CN112258374A CN202011102689.0A CN202011102689A CN112258374A CN 112258374 A CN112258374 A CN 112258374A CN 202011102689 A CN202011102689 A CN 202011102689A CN 112258374 A CN112258374 A CN 112258374A
Authority
CN
China
Prior art keywords
immigration
design
project
service
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011102689.0A
Other languages
Chinese (zh)
Inventor
杨香东
熊壮
刘贤才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hubei Provincial Water Resources and Hydropower Planning Survey and Design Institute
Original Assignee
Hubei Provincial Water Resources and Hydropower Planning Survey and Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Provincial Water Resources and Hydropower Planning Survey and Design Institute filed Critical Hubei Provincial Water Resources and Hydropower Planning Survey and Design Institute
Priority to CN202011102689.0A priority Critical patent/CN112258374A/en
Publication of CN112258374A publication Critical patent/CN112258374A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q90/00Systems or methods specially adapted for administrative, commercial, financial, managerial or supervisory purposes, not involving significant data processing
    • G06Q90/20Destination assistance within a business structure or complex
    • G06Q90/205Building evacuation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Architecture (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of engineering management, in particular to a system and a method for managing a total engineering contract land acquisition and migration project of migrants. The system comprises a project land acquisition and migration list module, a management module and a management module, wherein the project land acquisition and migration list module is used for acquiring permanent and temporary land acquisition, removal and forest felling demand information; the immigration design technology service module is used for collecting immigration investigation, technical support service and immigration design service information; the immigration supervision and evaluation module is used for evaluating land acquisition, removal and fund exchange conditions of the immigration; the county/country/village tracking service module is used for counting and summarizing the relocation, land acquisition compensation, removal and compensation conditions of the immigrants; the owner immigration shift tracking module is used for acquiring dynamic information of permanent and temporary land occupation, immigration, land acquisition compensation, removal and compensation conditions and fund exchange and payment conditions; and the homeland/forestry approval feedback module is used for feeding back the dynamic approval process. The deep fusion of immigration design and construction implementation can be promoted, and the project construction speed and benefit can be improved.

Description

Engineering general contract expropriation and land movement migrant project management system and method
Technical Field
The invention relates to the technical field of engineering management, in particular to a system and a method for managing a total engineering contract land acquisition and migration project of migrants.
Background
In the project engineering general portfolio management process, land acquisition, migration, dismantling, forest cutting and migration design and construction of a professional team and a professional team service of county, town and village coordination are often disconnected, the connection is not tight, the construction cannot be started, and the construction progress is influenced. The method is mainly characterized in that land acquisition, migration, removal and forest felling are not in place, and problems that design supply drawings and design services (land acquisition range drawings, coordinate control points, technical consultation, construction organization arrangement and the like) of the migration are not timely or not in accordance with actual sites exist. In addition, most services adopt a paper recording mode, an electronic document storage record and a telephone communication mode to implement, so that the management cannot realize the consistent transmission of information, the problems of information transmission omission, real-time and timely communication and the like are easily caused, therefore, the communication mode easily causes the problems of incomplete engineering management supervision and low engineering efficiency, and certain paper waste and the increase of engineering cost are caused by various paper text schemes and file records. In the project construction process, various information such as immigration, land acquisition and the like are changed, a lot of information needs to be counted and updated continuously and repeatedly by spending a lot of manpower, huge workload is brought to general contract project managers, work coordination and disjunction are caused, adverse effects are brought to general contract project management, and project construction progress is directly influenced.
Disclosure of Invention
The invention aims to provide a management system and a management method for a removal project of a total construction contract expropriation place migrant, which can enable the design of the migrant of a project to be deeply fused with the starting of the project construction, and enable the coordination service of owners and counties, villages and the examination and approval process to be tightly combined with the construction preparation, thereby effectively improving the implementation and management efficiency of the project.
The invention relates to a management system for removal projects of general engineering contract expropriation and land movement residents, which adopts the technical scheme that: the system comprises a project land acquisition and immigration list module, a server and a management module, wherein the project land acquisition and immigration list module is used for acquiring permanent and temporary land acquisition, removal and forest felling requirement information provided by a construction contractor and uploading the information to the server;
the immigration design technology service module is used for collecting immigration investigation, technology support service and immigration design service information provided by immigration design technicians and uploading the immigration investigation, the technology support service and the immigration design service information to the server;
the system comprises a immigration supervision evaluation module, a server and a management module, wherein the immigration supervision evaluation module is used for evaluating the land acquisition, removal and fund exchange conditions of immigration completed by county-level people governments and town governments and feeding back evaluation information to the server;
the county/country/village tracking service module is used for counting and summarizing the relocation, land acquisition compensation, removal and compensation conditions of immigration completed by counties, country governments and village committees and uploading the statistics and summary to the unified server;
the owner immigration shift tracking module is used for acquiring dynamic information of permanent and temporary land occupation, immigration relocation, land acquisition compensation, removal and compensation conditions and fund exchange and payment conditions;
and the homeland/forestry approval feedback module is used for feeding back the engineering construction land and the dynamic conditions of the forest approval procedures required to be felled to the owners.
Preferably, the immigration design technology service module comprises
And the immigration design technology service tracking module is used for collecting and concentrating immigration project information which needs special attention in the execution process of the engineering project through immigration symbol map and statistical table progress tracking, immigration design technology service quality tracking and immigration design technology data tracking, and generating a technical support and guide file.
Preferably, the immigration design technology service module comprises
And the immigration design map supply progress management module is used for managing immigration map supply progress plans and removal statistics in engineering projects, inputting immigration project map supply progress, performing statistics summary service on engineering immigration expropriation in a construction implementation stage, and uploading completed immigration survey, technical support service and immigration design service information to the server.
Preferably, the immigration design technology service module comprises
The immigration design technology service quality feedback module is used for evaluating immigration, land acquisition, quantity of design drawings for removal, drawing quality, immigration design technology service and technology support data uploaded into a server by design technicians of immigration design units by an owner, a county and village three-level coordination professional and a construction contractor, and submitting an immigration design drawing supply list and a design technology service feedback suggestion list.
The immigration project information needing special attention comprises land acquisition, immigration, a removal range map providing progress, coordinate control points, immigration design technology service quality, immigration land acquisition drawings and immigration design technology data.
The invention relates to a management method for removal projects of general engineering contract expropriation migrants, which has the technical scheme that: comprises that
Acquiring a permanent and temporary land use, migrant removal, forest felling requirement list and a construction arrangement service requirement list for design and provision submitted by a construction contractor;
the general contractor checks and uploads permanent and temporary land utilization, migrant removal, forest felling requirement lists and construction organization arrangement service requirement lists provided by design;
the immigration design provides technical support, and an owner coordinates a special shift to carry out organization and coordination work;
the method comprises the following steps that an owner coordinates a special shift to receive a service application list in an electronic platform, and organizes, coordinates and carries out work of dismantling, land examination and approval, butting and cashing of wood forest cutting certificates and approval with country and village afflictions and migrants;
the national and local departments and the forestry departments perform examination and approval service feedback, and organize and coordinate rural and rural real village collections or rural land seeking immigration compensation, exchange and coordination work on the basis of county-level immigration special shifts;
the immigration supervision carries out supervision and evaluation work, carries out on-site investigation, rechecking and evaluation on the conditions before and after the implementation of the land acquisition and immigration work, and feeds back the conditions to owners, county-level special shifts for land acquisition and immigration and construction contractor electronic platforms;
the construction contractor evaluates the realization degree and the satisfaction degree of the demand application list, and provides the demand list which is not implemented again;
and repeating the steps until the achievement degree and the satisfaction degree in the construction contractor technical responsible person requirement application list are reached.
Preferably, the site responsible personnel of the project of the general engineering contract logs on the authority account number of the site responsible personnel, distributes the corresponding authority to the technical responsible personnel of the construction contractors and the professional technical personnel of the immigration design in different standard sections, establishes a corresponding relation table of the immigration, the land acquisition, the removal list and the design service list of the immigration, and distributes the account number of the corresponding authority to the technical responsible personnel of the construction contractors, the professional technical personnel of the immigration design, the supervision of the immigration, the professional worker-coordinated working person responsible personnel, the county and country land acquisition and immigration coordinated person-coordinated person contact person and the related responsible personnel examined and approved by the forestry national and soil departments.
Preferably, the owner coordinates the professional shift personnel, the county and country expropriation and removal managers, the immigration supervisors, the authority accounts of the immigration design professional technicians and the accounts of the construction contractor technical responsible personnel to be uploaded to the management accounts and audited and distributed by the general contractor field responsible personnel.
The invention has the beneficial effects that: the map supply service work of the land acquisition and removal range and the land acquisition coordinate control point of the immigration design is closely integrated through the whole-course recording of services such as land acquisition, citizen movement, removal and forest felling related to the owner coordination special shift and the county, country and village coordination special shift before the project is started by the whole-course electronic platform, the immigration design of the project is deeply integrated with the project construction starting construction, the cooperation service of the owner, the county and the village and the examination and approval process are closely combined with the construction preparation, and therefore the implementation and management efficiency of the project is effectively improved. Meanwhile, the real and reliable timeliness of the data can be guaranteed, and the traceability of the data is really realized. The support and service project work of the owners and local governments are promoted, the deep integration of immigration design and construction implementation is promoted, and therefore the project construction speed, efficiency and benefit are improved.
Drawings
FIG. 1 is a schematic diagram of a system for managing removal projects of general construction contract expropriation and migration people according to the present invention;
FIG. 2 is a schematic diagram of a immigration design technology service module according to the present invention;
FIG. 3 is a flow chart of a method for managing a removal project of a general construction contract seeking area of a migrant;
FIG. 4 is a flowchart of the WEB server of the present invention.
Detailed Description
The invention will be further described in detail with reference to the following drawings and specific examples, which are not intended to limit the invention, but are for clear understanding.
As shown in fig. 1, a system for managing a removal project of a general engineering contract seeking place migrant includes: the system comprises a project land acquisition and migration list module, a migration design technology service module, a migration supervision evaluation module, a county/country/village tracking service module, an owner migration shift tracking module and a state/forestry examination and approval feedback module.
The project land acquisition and immigration list module is used for acquiring and storing permanent and temporary land acquisition, removal and forest felling requirement information required by a construction contractor for starting project construction in the project construction process into a system server for a general contractor technical responsible person to examine and check.
As shown in fig. 2, the immigration design technology service module includes an immigration design technology service tracking module, an immigration design plan progress management module, and an immigration design technology service quality feedback module. The immigration design technical service module is used for collecting and storing immigration design service information for a design unit immigration design technician to provide immigration investigation, technical support service (land acquisition range diagram, coordinate control points, technical consultation and the like) and immigration design service information in a system server for a general contract unit technical responsible person to check.
The immigration design technology service tracking module collects and concentrates immigration project information needing special attention in the engineering project execution process, such as land acquisition, immigration, removal range supply map progress, coordinate control points, immigration design technology service quality, immigration land acquisition drawings, immigration design technology data and other project information through immigration sign map and statistical form progress tracking, immigration design technology service quality tracking and immigration design technology data tracking, and generates a technology support and guide file on an electronic platform, so that owners, counties, villages, village coordination special shifts and general contract project managers can master the immigration land acquisition removal drawings and immigration design technology service project statistical information report lists in time.
The immigration design map supply progress management module manages immigration map supply progress plans and removal statistics in engineering projects, inputs immigration project map supply progress and performs statistics collection service on engineering immigration expropriation removal in a construction implementation stage; and uploading completed immigration survey, technical support services (land acquisition range diagram, coordinate control points, technical consultation and the like) in time, and acquiring immigration design service information into an electronic platform system server.
The immigration design technology service quality feedback module is a feedback opinion obtained by comprehensively evaluating the immigration, land acquisition, removal design supply map quantity, drawing quality, immigration design technology service and technology support data (land acquisition range map, coordinate control points, technical consultation and the like) quality uploaded into a server by a resident design technician, uploads the immigration design supply map list and a design technology service feedback opinion list to an electronic platform, evaluates the immigration, land acquisition, removal design supply map quantity, drawing quality, immigration design technology service, technology support data (land acquisition range map, coordinate control points, technical consultation and the like) quality realization degree and satisfaction degree provided by immigration design, and provides the immigration land acquisition technology support demand list and the design service demand application list again, and timely uploading to a system server, thereby promoting the immigration design to be continuously perfected and meeting the requirement of quick start construction of the project.
The immigration supervision and evaluation module is used for evaluating the situation of expropriating land, removing and cashing funds of the immigration completed by county-level people government and village and town government and feeding back evaluation information to the server. The method is particularly used for evaluating the coordination permanent and temporary land acquisition and removal progress and the immigration design technical service quality of local governments and owners, and objectively reflecting the land acquisition, immigration, removal progress and immigration design technical service quality of projects through the dynamic states of the land acquisition progress and the coordination service projects, so that project management departments and managers can conveniently master the land acquisition, immigration, removal progress conditions and immigration design service dynamic states of the projects.
The county/country/village tracking service module is used for counting and summarizing the relocation, land acquisition compensation, removal and compensation conditions of immigration completed by counties, country governments and village committees and uploading the statistics and summary to the unified server;
the owner immigration shift tracking module is used for acquiring dynamic information of permanent and temporary land occupation, immigration relocation, land acquisition compensation, removal and compensation conditions and fund exchange and payment conditions;
and the homeland/forestry approval feedback module is used for feeding back the dynamic conditions of engineering construction land (permanent and/or temporary) and the approval procedures of the trees to be felled to the owners.
As shown in fig. 3, a method for managing a removal project of a general engineering contract seeking place migrant first needs to perform authority assignment:
engineering general contract project site responsible personnel log in own authority account numbers, corresponding authorities are distributed to construction contractor technical responsible personnel and immigration design professional technical personnel of different standard sections, corresponding relation tables of immigration, land acquisition, removal lists and immigration design service lists are established, and account numbers of corresponding authorities are distributed to the construction contractor technical responsible personnel, the immigration design professional technical personnel, immigration supervision, owner coordination work professional responsible personnel, county and country land acquisition immigration coordination professional contact responsible personnel and forestry national and soil department approval related responsible personnel. The authority account numbers of the professional operators, the county and country expropriation land migration managers, the immigration supervisors, the immigration design professional technicians and the account numbers of the construction contractor technical responsible persons are uploaded to the management account numbers and are audited and distributed by the general contractor field responsible persons. After the authority distribution is completed, the management process is as follows:
the method comprises the following steps:
s101: acquiring permanent and temporary land use submitted by a construction contractor, removal of immigrants, forest felling requirement lists and designing and providing construction arrangement service requirement lists. A technical responsible person of a construction contractor logs in a management account, uploads a permanent and temporary land acquisition drawing demand list and a demand application list of immigration and design service removal (land acquisition range diagram, coordinate control points, technical consultation construction organization arrangement and the like) and a demand application list of land approval and forestry felling certificate, and provides a demand application list summary table;
s102: the general contractor reviews and uploads permanent and temporary land use, migrant removal, forest felling requirement lists and design provision construction organization arrangement service requirement lists.
S103: the immigration design provides technical support (land acquisition range diagram, coordinate control points, technical consultation and the like), and provides a coordination professional for the owner to carry out organization and coordination work. The general contract unit technical responsible person sends the checked expropriated land acquisition, immigration and removal demand list and immigration design service application list to the electronic commerce platform, and supervises the immigration design professional technical personnel to complete the demand list and the design service application list, so as to provide the owner to coordinate the professional shift to carry out organization and coordination work;
s104: the method comprises the following steps that an owner coordinates a special shift to receive a service application list in an electronic platform, and organizes, coordinates and carries out work of dismantling, land examination and approval, butting and cashing of wood forest cutting certificates and approval with country and village afflictions and migrants;
s105: and the service and approval platforms of the three departments are in butt joint with an electronic interface.
The system comprises a national and local department approval service feedback module (land acquisition range diagram, coordinate control points and the like) which feeds back to an owner service electronic platform;
the feedback module of the approval service (forest felling certificate and the like) of the forestry department feeds back to the business owner service electronic platform;
the county-level land seeking migration special shift service feedback module organizes and coordinates compensation, cashing and coordination work such as rural area, rural real village collective or rural land seeking migration of the migrant and the like on the basis of the county-level land seeking migration special shift and feeds the compensation, cashing and coordination work back to the owner service electronic platform.
S106: the immigration supervision carries out supervision and evaluation work, and carries out on-site investigation, rechecking and evaluation on the conditions before and after the implementation of land acquisition and immigration work. And timely feeding back to the electronic platforms of the owners, the county-level land acquisition and immigration shifts and the construction contractors;
s107: the construction contractor evaluates the achievement degree and the satisfaction degree of the demand application list, and provides the demand list which is not realized again, namely the steps S101 to S107 are repeated until the achievement degree and the satisfaction degree of the demand application list of the technical responsible person of the construction contractor are reached or basically reached.
As shown in fig. 4, a construction contractor or general contract construction site manager client user sends a request for providing a construction organization layout service requirement from a mobile phone APP/computer client to a permanent and temporary land to be implemented, a migrant removal, a forest felling requirement list and a design, and the request is processed by a WEB page server to operate a database of the system, and an output result is formatted into a form required by the construction contractor or general contract construction site manager user and returned to the client, wherein the client is an external interface part of the system, i.e. a window for information interaction between the user and the system, when the system receives a service request sent by a client browser, a BLL project (a service logic layer, mainly representing a WEB page mode) analyzes the request and converts the request into an input parameter of a WEB page, when the service processing is completed, the WEB page project generates a corresponding page to return to the browser, the WEB page project (the page is used for displaying the system service function on the page through the result obtained by program operation on the server), the dynamic server page is adopted for manufacturing, the BLL project (a service logic layer, which mainly represents a WEB page mode) is used for completing all service functions and logic judgment in the system, the DAL is a data access layer (which mainly provides technical support (a land acquisition range diagram, a coordinate control point, technical consultation and the like) for a migrant design special shift, and the DAL coordinates the migrant felling coordination shift of a forest in a country and coordinates the real requirement list data to complete the basic access and operation work flow of a system database.
The method establishes a method for water conservancy project general contract project immigration and land acquisition survey list and immigration design technology service feedback opinion list, binds related information, and refines specific technical support and guarantee related information of land acquisition immigration coordination management, service and immigration design service (land acquisition range diagram, coordinate control point, technical consultation, joint acceptance check and the like) to specific project starting implementation specific parts and links in a mode of no paper recording or the like. Different personnel update the land acquisition survey list and the land acquisition technical service feedback opinion list information of the general contract of the project every day, realize the dynamic management of the land acquisition and migration physical data of the general contract project and the immigration service (land acquisition range diagram, coordinate control points, technical consultation, joint acceptance and the like), greatly promote the land acquisition and migration physical data of the immigration of the general contract project, the land acquisition and migration redemption compensation, the project construction starting depth fusion and the integral connection, invisibly improve the overall coordination and management efficiency centering on the general contract, can quickly and conveniently inquire, can ensure the truth and reliability of the data, really realize the traceability of the data, further avoid the difficult land acquisition and migration compensation of the general contract unit, the field work resistance can not start the construction, the land acquisition and the transformation of the general contract unit after the management and the approval of a flow module, and further improve the dynamic management of the land acquisition and the transformation service of the general contract project, The problem of untimely technical support service and the risk of on-site general contract management.
In an electronic platform management system for expropriating and removing land for general contract and immigration of a project by different managers everyday, aiming at expropriating and removing physical data of the general contract and immigration of the general contract and the immigration of the immigration, design services (expropriation range diagram, coordinate control points, technical consultation, joint acceptance and the like), coordination management of the expropration of the immigration of owners and local governments (counties, counties and villages), dynamic management of services and examination and approval feedback opinions, information updating is carried out in time, the design expropriation and removal physical data of the immigration of the.
Details not described in this specification are within the skill of the art that are well known to those skilled in the art. The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the application. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
The present invention is not limited to the above embodiments, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention are included in the scope of the claims of the present invention which are filed as the application.

Claims (8)

1. A project management system for removal and migration of general engineering contract expropriation and migration people is characterized in that: comprises that
The system comprises a project land acquisition and immigration list module, a server and a management module, wherein the project land acquisition and immigration list module is used for acquiring permanent and temporary land acquisition, removal and forest felling requirement information provided by a construction contractor and uploading the information to the server;
the immigration design technology service module is used for collecting immigration investigation, technology support service and immigration design service information provided by immigration design technicians and uploading the immigration investigation, the technology support service and the immigration design service information to the server;
the system comprises a immigration supervision evaluation module, a server and a management module, wherein the immigration supervision evaluation module is used for evaluating the land acquisition, removal and fund exchange conditions of immigration completed by county-level people governments and town governments and feeding back evaluation information to the server;
the county/country/village tracking service module is used for counting and summarizing the relocation, land acquisition compensation, removal and compensation conditions of immigration completed by counties, country governments and village committees and uploading the statistics and summary to the unified server;
the owner immigration shift tracking module is used for acquiring dynamic information of permanent and temporary land occupation, immigration relocation, land acquisition compensation, removal and compensation conditions and fund exchange and payment conditions;
and the homeland/forestry approval feedback module is used for feeding back the engineering construction land and the dynamic conditions of the forest approval procedures required to be felled to the owners.
2. The system for managing a project of migration of a general construction contract of a migrant according to claim 1, further comprising: the immigration design technology service module comprises
And the immigration design technology service tracking module is used for collecting and concentrating immigration project information which needs special attention in the execution process of the engineering project through immigration symbol map and statistical table progress tracking, immigration design technology service quality tracking and immigration design technology data tracking, and generating a technical support and guide file.
3. The system for managing a project of migration of a general construction contract of a migrant according to claim 1, further comprising: the immigration design technology service module comprises
And the immigration design map supply progress management module is used for managing immigration map supply progress plans and removal statistics in engineering projects, inputting immigration project map supply progress, performing statistics summary service on engineering immigration expropriation in a construction implementation stage, and uploading completed immigration survey, technical support service and immigration design service information to the server.
4. The system for managing a project of migration of a general construction contract of a migrant according to claim 1, further comprising: the immigration design technology service module comprises
The immigration design technology service quality feedback module is used for evaluating immigration, land acquisition, quantity of design drawings for removal, drawing quality, immigration design technology service and technology support data uploaded into a server by design technicians of immigration design units by an owner, a county and village three-level coordination professional and a construction contractor, and submitting an immigration design drawing supply list and a design technology service feedback suggestion list.
5. The system for managing a project of migration of a general construction contract of a migrant according to claim 2, wherein: the immigration project information needing special attention comprises land acquisition, immigration, a removal range map providing progress, coordinate control points, immigration design technology service quality, immigration land acquisition drawings and immigration design technology data.
6. A method for managing a removal project of a general engineering contract expropriation and migration citizen is characterized by comprising the following steps: comprises that
Acquiring a permanent and temporary land use, migrant removal, forest felling requirement list and a construction arrangement service requirement list for design and provision submitted by a construction contractor;
the general contractor checks and uploads permanent and temporary land utilization, migrant removal, forest felling requirement lists and construction organization arrangement service requirement lists provided by design;
the immigration design provides technical support, and an owner coordinates a special shift to carry out organization and coordination work;
the method comprises the following steps that an owner coordinates a special shift to receive a service application list in an electronic platform, and organizes, coordinates and carries out work of dismantling, land examination and approval, butting and cashing of wood forest cutting certificates and approval with country and village afflictions and migrants;
the national and local departments and the forestry departments perform examination and approval service feedback, and organize and coordinate rural and rural real village collections or rural land seeking immigration compensation, exchange and coordination work on the basis of county-level immigration special shifts;
the immigration supervision carries out supervision and evaluation work, carries out on-site investigation, rechecking and evaluation on the conditions before and after the implementation of the land acquisition and immigration work, and feeds back the conditions to owners, county-level special shifts for land acquisition and immigration and construction contractor electronic platforms;
the construction contractor evaluates the realization degree and the satisfaction degree of the demand application list, and provides the demand list which is not implemented again;
and repeating the steps until the achievement degree and the satisfaction degree in the construction contractor technical responsible person requirement application list are reached.
7. The management method of the project of removal and migration of the general construction contract citizen according to claim 6, wherein: the method further comprises the steps that a project general contract project site responsible person logs in an authority account number of the project general contract project site responsible person, corresponding authorities are distributed to construction contractor technical responsible persons and immigration design professional technical persons of different standard sections, a corresponding relation table of immigration, land acquisition, removal lists and immigration design service lists is established, and account numbers of the corresponding authorities are distributed to the construction contractor technical responsible persons, the immigration design professional technical persons, immigration supervision, an owner coordination work professional responsible person, a county and country land acquisition immigration coordination professional team contact responsible person and forestry national earth department examination and approval related responsible persons.
8. The management method of the project of removal and migration of the general construction contract citizen according to claim 6, wherein: and the authority accounts of the owners coordinating special shifts, county and country expropriating land migration managers, immigrants supervision, immigrants design professional technicians and the accounts of the technical responsible persons of the construction contractors are uploaded to the management accounts and are audited and distributed by the on-site responsible persons of the general contractors.
CN202011102689.0A 2020-10-15 2020-10-15 Engineering general contract expropriation and land movement migrant project management system and method Pending CN112258374A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011102689.0A CN112258374A (en) 2020-10-15 2020-10-15 Engineering general contract expropriation and land movement migrant project management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011102689.0A CN112258374A (en) 2020-10-15 2020-10-15 Engineering general contract expropriation and land movement migrant project management system and method

Publications (1)

Publication Number Publication Date
CN112258374A true CN112258374A (en) 2021-01-22

Family

ID=74242269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011102689.0A Pending CN112258374A (en) 2020-10-15 2020-10-15 Engineering general contract expropriation and land movement migrant project management system and method

Country Status (1)

Country Link
CN (1) CN112258374A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113688179A (en) * 2021-08-16 2021-11-23 北京科豆加速器科技有限公司 User data management system based on front-end APP and back-end platform

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN110503321A (en) * 2019-08-13 2019-11-26 湖北省水利水电规划勘测设计院 General contract of civil engineering project management system
CN209873933U (en) * 2019-03-19 2019-12-31 湖北省水利水电规划勘测设计院 Hilly area is concentrated antithetical couplet sheet rainfall flood collection and is held and utilize device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107705020A (en) * 2017-10-12 2018-02-16 山东联诚工程建设监理有限公司 A kind of overall process intelligence engineering supervisory information managing and control system
CN209873933U (en) * 2019-03-19 2019-12-31 湖北省水利水电规划勘测设计院 Hilly area is concentrated antithetical couplet sheet rainfall flood collection and is held and utilize device
CN110503321A (en) * 2019-08-13 2019-11-26 湖北省水利水电规划勘测设计院 General contract of civil engineering project management system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冯雪: "建设征地移民安置项目管理分析", 《工程建设与设计》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113688179A (en) * 2021-08-16 2021-11-23 北京科豆加速器科技有限公司 User data management system based on front-end APP and back-end platform

Similar Documents

Publication Publication Date Title
CN110503321B (en) Project total contractor management system
CN112232761B (en) Infrastructure application system and method
CN105373885A (en) Electric power engineering design review and technical economic evaluation information system
CN108416571A (en) A kind of application method of scientific research service integration management system
CN107392570A (en) A kind of whole process e-bidding bid bid evaluation system and its tender Evaluation Method of inviting and submitting bids
CN107506898A (en) A kind of ecological management project information dynamic management system and method
CN105469246A (en) Colleague circle system and management method thereof
CN102496083B (en) Credit rating report manuscript manufacturing method
CN115375146A (en) Digital construction integrated platform
CN114186984B (en) Two-dimensional and three-dimensional integrated collaborative design system for architectural design enterprise
CN115934680B (en) One-stop big data analysis processing system
CN111897866A (en) Remote sensing monitoring pattern spot docking system and using method thereof
CN104899143A (en) Software peer review system realizing device for providing DM (Data Mining)
CN115496452A (en) Digital delivery system based on digital twin
CN104573885A (en) Auditing service working platform based on Internet cloud computing service function
CN113204329A (en) Control method for driving business application by unified data model and application system thereof
CN112258374A (en) Engineering general contract expropriation and land movement migrant project management system and method
CN114511296A (en) High-standard farmland construction project management platform
CN113743830A (en) BIM technology-based whole process engineering consultation information management system and method
CN112419124B (en) Method and device for quickly identifying low-efficiency industrial land and storage medium thereof
KR100791475B1 (en) Architectural design management system for cooperating with active partners
CN110321536B (en) Science and technology report online writing and presenting management system
CN112613849A (en) BIM-based project supervision information management method
CN112232760A (en) Infrastructure management system and method
CN111708827A (en) Real estate unit coding system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination