CN110069826A - A kind of project management method based on BIM, system and storage medium - Google Patents

A kind of project management method based on BIM, system and storage medium Download PDF

Info

Publication number
CN110069826A
CN110069826A CN201910240371.XA CN201910240371A CN110069826A CN 110069826 A CN110069826 A CN 110069826A CN 201910240371 A CN201910240371 A CN 201910240371A CN 110069826 A CN110069826 A CN 110069826A
Authority
CN
China
Prior art keywords
current
project
information
equipment
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910240371.XA
Other languages
Chinese (zh)
Other versions
CN110069826B (en
Inventor
董立功
魏星
覃先宁
陈振
张恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Opening Construction Engineering Co Ltd
Original Assignee
Jiangsu Opening Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Opening Construction Engineering Co Ltd filed Critical Jiangsu Opening Construction Engineering Co Ltd
Priority to CN201910240371.XA priority Critical patent/CN110069826B/en
Publication of CN110069826A publication Critical patent/CN110069826A/en
Application granted granted Critical
Publication of CN110069826B publication Critical patent/CN110069826B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a kind of project management method based on BIM, system and storage mediums, are related to construction engineering technical field, solve the problem of management that engineering project is confined to the scattered point such as monomer engineering more, lack the construction management and control means of overall process;Wherein: including: to control equipment detection generator to whether there is the real-time generation of current project source information;If there is the real-time generation of current project source information, it then controls image capture device and acquires the current project source information generated in real time, and from the corresponding relationship of pre-set project source information and project operation information, current project operation information is searched, and current project source information, current project operation information are loaded in basic BIM model;Control equipment stores BIM model to fixed equipment, handheld device and synchronized upload to cloud server;A kind of project management method based on BIM, system and storage medium of the invention, the convenient construction management and control that overall process is given to engineering project.

