CN112766720A - Management and control system for main entertainment project art engineering - Google Patents
Management and control system for main entertainment project art engineering Download PDFInfo
- Publication number
- CN112766720A CN112766720A CN202110067258.3A CN202110067258A CN112766720A CN 112766720 A CN112766720 A CN 112766720A CN 202110067258 A CN202110067258 A CN 202110067258A CN 112766720 A CN112766720 A CN 112766720A
- Authority
- CN
- China
- Prior art keywords
- control system
- progress
- construction
- management
- engineering
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 claims abstract description 68
- 238000007726 management method Methods 0.000 claims abstract description 57
- 238000013461 design Methods 0.000 claims abstract description 27
- 230000000694 effects Effects 0.000 claims abstract description 7
- 238000003860 storage Methods 0.000 claims abstract description 6
- 239000000463 material Substances 0.000 claims description 59
- 238000004519 manufacturing process Methods 0.000 claims description 10
- 238000004458 analytical method Methods 0.000 claims description 9
- 238000000034 method Methods 0.000 claims description 8
- 230000003442 weekly effect Effects 0.000 claims description 7
- 230000003111 delayed effect Effects 0.000 claims description 6
- 230000003203 everyday effect Effects 0.000 claims description 6
- 238000012856 packing Methods 0.000 claims description 5
- 238000003908 quality control method Methods 0.000 claims description 5
- 238000012384 transportation and delivery Methods 0.000 claims description 5
- 238000006243 chemical reaction Methods 0.000 claims description 3
- 238000012790 confirmation Methods 0.000 claims description 3
- 238000012545 processing Methods 0.000 claims description 3
- 238000010835 comparative analysis Methods 0.000 claims description 2
- 230000001360 synchronised effect Effects 0.000 claims 1
- 238000013439 planning Methods 0.000 abstract description 5
- 238000004806 packaging method and process Methods 0.000 abstract description 3
- 230000000007 visual effect Effects 0.000 abstract description 3
- 238000011084 recovery Methods 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 4
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000004904 shortening Methods 0.000 description 2
- 241000282414 Homo sapiens Species 0.000 description 1
- 241001465754 Metazoa Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000013507 mapping Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 239000005445 natural material Substances 0.000 description 1
- 239000002994 raw material Substances 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
-
- G—PHYSICS
- G07—CHECKING-DEVICES
- G07C—TIME OR ATTENDANCE REGISTERS; REGISTERING OR INDICATING THE WORKING OF MACHINES; GENERATING RANDOM NUMBERS; VOTING OR LOTTERY APPARATUS; ARRANGEMENTS, SYSTEMS OR APPARATUS FOR CHECKING NOT PROVIDED FOR ELSEWHERE
- G07C9/00—Individual registration on entry or exit
- G07C9/30—Individual registration on entry or exit not involving the use of a pass
- G07C9/32—Individual registration on entry or exit not involving the use of a pass in combination with an identity check
- G07C9/37—Individual registration on entry or exit not involving the use of a pass in combination with an identity check using biometric data, e.g. fingerprints, iris scans or voice recognition
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- General Physics & Mathematics (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Health & Medical Sciences (AREA)
- Data Mining & Analysis (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Human Computer Interaction (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a management and control system for a main entertainment project artistic project, which relates to the technical field of project management and control, and is characterized in that the comprehensive application of a professional design system, a digital engineering system, a mountain engineering design system, an engineering quality management and control system, an artistic effect management and control system and a resource storage system can be used for carrying out various style designs suitable for different requirements of customers and customizing various scenes and the like by carrying out all-around theme packaging and scene creation on the rich entertainment artistic project through the cooperation of professional professionals in multiple fields such as overall planning, concept design, theme scheme design, construction planning, project management and the like, and the advanced style concept is fused with originality to form a unique design style, so that strong visual impact feeling is brought, the finally delivered result is high in recovery degree, the construction period is shortened, and the cost is lower.
Description
Technical Field
The invention relates to the technical field of engineering management and control, in particular to a management and control system for a main entertainment project artistic project.
Background
The main entertainment project artistic engineering service content generally covers planning, conception, scheme, initial design, construction drawing making, construction building and operation till landing from the previous project, the general engineering quantity is large, the construction comprises omnibearing theme packaging construction, such as construction of artistic themes of rockery, cartoon animals or human beings, artificial trees, pavilions and the like, the engineering can be completed only by cooperation of professionals in multiple fields of design, construction, management and the like, the construction period is long, the cost is high, common construction teams are difficult to guarantee quality, and on the basis, a set of full-flow integrated engineering management and control system is especially necessary to be researched.
Disclosure of Invention
The invention aims to provide a management and control system for the artistic engineering of a main entertainment project, which can shorten the construction period, reduce the cost and ensure the engineering quality.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows:
a management and control system for a subject entertainment project art project comprises:
the background control system comprises a design system, a digital engineering system, a mountain engineering design system, an engineering quality control system, an artistic effect control system and a resource storage system which are comprehensively applied, and the background control system collects, analyzes and processes data of the systems;
the BIM system is used for compiling a material purchasing plan, a total progress plan and a monthly plan of a construction task, simulating a resource curve, a capital curve and a progress plan of any time period in the whole construction process in the BIM system, analyzing the rationality of the progress plan scheduling according to curve data, arranging a week progress plan by combining a BIM webpage end and generating a construction digital week report;
the material two-dimension code is generated according to the name, the category, the ordering amount and the supplier information of the material on the material purchasing plan and is attached to the corresponding material package;
the intelligent terminal is held by hand, after the material is purchased and enters a construction site, a site material auditor scans the material two-dimensional code by adopting the intelligent terminal, and transmits product information to the BIM system for auditing and confirmation to manage and control the material;
the mobile phone end receives data of the background control system and the BIM system, pushes the data to the mobile phone ends of project management personnel and field management personnel, and the field management personnel report the actual field progress and the labor amount every day at the mobile phone end and upload the data; the project department manager carries out dynamic management and control every week according to the construction digital weekly report, carries out comparative analysis of actual progress and planned progress, adjusts resource comparison of personnel, materials and equipment, analyzes the reason of progress delay, and timely takes corresponding solving measures to optimize the construction period, balance resources and adjust the progress and ensure the achievement of the construction period target;
the identification system comprises a face identification gate and a GPS positioning module, wherein the face identification gate is arranged at an entrance of a construction site and used for reading an information card of a site constructor and identifying identity approval to enter the site by combining face identification; the GPS positioning module is installed on the safety helmet and used for transmitting the position information of site constructors to the background control system in real time in a wireless mode, and the background control system carries out format conversion processing on the data and guides the data into the BIM system to realize personnel management and control.
Furthermore, the mobile phone end receives data sent by the background control system in real time, and management personnel of the project department check the number, delayed start and delayed completion of the production tasks in the week in real time at the mobile phone end, and timely release factors restricting progress in the construction production process, so that real-time supervision and implementation are achieved.
Furthermore, field management personnel check the completion condition of the production task at the mobile phone end in real time, cooperate with field workers to find out the common problem, solve the problem in real time, reduce recording work and efficiently optimize progress and resources.
Furthermore, before the materials leave the factory, the two-dimensional codes of the materials are attached to corresponding packages, the information of entrusted logistics companies, the actual delivery date, the arrival date and other logistics information are synchronously pushed to the background control system, the BIM system is guided into the background control system and pushed to the personnel terminal which is responsible for entering the factory for acceptance on the construction site, and the progress condition of the materials is conveniently known in real time.
Furthermore, the identification system further comprises an intelligent camera, the intelligent camera is installed on a construction site, the intelligent camera transmits the acquired image to the background control system for automatic analysis, whether the personnel in the image normally wear the safety helmet or not is judged, if the personnel do not wear the safety helmet, the background control system sends violation information to a mobile phone end of corresponding site management personnel according to the construction site of the violation personnel, and the site management personnel remind the workers.
The invention has the beneficial effects that: a material purchasing plan is made and derived through a BIM system, the flow direction of the material is tracked in time according to the material two-dimensional code, and material management and control are performed, so that the material is supplied in time, and the cost in the aspect of the material is reduced to a certain extent; the BIM system is used for compiling a construction task, a total progress plan and a monthly plan, generating a construction digital weekly report, pushing the construction digital weekly report to a mobile phone end of project site management personnel, and the site management personnel fills and uploads the actual site progress and the labor amount at the mobile phone end every day, so that the integrated progress control of the whole flow is realized, the construction without regulation in the traditional technology is avoided, the powerful guarantee is provided for further shortening the construction period, and the labor cost is effectively reduced through the application of the BIM system, a background control system and the mobile phone end; every week, the management personnel of project department carry out dynamic management and control according to construction number week report, carry out the contrastive analysis of actual progress and planned progress, the resource contrast of adjustment personnel, material, equipment, the reason that the analysis progress is lagged to in time take corresponding solution measures, realize the professional collaborative work in many fields, compare with prior art, make the reduction degree of main part packing construction higher, guaranteed engineering quality.
Detailed Description
The present invention will be further described below.
A management and control system for a subject entertainment project art project comprises:
the background control system comprises a design system, a digital engineering system, a mountain engineering design system, an engineering quality control system, an artistic effect control system and a resource storage system which are comprehensively applied, and the background control system collects, analyzes and processes data of the systems.
The digital engineering system applies the digital model technology to the field of main body design and construction, so that a design blueprint can be quickly converted into a constructable dynamic model, the communication efficiency and the construction efficiency are greatly improved in the design and production links and the design and construction links, and the design effect is highly restored by more than 90%.
In the main part packing project, huge mapping data lets mountain body design become the trade technological difficulty, relies on 3D model technique and BIM system to assist, accomplishes mountain body measurement fast, becomes visual, digital, the concrete model of modularization to the design drawing to realize accurate unloading, practice thrift the raw materials cost, become three-dimensional cube notion to complicated mountain body structure simultaneously, make things convenient for later stage net piece system installation, practiced thrift the time cost to the at utmost.
The engineering quality control system and the artistic effect control system have strong strain capacity and quick problem solving capacity, and can meet the requirements of customers with high quality and high efficiency and create higher value.
The resource storage system accumulates a huge natural material database, and can quickly build a high-quality technical service platform for the client.
The BIM system is used for compiling a material purchasing plan, a total progress plan and a monthly plan of a construction task, simulating a resource curve, a fund curve and a progress plan of any time period in the whole construction process in the BIM system, analyzing the rationality of progress plan scheduling according to curve data, arranging a week progress plan by combining a BIM webpage end and generating a construction digital week report.
The BIM system is used for compiling a construction task, a total progress plan and a monthly plan, a construction digital weekly report is generated and pushed to a mobile phone end of project site management personnel, the site management personnel fills in actual site progress and labor amount at the mobile phone end every day and uploads the actual site progress and the labor amount, so that the progress management and control of the whole process integration are realized, construction without rules in the traditional technology is avoided, the construction period is further shortened, powerful guarantee is provided, and labor cost is effectively reduced through the application of the BIM system, a background control system and the mobile phone end.
The material two-dimensional code is generated according to the name, the category, the ordering amount and the supplier information of a material on a material purchasing plan and is attached to a corresponding material package, the material two-dimensional code is attached to the corresponding package before delivery, information of a consignment logistics company, actual delivery date, arrival date and other logistics information are synchronously pushed to a background control system, the material two-dimensional code is led into a BIM system through the background control system and pushed to a terminal of a person responsible for entering a factory and checking and accepting on a construction site, and the progress condition of the material is conveniently known in real time.
Make and derive material purchase plan through the BIM system, in time trail the flow direction of material according to the material two-dimensional code, carry out the material management and control, ensure that the supply of material is timely, and reduced the cost in the aspect of the material to a certain extent.
And (4) the intelligent terminal is held by hand, after the material is purchased and enters a construction site, a site material auditor scans the material two-dimensional code by adopting the intelligent terminal, and transmits the product information to the BIM system for auditing and confirmation to perform material management and control.
