN 212569860U CN 202020244965 U CN202020244965 U CN 202020244965U CN 212569860 U CN212569860 U CN 212569860U
Authority
CN
China
Prior art keywords
module
construction
management
project
department
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020244965.6U
Other languages
Chinese (zh)
Inventor
张硕凯
赵东
李慧龙
邢再鹏
申月月
宋金
陈小飞
王灏宸
黄兴石
王然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Construction Group Corp Ltd
Original Assignee
Hebei Construction Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Construction Group Corp Ltd filed Critical Hebei Construction Group Corp Ltd
Priority to CN202020244965.6U priority Critical patent/CN212569860U/en
Application granted granted Critical
Publication of CN212569860U publication Critical patent/CN212569860U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model relates to a construction progress management system belongs to construction control and progress management technical field. The system is divided into a system management part and a project management part according to the architecture of the system; the system management part comprises a role management module, a permission management module and a user management module; the project management part comprises a project department module, an auditing department module and a management department module; the construction progress management system is embedded in the computer and displayed through the display. The construction progress management system can ensure the continuity and the balance of construction, visually analyze the feasibility of construction design, strengthen the communication and the communication of each department, analyze the problems in construction according to the condition of construction nodes uploaded by projects, contrast the weekly plan and the monthly plan of construction progress, adjust the construction organization plan in time, meet the construction requirements and deliver the construction on time.

Description

Construction progress management system
Technical Field
The utility model relates to a construction progress management system belongs to construction control and progress management technical field.
Background
At the present stage, with the development of the building industry, construction progress management is not only the construction period control in the traditional sense, but also a series of management activities with wide related range and numerous influence factors directly influence the economic benefit and social benefit of construction enterprises. In the engineering project construction process, the actual progress of the engineering project can not be realized according to the planned progress often due to unreasonable project progress plan, untight project implementation process, lack of professional project management departments and project design change problems.
In order to solve the above problems, a real-time progress management system is needed, which improves the scientificity and coordination of the construction progress plan, controls the change of the construction progress in real time, establishes online cooperation of a plurality of departments, and further realizes the intelligent management of the construction progress.
Disclosure of Invention
The utility model aims at providing a construction progress management system solves above-mentioned technical problem.
In order to realize the purpose, the utility model discloses a technical scheme is:
a construction progress management system is divided into a system management part and a project management part according to the architecture of the system; the system management part comprises a role management module, a permission management module and a user management module; the project management part comprises a project department module, an auditing department module and a management department module; the construction progress management system is embedded in the computer and displayed through the display.
The utility model discloses technical scheme's further improvement does, project department module divide into project overview module, total progress plan module, month plan module, week plan module and real-time node module again.
The utility model discloses technical scheme's further improvement does, and the portion module of examining and verifying is divided into again and examines and verifies progress plan module and examine and verify real-time node module.
The utility model discloses technical scheme's further improvement does, and the management part module divide into view module and feedback module again.
The utility model discloses technical scheme's further improvement does, and total progress plan module, month plan module and week plan module use the Exel to formulate then upload.
A construction progress management method uses a construction progress management system; the project department, the examination department and the management department cooperate to manage the construction progress, which comprises the following contents,
(1) before the project department is constructed, making a total progress plan on a construction progress management system and uploading the total progress plan;
(2) the checking part checks the total progress plan uploaded by the project part, if the plan is reasonable, the next process is carried out, otherwise, project group planning suggestions are given;
(3) the management part receives the total progress plan for analysis, arranges the resources of each plan node through a network progress chart formed by the construction progress management system, considers the feasibility of each node and controls the construction time period of each node; feeding back the condition that each node is easy to appear and the decomposition details of each node to the item part;
(4) the project department receives the feedback given by the management department to further divide the schedule, and makes and uploads the monthly schedule and the weekly schedule;
(5) the auditing part receives the monthly plan and the weekly plan, and the feasibility of the auditing plan gives an opinion or passes;
(6) the management part receives the passed month plan and week plan and feeds back problems which are easy to appear in the construction;
(7) the project department receives the feedback given by the management department to carry out construction optimization, and the project department uploads project progress nodes in real time during construction;
(8) the real-time node uploaded by the audit department audit project department supervises the project department work and reminds the project department to carry out the next work;
(9) the management part summarizes the problems in construction according to the uploaded real-time nodes and adjusts the next working plan in time; and a project department for encouraging the completion of the construction task with high quality, rapidness, safety and civilization.
(10) And the project department receives the plan adjusted by the management department, changes the next plan and applies the next plan to construction.
Since the technical scheme is used, the utility model discloses the technological effect who gains has:
can design a construction plan on line, cooperate with multiple departments and monitor project construction nodes in real time,
1. by the project management part, the online matching and communication of multiple departments are realized, the work efficiency is improved, and the problems of complex communication and inconvenience of offline communication of the multiple departments are solved
2. Through the project department module, the scientific rationality of making the progress plan is realized, the phenomenon of excessive missing projects is avoided, and the construction plan of each node is conveniently refined. The problems that the progress planning is incomplete and discontinuous construction efficiency of the progress planning is low are solved.
3. By the audit department module and the management department module, the execution force of projects is promoted, and the trend of the development of the construction period and the construction cost are controlled. The problems of construction delay, excessive capital and resource waste are solved.
4. The utility model discloses a construction progress management system can ensure the continuity and the equilibrium of construction, and the feasibility of audio-visual analysis construction design strengthens the communication and the interchange of each department, uploads the condition of construction node according to the project, compares week plan, the month plan of construction progress, and the problem that exists in the analysis construction carries out construction organization plan through the mode of feedback readjustment, satisfies the construction requirement, delivers the use on time.
Drawings
FIG. 1 is a schematic diagram of a framework for managing modules according to the present invention;
fig. 2 is a schematic view of the flow of the cooperation between the departments of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the following drawings and specific embodiments:
the utility model discloses a construction progress management system for manage the construction, can make the construction can be fast, high-efficient, high-quality completion through continuous feedback, correction.
The construction progress management system is based on a computer, is embedded in the computer and is visually displayed through a display. Fig. 1 is a schematic diagram of the framework of the present invention. The construction progress management system is divided into a system management part and a project management part according to the architecture. The system management part comprises a role management module, a right management module and a user management module. The project management part comprises a project department module, an auditing department module and a management department module. The project department module is divided into a project overview module, a total progress planning module, a month planning module, a week planning module and a real-time node module; the auditing part module is divided into an auditing progress plan module and an auditing real-time node module; the management part module is divided into a view module and a feedback module. The auditing part module is divided into a view module and a feedback module.
The functions of the various modules are as follows:
the role management module: the method is used for creating a plurality of departments and carrying out interaction among the departments.
The authority management module: and allocating the responsibility of each department.
A user management module: and creating user information, and adding, deleting, changing and searching the user.
A project profile module: the detailed information of the project is convenient for other departments to know the project.
The overall schedule planning module: the overall schedule is made, and can be made by using Exel and then uploaded.
A month planning module: the monthly plan can be made by using Exel and then uploaded.
A week planning module: the weekly plan can be made by using Exel and then uploaded.
A real-time node module: in project construction, constructors upload according to the actual construction conditions.
An audit progress planning module: and checking the total schedule plan, the month schedule and the week schedule.
An audit real-time node module: and auditing the real-time node information uploaded by the constructor.
A view module: and viewing a network progress chart formed by the total progress plan, the month plan and the week plan, and the details of the total progress plan, the month plan and the week plan.
A feedback module: the management unit gives corresponding opinions and plans.
The system comprises a role management module, a right management module and a user management module, wherein the three functional modules are connected together to form a system management part. The system comprises a project department module, an auditing department module and a management department module, wherein the three functional modules are connected together to form a project management part. The system management part and the project management part are connected together to form a construction progress management system.
Fig. 2 is a flow of cooperation of each department in an actual application process, and a method for managing construction progress by using the construction management system includes:
(1) and the project department makes a total progress plan on the construction progress management system before construction and uploads the total progress plan.
(2) And the auditing part audits the general plan uploaded by the project part, considers that the plan is scientifically and reasonably audited to pass, and performs the next process, otherwise, provides project group planning suggestions.
(3) And the management part receives the passing schedule total plan to analyze, and arranges the resources of each schedule node through a network schedule formed by the construction schedule management system, so that the excessive concentration and resource waste at a certain schedule point are avoided. And considering the feasibility of each node, and controlling the construction time period of each node to prevent the construction period from being delayed. The condition that each node is easy to appear and the decomposition details of each node are fed back to the item part.
(4) And the project department receives the feedback given by the management department to further divide the schedule, and makes the monthly schedule and the weekly schedule for uploading.
(5) And the auditing part receives the feasibility giving opinions or passing of the monthly plan and the weekly plan for auditing the plans.
(6) And a management unit that receives the passed month plan and week plan and feeds back a problem that is likely to occur during construction.
(7) And the project department receives the feedback given by the management department to carry out construction optimization, and the project department uploads project progress nodes in real time during construction.
(8) And the real-time node uploaded by the audit part of the audit supervises the work of the project part and reminds the project part of carrying out the next work.
(9) And the management part summarizes the problems in construction according to the uploaded real-time nodes, adjusts the next working plan in time, prevents the problems of construction period delay, capital excess and the like, and encourages a project part to finish the construction task with high quality, rapidness, safety and civility.
(10) And the project department receives the plan adjusted by the management department and changes the next plan, and applies the plan to construction to ensure that the construction can be smoothly carried out and the construction is finished in the specified time limit.
According to the construction management method, through continuous auditing feedback of the auditing part and the management part, the construction is more scientific and reasonable, the construction progress is more perfect, and the construction efficiency is greatly improved.

Claims (5)

1. A construction progress management system is characterized in that: the system is divided into a system management part and a project management part according to the architecture of the system; the system management part comprises a role management module, a permission management module and a user management module; the project management part comprises a project department module, an auditing department module and a management department module; the construction progress management system is embedded in the computer and displayed through the display.
2. The construction progress management system according to claim 1, characterized in that: the project department module is divided into a project overview module, a total progress planning module, a month planning module, a week planning module and a real-time node module.
3. The construction progress management system according to claim 2, characterized in that: the auditing part module is divided into an auditing progress plan module and an auditing real-time node module.
4. A construction progress management system according to claim 3, characterized in that: the management part module is divided into a view module and a feedback module.
5. The construction progress management system according to claim 2, characterized in that: the overall schedule module, the month schedule module, and the week schedule module are formulated using Exel and then uploaded.
CN202020244965.6U 2020-03-03 2020-03-03 Construction progress management system Active CN212569860U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020244965.6U CN212569860U (en) 2020-03-03 2020-03-03 Construction progress management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020244965.6U CN212569860U (en) 2020-03-03 2020-03-03 Construction progress management system

Publications (1)

Publication Number Publication Date
CN212569860U true CN212569860U (en) 2021-02-19

Family

ID=74619566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020244965.6U Active CN212569860U (en) 2020-03-03 2020-03-03 Construction progress management system

Country Status (1)

Country Link
CN (1) CN212569860U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113379195A (en) * 2021-05-14 2021-09-10 南京智慧建筑研究院有限公司 Management system of project under construction based on wisdom building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113379195A (en) * 2021-05-14 2021-09-10 南京智慧建筑研究院有限公司 Management system of project under construction based on wisdom building

Similar Documents

Publication Publication Date Title
CN109740849A (en) Structure design work management method, platform and the system quickly delivered
CN111582728A (en) Multichannel complex building engineering dynamic management system
CN111428999A (en) Shield project construction scheduling and worker capability evaluation system
CN212569860U (en) Construction progress management system
CN102663554A (en) Procedure customization method for project management
CN115187039A (en) Construction progress management method and system based on BIM
Lapidus et al. Construction project organizational and technological parameters analysis
CN109447370B (en) Centralized safety analysis method, device and system for multi-component electric quantity decentralized transaction of multi-power plant
CN117519023A (en) Long-period plan feasibility assessment method, system, equipment and medium
CN111311196A (en) Construction progress management system and construction management method
Liu et al. Research on the application of BIM technology in the efficiency and effectiveness of construction project management
Susilo et al. The implementation of robotic process automation for banking sector case study of a private bank in Indonesia
CN113869787B (en) Engineering project comprehensive management and control and evaluation method based on information system
CN109784836A (en) A kind of cloud design and craft cooperating management platform
CN116228118A (en) Spacecraft production control method and system based on flexible workflow
CN110992001A (en) Product design process management method
CN115600968A (en) Regional industry collaborative management method for power generation enterprises
CN114298645A (en) Building decoration project building control system and method
Lawrence Resource Balance Optimization Method of Mechanical Engineering Project Considering Multi-objective Optimization
CN109816193A (en) Architectural design work management method, platform and the system quickly delivered
Lu Innovation of production scheduling and service models for cloud manufacturing of tourism equipment based on artificial intelligence
Chen et al. Analysis of the current status and comprehensive application research on BIM technology in construction cost management
CN114169918B (en) Instant cost analysis method for cement
Ma et al. Research on Financial Shared Service Mode Application for Enterprise Group from the Practice of Chongqing Branch of CCC First Highway Engineering Group
Zhao Application of integer programming in project investment