Description

A kind of project management method based on BIM, system and storage medium
Technical field
The present invention relates to construction engineering technical field, in particular to a kind of project management method based on BIM, system and deposit Storage media.
Background technique
Building Information Model BIM is the new tool of architecture, engineering science and civil engineering.Building Information Model or building money News one word of model is created by Autodesk.It come describe those based on 3-D graphic, object orientation, architecture it is related Computer aided design.
Promotion and development based on BIM technology, BIM technology starts to influence the whole flow process of construction, in engineering project Equal fields are confined to the management of the scattered point such as monomer engineering more, lack the construction management and control means of overall process.Such as In an architectural engineering, BIM threedimensional model for related personnel by terminal device can be directly viewable the progress of current engineering with And parameter, but the information such as cost parameters and engineering project involved in specific current schedules, then it is in space state, it is inconvenient In the construction management and control of overall process, there is improved space.
Summary of the invention
The first object of the present invention is to provide a kind of project management method based on BIM, convenient to give entirely to engineering project The construction management and control of process.
Above-mentioned technical purpose of the invention has the technical scheme that
A kind of project management method based on BIM, the method be applied at least one control equipment, the control equipment with hold Equipment, fixed equipment communication connection, the control equipment control handheld device, fixed equipment, which have, to be previously provided with comprising project pipe Manage the basic BIM model of essential information;The control equipment and image capture device communicate to connect, which comprises
The control equipment detection generator whether there is the real-time generation of current project source information;The current project source information Builder's diary information on the day of including: the current construction speed information of project, project;
If detecting the real-time generation on generator there are current project source information, equipment control described image acquisition is controlled Equipment acquires the current project source information generated in real time, and corresponding with project operation information from pre-set project source information In relationship, corresponding with current project source information current project operation information is searched, and the control equipment is by currentitem Mesh source information, current project operation information load in basic BIM model;The project operation information includes the current one time Output value T, current one time cost I and current one time schedule V;
The control equipment stores the BIM model for being loaded with current project source information, current project operation information to solid Locking equipment, handheld device and synchronized upload are to cloud server.
By using above-mentioned technical proposal, during project carries out, by project source information and pass through project source in real time Treated that project operation information loads in BIM model for information operation, control equipment will be loaded with current project source information, when The BIM model of preceding project operation information is stored to fixed equipment, handheld device and synchronized upload to cloud server, is convenient for Staff relevant to the project gives the construction management and control of overall process to project.
The present invention is further arranged to: when described image acquisition equipment acquires the current project source information generated in real time, institute The multiframe target image for the current project source information that control equipment control described image acquisition equipment acquisition generates in real time is stated, and is remembered Record the timestamp of each frame target image.
By using above-mentioned technical proposal, controls equipment control described image acquisition equipment and acquire the currentitem generated in real time The multiframe target image of mesh source information, and the timestamp of each frame target image is recorded, convenient for the staff with the project Solve current project source information, the generation time of current project operation information.
The present invention is further arranged to: will be loaded with current project source information, current project operation in the control equipment The BIM model of information is stored to before handheld device, the method also includes:
The control equipment obtains the first control instruction, and first control instruction is used to indicate to be directed to and will store up to handheld device The BIM model carry out light-weight technologg;
The control equipment is based on first control instruction obtained, for will store up to the BIM mould of handheld device Type carries out light-weight technologg.
By using above-mentioned technical proposal, light-weight technologg is given to the BIM model of storage to handheld device, it is ensured that Under the premise of important information is stored into handheld device, mitigate the operating pressure of handheld device.
The present invention is further arranged to: the control equipment will be loaded with current project source information, current project operation letter The BIM model of breath is stored to before fixed equipment, handheld device and synchronized upload to cloud server, and this method is also wrapped It includes:
The control equipment obtains the second control instruction, and second control instruction is used to indicate for the current one time output value T and current one time schedule V does the first algorithm operation and the first algorithm operation result is loaded on the BIM model, described First algorithm operation are as follows:
--- current one time output value T, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time output value T;
--- it is the variance of current one time schedule V;
--- it is current one time output value T, two covariance of current one time schedule V;
The control equipment is based on second control instruction obtained, for current one time output value T and current one Time schedule V does the first algorithm operation and the first algorithm operation result is loaded on the BIM model.
By using above-mentioned technical proposal, by the first algorithm calculate unit time output value T and current one time into The related coefficient of V is spent, so that can have to the two related coefficient clearly in projects convenient for staff relevant to the project Clear understanding adjusts current project progress convenient for finding the problem in time.
The present invention is further arranged to: the control equipment will be loaded with current project source information, current project operation letter The BIM model of breath is stored to before fixed equipment, handheld device and synchronized upload to cloud server, and this method is also wrapped It includes:
The control equipment obtains third control instruction, and the third control instruction is used to indicate for current one time cost I and current one time schedule V does the second algorithm operation and the second algorithm operation result is loaded on the BIM model, described Second algorithm operation are as follows:
--- it is current one time cost I, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time cost I;
--- it is the variance of current one time schedule V;
--- it is current one time cost I, two covariance of current one time schedule V;
The control equipment is based on second control instruction obtained, for current one time cost I and current one Time schedule V does the second algorithm operation and the second algorithm operation result is loaded on the BIM model.
By using above-mentioned technical proposal, when calculating current one time cost I and current one by the second algorithm Between progress V related coefficient so that in projects convenient for staff relevant to the project can be to the two related coefficient Have and clearly understand, adjusts current project progress convenient for finding the problem in time.
The present invention is further arranged to: the method also includes:
The control equipment obtains the 4th control instruction, and the 4th control instruction is used to indicate handheld device or fixed equipment Interface is registered into specific information, specific information registration interface includes at least the registration option of two kinds of different register informations;
The control equipment obtains the 4th control instruction, and handheld device or fixed equipment, which enter into specific information, registers boundary Face, and in response to the selection at least one registration option for the registration of corresponding specific information.
By using above-mentioned technical proposal, specific information registers the setting at interface, is convenient for professional people relevant to the project Member increases specific information by handheld device or fixed equipment.
The present invention is further arranged to: the registration of the specific information includes the registration of special equipment relevant information;It is described It controls equipment and obtains the 4th control instruction, handheld device or fixed equipment, which enter into specific information, registers interface, and responds After the selection of option being registered at least one for the typing of corresponding specific information, the method also includes:
The control equipment obtains the 5th control instruction, and the 5th control instruction is used to specific information being integrated in two dimensional code;
The control equipment obtains the 5th control instruction, generates the two dimensional code for being integrated with specific information to realize that it is special that barcode scanning is checked Information.
By using above-mentioned technical proposal, the setting of two dimensional code can be obtained convenient for staff by barcode scanning two dimensional code Specific information, and then realize the shared of specific information.
The second object of the present invention is to provide a kind of project management system based on BIM, convenient to give entirely to engineering project The construction management and control of process.
Above-mentioned technical purpose of the invention has the technical scheme that
A kind of project management system based on BIM, is applied at least one control equipment, and the control equipment and handheld device are consolidated Locking equipment communication connection, the control equipment generate basic BIM model according to project management essential information, further includes:
Detection unit, the control equipment detection generator whether there is the real-time generation of current project source information;It is described current Project source information include: the current construction speed information of project, project on the day of builder's diary information;
Processing unit is controlled, if for detecting that the real-time generation on generator there are current project source information, control are set Standby control described image acquisition equipment acquires the current project source information generated in real time, and from pre-set project source information with In the corresponding relationship of project operation information, current project operation information corresponding with the current project source information, and institute are searched Control equipment is stated to load on current project source information, current project operation information in basic BIM model;The project operation letter Breath includes current one time output value T, current one time cost I and current one time schedule V;
The control processing unit, current project source information, current project operation information will be loaded with by being also used to control equipment The BIM model is stored to fixed equipment, handheld device and synchronized upload to cloud server.