The mobile phone end receives data of the background control system and the BIM system, pushes the data to the mobile phone ends of project management personnel and field management personnel, and the field management personnel report the actual field progress and the labor amount every day at the mobile phone end and upload the data; every week, the management personnel of project department carry out dynamic management and control according to construction number week report, carry out the contrastive analysis of actual progress and planned progress, the resource contrast of adjustment personnel, material, equipment, the reason that the analysis progress lags, and in time take corresponding solution, optimize time limit for a project, balanced resource, adjustment progress, ensure to realize the time limit for a project target, realize the professional collaborative work in many fields, compare with prior art, make the degree of reduction degree of main part packing construction higher, guaranteed engineering quality.
The mobile phone end receives data sent by the background control system in real time, and management personnel of the project department check the number, delayed starting and delayed completion of the production tasks in the week in real time at the mobile phone end, and timely release factors restricting progress in the construction production process to achieve real-time supervision and implementation.
The field management personnel check the completion condition of the production task in the current day at the mobile phone end in real time, cooperate with field workers to find out common problems, solve the problems in real time, reduce recording work and efficiently optimize progress and resources.
The identification system comprises a face identification gate, a GPS (global positioning system) positioning module and an intelligent camera, wherein the face identification gate is arranged at an entrance of a construction site and is used for reading an information card of a site constructor and identifying identity approval to enter the site by combining face identification; the GPS positioning module is installed on the safety helmet and used for transmitting the position information of site constructors to the background control system in real time in a wireless mode, and the background control system carries out format conversion processing on the data and guides the data into the BIM system to realize personnel management and control.
Through the cooperative cooperation of multiple departments, the project cost is controllable, the period is controllable, the personnel is controllable, the project can accurately land, the super-first-class scene creative building system language can be converted through the project implementation land, and the super-first-class entertainment artistic project engineering can be customized for the customer.
The intelligent camera is installed on a construction site, transmits the acquired image to the background control system for automatic analysis, judges whether personnel in the image normally wear the safety helmet, and if the personnel in the image do not wear the safety helmet, the background control system sends violation information to a mobile phone end of corresponding site management personnel according to the construction site of the violation personnel, and reminds workers through the site management personnel.
According to the invention, a material purchasing plan is made and derived through the BIM system, the flow direction of the material is tracked in time according to the material two-dimensional code, the material is controlled, the material is supplied in time, and the cost in the aspect of the material is reduced to a certain extent; the BIM system is used for compiling a construction task, a total progress plan and a monthly plan, generating a construction digital weekly report, pushing the construction digital weekly report to a mobile phone end of project site management personnel, and the site management personnel fills and uploads the actual site progress and the labor amount at the mobile phone end every day, so that the integrated progress control of the whole flow is realized, the construction without regulation in the traditional technology is avoided, the powerful guarantee is provided for further shortening the construction period, and the labor cost is effectively reduced through the application of the BIM system, a background control system and the mobile phone end; every week, the management personnel of project department carry out dynamic management and control according to construction number week report, carry out the contrastive analysis of actual progress and planned progress, the resource contrast of adjustment personnel, material, equipment, the reason that the analysis progress is lagged to in time take corresponding solution measures, realize the professional collaborative work in many fields, compare with prior art, make the reduction degree of main part packing construction higher, guaranteed engineering quality.
The invention carries out omnibearing theme packaging and scene creation on rich entertainment artistic engineering through the cooperation of professional personnel in multiple fields such as overall planning, concept design, theme scheme design, construction planning, project management and the like, can carry out multiple style design by applying a professional design system, a digital engineering system, a mountain engineering design system, an engineering quality control system, an artistic effect control system and a resource storage system, can be suitable for different requirements of customers, customizes various scenes and the like, integrates advanced style concepts into creativity to form a unique design style, brings strong visual impact feeling, and has high final delivery result reduction degree, short construction period and lower cost.
The technical scope of the present invention is not limited to the above embodiments, and any modifications, equivalent variations and modifications made to the above embodiments according to the technical spirit of the present invention still fall within the technical scope of the present invention.
Claims (5)
1. The utility model provides a management and control system of main part class amusement project art engineering which characterized in that includes:
the background control system comprises a design system, a digital engineering system, a mountain engineering design system, an engineering quality control system, an artistic effect control system and a resource storage system which are comprehensively applied, and the background control system collects, analyzes and processes data of the systems;
the BIM system is used for compiling a material purchasing plan, a total progress plan and a monthly plan of a construction task, simulating a resource curve, a capital curve and a progress plan of any time period in the whole construction process in the BIM system, analyzing the rationality of the progress plan scheduling according to curve data, arranging a week progress plan by combining a BIM webpage end and generating a construction digital week report;
the material two-dimension code is generated according to the name, the category, the ordering amount and the supplier information of the material on the material purchasing plan and is attached to the corresponding material package;
the intelligent terminal is held by hand, after the material is purchased and enters a construction site, a site material auditor scans the material two-dimensional code by adopting the intelligent terminal, and transmits product information to the BIM system for auditing and confirmation to manage and control the material;
the mobile phone end receives data of the background control system and the BIM system, pushes the data to the mobile phone ends of project management personnel and field management personnel, and the field management personnel report the actual field progress and the labor amount every day at the mobile phone end and upload the data; the project department manager carries out dynamic management and control every week according to the construction digital weekly report, carries out comparative analysis of actual progress and planned progress, adjusts resource comparison of personnel, materials and equipment, analyzes the reason of progress delay, and timely takes corresponding solving measures to optimize the construction period, balance resources and adjust the progress and ensure the achievement of the construction period target;
the identification system comprises a face identification gate and a GPS positioning module, wherein the face identification gate is arranged at an entrance of a construction site and used for reading an information card of a site constructor and identifying identity approval to enter the site by combining face identification; the GPS positioning module is installed on the safety helmet and used for transmitting the position information of site constructors to the background control system in real time in a wireless mode, and the background control system carries out format conversion processing on the data and guides the data into the BIM system to realize personnel management and control.
2. The system for managing and controlling the artistic engineering of the subject entertainment projects, according to claim 1, wherein: the mobile phone end receives data sent by the background control system in real time, and management personnel of the project department check the number, delayed starting and delayed completion of the production tasks in the week in real time at the mobile phone end, and timely release factors restricting progress in the construction production process to achieve real-time supervision and implementation.
3. The system for managing and controlling the artistic engineering of the subject entertainment projects, according to claim 2, wherein: the field management personnel check the completion condition of the production task in the current day at the mobile phone end in real time, cooperate with field workers to find out common problems, solve the problems in real time, reduce recording work and efficiently optimize progress and resources.
4. The system for managing and controlling the artistic engineering of the subject entertainment projects, according to claim 1, wherein: before the material leaves the factory, paste the material two-dimensional code on corresponding packing, with logistics information such as entrusting logistics company's information and actual delivery date, arrival date, synchronous propelling movement to backstage control system, through the leading-in BIM system of backstage control system to on the personnel terminal that the job site is responsible for entering the factory and checks and accept is pushed to, conveniently know the goods and materials progress condition in real time.
5. The system for managing and controlling the artistic engineering of the subject entertainment projects, according to claim 1, wherein: the identification system further comprises an intelligent camera, the intelligent camera is installed on a construction site, the intelligent camera transmits the collected images to the background control system for automatic analysis, whether the personnel in the images wear the safety helmet normally is judged, if the personnel do not wear the safety helmet, the background control system sends violation information to a mobile phone end of corresponding site management personnel according to the construction site of the violation personnel, and the site management personnel remind workers.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110067258.3A CN112766720A (en) | 2021-01-19 | 2021-01-19 | Management and control system for main entertainment project art engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110067258.3A CN112766720A (en) | 2021-01-19 | 2021-01-19 | Management and control system for main entertainment project art engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN112766720A true CN112766720A (en) | 2021-05-07 |
Family
ID=75703034
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110067258.3A Pending CN112766720A (en) | 2021-01-19 | 2021-01-19 | Management and control system for main entertainment project art engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112766720A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN106228208A (en) * | 2016-07-21 | 2016-12-14 | 重庆工程职业技术学院 | Control system based on BIM and method |
CN109747326A (en) * | 2019-02-28 | 2019-05-14 | 广州市设计院工程建设总承包公司 | Artificial hillock preparation method and system |
CN110287859A (en) * | 2019-06-21 | 2019-09-27 | 国网天津市电力公司 | A kind of personnel's material dispatching system based on artificial intelligence technology |
CN111340458A (en) * | 2020-03-17 | 2020-06-26 | 中铁城建集团有限公司 | Construction progress informatization management method |
CN112163264A (en) * | 2020-10-10 | 2021-01-01 | 中国建筑第二工程局有限公司 | BIM-based rockery modular construction method and device and storage medium |
-
2021
- 2021-01-19 CN CN202110067258.3A patent/CN112766720A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105719200A (en) * | 2016-01-19 | 2016-06-29 | 上海杰图天下网络科技有限公司 | Method for carrying out engineering progress supervision by use of three-dimensional panoramic technology by combining BIM technology |
CN106228208A (en) * | 2016-07-21 | 2016-12-14 | 重庆工程职业技术学院 | Control system based on BIM and method |
CN109747326A (en) * | 2019-02-28 | 2019-05-14 | 广州市设计院工程建设总承包公司 | Artificial hillock preparation method and system |
CN110287859A (en) * | 2019-06-21 | 2019-09-27 | 国网天津市电力公司 | A kind of personnel's material dispatching system based on artificial intelligence technology |
CN111340458A (en) * | 2020-03-17 | 2020-06-26 | 中铁城建集团有限公司 | Construction progress informatization management method |
CN112163264A (en) * | 2020-10-10 | 2021-01-01 | 中国建筑第二工程局有限公司 | BIM-based rockery modular construction method and device and storage medium |
Non-Patent Citations (1)
Title |
---|
王海斌等: "万达文旅项目的BIM 设计施工一体化管控探索", 《土木建筑工程信息技术》, vol. 8, no. 5, pages 4 - 5 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Rohani et al. | Production line analysis via value stream mapping: a lean manufacturing process of color industry | |
CN104657835B (en) | A kind of engineering shop's scheduling and monitoring system and method | |
CN109146372A (en) | Global wisdom manufactures sales service system | |
CN113258669B (en) | Networked intelligent scheduling method and terminal based on distribution network maintenance | |
CN103246950A (en) | Method for promising order of semiconductor assembly and test enterprise | |
CN102955982A (en) | System for managing construction project contracting | |
CN110335017A (en) | One kind being based on BIM project amount charging Informatization Cooperative working method | |
CN106503896A (en) | Construction equipment management method based on BIM technology | |
CN108960519A (en) | Time based on big data analysis most short transportation route selection method | |
CN102081760A (en) | A method and a system for executing a scheduled production process | |
Ratajczak et al. | BIM-based augmented reality tool for the monitoring of construction performance and progress | |
CN103020723A (en) | Control method for booking cargo concentration in container wharf | |
CN112766720A (en) | Management and control system for main entertainment project art engineering | |
CN109583534B (en) | Equipment purchase fee automatic statistical method based on material ID and Internet of things label | |
CN110069826A (en) | A kind of project management method based on BIM, system and storage medium | |
CN103628483A (en) | Combined pouring simulation and optimization method for concrete dam pouring warehousing machinery | |
CN103473628A (en) | Method for controlling automatic fund transferring system | |
Chong et al. | Quality management on the 4th industrial revolution | |
CN115409392A (en) | Method and device for determining material production plan, storage medium and electronic equipment | |
CN115147175A (en) | Supply and demand matching purchasing analysis method and system based on integrated supply management | |
CN108256625A (en) | It is decomposed based on multilayer in modelling cloud and innovates creative method with the gunz summed up | |
Sumereder et al. | Digital Optimization in Action: From Models towards an Industrial Application. | |
Kibira et al. | Analysis of standards towards simulation-based integrated production planning | |
CN108764733A (en) | A kind of intelligent integrated for cable and its attachment production to sale manages system | |
CN116824010B (en) | Feedback type multiterminal animation design online interaction method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 528403 2nd floor, No.11 Huayuan new village, East District, Zhongshan City, Guangdong Province Applicant after: Guangdong vale Art Engineering Co.,Ltd. Address before: B209-1, 12 Minying West Road, Shiqi District, Zhongshan City, Guangdong Province, 528499 Applicant before: Guangdong vale Art Engineering Co.,Ltd. |