CN108446895A - A kind of engineering construction project intelligent management system - Google Patents
A kind of engineering construction project intelligent management system Download PDFInfo
- Publication number
- CN108446895A CN108446895A CN201810252305.XA CN201810252305A CN108446895A CN 108446895 A CN108446895 A CN 108446895A CN 201810252305 A CN201810252305 A CN 201810252305A CN 108446895 A CN108446895 A CN 108446895A
- Authority
- CN
- China
- Prior art keywords
- project
- engineering
- module
- management
- management module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 39
- 238000007726 management method Methods 0.000 claims abstract description 86
- 238000000034 method Methods 0.000 claims abstract description 14
- 238000012502 risk assessment Methods 0.000 claims abstract description 9
- 238000004458 analytical method Methods 0.000 claims description 8
- 238000005457 optimization Methods 0.000 claims description 3
- 238000012797 qualification Methods 0.000 claims description 3
- 238000000275 quality assurance Methods 0.000 claims description 3
- 238000004445 quantitative analysis Methods 0.000 claims description 3
- 238000013070 change management Methods 0.000 claims description 2
- 238000011156 evaluation Methods 0.000 claims 2
- 238000005516 engineering process Methods 0.000 abstract description 5
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of engineering construction project intelligent management systems of project management technical field, the system includes project information acquisition module, program assessment module, bidding management module, risk analysis module, resource management module, project tracking module, contract payment management module, engineering archive management module, project scheduling management module, project management techniques are combined by the present invention with modern information technologies, increase substantially the efficiency of management of engineering project, project manager is set easily to grasp the project progress of project, the various informations consolidated statement such as project quality and project cost, and it forms powerful background function module and supports platform, revolutionize project construction cost extensive style management status, realize the movable coordinating and unifying of project management and Efficient Operation.
Description
Technical field
The invention discloses a kind of engineering construction project intelligent management systems, specially project management technical field.
Background technology
The management of engineering project is a complexity, arduous system engineering, is related to progress, quality, investment, contract, people
Various work such as member, risk, Drawings and documents, numerous participating departments and unit so that common and coordination operational difficulties,
A large amount of information needs effective management, especially domestic three universal side engineerings to increase the difficulty of engineering management.With interconnection
The development of network technology and wireless communication technique, modern society stepped into the information age, traditional project management system,
Seem more and more painstaking, has needed to find new Method and kit for.For this purpose, we have proposed a kind of inventions to come into operation, with
It solves the above problems.
Invention content
The purpose of the present invention is to provide a kind of engineering construction project intelligent management systems, to solve in above-mentioned background technology
The problem of proposition.
To achieve the above object, the present invention provides the following technical solutions:A kind of engineering construction project intelligent management system, should
System includes project information acquisition module, program assessment module, bidding management module, risk analysis module, resource management mould
Block, project tracking module, contract payment management module, engineering archive management module, project scheduling management module;
The project information acquisition module is for being acquired and storing to the various project information in Process of Engineering Construction
Into system server;
The program assessment module passes through progress difference, expense for assessing the progress and cost of engineering project
The quantitative data that difference, schedule performance index and expense execute index carrys out objective reaction engineering general overview, is led convenient for project
It leads and administrative staff grasps project overall information;
The bidding management module be directed to the qualification of relevant bidder in engineering project, pricing system, quality assurance,
After-sale service and its history credit are examined, and are uploaded in system server;
The risk analysis module be used for during Engineering Project Construction duration and cost carry out quantitative analysis, according to
Project schedule plan and estimated cost calculate Percent Complete;
The resource management module for realizing large scale equipment, the configuration of project personnel, optimization and management, reduce equipment at
This, and control cost of human resources;
The project tracking module by being tracked by expense, project tracking, finance tracking, resource tracing holds engineering project
The project information that common during row, needs are paid special attention to collects generation and grasps overall project information convenient for project manager
Report;
The contract payment management module is used for engineering contract and progress payment in project construction process and pays work
Whole Course Management;
The engineering archive management module is used to preserve the data information in Construction Process of Engineering Project, and in system background
Chart is generated, for project management personnel's real-time query;
The project scheduling management module include the schedule in engineering project is managed, implementation plan management,
Project progress typing and checking to the engineering of implementation phase.
Preferably, the information of project information acquisition module acquisition includes that engineering drawing, work order, material requistion, construction refer to
It enables, materials warehouse information in the report of job order, project construction and engineering construction.
Preferably, the program assessment module can be generated by week, Yue Deng chronomeres and earn value analysis curve, and be had abundant
Report and data function, react assessment result from different perspectives.
Preferably, the bidding management module allows User Defined multistage bid performance assessment criteria, allows several correlations
Expert gives a mark to indices, and system summarizes the expert analysis mode summary sheet and detail list for generating bid producer automatically, in being
It marks decision and foundation is provided.
Preferably, the risk analysis module by histogram, curve graph and pie chart intuitively show PROJECT TIME and
Cost risk content.
Preferably, the contract payment management module includes bidding, engineering contract, scheduled fun application, modification of contract pipe
The contents such as reason, scheduled fun payment, engineering funds clearing and expense allocation.
Preferably, the engineering construction project management system further includes user management module, the user management module packet
Include the role of user department, the real name of user, the login account of user and password, user in engineering project.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is by project management techniques and modern information technologies
Be combined, increase substantially the efficiency of management of engineering project, enable project manager easily grasp project project progress,
The various informations consolidated statement such as project quality and project cost, and form powerful background function module and support platform, thoroughly
Project construction cost extensive style management status is changed, the movable coordinating and unifying of project management and efficiently fortune are realized
Make.
Description of the drawings
Fig. 1 is present system module map;
Fig. 2 is present system flow chart.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution:A kind of engineering construction project intelligent management system, the system
Including project information acquisition module, program assessment module, bidding management module, risk analysis module, resource management module, item
Mesh tracking module, contract payment management module, engineering archive management module, project scheduling management module;
The project information acquisition module is for being acquired and storing to the various project information in Process of Engineering Construction
Into system server;
The program assessment module passes through progress difference, expense for assessing the progress and cost of engineering project
The quantitative data that difference, schedule performance index and expense execute index carrys out objective reaction engineering general overview, is led convenient for project
It leads and administrative staff grasps project overall information;
The bidding management module be directed to the qualification of relevant bidder in engineering project, pricing system, quality assurance,
After-sale service and its history credit are examined, and are uploaded in system server;
The risk analysis module be used for during Engineering Project Construction duration and cost carry out quantitative analysis, according to
Project schedule plan and estimated cost calculate Percent Complete;
The resource management module for realizing large scale equipment, the configuration of project personnel, optimization and management, reduce equipment at
This, and control cost of human resources;
The project tracking module by being tracked by expense, project tracking, finance tracking, resource tracing holds engineering project
The project information that common during row, needs are paid special attention to collects generation and grasps overall project information convenient for project manager
Report;
The contract payment management module is used for engineering contract and progress payment in project construction process and pays work
Whole Course Management;
The engineering archive management module is used to preserve the data information in Construction Process of Engineering Project, and in system background
Chart is generated, for project management personnel's real-time query;
The project scheduling management module include the schedule in engineering project is managed, implementation plan management,
Project progress typing and checking to the engineering of implementation phase.
Wherein, the information of project information acquisition module acquisition include engineering drawing, work order, material requistion, directives for construction,
Materials warehouse information in job order, project construction report and engineering construction, the program assessment module can be by times such as week, the moons
Value analysis curve is earned in unit generation, and has abundant report and data function, reacts assessment result, the trick from different perspectives
Bidding management module allows User Defined multistage bid performance assessment criteria, and several associated specialists is allowed to beat indices
Point, system summarizes the expert analysis mode summary sheet and detail list for generating bid producer automatically, and foundation, the wind are provided for acceptance of the bid decision
Dangerous analysis module intuitively shows PROJECT TIME and cost risk content, the contract by histogram, curve graph and pie chart
Payment management module includes bidding, engineering contract, scheduled fun application, contract change management, scheduled fun payment, engineering funds clearing
And the contents such as expense allocation, the engineering construction project management system further includes user management module, the user management mould
Block includes the angle of user department, the real name of user, the login account of user and password, user in engineering project
Color.
Referring to Fig. 2, user sends service request by cell phone application/computer client, handled through WEB server, to system
Database operated, output result be formatted as user needs form and be back to client, wherein client is to be
The external interface part of system, i.e., the window that user interacts with Inter-System Information, when system receives what client browser was sent out
When service request, BLL projects (Business Logic)) analysis request and the input parameter of WEB is converted to, when business processing is completed,
WEB projects generate the corresponding page and are back in browser, and (i.e. the page is as obtained by the sequential operation on server for WEB projects
The result gone out) for system business function to be shown on the page, made of Active Server Pages, BLL projects are complete
At all business functions and logic judgment in system, DAL is data access layer, complete to the basic access of system database with
Operation element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace
And modification, the scope of the present invention is defined by the appended.
Claims (7)
1. a kind of engineering construction project intelligent management system, it is characterised in that:The system includes project information acquisition module, project
Evaluation module, bidding management module, risk analysis module, resource management module, project tracking module, contract payment manage mould
Block, engineering archive management module, project scheduling management module;
The project information acquisition module is for being acquired the various project information in Process of Engineering Construction and storing to being
In system server;
The program assessment module for assessing the progress and cost of engineering project, by progress difference, expense variance,
The quantitative data that schedule performance index and expense execute index carrys out objective reaction engineering general overview, convenient for project leadership and
Administrative staff grasp project general overview;
The bidding management module is directed to the qualification of relevant bidder in engineering project, pricing system, quality assurance, after sale
Service and its history credit are examined, and are uploaded in system server;
The risk analysis module be used for during Engineering Project Construction duration and cost carry out quantitative analysis, according to project
Schedule and estimated cost calculate Percent Complete;
The resource management module reduces equipment cost for realizing large scale equipment, the configuration of project personnel, optimization and management,
And control cost of human resources;
The project tracking module by being tracked by expense, project tracking, finance tracking, resource tracing executed engineering project
The project information that common in journey, needs are paid special attention to collects generation and grasps overall project information report convenient for project manager
It accuses;
The contract payment management module is used for engineering contract and progress payment in project construction process and pays the complete of work
Process management;
The engineering archive management module is used to preserve the data information in Construction Process of Engineering Project, and is generated in system background
Chart, for project management personnel's real-time query;
The project scheduling management module include the schedule in engineering project is managed, project progress typing and right
The engineering of implementation phase check.
2. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The project information
The information of acquisition module acquisition includes engineering drawing, work order, material requistion, directives for construction, job order, project construction report and work
Materials warehouse information in Cheng Jianshe.
3. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The project evaluation
Module can be generated by week, Yue Deng chronomeres and earn value analysis curve, and have abundant report and data function, from different perspectives
React assessment result.
4. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The bidding pipe
Managing module allows User Defined multistage bid performance assessment criteria, allows several associated specialists to give a mark indices, system
It is automatic to summarize the expert analysis mode summary sheet and detail list for generating bid producer, provide foundation for acceptance of the bid decision.
5. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The risk analysis
Module intuitively shows PROJECT TIME and cost risk content by histogram, curve graph and pie chart.
6. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The contract payment
Management module include bidding, engineering contract, scheduled fun application, contract change management, scheduled fun payment, engineering funds clearing and
The contents such as expense allocation.
7. a kind of engineering construction project intelligent management system according to claim 1, it is characterised in that:The engineering construction
Project management system further includes user management module, the user management module include user department, user practical surname
Name, the role of the login account of user and password, user in engineering project.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810252305.XA CN108446895A (en) | 2018-03-26 | 2018-03-26 | A kind of engineering construction project intelligent management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810252305.XA CN108446895A (en) | 2018-03-26 | 2018-03-26 | A kind of engineering construction project intelligent management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108446895A true CN108446895A (en) | 2018-08-24 |
Family
ID=63196712
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810252305.XA Pending CN108446895A (en) | 2018-03-26 | 2018-03-26 | A kind of engineering construction project intelligent management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108446895A (en) |
Cited By (33)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108830515A (en) * | 2018-09-25 | 2018-11-16 | 晋能清洁能源光伏发电有限责任公司 | A kind of photovoltaic plant capital construction information management system |
CN109493003A (en) * | 2018-11-08 | 2019-03-19 | 国家电网有限公司 | Item data management method and terminal device |
CN109711758A (en) * | 2019-01-28 | 2019-05-03 | 上海建科工程咨询有限公司 | A kind of whole process engineering consulting service evaluation method and system |
CN109726513A (en) * | 2019-01-29 | 2019-05-07 | 杭州凌望建筑科技有限公司 | Project big data analysis system based on BIM |
CN109766379A (en) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | A kind of construction project credit wire examination method Internet-based and system |
CN110084633A (en) * | 2019-03-14 | 2019-08-02 | 深圳市丰浩达工程项目管理有限公司 | Project cost, bid, consulting total management system |
CN110147957A (en) * | 2019-05-21 | 2019-08-20 | 大连地拓重工有限公司 | A kind of manufacturing enterprise's internal contract team competence assessment system |
CN110163581A (en) * | 2019-05-31 | 2019-08-23 | 黄亮清 | A kind of intelligentized project management method and system |
CN110503321A (en) * | 2019-08-13 | 2019-11-26 | 湖北省水利水电规划勘测设计院 | General contract of civil engineering project management system |
CN110930025A (en) * | 2019-11-21 | 2020-03-27 | 中国十九冶集团有限公司 | Project management system for engineering construction |
CN111291994A (en) * | 2020-02-12 | 2020-06-16 | 普元信息技术股份有限公司 | Multi-project management system and method suitable for agile development mode in big data environment |
CN111369116A (en) * | 2020-02-26 | 2020-07-03 | 国网上海市电力公司 | Project early-stage and project early-stage management system based on visualization technology |
CN111369211A (en) * | 2020-03-02 | 2020-07-03 | 辽宁工程技术大学 | Project operation data management system and method based on business intelligence |
CN111507681A (en) * | 2020-03-23 | 2020-08-07 | 南京熊猫电子股份有限公司 | Building engineering integrated management system |
CN111652493A (en) * | 2020-05-28 | 2020-09-11 | 南京维斯德软件有限公司 | Multi-project collaborative management system based on ACM platform |
CN111738669A (en) * | 2020-04-22 | 2020-10-02 | 汇智赛服(北京)科技有限公司 | SGO sports event flow management system |
CN111898853A (en) * | 2020-06-18 | 2020-11-06 | 深圳瑞和建筑装饰股份有限公司 | Engineering construction fine management system |
CN112085481A (en) * | 2020-09-22 | 2020-12-15 | 国网山东省电力公司烟台供电公司 | Whole-process tracking system for electric power engineering project management |
CN112085361A (en) * | 2020-08-28 | 2020-12-15 | 上海谊逅信息技术有限公司 | Construction engineering overall process management method |
CN112418806A (en) * | 2020-11-27 | 2021-02-26 | 上海妙一生物科技有限公司 | Clinical research project management system |
CN112560044A (en) * | 2020-12-03 | 2021-03-26 | 星汉供应链有限公司 | Project bug tracking and counting method, system and equipment |
CN112862341A (en) * | 2021-02-25 | 2021-05-28 | 中铁一局集团有限公司 | Project cost management system |
CN113379195A (en) * | 2021-05-14 | 2021-09-10 | 南京智慧建筑研究院有限公司 | Management system of project under construction based on wisdom building |
CN113379369A (en) * | 2021-05-14 | 2021-09-10 | 南京智慧建筑研究院有限公司 | Full life cycle's management system based on wisdom building |
CN113837533A (en) * | 2021-08-16 | 2021-12-24 | 江苏金小满信息科技有限公司 | Multi-dimensional examination and evaluation system for real estate engineering project management |
CN113935598A (en) * | 2021-09-29 | 2022-01-14 | 国网浙江省电力有限公司杭州供电公司 | Information management platform based on heat supply and demand relationship and data processing method thereof |
CN114037316A (en) * | 2021-11-17 | 2022-02-11 | 北京中百信信息技术股份有限公司 | Information system engineering supervision project risk situation query method |
CN114462953A (en) * | 2020-11-07 | 2022-05-10 | 苏州冀联通信工程有限公司 | Intelligent management system for communication engineering |
CN114676993A (en) * | 2022-03-17 | 2022-06-28 | 中铁上海工程局集团第五工程有限公司 | Engineering project economic activity analysis system |
CN114677117A (en) * | 2022-03-29 | 2022-06-28 | 广州华炬质量技术服务有限公司 | Building engineering management system and device |
CN117273456A (en) * | 2023-09-27 | 2023-12-22 | 深圳叮当科技技术有限公司 | Project cost intelligent management system based on big data technology |
CN117541052A (en) * | 2023-11-13 | 2024-02-09 | 安徽省招标集团股份有限公司 | Engineering bid management risk pre-control system and method |
CN117670262A (en) * | 2024-01-31 | 2024-03-08 | 成都双流建工建设集团有限公司 | Project management system and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101551882A (en) * | 2008-12-31 | 2009-10-07 | 东莞市天新企业管理咨询有限公司 | Engineering management monitoring system and method |
US20110307281A1 (en) * | 2010-06-11 | 2011-12-15 | Satterfield & Pontikes Construction, Inc. | Model inventory manager |
CN103136626A (en) * | 2011-11-29 | 2013-06-05 | 北京建龙重工集团有限公司 | On-line management method for engineering project |
CN104318408A (en) * | 2014-11-25 | 2015-01-28 | 上海建科工程咨询有限公司 | Multi-target and multi-dimension risk management system for large building engineering construction |
CN107437167A (en) * | 2017-07-19 | 2017-12-05 | 中诚工程建设管理(苏州)股份有限公司 | Construction-engineering project data handling system |
-
2018
- 2018-03-26 CN CN201810252305.XA patent/CN108446895A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101551882A (en) * | 2008-12-31 | 2009-10-07 | 东莞市天新企业管理咨询有限公司 | Engineering management monitoring system and method |
US20110307281A1 (en) * | 2010-06-11 | 2011-12-15 | Satterfield & Pontikes Construction, Inc. | Model inventory manager |
CN103136626A (en) * | 2011-11-29 | 2013-06-05 | 北京建龙重工集团有限公司 | On-line management method for engineering project |
CN104318408A (en) * | 2014-11-25 | 2015-01-28 | 上海建科工程咨询有限公司 | Multi-target and multi-dimension risk management system for large building engineering construction |
CN107437167A (en) * | 2017-07-19 | 2017-12-05 | 中诚工程建设管理(苏州)股份有限公司 | Construction-engineering project data handling system |
Cited By (36)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108830515A (en) * | 2018-09-25 | 2018-11-16 | 晋能清洁能源光伏发电有限责任公司 | A kind of photovoltaic plant capital construction information management system |
CN109493003A (en) * | 2018-11-08 | 2019-03-19 | 国家电网有限公司 | Item data management method and terminal device |
CN109766379A (en) * | 2018-12-29 | 2019-05-17 | 福建华闽通达信息技术有限公司 | A kind of construction project credit wire examination method Internet-based and system |
CN109711758A (en) * | 2019-01-28 | 2019-05-03 | 上海建科工程咨询有限公司 | A kind of whole process engineering consulting service evaluation method and system |
CN109726513A (en) * | 2019-01-29 | 2019-05-07 | 杭州凌望建筑科技有限公司 | Project big data analysis system based on BIM |
CN110084633A (en) * | 2019-03-14 | 2019-08-02 | 深圳市丰浩达工程项目管理有限公司 | Project cost, bid, consulting total management system |
CN110147957A (en) * | 2019-05-21 | 2019-08-20 | 大连地拓重工有限公司 | A kind of manufacturing enterprise's internal contract team competence assessment system |
CN110163581A (en) * | 2019-05-31 | 2019-08-23 | 黄亮清 | A kind of intelligentized project management method and system |
CN110503321A (en) * | 2019-08-13 | 2019-11-26 | 湖北省水利水电规划勘测设计院 | General contract of civil engineering project management system |
CN110503321B (en) * | 2019-08-13 | 2023-06-30 | 湖北省水利水电规划勘测设计院 | Project total contractor management system |
CN110930025A (en) * | 2019-11-21 | 2020-03-27 | 中国十九冶集团有限公司 | Project management system for engineering construction |
CN111291994A (en) * | 2020-02-12 | 2020-06-16 | 普元信息技术股份有限公司 | Multi-project management system and method suitable for agile development mode in big data environment |
CN111369116A (en) * | 2020-02-26 | 2020-07-03 | 国网上海市电力公司 | Project early-stage and project early-stage management system based on visualization technology |
CN111369211A (en) * | 2020-03-02 | 2020-07-03 | 辽宁工程技术大学 | Project operation data management system and method based on business intelligence |
CN111507681A (en) * | 2020-03-23 | 2020-08-07 | 南京熊猫电子股份有限公司 | Building engineering integrated management system |
CN111738669A (en) * | 2020-04-22 | 2020-10-02 | 汇智赛服(北京)科技有限公司 | SGO sports event flow management system |
CN111652493A (en) * | 2020-05-28 | 2020-09-11 | 南京维斯德软件有限公司 | Multi-project collaborative management system based on ACM platform |
CN111898853A (en) * | 2020-06-18 | 2020-11-06 | 深圳瑞和建筑装饰股份有限公司 | Engineering construction fine management system |
CN112085361A (en) * | 2020-08-28 | 2020-12-15 | 上海谊逅信息技术有限公司 | Construction engineering overall process management method |
CN112085481A (en) * | 2020-09-22 | 2020-12-15 | 国网山东省电力公司烟台供电公司 | Whole-process tracking system for electric power engineering project management |
CN114462953A (en) * | 2020-11-07 | 2022-05-10 | 苏州冀联通信工程有限公司 | Intelligent management system for communication engineering |
CN112418806A (en) * | 2020-11-27 | 2021-02-26 | 上海妙一生物科技有限公司 | Clinical research project management system |
CN112560044A (en) * | 2020-12-03 | 2021-03-26 | 星汉供应链有限公司 | Project bug tracking and counting method, system and equipment |
CN112862341A (en) * | 2021-02-25 | 2021-05-28 | 中铁一局集团有限公司 | Project cost management system |
CN113379369A (en) * | 2021-05-14 | 2021-09-10 | 南京智慧建筑研究院有限公司 | Full life cycle's management system based on wisdom building |
CN113379195A (en) * | 2021-05-14 | 2021-09-10 | 南京智慧建筑研究院有限公司 | Management system of project under construction based on wisdom building |
CN113837533A (en) * | 2021-08-16 | 2021-12-24 | 江苏金小满信息科技有限公司 | Multi-dimensional examination and evaluation system for real estate engineering project management |
CN113935598A (en) * | 2021-09-29 | 2022-01-14 | 国网浙江省电力有限公司杭州供电公司 | Information management platform based on heat supply and demand relationship and data processing method thereof |
CN114037316A (en) * | 2021-11-17 | 2022-02-11 | 北京中百信信息技术股份有限公司 | Information system engineering supervision project risk situation query method |
CN114676993A (en) * | 2022-03-17 | 2022-06-28 | 中铁上海工程局集团第五工程有限公司 | Engineering project economic activity analysis system |
CN114677117A (en) * | 2022-03-29 | 2022-06-28 | 广州华炬质量技术服务有限公司 | Building engineering management system and device |
CN117273456A (en) * | 2023-09-27 | 2023-12-22 | 深圳叮当科技技术有限公司 | Project cost intelligent management system based on big data technology |
CN117273456B (en) * | 2023-09-27 | 2024-08-23 | 深圳叮当科技技术有限公司 | Project cost intelligent management system based on big data technology |
CN117541052A (en) * | 2023-11-13 | 2024-02-09 | 安徽省招标集团股份有限公司 | Engineering bid management risk pre-control system and method |
CN117670262A (en) * | 2024-01-31 | 2024-03-08 | 成都双流建工建设集团有限公司 | Project management system and method |
CN117670262B (en) * | 2024-01-31 | 2024-04-26 | 成都双流建工建设集团有限公司 | Project management system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108446895A (en) | A kind of engineering construction project intelligent management system | |
Shi et al. | Enterprise resource planning for construction business management | |
US20110071867A1 (en) | Transformation of data centers to manage pollution | |
CN105955753B (en) | A kind of creation method of integration whole process fining intelligence ERP workbench | |
GB2380835A (en) | Monitoring the profitability of a manufacturing plant | |
CN109034610A (en) | Software development cloud platform based on different periods difference distribution mechanism | |
CN115719207A (en) | Super-automation platform system | |
CN115170090A (en) | Project management method and device, electronic equipment and readable storage medium | |
JP2016110610A (en) | Management support program | |
US20110029450A1 (en) | Computer-implemented method, system, and computer program product for connecting contract management and claim management | |
Jung et al. | Informatization index for the construction industry | |
Luo et al. | Conceptual framework for the service-oriented management of construction labor resource | |
CN112990886B (en) | Aviation industry data management display system based on mobile phone terminal | |
RU2480830C2 (en) | Method for automated data processing for making managerial decisions on project or project portfolio | |
CN109102168A (en) | Exploitation cloud platform based on page metering and timeliness control | |
CN116739208A (en) | Unified management system for power supply service | |
CN115577971A (en) | Staff ability dynamic value evaluation system based on algorithm model | |
Nikiforova et al. | Solution to CAD Designer Effort Estimation based on Analogy with Software Development Metrics. | |
KR20210053564A (en) | A method of construction information management system with using big data processing | |
KR20210053563A (en) | Construction information management system with using big data processing | |
CN111311037A (en) | Method for compiling custom construction plan, progress summarizing and data analysis | |
Yunna et al. | On the method and model of energy enterprise project portfolio selection and optimal allocation of resources | |
CN111652466B (en) | Table box repairing application method based on work order management | |
Ma et al. | Application Analysis of Business Intelligence in Enterprise Material Management | |
Rzepka et al. | Implementation and Use of Green Computing in Polish Companies versus Implementation of Features Characteristic of Teal Organizations |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||