By using above-mentioned technical proposal, during project carries out, by project source information and pass through project source in real time Treated that project operation information loads in BIM model for information operation, control equipment will be loaded with current project source information, when The BIM model of preceding project operation information is stored to fixed equipment, handheld device and synchronized upload to cloud server, is convenient for Staff relevant to the project gives the construction management and control of overall process to project.
The third object of the present invention is to provide storage medium, is stored with computer executable instructions in the storage medium, A kind of any one of 1-7 project management method based on BIM is required for perform claim when executed.
In conclusion the invention has the following advantages: it is convenient to engineering project give overall process construction management and Control.
Detailed description of the invention
Fig. 1 is a kind of flow chart of project management method based on BIM;
Fig. 2 is a kind of management module of project management method based on BIM.
Specific embodiment
Below in conjunction with attached drawing 1-2, invention is further described in detail.
The embodiment of the present invention provides a kind of project management method based on BIM, and method is applied at least one control equipment, control Control equipment and handheld device, fixed equipment communicate to connect, and control equipment control handheld device, fixed equipment, which have, is previously provided with packet The basic BIM model of the essential information containing project management.Basic BIM model carries out work by the software of core of REVIT and BENTLEY Journey model creation, and it is fine including model fractionation rule, model naming rule, modeling depth requirements, model based coding rule, model Degree;Secondly according to project essential information, the basic BIM model for being loaded with project essential information is completed.
The main flow of method is described as follows.
Referring to Fig.1:
Step 110: control equipment detection generator whether there is the real-time generation of current project source information;Current project source information Builder's diary information on the day of including: the current construction speed information of project, project;
Step 120: if detecting the real-time generation on generator there are current project source information, controlling equipment control image Acquisition equipment acquires the current project source information that generates in real time, and from pre-set project source information and project operation information In corresponding relationship, current project operation information corresponding with current project source information is searched, and controls equipment for current project source Information, current project operation information load in basic BIM model;Project operation information include current one time output value T, when Preceding long-run cost rate I and current one time schedule V;In the present embodiment, the unit time can be one day, one week, one Month etc..
Step 130: control equipment stores the BIM model for being loaded with current project source information, current project operation information To fixed equipment, handheld device and synchronized upload to cloud server.
During project carries out, transported in real time by project source information and by the project after project source information calculation process It calculates information to load in BIM model, control equipment will be loaded with the BIM mould of current project source information, current project operation information Type is stored to fixed equipment, handheld device and synchronized upload to cloud server, is convenient for staff couple relevant to the project Project gives the construction management and control of overall process.
BIM model using basic BIM model as core, serve as theme by construction speed herein, and builder's diary is supplementary means, collection At BIM project management platform;Integrated site operation safe mass information, progress cost information form projects information data Library.And current project source information further includes turnkey contract essential information, signs information, bill of quantities, subcontract inventory, base This information signs information, bill of quantities, construction task.
Meanwhile project progress and cost management are realized by the BIM of building, schedule and threedimensional model are mounted, shape At progress model, acquire builder's diary data, driving threedimensional model forms actual progress model, realize actual progress and plan into Degree compares, according to the actual situation timely plan for adjustment progress;According to monthly actual progress situation, incorporation engineering amount inventory forms this Month output value and cost statistics table.Engineering material management is realized by the BIM project management platform of building, and the storage of project goods and materials is stepped on Note, buying registration.System is registered by materials warehousing, can form main material price trend curve, the prediction of project gross profit;System is logical The consumption of materials is crossed, cost of building projects is estimated.Engineering site management is realized by the BIM of building, by site operation log, task It assigns, the data summarizations such as site safety quality problems, forms report, case is stayed to achieve.Realize that engineering technology is handed over by the BIM of building Bottom and management of blueprint mount the relevant construction drawing of component and file of confiding a technological secret with component, and realization is read from model Data, on-the-spot guidance construction are taken, and then the personnel's construction management that develops skill is horizontal.Engineering data pipe is realized by the BIM of building The data such as the security document of engineering project, qualitative data, project News Review, vital document are carried out upload management, make item by reason Mesh personnel understand newest project information, newest trade trend, the latest specification file etc. in time.
Engineering safety and quality management are realized by the BIM project management platform of building, and project safety, quality problem is mentioned Upper problem rectifies and improves process, pushes in real time, carries out the inspection that situation is replied in rectification, auxiliary according to safety, quality problem early warning prompt Project carries out safety, quality management.The management of engineering project enterprise-level is realized by the BIM project management platform of building, by enterprise Accepted project carries out targeted information integration, realizes overall management of the enterprise to all engineering projects.
Herein, when image capture device acquires the current project source information generated in real time, control equipment control image is adopted The multiframe target image for the current project source information that collection equipment acquisition generates in real time, and record the time of each frame target image Stamp.And generator is the operation pages that can input information, when input has information in operation pages, then controls equipment and detects life There is the real-time generation of information on growing up to be a useful person.
The BIM model for being loaded with current project source information, current project operation information is stored to hand-held in control equipment Before equipment, method further include: control equipment obtain the first control instruction, the first control instruction be used to indicate for will store up to The BIM model of handheld device carries out light-weight technologg;Control equipment be based on the first control instruction obtained, for will store up to The BIM model of handheld device carries out light-weight technologg.Light-weight technologg is given to the BIM model of storage to handheld device, it is ensured that Under the premise of important information is stored into handheld device, mitigate the operating pressure of handheld device.
The BIM model for being loaded with current project source information, current project operation information is stored to fixation and is set by control equipment Before standby, handheld device and synchronized upload to cloud server, this method further include: control equipment obtains the second control instruction, Second control instruction be used to indicate for current one time output value T and current one time schedule V do the first algorithm operation and First algorithm operation result is loaded on into BIM model, the first algorithm operation are as follows:
--- current one time output value T, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time output value T;
--- it is the variance of current one time schedule V;
--- it is current one time output value T, two covariance of current one time schedule V;
It controls equipment and is based on the second control instruction obtained, for current one time output value T and current one time schedule V It does the first algorithm operation and the first algorithm operation result is loaded on into BIM model.
The BIM model for being loaded with current project source information, current project operation information is stored to fixation and is set by control equipment Before standby, handheld device and synchronized upload to cloud server, this method further include:
It controls equipment and obtains third control instruction, third control instruction is used to indicate for current one time cost I and current Unit time progress V does the second algorithm operation and the second algorithm operation result is loaded on BIM model, the second algorithm operation are as follows:
--- it is current one time cost I, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time cost I;
--- it is the variance of current one time schedule V;
--- it is current one time cost I, two covariance of current one time schedule V;
It controls equipment and is based on the second control instruction obtained, for current one time cost I and current one time schedule V It does the second algorithm operation and the second algorithm operation result is loaded on into BIM model.When current one time cost I, current one Between progress V pairwise correlation coefficient and current one time output value T, current one time schedule V pairwise correlation coefficient load, be convenient for phase The staff of pass learns related coefficient, adjusts current project progress convenient for finding the problem in time.
Method further include: control equipment obtain the 4th control instruction, the 4th control instruction be used to indicate handheld device or Fixed equipment enters specific information registration interface, and specific information registers the registration choosing that interface includes at least two kinds of different register informations ?;It controls equipment and obtains the 4th control instruction, handheld device or fixed equipment, which enter into specific information, registers interface, and rings Ying Yu registers the selection of option at least one for the registration of corresponding specific information.
The registration of specific information includes the registration of special equipment relevant information, such as special equipment certificate expiration time letter Breath, equipment annual test prompting message;It controls equipment and obtains the 4th control instruction, handheld device or fixed equipment enter into special After information registers interface, and the selection in response to registering option at least one is for the typing of corresponding specific information, side Method further include: control equipment obtains the 5th control instruction, and the 5th control instruction is used to specific information being integrated in two dimensional code;Control Equipment obtains the 5th control instruction, generates the two dimensional code for being integrated with specific information to realize that barcode scanning checks specific information.Secondly, control Control equipment control handheld device or fixed equipment are given certificate expiration to staff and are reminded, the function that equipment annual test is reminded. Its secondary control equipment opens the main interface of handheld device or fixed equipment receiving can control when checking instruction for staff, Main interface include builder's diary, task dynamic, task assignment, safety problem reports, quality problems report, learning center, The information such as 4DBIM, wisdom building site, video conference rewards and punishments notice, it is real by handheld device or fixed equipment convenient for staff Existing project management function.
In the present embodiment, the first control instruction, the second control instruction, third control instruction, the 4th control instruction, the 5th Control instruction can be issued after the operational order for obtaining staff by special control operation panel, can also be by the people that works Member's operation handheld device (such as mobile phone, tablet computer, hand-held remote controller)/fixed equipment issues, on condition that the handheld device/ The communication connection of equipment will be established and be controlled to fixed equipment, and can come as the instruction triggers equipment of control equipment using.
The embodiment of the invention also provides storage medium, computer executable instructions are stored in the storage medium, work as finger Order is performed for executing a kind of project management method based on BIM of the embodiment of the present invention.
Based on the same inventive concept, the embodiment of the present invention provides a kind of project management system based on BIM, is applied at least One control equipment, control equipment and handheld device, fixed equipment communicate to connect, and control equipment is raw according to project management essential information At basic BIM model;Include:
Detection unit, control equipment detection generator whether there is the real-time generation of current project source information;Current project source letter Breath include: the current construction speed information of project, project on the day of builder's diary information;
Processing unit is controlled, if for detecting that the real-time generation on generator there are current project source information, control are set Standby control image capture device acquires the current project source information generated in real time, and from pre-set project source information and project In the corresponding relationship of operation information, current project operation information corresponding with current project source information is searched, and controlling equipment will Current project source information, current project operation information load in basic BIM model;When project operation information includes current one Between output value T, current one time cost I and current one time schedule V;
Processing unit is controlled, is also used to control the BIM mould that equipment will be loaded with current project source information, current project operation information Type is stored to fixed equipment, handheld device and synchronized upload to cloud server.
It is apparent to those skilled in the art that for convenience and simplicity of description, only with above-mentioned each function The division progress of module can according to need and for example, in practical application by above-mentioned function distribution by different function moulds Block is completed, i.e., the internal structure of device is divided into different functional modules, to complete all or part of function described above Energy.The specific work process of the system, apparatus, and unit of foregoing description, can be with reference to corresponding in preceding method embodiment Journey, details are not described herein.
In embodiment provided herein, it should be understood that disclosed system, device and method can pass through Other modes are realized.For example, the apparatus embodiments described above are merely exemplary, for example, stroke of module or unit Point, only a kind of logical function partition, there may be another division manner in actual implementation, such as multiple units or components can To combine or be desirably integrated into another system, or some features can be ignored or not executed.Another point, it is shown or beg for The mutual coupling, direct-coupling or communication connection of opinion can be through some interfaces, the INDIRECT COUPLING of device or unit Or communication connection, it can be electrical property, mechanical or other forms.
Above-mentioned unit as illustrated by the separation member may or may not be physically separated, aobvious as unit The component shown may or may not be physical unit, it can and it is in one place, or may be distributed over multiple In network unit.It can select some or all of unit therein according to the actual needs to realize the mesh of this embodiment scheme 's.
It, can also be in addition, each functional unit in each embodiment of the application can integrate in one processing unit It is that each unit physically exists alone, can also be integrated in one unit with two or more units.Above-mentioned integrated list Member both can take the form of hardware realization, can also realize in the form of software functional units.
Those of ordinary skill in the art will appreciate that: realize that all or part of the steps of above method embodiment can pass through The relevant hardware of program instruction is completed, and program above-mentioned can store in computer-readable storage medium, which exists When execution, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes: movable storage device, read-only deposits The various media that can store program code such as reservoir (Read Only Memory, ROM), magnetic or disk.
If alternatively, the above-mentioned integrated unit of the present invention is realized in the form of software function module and as independent product When selling or using, it also can store in a computer readable storage medium.Based on this understanding, the present invention is implemented Substantially the part that contributes to existing technology can be embodied in the form of software products the technical solution of example in other words, The computer software product is stored in a storage medium, including some instructions are used so that computer equipment (can be with It is personal computer, server or network equipment etc.) execute all or part of each embodiment method of the present invention.And it is preceding The storage medium stated includes: the various media that can store program code such as movable storage device, ROM, magnetic or disk.
Above embodiments are only described in detail to the technical solution to the application, but the explanation of above embodiments is only It is to be used to help understand method and its core concept of the invention, should not be construed as limiting the invention.The art In the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of by technical staff, should all cover in guarantor of the invention Within the scope of shield.

Claims (9)

1. a kind of project management method based on BIM, the method is applied at least one control equipment, the control equipment and hand Holding equipment, fixed equipment communication connection, the control equipment control handheld device, fixed equipment, which have, to be previously provided with comprising project Manage the basic BIM model of essential information;It is characterized by: the control equipment and image capture device communicate to connect, it is described Method includes:
The control equipment detection generator whether there is the real-time generation of current project source information;The current project source information Builder's diary information on the day of including: the current construction speed information of project, project;
If detecting the real-time generation on generator there are current project source information, equipment control described image acquisition is controlled Equipment acquires the current project source information generated in real time, and corresponding with project operation information from pre-set project source information In relationship, corresponding with current project source information current project operation information is searched, and the control equipment is by currentitem Mesh source information, current project operation information load in basic BIM model;The project operation information includes the current one time Output value T, current one time cost I and current one time schedule V;
The control equipment stores the BIM model for being loaded with current project source information, current project operation information to solid Locking equipment, handheld device and synchronized upload are to cloud server.
2. a kind of project management method based on BIM according to claim 1, it is characterized in that: described image acquires equipment When acquiring the current project source information generated in real time, what the control equipment control described image acquisition equipment acquisition generated in real time The multiframe target image of current project source information, and record the timestamp of each frame target image.
3. a kind of project management method based on BIM according to claim 2, it is characterized in that: being incited somebody to action in the control equipment It is loaded with current project source information, the BIM model of current project operation information is stored to before handheld device, the method Further include:
The control equipment obtains the first control instruction, and first control instruction is used to indicate to be directed to and will store up to handheld device The BIM model carry out light-weight technologg;
The control equipment is based on first control instruction obtained, for will store up to the BIM mould of handheld device Type carries out light-weight technologg.
4. a kind of project management method based on BIM according to claim 1, it is characterized in that: the control equipment will add It is loaded with current project source information, the BIM model of current project operation information is stored to fixed equipment, handheld device and synchronization It is uploaded to before cloud server, this method further includes
The control equipment obtains the second control instruction, and second control instruction is used to indicate for the current one time output value T and current one time schedule V does the first algorithm operation and the first algorithm operation result is loaded on the BIM model, described First algorithm operation are as follows:
--- current one time output value T, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time output value T;
--- it is the variance of current one time schedule V;
--- it is current one time output value T, two covariance of current one time schedule V;
The control equipment is based on second control instruction obtained, for current one time output value T and current one Time schedule V does the first algorithm operation and the first algorithm operation result is loaded on the BIM model.
5. a kind of project management method based on BIM according to claim 4, it is characterized in that: the control equipment will add It is loaded with current project source information, the BIM model of current project operation information is stored to fixed equipment, handheld device and synchronization It is uploaded to before cloud server, this method further include:
The control equipment obtains third control instruction, and the third control instruction is used to indicate for current one time cost I and current one time schedule V does the second algorithm operation and the second algorithm operation result is loaded on the BIM model, described Second algorithm operation are as follows:
--- it is current one time cost I, current one time schedule V pairwise correlation coefficient;
--- it is the variance of current one time cost I;
--- it is the variance of current one time schedule V;
--- it is current one time cost I, two covariance of current one time schedule V;
The control equipment is based on second control instruction obtained, for current one time cost I and current one Time schedule V does the second algorithm operation and the second algorithm operation result is loaded on the BIM model.
6. a kind of project management method based on BIM according to claim 1, it is characterized in that: the method also includes:
The control equipment obtains the 4th control instruction, and the 4th control instruction is used to indicate handheld device or fixed equipment Interface is registered into specific information, specific information registration interface includes at least the registration option of two kinds of different register informations;
The control equipment obtains the 4th control instruction, and handheld device or fixed equipment, which enter into specific information, registers boundary Face, and in response to the selection at least one registration option for the registration of corresponding specific information.
7. a kind of project management method based on BIM according to claim 6, it is characterized in that: the specific information is stepped on Note includes the registration of special equipment relevant information;The control equipment obtains the 4th control instruction, and handheld device or fixation are set The standby specific information that enters registers interface, and in response to the selection at least one registration option for corresponding specific information Typing after, the method also includes:
The control equipment obtains the 5th control instruction, and the 5th control instruction is used to specific information being integrated in two dimensional code;
The control equipment obtains the 5th control instruction, generates the two dimensional code for being integrated with specific information to realize that it is special that barcode scanning is checked Information.
8. a kind of project management system based on BIM, it is applied at least one control equipment, the control equipment and handheld device, Fixed equipment communication connection, the control equipment generate basic BIM model according to project management essential information, it is characterised in that: Further include:
Detection unit, the control equipment detection generator whether there is the real-time generation of current project source information;It is described current Project source information include: the current construction speed information of project, project on the day of builder's diary information;
Processing unit is controlled, if for detecting that the real-time generation on generator there are current project source information, control are set Standby control described image acquisition equipment acquires the current project source information generated in real time, and from pre-set project source information with In the corresponding relationship of project operation information, current project operation information corresponding with the current project source information, and institute are searched Control equipment is stated to load on current project source information, current project operation information in basic BIM model;The project operation letter Breath includes current one time output value T, current one time cost I and current one time schedule V;
The control processing unit, current project source information, current project operation information will be loaded with by being also used to control equipment The BIM model is stored to fixed equipment, handheld device and synchronized upload to cloud server.
9. storage medium, computer executable instructions are stored in the storage medium, when executed for holding A kind of any one of row claim 1-7 project management method based on BIM.
CN201910240371.XA 2019-03-28 2019-03-28 Project management method, system and storage medium based on BIM Active CN110069826B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910240371.XA CN110069826B (en) 2019-03-28 2019-03-28 Project management method, system and storage medium based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910240371.XA CN110069826B (en) 2019-03-28 2019-03-28 Project management method, system and storage medium based on BIM

Publications (2)

Publication Number Publication Date
CN110069826A true CN110069826A (en) 2019-07-30
CN110069826B CN110069826B (en) 2022-12-06

Family

ID=67366692

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910240371.XA Active CN110069826B (en) 2019-03-28 2019-03-28 Project management method, system and storage medium based on BIM

Country Status (1)

Country Link
CN (1) CN110069826B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110782124A (en) * 2019-09-20 2020-02-11 中铁二十一局集团电务电化工程有限公司 BIM-based task processing method and device, server and storage medium
CN111428965A (en) * 2020-02-27 2020-07-17 中铁城建集团有限公司 Method for rapidly analyzing project cost
CN111539690A (en) * 2020-04-28 2020-08-14 悉地(苏州)勘察设计顾问有限公司 Construction project collaborative management method and system based on BIM

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
US20170053244A1 (en) * 2015-08-22 2017-02-23 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN108388711A (en) * 2018-02-07 2018-08-10 深圳群伦项目管理有限公司 A kind of engineering design based on BIM and management system
CN109408979A (en) * 2018-10-31 2019-03-01 广西路桥工程集团有限公司 A kind of engineering construction internal control data management system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20170053244A1 (en) * 2015-08-22 2017-02-23 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN105844380A (en) * 2016-01-26 2016-08-10 湖北文理学院 BIM-based BIM project element management method and system
CN108388711A (en) * 2018-02-07 2018-08-10 深圳群伦项目管理有限公司 A kind of engineering design based on BIM and management system
CN109408979A (en) * 2018-10-31 2019-03-01 广西路桥工程集团有限公司 A kind of engineering construction internal control data management system

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
寇雪霞等: "BIM技术在施工阶段的成本控制应用", 《经济师》 *
张连营等: "基于BIM的建筑工程项目进度-成本协同管理系统框架构建", 《项目管理技术》 *
董娜等: "基于BIM和PDCA的施工项目精益管理研究", 《项目管理技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110782124A (en) * 2019-09-20 2020-02-11 中铁二十一局集团电务电化工程有限公司 BIM-based task processing method and device, server and storage medium
CN111428965A (en) * 2020-02-27 2020-07-17 中铁城建集团有限公司 Method for rapidly analyzing project cost
CN111428965B (en) * 2020-02-27 2023-11-03 中铁城建集团有限公司 Method for rapidly analyzing project cost
CN111539690A (en) * 2020-04-28 2020-08-14 悉地(苏州)勘察设计顾问有限公司 Construction project collaborative management method and system based on BIM

Also Published As

Publication number Publication date
CN110069826B (en) 2022-12-06

Similar Documents

Publication Publication Date Title
Abdirad Metric-based BIM implementation assessment: a review of research and practice
CN111598379A (en) Project management method, platform, device, computer equipment and storage medium
Hasan et al. Blockchain-based solution for the traceability of spare parts in manufacturing
US7860810B2 (en) Discrete event system and method for simulating global product development
CN111950975A (en) BIM technology-based multi-organization coordination management cloud platform for construction engineering project
CN108416701A (en) A kind of processing method of the Engineering Project Construction real data based on BIM
CN110069826A (en) A kind of project management method based on BIM, system and storage medium
CN109685452A (en) A kind of power supply company's item data management platform
CN102662069A (en) Detection system and detection method of plastic packaging materials based on Internet of things and cloud technology
Kang et al. Managing construction schedule by telepresence: Integration of site video feed with an active nD CAD simulation
CN115375146A (en) Digital construction integrated platform
CN112541692B (en) Scientific data management plan generation method and device
CN104182829A (en) Instrument development reliability management and support system
CN108960758A (en) Architectural engineering process control management system
CN109033253A (en) Data integrating method and device
CN113379369A (en) Full life cycle's management system based on wisdom building
CN108470049A (en) A kind of construction project management system based on instrument board
Zhao et al. Design of project cost information management and analysis system based on BIM technology
US20220300889A1 (en) Work management apparatus, work management method, and recording medium
CN112085341A (en) Master station system suitable for risk management and control of overall process of power production operation
Osan et al. The BIM revolution
Elitok Digital transformation toward industry 4.0: a case studyin Turkey
Genaidy et al. A roadmap for a methodology to assess, improve and sustain intra‐and inter‐enterprise system performance with respect to technology‐product life cycle in small and medium manufacturers
Yung et al. A mechanism for the integration of TQM and MRPII
Williamson et al. A policy toolkit for the app economy-where online meets offline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant