CN110503321B - Project total contractor management system - Google Patents
Project total contractor management system Download PDFInfo
- Publication number
- CN110503321B CN110503321B CN201910745267.6A CN201910745267A CN110503321B CN 110503321 B CN110503321 B CN 110503321B CN 201910745267 A CN201910745267 A CN 201910745267A CN 110503321 B CN110503321 B CN 110503321B
- Authority
- CN
- China
- Prior art keywords
- design
- service
- list
- project
- contractor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P90/00—Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
- Y02P90/30—Computing systems specially adapted for manufacturing
Abstract
The invention discloses an engineering total contractor project management system, which comprises a user management module, a project design picture supply list module, a design technology service module, a design picture supply evaluation module, a design technology service tracking module, a design picture supply progress management module and a design technology service quality feedback module; the system takes a design unit as a tap, realizes dynamic management of design and design service of a total contractor project through whole trace management of an electronic platform, and promotes deep fusion of design and construction; the design is designed as the total contractor optimization design of the faucet for drawing and service, so that the project design and the construction depth are fused, and the management efficiency is improved. The project total contractual project management system takes the design unit as a tap, and the design support and the technical service support are enhanced through the total control and the coordinated management of the total contractual unit, so that the project is effectively controlled in the starting stage, and the smooth implementation of the project is promoted.
Description
Technical Field
The invention relates to a project management system, in particular to an engineering total contractor project management system.
Background
In the general contractual management process of the hydraulic project engineering, the design and construction are often disjointed and not closely connected, the design and supply diagram is slow, the construction progress is affected, the design and technology service is often not in place, most of the design and supply diagram and service adopt a paper recording mode, an electronic document is stored and recorded, a telephone communication mode is implemented, the management can not achieve consistent information transmission, the problems that information transmission is missed and communication can not be carried out in real time and in time are easily caused, and the like are easily caused, so that the engineering management is not supervised in place by the communication mode, the engineering efficiency is low, and certain paper waste and increase of engineering cost are also caused by various paper text schemes and file records. In the project construction process, various information such as design map service and the like are changed, a lot of information needs to be counted and updated repeatedly, and huge workload is brought to the total contractor project manager, so that adverse effects are brought to the total contractor project management, and project construction progress is directly influenced.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides an engineering total contractor project management system, which takes a design unit as a tap, realizes dynamic management of a total contractor project design for drawing and design service (technical consultation, joint acceptance and the like) through whole trace management of an electronic platform, and promotes deep fusion of design and construction; the design is designed as the total contractor optimization design of the faucet for drawing and service, so that the project design and the construction depth are fused, and the management efficiency is improved.
In order to achieve the above purpose, the invention designs an engineering total contractor project management system, which comprises a user management module, a project design diagram supply list module, a design technology service module, a design diagram supply evaluation module, a design technology service tracking module, a design diagram supply progress management module and a design technology service quality feedback module; wherein, the liquid crystal display device comprises a liquid crystal display device,
the project design map supply list module is used for collecting and storing construction drawing demand information required by a construction contractor in the project construction process into a system server (for auditing by a technical responsible person of a total contractor);
the design technology service module is used for a design unit technician to collect and store the provided drawing and design service information in a system server (for the auditing of a master contractor technical responsible person);
the design diagram supply evaluation module is used for evaluating the progress of the design diagram supply and the quality of service of the design technology, and objectively reflects the project diagram supply progress and the quality of service of the design technology through quantitative data of progress difference and service execution index (so that project leaders and management staff can master project design diagram supply and design service profiles);
the design technology service tracking module gathers project information needing special attention in the engineering project execution process to generate a project information report which is convenient for a master contractor project manager to master design drawings and design technology service project information through drawing progress tracking, design technology service quality tracking and drawing and design technology data tracking;
the design picture supply progress management module comprises management of a picture supply progress plan in an engineering project, entry of an engineering picture supply progress and management of engineering in a construction implementation stage;
the design technology service quality feedback module is a feedback opinion after the total contractor and the construction contractor upload the design picture supply quantity, the drawing quality and the design technology service quality into the server aiming at design unit design technicians, uploads a design picture supply list and a design technology service feedback opinion list to the electronic platform, evaluates the realization degree and satisfaction degree of a demand application list, proposes a drawing demand list and a design service demand application list again, and uploads the drawing demand list and the design service demand application list to the system server in time.
Further, the user management module comprises a master contractor field responsible person logging in own authority account, and accounts of construction contractor technical responsible persons and design professional technicians with corresponding authorities of different mark segments.
Still further, the project plan view list includes permanent and temporary land feature plan views, building coordinate control point plan views, foundation excavation drawings, building plan and elevation views, structural mass drawings, electromechanical device arrangement and installation drawings, electrical primary and secondary device arrangement drawings, and architectural decoration drawings.
Still further, the project information of particular interest includes a map-providing schedule table, a design specification, a design technical intersection record table, a design technical quality of service feedback table, a drawing and a design technical data distribution registration confirmation table.
The invention also provides a management method of the project total contractor project management system (before the method operates, the total contractor project is designed as a tap total contractor project, a site responsible person of the total contractor project logs in a permission account number of the total contractor project, corresponding permissions are distributed to construction contractor technical responsible persons of different mark segments, a design professional technician is established, a corresponding relation table of a picture supply list and a design service list is established, accounts of corresponding permissions are distributed to the construction contractor technical responsible person and the design professional technician, and the permission account number of the design unit technician and the account number of the construction contractor technical responsible person are uploaded to a management account number and checked by the site responsible person of the total contractor), and the method comprises the following steps:
s101: a technical responsible person of a construction contractor logs in a management account, uploads a drawing demand list and a design service demand application list, and proposes a demand application list;
s102: the technical responsible person of the main contractor unit logs in the management account number, and controls, coordinates and audits the drawing demand application list and the design service demand application list; then, S103 is entered:
s103: the technical responsibility of the general contractor unit sends the audited drawing demand list and the design service application list to the electronic commerce platform to prompt the design professional technician to complete the drawing demand list and the design service application list;
s104: the design professional technician sends the completed map supply demand list and the design service application list to an electronic commerce platform, and the electronic commerce platform submits the map supply demand list and the design service application list to a construction professional contractor technical responsible person after submitting the map supply demand list and the design service application list to a site responsible person for auditing the general contractor;
s105: the construction contractor technical responsible person feeds back the design picture supply list and the design technology service feedback opinion list to the electronic platform, evaluates and scores the realization degree and satisfaction degree of the demand application list, and puts forward the drawing demand list and the design service demand application list again, namely, repeating the step S101, and entering S102 according to the flow: s103: s104: s105: s101: s102 … …. And the method is repeated until reaching or basically reaching the realization degree and satisfaction degree of the application list required by the technical responsibility of the construction contractor, and provides related improvement comments (the method promotes the fusion of the design and the construction depth of the total contractor project, thereby improving the project construction efficiency and benefit, simultaneously, the method can be used for quickly and conveniently inquiring, ensuring the authenticity and reliability of the data and really realizing the traceability of the data).
In the preferred scheme, in S101, a technical responsible person of the construction contractor timely tracks and controls the definite time in the project list according to the determined project start schedule and the map supply schedule.
In the preferred scheme, in S101, a technical responsible person of the construction contractor submits an application to a general contractor site responsible person according to the uploaded drawing demand list and design service demand application list, when the manager finishes the process deviation limit value set by the technical responsible person of the construction contractor under the contract, and the time limit deviation of the information of the drawing demand list and the design service application list submitted by the technical responsible person of the construction contractor is greater than the established process deviation limit value,
or, when the limit value of the service time of the design drawing and the follow-up design technology is larger than the limit value of the established progress deviation limit value, the total contractor manager designed as the faucet automatically sends out relevant early warning information according to the fed back working content list information result.
In S101, a technical responsible person who is a construction contractor uploads a drawing demand list and a design service demand application list in time, and a general contractor site responsible person performs spot check according to the actual progress of the project, specifically including work content tracked by an account manager of an electronic platform of the general contractor site responsible person from a design providing service and drawing supply list table, and when the work is not completed, relevant early warning information is sent through the platform.
The invention has the beneficial effects that:
the invention establishes a project total contractual project management system of the hydraulic engineering project with the design unit as the tap, and related information is not used in modes of paper recording and the like, and related project starting and construction information is refined into programs with specific design units of overall control and coordinated management of the tap, design map supply, technical service support and guarantee and the like. Different personnel update the information of the management method module of the project total contractor management system every day, so that the dynamic management of the total contractor project data is realized, the overall coordination and management efficiency is improved intangibly, the inquiry can be quickly and conveniently carried out, the true reliability of the data can be ensured, the traceability of the data is truly realized, and the decision risk of the implementation and the starting of the project construction of the total contractor unit is further avoided after the management and the report and the examination of the flow-process module.
The project total contractual project management system takes the design unit as a tap, and the design support and the technical service support are enhanced through the total control and the coordinated management of the total contractual unit, so that the project is effectively controlled in the starting stage, and the smooth implementation of the project is promoted.
Drawings
FIG. 1 is a block diagram of an engineering total contractor project management system of the present invention;
FIG. 2 is a flow chart of the project total contractor project management system of the present invention;
FIG. 3 is a flow chart of a WEB server of the project total contractor project management system of the present invention.
Detailed Description
The present invention is described in further detail below in conjunction with specific embodiments for understanding by those skilled in the art.
The project total contractor project management system shown in fig. 1 comprises a user management module, a project design map supply list module, a design technology service module, a design map supply evaluation module, a design technology service tracking module, a design map supply progress management module and a design technology service quality feedback module; wherein, the liquid crystal display device comprises a liquid crystal display device,
the project design map supply list module is used for collecting and storing construction drawing demand information required by a construction contractor in the project construction process into a system server (for auditing by a technical responsible person of a total contractor);
the design technology service module is used for a design unit technician to collect and store the provided drawing and design service information in a system server (for the auditing of a master contractor technical responsible person);
the design diagram supply evaluation module is used for evaluating the progress of the design diagram supply and the quality of service of the design technology, and objectively reflects the project diagram supply progress and the quality of service of the design technology through quantitative data of progress difference and service execution index (so that project leaders and management staff can master project design diagram supply and design service profiles);
the design technology service tracking module gathers project information needing special attention in the engineering project execution process to generate a project information report which is convenient for a master contractor project manager to master design drawings and design technology service project information through drawing progress tracking, design technology service quality tracking and drawing and design technology data tracking;
the design picture supply progress management module comprises management of a picture supply progress plan in an engineering project, entry of an engineering picture supply progress and management of engineering in a construction implementation stage;
the design technology service quality feedback module is a feedback opinion after the total contractor and the construction contractor upload the design picture supply quantity, the drawing quality and the design technology service quality into the server aiming at design unit design technicians, uploads a design picture supply list and a design technology service feedback opinion list to the electronic platform, evaluates the realization degree and satisfaction degree of a demand application list, proposes a drawing demand list and a design service demand application list again, and uploads the drawing demand list and the design service demand application list to the system server in time.
The user management module comprises authority accounts of the personnel responsible for logging in the general contractor on site, accounts of construction contractor technical responsible personnel with different mark segments and accounts of corresponding authorities of design professional technicians.
The project design map list comprises a permanent and temporary land feature range plane map, a building coordinate control point plane map, a foundation excavation map, building plane and elevation maps, a structure large-scale map, an electromechanical equipment arrangement and installation map, an electric primary and secondary equipment arrangement map and a building decoration map.
The project information of particular interest includes a map-providing schedule table, a design specification, a design-technical-issue record table, a design-technical-quality-of-service feedback table, a drawing and design-technical-data distribution registration confirmation table.
The method for managing the project total contractor project management system shown in fig. 2 (before the method is operated, the total contractor project site responsible person is designed as a tap to log in his own authority account, the corresponding authorities are distributed to the construction contractor technical responsible person and the design professional technician in different benchmarks, a corresponding relation table of a picture supply list and a design service list is established, the accounts of the corresponding authorities are distributed to the construction contractor technical responsible person and the design professional technician, and the authority account of the design unit technician and the account of the construction contractor technical responsible person are uploaded to the management account and checked by the total contractor site responsible person) includes the following steps:
s101: a technical responsible person of a construction contractor logs in a management account, uploads a drawing demand list and a design service demand application list, and proposes a demand application list; wherein, the liquid crystal display device comprises a liquid crystal display device,
and the technical responsibility of the construction contractor timely tracks and controls the definite time in the project list according to the determined project start time table and the picture supply time table.
The technical responsible person of the construction contractor submits an application to the general contractor site responsible person according to the uploaded drawing demand list and design service demand application list, when the manager finishes the process deviation extreme value set by the technical responsible person of the construction contractor through the audited construction contractor to the design technician and the time deviation of the information of the drawing demand list and the design service application list is larger than the established process deviation extreme value,
or, when the limit value of the service time of the design drawing and the follow-up design technology is larger than the limit value of the established progress deviation limit value, the total contractor manager designed as the faucet automatically sends out relevant early warning information according to the fed back working content list information result.
The technical responsible person of the construction contractor uploads a drawing demand list and a design service demand application list in time, and the general contractor site responsible person performs spot check in time according to the actual progress of engineering.
S102: the technical responsible person of the main contractor unit logs in the management account number, and controls, coordinates and audits the drawing demand application list and the design service demand application list; then, S103 is entered:
s103: the technical responsibility of the general contractor unit sends the audited drawing demand list and the design service application list to the electronic commerce platform to prompt the design professional technician to complete the drawing demand list and the design service application list;
s104: the design professional technician sends the completed map supply demand list and the design service application list to an electronic commerce platform, and the electronic commerce platform submits the map supply demand list and the design service application list to a construction professional contractor technical responsible person after submitting the map supply demand list and the design service application list to a site responsible person for auditing the general contractor;
s105: the construction contractor technical responsible person feeds back the design picture supply list and the design technology service feedback opinion list to the electronic platform, evaluates and scores the realization degree and satisfaction degree of the demand application list, and puts forward the drawing demand list and the design service demand application list again, namely, repeating the step S101, and entering S102 according to the flow: s103: s104: s105: s101: s102 … …. And the method is repeated until reaching or basically reaching the realization degree and satisfaction degree of the application list required by the technical responsibility of the construction contractor, and provides related improvement comments (the method promotes the fusion of the design and the construction depth of the total contractor project, thereby improving the project construction efficiency and benefit, simultaneously, the method can be used for quickly and conveniently inquiring, ensuring the authenticity and reliability of the data and really realizing the traceability of the data).
As shown in fig. 3: the method comprises the steps that a user of a construction contractor or a general contractor construction site manager client sends a service request through a mobile phone APP/computer client, the service request is processed through a WEB page server, a database of a system is operated, an output result is formatted into a form required by the user and is returned to the client, the client is an external interface part of the system, namely a window for information interaction between the user and the system, when the system receives the service request sent by a browser of the client, a BLL item (a service logic layer mainly shows a WEB page mode) analyzes the request and is converted into an input parameter of a WEB page, when service processing is completed, the WEB page item generates a corresponding page and is returned to the browser, the WEB page item (a result obtained by program operation on the page through the server) is used for displaying a system service function on the page, dynamic server page manufacturing is adopted, the BLL item (the service logic layer mainly shows the WEB page mode) completes all service functions and logic judgment in the system, and DAL is a data access layer (mainly shows picture list data and design technology service list data) and completes basic access and operation work flow to the system database.
By adopting the management structure flow chart, the engineering total contractual project management system with the design unit as the tap can separate the design drawing supply or design technical service responsibility, promote the related responsibility personnel to perform responsibility, avoid the occurrence of bad phenomena of incomplete design drawing supply or design technical service, and improve the working efficiency of project starting and construction preparation stages. And the permanent storage of the beneficial data is realized, and the whole process trace management in the project starting and construction preparation stage is realized.
Other parts not described in detail are prior art. Although the foregoing embodiments have been described in some, but not all, embodiments of the invention, it should be understood that other embodiments may be devised in accordance with the present embodiments without departing from the spirit and scope of the invention.
Claims (1)
1. The management method of the project total contractor project management system comprises a user management module, a project design map supply list module, a design technology service module, a design map supply evaluation module, a design technology service tracking module, a design map supply progress management module and a design technology service quality feedback module; wherein, the liquid crystal display device comprises a liquid crystal display device,
the project design picture supply list module is used for collecting and storing construction drawing demand information required by a construction contractor in the project construction process into the system server;
the design technology service module is used for a design unit technician to collect and store the provided drawing and design service information in the system server;
the design diagram supply evaluation module is used for evaluating the progress of the design diagram supply and the quality of service of the design technology, and objectively reflecting the progress of the diagram supply and the quality of service of the design technology of the engineering through quantitative data of progress difference and service execution index;
the design technology service tracking module gathers project information which needs to be particularly concerned in the engineering project execution process to generate a project information report which is convenient for a manager of a general contractor to master design drawings and design technology service project information by drawing progress tracking, design technology service quality tracking and drawing and design technology data tracking;
the design picture supply progress management module comprises management of a picture supply progress plan in an engineering project, entry of an engineering picture supply progress and management of engineering in a construction implementation stage;
the design technology service quality feedback module is a feedback opinion after the total contractor and the construction contractor comprehensively evaluate the number of design drawings, the quality of drawings and the quality of design technology service in a server aiming at design unit design technicians, uploads a design drawing list and a design technology service feedback opinion list to an electronic platform, evaluates the realization degree and satisfaction degree of a demand application list, proposes a drawing demand list and a design service demand application list again, and uploads the drawing demand list and the design service demand application list to a system server in time; the user management module comprises a field responsible person of a general contractor logging in a right account number of the user, and technical responsible persons of construction contractors with different mark segments and accounts of corresponding rights of design professional technicians; the project design map supply list comprises a permanent and temporary land feature range plane map, a building coordinate control point plane map, a foundation excavation map, building plane and elevation maps, a structure large-scale pattern, an electromechanical equipment arrangement and installation map, an electric primary and secondary equipment arrangement map and a building decoration map; the project information of special interest comprises a map supply progress comparison table, a design technical requirement, a design technical intersection record table, a design technical service quality feedback table, a drawing and design technical data distribution registration confirmation table; the method is characterized in that: the method comprises the following steps:
s101: a technical responsible person of a construction contractor logs in a management account, uploads a drawing demand list and a design service demand application list, and proposes a demand application list; the technical responsibility of the construction contractor timely tracks and controls the definite time in the project list according to the determined project start time table and the picture supply time table;
the technical responsible person of the construction contractor puts forward an application to the site responsible person of the total contractor according to the uploaded drawing demand list and design service demand application list, the site responsible person of the total contractor sets a schedule deviation limit value according to the contract,
when the manager finishes the time limit deviation of the information of the map supply demand list and the design service application list, which are proposed by the audited construction contractor technical responsible person, to the design technician to be larger than the time limit value of the established progress deviation extreme value,
or, when the service time limit value of the follow-up design technology is greater than the time limit value of the established progress deviation limit value, a master contractor manager designed as a faucet automatically sends out relevant early warning information according to the fed back work content list information result;
the technical responsible person of the construction contractor uploads a drawing demand list and a design service demand application list in time, and the general contractor site responsible person performs spot check in time according to the actual progress of engineering, specifically comprises working contents tracked by an account manager of an electronic platform of the general contractor site responsible person from a design providing service and drawing supply list, and when the work is not completed, relevant early warning information is sent out through a platform;
s102: the technical responsible person of the general contractor logs in the management account number, controls, coordinates and audits the drawing demand application list and the design service demand application list; then, S103 is entered:
s103: the technical responsibility of the general contractor unit sends the audited drawing demand list and the design service application list to the electronic commerce platform to prompt the design professional technician to complete the drawing demand list and the design service application list;
s104: the design professional technician sends the completed map supply demand list and the design service application list to an electronic commerce platform, and the electronic commerce platform submits the on-site responsible person of the total contractor to be checked and then feeds back to the technical responsible person of the construction contractor;
s105: the technical responsibility of the construction contractor feeds back the design picture supply list and the design technical service feedback opinion list to the electronic platform, evaluates and scores the realization degree and satisfaction degree of the demand application list, and puts forward the drawing demand list and the design service demand application list again, namely, repeats the step S101, and enters S102 according to the flow: s103: s104: s105: s101: s102 … …;
and (5) repeating the process until reaching or basically reaching the realization degree and satisfaction degree of the technical responsible person demand application list of the construction contractor, and providing related improvement suggestions.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910745267.6A CN110503321B (en) | 2019-08-13 | 2019-08-13 | Project total contractor management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910745267.6A CN110503321B (en) | 2019-08-13 | 2019-08-13 | Project total contractor management system |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110503321A CN110503321A (en) | 2019-11-26 |
CN110503321B true CN110503321B (en) | 2023-06-30 |
Family
ID=68586535
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910745267.6A Active CN110503321B (en) | 2019-08-13 | 2019-08-13 | Project total contractor management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110503321B (en) |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112241838B (en) * | 2020-10-15 | 2022-04-12 | 四川省农业机械研究设计院 | Design system and method for large-scale beef cattle farm |
CN112258374A (en) * | 2020-10-15 | 2021-01-22 | 湖北省水利水电规划勘测设计院 | Engineering general contract expropriation and land movement migrant project management system and method |
CN112446690A (en) * | 2020-12-15 | 2021-03-05 | 湖北省水利水电规划勘测设计院 | Hydraulic engineering building-up modularized management system and method |
CN113095641A (en) * | 2021-03-29 | 2021-07-09 | 中天昊建设管理集团股份有限公司 | Project general contract project management system |
CN112907228A (en) * | 2021-04-01 | 2021-06-04 | 湖北省水利水电规划勘测设计院 | Water conservancy project EPC complex general contract project management and control system and method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107844961A (en) * | 2017-11-23 | 2018-03-27 | 浙江精工钢结构集团有限公司 | Over contract Construction stage intelligent management system and method based on BIM |
CN108269071A (en) * | 2018-03-15 | 2018-07-10 | 叶枫 | The method that buildings model is shared cloud platform and project management is carried out using platform |
CN108446895A (en) * | 2018-03-26 | 2018-08-24 | 郑州大学 | A kind of engineering construction project intelligent management system |
CN108846644A (en) * | 2018-06-22 | 2018-11-20 | 中船第九设计研究院工程有限公司 | A kind of integrated emulation technology, collaborative work, information management and project management managing and control system |
CN109740372A (en) * | 2018-12-17 | 2019-05-10 | 广州天越电子科技有限公司 | Based on the system and method for realizing that conceptual schematic drawing paper is divided in automatic audit room on WEB |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
MY127543A (en) * | 2000-02-26 | 2006-12-29 | Natsteel Holdings Pte Ltd | Method and system for efficiently transacting an order and for communicating order information between a construction contractor and a construction material supplier |
US7062514B2 (en) * | 2003-04-28 | 2006-06-13 | Elbert Harris | Construction project submittal management |
US8805731B2 (en) * | 2003-10-24 | 2014-08-12 | Elbert Harris | Construction project submittal management |
US20070005440A1 (en) * | 2003-10-24 | 2007-01-04 | Elbert Harris | Construction project submittal management |
US20180341896A1 (en) * | 2017-05-24 | 2018-11-29 | Jason Grimes | Enterprise Construction Project Management and Business Integration System |
CN109636122A (en) * | 2018-11-16 | 2019-04-16 | 成都生活家网络科技有限公司 | Intelligent house ornamentation management system and method based on VR |
-
2019
- 2019-08-13 CN CN201910745267.6A patent/CN110503321B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107844961A (en) * | 2017-11-23 | 2018-03-27 | 浙江精工钢结构集团有限公司 | Over contract Construction stage intelligent management system and method based on BIM |
CN108269071A (en) * | 2018-03-15 | 2018-07-10 | 叶枫 | The method that buildings model is shared cloud platform and project management is carried out using platform |
CN108446895A (en) * | 2018-03-26 | 2018-08-24 | 郑州大学 | A kind of engineering construction project intelligent management system |
CN108846644A (en) * | 2018-06-22 | 2018-11-20 | 中船第九设计研究院工程有限公司 | A kind of integrated emulation technology, collaborative work, information management and project management managing and control system |
CN109740372A (en) * | 2018-12-17 | 2019-05-10 | 广州天越电子科技有限公司 | Based on the system and method for realizing that conceptual schematic drawing paper is divided in automatic audit room on WEB |
Non-Patent Citations (3)
Title |
---|
浅谈EPC 总承包项目管理在水利工程中的应用;黄伟;珠江水运(第1期);68-69 * |
湖北"建设管理―工程总承包"模式的探索与实践;杨香东;;水利建设与管理(第05期);61-64 * |
项目管理总承包在水利工程中的探索与实践;赵明伟;;中国水利(第10期);43-44 * |
Also Published As
Publication number | Publication date |
---|---|
CN110503321A (en) | 2019-11-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110503321B (en) | Project total contractor management system | |
CN111598379B (en) | Project management method, platform, device, computer equipment and storage medium | |
CN110782154A (en) | Construction plan management system based on BIM + GIS | |
CN107622355A (en) | Project cluster work progress digital management system and method | |
CN106096905A (en) | A kind of project management method and system | |
CN105447627A (en) | Design review process management and control mode research method | |
Onungwa et al. | Building information modelling and collaboration in the Nigerian construction industry | |
CN102208064A (en) | Administrative collaborative approval system and approval method | |
CN107423886A (en) | Engineering data management by synchronization system and management method based on Track Table | |
CN115271472A (en) | BIM model-based engineering acceptance method | |
CN113487172A (en) | Project supervision method | |
Chou et al. | Benefit evaluation of implementing BIM in construction projects | |
CN111666619A (en) | BIM technology-based substation engineering implementation field digital management system | |
CN113743830A (en) | BIM technology-based whole process engineering consultation information management system and method | |
CN105335846A (en) | Diesel engine overall test process management system | |
CN109360291B (en) | Construction machinery equipment inspection service system | |
CN110942281A (en) | Highway electromechanical engineering informatization management and control platform and method thereof | |
CN116561871A (en) | Deep construction method for mounting embedded part of bridge bearing platform | |
CN112258374A (en) | Engineering general contract expropriation and land movement migrant project management system and method | |
Lambers et al. | Key residential construction defects: a framework for their identification and correlated causes | |
Parn et al. | Building Information Modelling (BIM) for UK housing: exploring potential drivers and opportunities to deliver better customer experience | |
CN113807660A (en) | High-standard farmland construction information management system | |
CN112330265A (en) | Land supply supervisory systems | |
CN112085341A (en) | Master station system suitable for risk management and control of overall process of power production operation | |
Wu et al. | Research on fine management of construction project based on BIM5D technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |