CN112064676A - Movable formwork structure and construction method thereof - Google Patents

Movable formwork structure and construction method thereof Download PDF

Info

Publication number
CN112064676A
CN112064676A CN202011056460.8A CN202011056460A CN112064676A CN 112064676 A CN112064676 A CN 112064676A CN 202011056460 A CN202011056460 A CN 202011056460A CN 112064676 A CN112064676 A CN 112064676A
Authority
CN
China
Prior art keywords
groove
template
construction
formwork
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011056460.8A
Other languages
Chinese (zh)
Inventor
庞有源
孙娜
伍晓波
吴文谷
幸化兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Chongqing Construction Engineering Group Co Ltd
No 3 Construction Co Ltd of Chongqing Construction Engineering Group
Original Assignee
NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Chongqing Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP, Chongqing Construction Engineering Group Co Ltd filed Critical NO3 CONSTRUCTION Co Ltd OF CHONGQING CONSTRUCTION ENGINEERING GROUP
Priority to CN202011056460.8A priority Critical patent/CN112064676A/en
Publication of CN112064676A publication Critical patent/CN112064676A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G9/00Installations of electric cables or lines in or on the ground or water
    • H02G9/02Installations of electric cables or lines in or on the ground or water laid directly in or on the ground, river-bed or sea-bottom; Coverings therefor, e.g. tile

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明属于电缆沟槽施工技术领域,具体的说是一种移动模架结构及其施工方法,且施工方法包括模架系统加工制作、施工准备、接触面处理、排水盲管安装、钢筋绑扎安装、模架移动定位、埋管件安装固定、模架整体加固封堵、一次性整体浇筑混凝、养护及拆模和模架移动进入下一施工段步骤;该施工方法施工操作简单、方便,质量好,施工速度快、效率高,劳动强度低,省时省工,综合施工成本低,经济效益好,适用于隧道电缆沟槽、路基排水沟等沟槽结构施工。

Figure 202011056460

The invention belongs to the technical field of cable trench construction, in particular to a movable formwork structure and a construction method thereof, and the construction method includes the processing and fabrication of a formwork system, construction preparation, contact surface treatment, installation of draining blind pipes, and installation of steel bar binding , The formwork is moved and positioned, the buried pipe fittings are installed and fixed, the formwork is integrally reinforced and blocked, the one-time integral concrete pouring, maintenance and formwork removal and formwork movement into the next construction section steps; the construction method is simple, convenient, and high-quality. Good, fast construction speed, high efficiency, low labor intensity, saving time and labor, low comprehensive construction cost, good economic benefits, suitable for tunnel cable trenches, roadbed drainage trenches and other trench structures.

Figure 202011056460

Description

一种移动模架结构及其施工方法A mobile formwork structure and its construction method

技术领域technical field

本发明属于电缆沟槽施工技术领域,具体的说是一种移动模架结构及其施工方法。The invention belongs to the technical field of cable trench construction, in particular to a movable formwork structure and a construction method thereof.

背景技术Background technique

电缆沟槽是电网系统中变电站、开关站的重要建筑工程,也常在隧道等基础设施中建造,其施工质量关系到电缆线路的运行质量和线路设备的运行寿命,其可持续性非常重要,因此电缆沟槽的施工技术越来越受到重视。传统的电缆沟槽施工主要采用木模和小块组合钢模分段施工,施工工序包括模板组装、加固、混凝土浇筑、模板拆卸、转场、清洁涂油等,费时费工,模板工程施工成本高,工序繁杂,循环时间长,加固支撑多,整体性差,顶面平整度不易控制,接槎处易渗漏水,外观质量难控制,作业面文明形象不好。随着我国电力基础设施的日趋完善,电缆沟槽建设规模也日益扩大,传统电缆沟槽施工技术迫切需要创新改进,满足电力基础设施可持续发展的需求。Cable trenches are important construction projects for substations and switch stations in the power grid system, and are often built in infrastructure such as tunnels. The construction quality is related to the operating quality of the cable line and the operating life of the line equipment. Its sustainability is very important. Therefore, more and more attention has been paid to the construction technology of cable trenches. The traditional cable trench construction mainly uses wooden formwork and small combined steel formwork for segmental construction. The construction process includes formwork assembly, reinforcement, concrete pouring, formwork disassembly, transfer, cleaning and oiling, etc., which is time-consuming and labor-intensive, and the construction cost of formwork works. High, complex procedures, long cycle time, many reinforcement supports, poor integrity, difficult to control the flatness of the top surface, easy to leak water at the joints, difficult to control the appearance quality, poor civilized image of the working surface. With the improvement of my country's power infrastructure, the scale of cable trench construction is also expanding. The traditional cable trench construction technology urgently needs innovation and improvement to meet the needs of sustainable development of power infrastructure.

重庆建工第三建设有限责任公司依托实际工程项目实践,针对施工难点痛点,根据现场实际情况,大胆创新,研发出移动式模架及配套的定型模板,通过丝杆把模板悬挂起来,再将模板移动调整到设计的位置,采用定位卡装置固定模板与模板之间的相对位置和模板与模架的相对位置,模板固定后浇注结构,待结构成型脱模后,通过人工推动或机械牵引使模架整体移动到下一段混凝土浇注的位置,从而将传统施工工艺中分层、多次、多工序浇筑合理优化为移动定位调节、清洁涂油和整体浇筑三道施工工序循环,极大提高了施工工效,基本杜绝了质量缺陷,经在多个项目的反复实践总结,最终形成了施工速度快、操作简单、质量高、综合成本低且符合“四节一环保”要求的基于新型装配移动式模架的电缆沟槽施工工法,受到业主等各方一致好评,具有良好的推广应用价值。Chongqing Construction Engineering Third Construction Co., Ltd. relies on the practice of actual engineering projects, aiming at the difficulties and pain points of construction, according to the actual situation on the site, boldly innovates, and develops a mobile formwork and matching stereotyped formwork, and hangs the formwork through a screw rod, and then installs the formwork. The template is moved and adjusted to the designed position. The relative position between the template and the template and the relative position between the template and the mold base are fixed by the positioning card device. After the template is fixed, the structure is poured. The formwork is moved as a whole to the position of the next stage of concrete pouring, so that the layered, multiple and multi-process pouring in the traditional construction process is rationally optimized into three construction process cycles of mobile positioning adjustment, cleaning and oiling and overall pouring, which greatly improves the efficiency of the construction process. Construction efficiency basically eliminates quality defects. After repeated practice and summary in multiple projects, a new type of assembly-based mobile type with fast construction speed, simple operation, high quality, low comprehensive cost, and the requirements of "four sections and one environmental protection" has been formed. The cable groove construction method of the formwork has been well received by the owners and other parties, and has good promotion and application value.

发明内容SUMMARY OF THE INVENTION

为了弥补现有技术的不足,以解决背景技术所描述的问题,本发明提出了一种移动模架结构施工方法,其施工方法包括以下步骤:In order to make up for the deficiencies of the prior art and to solve the problems described in the background technology, the present invention proposes a construction method for a mobile formwork structure, the construction method comprising the following steps:

S1:模架系统加工制作S1: Mould base system processing and production

根据现场及施工条件,采用框架式模架,长度宜控制在8~12米,模架框架底部安装行走轮,便于走行;模架墙面板及底模应加工成一体式,即“L型”,以便于安装、拆卸,并有效提高模板的整体刚度;沟槽墙面板利用模架框架采用悬挂方式;沟槽中隔定位器通过其横梁上的卡槽将“L型”模板上边沿定位,其定位器立柱将“L型”模板下边沿定位,方便易安装;沟槽外边模通过模架上的丝杆和定位器横梁上的卡槽联合定位,保证其竖直度;According to the site and construction conditions, a frame-type formwork should be used, and the length should be controlled at 8-12 meters. The bottom of the formwork frame is equipped with walking wheels to facilitate walking; the formwork wall panel and bottom form should be processed into one piece, that is, "L-shaped" , so as to facilitate installation and disassembly, and effectively improve the overall rigidity of the formwork; the groove wall panel uses the formwork frame to adopt the hanging method; The positioner column locates the lower edge of the "L-shaped" formwork, which is convenient and easy to install; the outer mold of the groove is jointly positioned by the screw rod on the mold base and the slot on the positioner beam to ensure its verticality;

S2:接触面处理S2: Contact surface treatment

根据模架长度,一次凿毛并清洗1~2个循环长度接触面,确保新鲜混凝土面在75%以上,衬砌与沟槽接触面也要凿毛,确保与衬砌面结合良好,避免沟槽滑动和移位;According to the length of the formwork, chisel and clean the contact surface for 1 to 2 cycles at a time to ensure that the fresh concrete surface is above 75%, and the contact surface between the lining and the groove should also be chiseled to ensure a good combination with the lining surface and avoid groove sliding. and shift;

S3:排水盲管安装S3: Drainage blind pipe installation

通过测量定位,将Φ107纵向打孔波纹管和Φ50环向打孔波纹管引出至沟槽内设计位置,端头采用土工布及扎丝绑紧封闭,并安装定位钢筋固定管位;By measuring and positioning, the Φ107 longitudinal perforated corrugated pipe and the Φ50 circumferential perforated corrugated pipe are led out to the design position in the groove, the ends are fastened and closed with geotextiles and binding wires, and the positioning steel bars are installed to fix the pipe position;

S4:钢筋绑扎安装S4: Rebar binding installation

按照设计安装沟槽边墙钢筋,注意顶部纵向接地钢筋的焊接质量,确保接地效果,若沟槽位于接地极段,须预先按照接地要求连接接地钢筋至设计位置;Install the groove side wall reinforcement according to the design, pay attention to the welding quality of the longitudinal grounding reinforcement at the top, and ensure the grounding effect. If the trench is located in the grounding pole section, the grounding reinforcement must be connected to the design position in advance according to the grounding requirements;

S5:模架移动定位S5: Mould base moving and positioning

沟槽模架在上一循环脱模后,收起模板系统,采用装载机或卷扬机牵引,慢行至下一循环设计位置,移动过程,注意调整模架位置,确保模架外侧距沟槽外边墙距离保持在40±10cm处;通过悬吊模板的丝杆将模板横向移动至设计平面位置,再通过拧动丝杆上的螺帽调节模板标高至设计标高;安装中隔定位器,拧紧定位螺栓;通过定位器上微调螺栓精确调整和控制模板位置;After the groove formwork is demolded in the previous cycle, the formwork system is retracted, pulled by a loader or a hoist, and slowly travels to the design position of the next cycle. During the moving process, pay attention to adjusting the position of the formwork to ensure that the outside of the formwork is far from the outside of the groove. Keep the wall distance at 40±10cm; move the formwork laterally to the design plane position through the screw rod of the hanging formwork, and then adjust the formwork elevation to the design elevation by screwing the nut on the screw rod; install the septum locator, tighten the positioning Bolts; precise adjustment and control of template position by fine-tuning bolts on the locator;

S6:预埋管件安装固定S6: Installation and fixation of embedded pipe fittings

调整Φ107纵向打孔波纹管和Φ50环向打孔波纹管位置,使其密贴模板面;通过模板上预留的孔洞安装沟槽身Φ20横向排水管和边墙内Φ100PVC横向排水管;若沟槽位于接地极段,按照设计要求安装接地端子;Adjust the positions of the Φ107 longitudinal perforated corrugated pipe and the Φ50 circumferential perforated corrugated pipe to make it close to the template surface; install the Φ20 horizontal drainage pipe in the groove body and the Φ100 PVC horizontal drainage pipe in the side wall through the holes reserved on the template; The slot is located in the grounding pole section, and the grounding terminal is installed according to the design requirements;

S7:模架整体加固及封堵S7: Overall reinforcement and blocking of formwork

为加强模架在浇筑砼过程中的整体稳定性,可在模架外侧的找平层混凝土面植入钢筋和安装斜撑加固;安装整体封端钢模,确保边墙纵向钢筋和沟槽端头止水胶条凹槽的预留;涂刷脱模剂,检查、报验,准备灌注混凝土。In order to strengthen the overall stability of the formwork during the concrete pouring process, steel bars can be implanted on the concrete surface of the leveling layer outside the formwork and diagonal bracing can be installed; Reservation of grooves for water-stop rubber strips; apply mold release agent, check, report for inspection, and prepare for pouring concrete.

S8:一次性整体浇筑混凝土S8: One-time integral pouring of concrete

由于沟槽断面小,为避免砼污染模架,不能直接用罐车入模,将薄钢板边沿结合沟槽位置制成“凸凹型”溜槽,便于引导混凝土入模,使各个沟槽内砼灌注均匀对称,保证模内混凝土面均匀上升;混凝土分层、对称浇筑,一次成型,坍落度宜控制在14~16cm之间;浇筑过程不宜过快,避免模架上浮;采用插入式振捣棒或附着式振动器捣固,不得触及钢筋、排水管、接地端子预埋管件。Due to the small cross section of the groove, in order to avoid the concrete contamination of the formwork, it is not possible to directly use a tanker to enter the mold. The edge of the thin steel plate combined with the groove position is made into a "convex and concave" chute, which is convenient for guiding the concrete into the mold and making the concrete pouring in each groove uniform. Symmetric, to ensure that the concrete surface in the mold rises evenly; the concrete is layered and poured symmetrically, and the slump should be controlled between 14 and 16 cm; The attached vibrator shall not touch the steel bars, drainage pipes, and pre-embedded fittings of the grounding terminal.

优选的,在施工之前,做好施工准备,以便应对施工过程中出现的问题,且施工准备为:Preferably, before construction, make construction preparations so as to deal with problems arising during the construction process, and the construction preparations are:

(1)、人员组织准备(1), personnel organization preparation

组织人员认真学习规范,熟悉设计图纸,了解工程的质量要求以及施工中的监控内容;成立项目管理小组及专业施工队组,并完成各级审核、审批程序;Organize personnel to study the specifications seriously, be familiar with the design drawings, understand the quality requirements of the project and the monitoring content during construction; set up a project management team and a professional construction team, and complete the review and approval procedures at all levels;

(2)、技术准备(2), technical preparation

a.组织工程管理和技术人员对设计图纸进行会审,并编制专项施工方案,专项施工方案内应制定有针对性的安全、质量和工期措施;a. Organize project management and technical personnel to conduct a joint review of the design drawings, and formulate a special construction plan. Targeted safety, quality and construction period measures should be formulated in the special construction plan;

b.根据施工图纸结合单位的设备和技术条件,制定出整体移动式模板加工的具体操作方案,并提出材料计划;b. According to the construction drawings combined with the equipment and technical conditions of the unit, formulate a specific operation plan for the overall mobile formwork processing, and propose a material plan;

c.组织技术人员和技工对图纸、相关规范和图集进行有针对性的学习,掌握各细部做法;c. Organize technical personnel and technicians to conduct targeted study on drawings, relevant specifications and atlases, and master the detailed practices;

(3)、场地准备(3), site preparation

a.对施工现场进行清理,对施工现场进行清洁,清除积垢、灰尘、油污和杂物,拆除障碍物;a. Clean up the construction site, clean the construction site, remove scale, dust, oil and sundries, and remove obstacles;

b.了解施工现场周边建筑状况,施工过程中避免影响临近建筑安全;b. Understand the conditions of the surrounding buildings on the construction site, and avoid affecting the safety of adjacent buildings during the construction process;

(4)、材料机具准备(4), material and equipment preparation

a.合理选择机械,保证使用功能齐全;对施工机械和检测设备的性能进行检验,保证施工过程中各项机具设备工作状态良好;a. Reasonable selection of machinery to ensure complete use of functions; inspection of the performance of construction machinery and testing equipment to ensure that various machinery and equipment are in good working condition during the construction process;

b.使用的材料除应有质量证明书外,还应根据现行国家标准的规定做出的复检证明,符合标准后方使用;b. In addition to the quality certificate, the materials used should also be re-inspected according to the provisions of the current national standards and used after meeting the standards;

c.材料进入现场后应对各材料的品种、规格和数量进行核对,并在指定场所堆放保管,以便于后续施工。c. After the materials enter the site, the variety, specification and quantity of each material should be checked, and they should be stacked and kept at the designated place to facilitate subsequent construction.

优选的,一次性整体浇筑混凝土后,等混凝土凝固后要对混凝土进行保护,以免混凝土开裂断层;砼浇筑完成后,采用土工布覆盖、洒水保湿养护,养护时间不宜低于12小时;拆模:松开定位螺栓和微调螺栓,拆除定位器;用小锤敲击震动模板,使模板与混凝土脱离;调整悬吊丝杆,使槽内两块模板一上一下后收拢,提升,移除模架;砼表面覆盖土工布,养生时间大于7天。Preferably, after the concrete is poured as a whole, the concrete should be protected after the concrete is solidified to prevent the concrete from cracking and faulting; after the concrete is poured, it should be covered with geotextile, sprinkled with water for moisturizing and curing, and the curing time should not be less than 12 hours; demoulding: Loosen the positioning bolts and fine-tuning bolts, and remove the positioner; tap the vibration template with a small hammer to separate the template from the concrete; adjust the suspension screw to make the two templates in the groove go up and down and then fold up, lift, and remove the formwork ; The concrete surface is covered with geotextile, and the curing time is more than 7 days.

一种移动模架结构,该移动模架结构适用于上述移动模架结构施工方法,且移动模架结构包括支撑单元和模板单元;所述支撑单元包括主纵梁、上横梁、外侧上纵梁、外侧下纵梁和连接柱;所述上横梁一端垂直固接主纵梁的侧壁,上横梁的另一端垂直固接连接柱的一端;所述连接柱的另一端垂直固接外侧下纵梁,连接柱与上横梁固接的下方垂直固接外侧上纵梁,且外侧上纵梁与外侧下纵梁平行,外侧上纵梁与外侧下纵梁所在平面与主纵梁平行;所述上横梁上安置模板单元;所述模板单元包括两张电力电缆沟槽模板、两张排水沟槽模板、两张通信电缆沟槽模板和一张边墙外模板;所述电力电缆沟槽模板、排水沟槽模板、通信电缆沟槽模板和边墙外模板的一端面设有竖向螺杆,且竖向螺杆的一端固接在电力电缆沟槽模板、排水沟槽模板、通信电缆沟槽模板和边墙外模板的一端面,竖向螺杆的另一端贯穿上横梁并通过螺母固定在上横梁的上端面。A mobile formwork structure, the mobile formwork structure is suitable for the above-mentioned construction method of the mobile formwork structure, and the mobile formwork structure includes a support unit and a formwork unit; the support unit includes a main longitudinal beam, an upper beam, and an outer upper longitudinal beam , the outer lower longitudinal beam and the connecting column; one end of the upper beam is vertically fixed to the side wall of the main longitudinal beam, and the other end of the upper beam is vertically fixed to one end of the connecting column; the other end of the connecting column is vertically fixed to the outer lower longitudinal beam The lower side where the connecting column is fixed to the upper cross beam is vertically fixed to the outer upper longitudinal beam, and the outer upper longitudinal beam is parallel to the outer lower longitudinal beam, and the plane where the outer upper longitudinal beam and the outer outer lower longitudinal beam are located is parallel to the main longitudinal beam; the The formwork unit is arranged on the upper beam; the formwork unit includes two power cable groove formwork, two drainage groove formwork, two communication cable groove formwork and one side wall external formwork; the power cable groove formwork, One end of the drainage groove formwork, the communication cable groove formwork and the outer formwork of the side wall is provided with a vertical screw, and one end of the vertical screw is fixed to the power cable groove formwork, the drainage groove formwork, the communication cable groove formwork and the One end face of the outer formwork of the side wall, the other end of the vertical screw penetrates the upper beam and is fixed on the upper end face of the upper beam by a nut.

优选的,所述上横梁的设有移动单元;所述移动单元包括支撑杆、滚轮和定位销;所述支撑杆的一端固接在上横梁的侧壁上,支撑杆量另一端开设通槽,通槽的侧壁上开设通孔,通孔内贯穿定位销,定位销的外圈转动连接滚轮的中心位置。Preferably, the upper beam is provided with a moving unit; the moving unit includes a support rod, a roller and a positioning pin; one end of the support rod is fixed on the side wall of the upper beam, and the other end of the support rod is provided with a through slot The side wall of the through groove is provided with a through hole, a positioning pin is inserted through the through hole, and the outer ring of the positioning pin rotates to connect the center position of the roller.

优选的,所述外侧上纵梁和外侧下纵梁所在平面设有挡板;所述挡板固接在外侧上纵梁和外侧下纵梁内侧壁上,挡板在纵向方向上对称设有两排横向螺杆;所述横向螺杆的一端贯穿挡板并固接在边墙外模板,横向螺杆的外圈通过螺母固接在挡板的外侧壁上。Preferably, baffles are arranged on the plane where the outer upper longitudinal beam and the outer lower longitudinal beam are located; the baffles are fixed on the inner side walls of the outer upper longitudinal beam and the outer lower longitudinal beam, and the baffles are symmetrically arranged in the longitudinal direction. Two rows of transverse screws; one end of the transverse screws penetrates the baffle and is fixed to the outer formwork of the side wall, and the outer ring of the transverse screws is fixed to the outer side wall of the baffle through nuts.

优选的,所述电力电缆沟槽模板、排水沟槽模板、通信电缆沟槽模板之间设有定位单元;所述定位单元包括连接板、定位杆和微调螺杆;所述连接板的一侧开设多个卡槽,卡槽个数与电力电缆沟槽模板、排水沟槽模板、通信电缆沟槽模板和边墙外模板个数总和相同,卡槽的槽口通过螺母连接微调螺杆,微调螺杆的一端固接在电力电缆沟槽模板、排水沟槽模板、通信电缆沟槽模板和边墙外模板的上端面;所述连接板的下板面固接三个定位杆,每个定位杆插入各插入两张电力电缆沟槽模板、两张排水沟槽模板和两张通信电缆沟槽模板之间。Preferably, a positioning unit is provided between the power cable groove template, the drainage groove template, and the communication cable groove template; the positioning unit includes a connecting plate, a positioning rod and a fine-tuning screw; one side of the connecting plate is provided with Multiple card slots, the number of card slots is the same as the sum of the power cable groove template, the drainage groove template, the communication cable groove template and the side wall outer template. One end is fixedly connected to the upper end face of the power cable groove formwork, the drainage groove formwork, the communication cable groove formwork and the outer formwork of the side wall; Insert between two power cable trench templates, two drainage trench templates, and two communication cable trench templates.

优选的,每个个所述定位杆的长度与所要浇注的电缆沟槽、排水沟槽和通信电缆沟槽深度相同,每个定位杆的端部对称开设倒角。Preferably, the length of each of the positioning rods is the same as the depth of the cable groove, the drainage groove and the communication cable groove to be poured, and the ends of each positioning rod are symmetrically chamfered.

本发明的技术效果和优点:Technical effects and advantages of the present invention:

1、施工操作简单、方便,质量好1. The construction operation is simple and convenient, and the quality is good

使用定位杆、横向螺杆、竖向螺杆零部件来固定、调节模板,提高了模板整体性,对模板工人技术水平要求不高,降低了测量、尺量等校验工序作业强度,极大地消除了人为因素对模板外观质量的不良影响,降低了施工误差,顶面平整度易于控制,保证了结构外观质量,结构尺寸可靠,施工质量好。The use of positioning rods, horizontal screws, and vertical screw parts to fix and adjust the template improves the integrity of the template, does not require high technical level of template workers, reduces the work intensity of calibration procedures such as measurement and ruler measurement, and greatly eliminates the need for The adverse effect of human factors on the appearance quality of the formwork reduces the construction error, the flatness of the top surface is easy to control, and the appearance quality of the structure is guaranteed, the structure size is reliable, and the construction quality is good.

2、施工速度快、效率高,劳动强度低,省时省工2. Fast construction speed, high efficiency, low labor intensity, saving time and labor

通过预制模架和定位单元把大块定型钢模拼装为整体系统,极大地减少了以往分层、分工序零散模板和钢模组装及模板转运的工作量,减少了作业人员,通过机械或卷扬设备牵引移至下一施工段,降低了工人劳动强度,提高了整体施工速度。The prefabricated formwork and positioning unit are used to assemble the large shaped steel formwork into a whole system, which greatly reduces the workload of the previous layered, sub-process scattered formwork and steel formwork assembly and formwork transfer, and reduces the number of operators, through mechanical or The hoisting equipment is pulled and moved to the next construction section, which reduces the labor intensity of workers and improves the overall construction speed.

3、综合施工成本低,经济效益好3. The comprehensive construction cost is low and the economic benefit is good

模架系统可周转使用,减少了传统方法中的临时支撑材料,综合施工成本低。The formwork system can be used in turnaround, reducing the temporary support materials in the traditional method, and the comprehensive construction cost is low.

4、文明施工,符合四节一环保绿色施工要求4. Civilized construction, in line with the requirements of four sections and one environmental protection and green construction

施工作业规范,施工作业区污染小,降低了施工作业区收拾、清理等作业强度,文明施工显著提高。The construction work is standardized, and the pollution in the construction work area is small, which reduces the work intensity of cleaning and cleaning in the construction work area, and the civilized construction is significantly improved.

附图说明Description of drawings

下面结合附图和实施方式对本发明进一步说明。The present invention will be further described below with reference to the accompanying drawings and embodiments.

图1是本发明中施工工艺流程图;Fig. 1 is the construction process flow chart in the present invention;

图2是本发明中移动模架结构的立体图;Fig. 2 is the perspective view of the mobile formwork structure in the present invention;

图3是本发明中移动模架结构的侧视图;Fig. 3 is the side view of the mobile formwork structure in the present invention;

图4是本发明中移动模架结构的等轴测视图;Fig. 4 is the isometric view of the mobile formwork structure in the present invention;

图中:支撑单元1、主纵梁11、上横梁12、外侧上纵梁13、外侧下纵梁14、连接柱15、挡板16、横向螺杆17、模板单元2、电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23、边墙外模板24、竖向螺杆25、螺母251、移动单元3、支撑杆31、通槽311、滚轮32、定位销33、定位单元4、连接板41、卡槽411、定位杆42、微调螺杆43。In the figure: support unit 1, main longitudinal beam 11, upper beam 12, outer upper longitudinal beam 13, outer lower longitudinal beam 14, connecting column 15, baffle 16, transverse screw 17, template unit 2, power cable groove template 21 , Drainage groove formwork 22, Communication cable groove formwork 23, Side wall external formwork 24, Vertical screw 25, Nut 251, Mobile unit 3, Support rod 31, Through groove 311, Roller 32, Positioning pin 33, Positioning unit 4 , connecting plate 41 , card slot 411 , positioning rod 42 , fine adjustment screw 43 .

具体实施方式Detailed ways

为了使本发明实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合实施方式,进一步阐述本发明。In order to make it easy to understand the technical means, creative features, achieved goals and effects of the present invention, the present invention will be further described below with reference to the embodiments.

如图1至图4所示,本发明所述的一种移动模架结构施工方法,其施工方法包括以下步骤:As shown in Figure 1 to Figure 4, the construction method of a mobile formwork structure according to the present invention, the construction method comprises the following steps:

S1:模架系统加工制作S1: Mould base system processing and production

根据现场及施工条件,采用框架式模架,长度宜控制在8~12米,模架框架底部安装行走轮,便于走行;模架墙面板及底模应加工成一体式,即“L型”,以便于安装、拆卸,并有效提高模板的整体刚度;沟槽墙面板利用模架框架采用悬挂方式;沟槽中隔定位器通过其横梁上的卡槽将“L型”模板上边沿定位,其定位器立柱将“L型”模板下边沿定位,方便易安装;沟槽外边模通过模架上的丝杆和定位器横梁上的卡槽联合定位,保证其竖直度;According to the site and construction conditions, a frame-type formwork should be used, and the length should be controlled at 8-12 meters. The bottom of the formwork frame is equipped with walking wheels to facilitate walking; the formwork wall panel and bottom form should be processed into one piece, that is, "L-shaped" , so as to facilitate installation and disassembly, and effectively improve the overall rigidity of the formwork; the groove wall panel uses the formwork frame to adopt the hanging method; The positioner column locates the lower edge of the "L-shaped" formwork, which is convenient and easy to install; the outer mold of the groove is jointly positioned by the screw rod on the mold base and the slot on the positioner beam to ensure its verticality;

S2:接触面处理S2: Contact surface treatment

根据模架长度,一次凿毛并清洗1~2个循环长度接触面,确保新鲜混凝土面在75%以上,衬砌与沟槽接触面也要凿毛,确保与衬砌面结合良好,避免沟槽滑动和移位;According to the length of the formwork, chisel and clean the contact surface for 1 to 2 cycles at a time to ensure that the fresh concrete surface is above 75%, and the contact surface between the lining and the groove should also be chiseled to ensure a good combination with the lining surface and avoid groove sliding. and shift;

S3:排水盲管安装S3: Drainage blind pipe installation

通过测量定位,将Φ107纵向打孔波纹管和Φ50环向打孔波纹管引出至沟槽内设计位置,端头采用土工布及扎丝绑紧封闭,并安装定位钢筋固定管位;By measuring and positioning, the Φ107 longitudinal perforated corrugated pipe and the Φ50 circumferential perforated corrugated pipe are led out to the design position in the groove, the ends are fastened and closed with geotextiles and binding wires, and the positioning steel bars are installed to fix the pipe position;

S4:钢筋绑扎安装S4: Rebar binding installation

按照设计安装沟槽边墙钢筋,注意顶部纵向接地钢筋的焊接质量,确保接地效果,若沟槽位于接地极段,须预先按照接地要求连接接地钢筋至设计位置;Install the groove side wall reinforcement according to the design, pay attention to the welding quality of the longitudinal grounding reinforcement at the top, and ensure the grounding effect. If the trench is located in the grounding pole section, the grounding reinforcement must be connected to the design position in advance according to the grounding requirements;

S5:模架移动定位S5: Mould base moving and positioning

沟槽模架在上一循环脱模后,收起模板系统,采用装载机或卷扬机牵引,慢行至下一循环设计位置,移动过程,注意调整模架位置,确保模架外侧距沟槽外边墙距离保持在40±10cm处;通过悬吊模板的丝杆将模板横向移动至设计平面位置,再通过拧动丝杆上的螺帽调节模板标高至设计标高;安装中隔定位器,拧紧定位螺栓;通过定位器上微调螺栓精确调整和控制模板位置;After the groove formwork is demolded in the previous cycle, the formwork system is retracted, pulled by a loader or a hoist, and slowly travels to the design position of the next cycle. During the moving process, pay attention to adjusting the position of the formwork to ensure that the outside of the formwork is far from the outside of the groove. Keep the wall distance at 40±10cm; move the formwork laterally to the design plane position through the screw rod of the hanging formwork, and then adjust the formwork elevation to the design elevation by screwing the nut on the screw rod; install the septum locator, tighten the positioning Bolts; precise adjustment and control of template position by fine-tuning bolts on the locator;

S6:预埋管件安装固定S6: Installation and fixation of embedded pipe fittings

调整Φ107纵向打孔波纹管和Φ50环向打孔波纹管位置,使其密贴模板面;通过模板上预留的孔洞安装沟槽身Φ20横向排水管和边墙内Φ100PVC横向排水管;若沟槽位于接地极段,按照设计要求安装接地端子;Adjust the positions of the Φ107 longitudinal perforated corrugated pipe and the Φ50 circumferential perforated corrugated pipe to make it close to the template surface; install the Φ20 horizontal drainage pipe in the groove body and the Φ100 PVC horizontal drainage pipe in the side wall through the holes reserved on the template; The slot is located in the grounding pole section, and the grounding terminal is installed according to the design requirements;

S7:模架整体加固及封堵S7: Overall reinforcement and blocking of formwork

为加强模架在浇筑砼过程中的整体稳定性,可在模架外侧的找平层混凝土面植入钢筋和安装斜撑加固;安装整体封端钢模,确保边墙纵向钢筋和沟槽端头止水胶条凹槽的预留;涂刷脱模剂,检查、报验,准备灌注混凝土。In order to strengthen the overall stability of the formwork during the concrete pouring process, steel bars can be implanted on the concrete surface of the leveling layer outside the formwork and diagonal bracing can be installed; Reservation of grooves for water-stop rubber strips; apply mold release agent, check, report for inspection, and prepare for pouring concrete.

S8:一次性整体浇筑混凝土S8: One-time integral pouring of concrete

由于沟槽断面小,为避免砼污染模架,不能直接用罐车入模,将薄钢板边沿结合沟槽位置制成“凸凹型”溜槽,便于引导混凝土入模,使各个沟槽内砼灌注均匀对称,保证模内混凝土面均匀上升;混凝土分层、对称浇筑,一次成型,坍落度宜控制在14~16cm之间;浇筑过程不宜过快,避免模架上浮;采用插入式振捣棒或附着式振动器捣固,不得触及钢筋、排水管、接地端子预埋管件。Due to the small cross section of the groove, in order to avoid the concrete contamination of the formwork, it is not possible to directly use a tanker to enter the mold. The edge of the thin steel plate combined with the groove position is made into a "convex and concave" chute, which is convenient for guiding the concrete into the mold and making the concrete pouring in each groove uniform. Symmetric, to ensure that the concrete surface in the mold rises evenly; the concrete is layered and poured symmetrically, and the slump should be controlled between 14 and 16 cm; The attached vibrator shall not touch the steel bars, drainage pipes, and pre-embedded fittings of the grounding terminal.

在施工之前,做好施工准备,以便应对施工过程中出现的问题,且施工准备为:Before construction, make construction preparations in order to deal with the problems that arise during the construction process, and the construction preparations are:

(1)、人员组织准备(1), personnel organization preparation

组织人员认真学习规范,熟悉设计图纸,了解工程的质量要求以及施工中的监控内容;成立项目管理小组及专业施工队组,并完成各级审核、审批程序;Organize personnel to study the specifications seriously, be familiar with the design drawings, understand the quality requirements of the project and the monitoring content during construction; set up a project management team and a professional construction team, and complete the review and approval procedures at all levels;

(2)、技术准备(2), technical preparation

a.组织工程管理和技术人员对设计图纸进行会审,并编制专项施工方案,专项施工方案内应制定有针对性的安全、质量和工期措施;a. Organize project management and technical personnel to conduct a joint review of the design drawings, and formulate a special construction plan. Targeted safety, quality and construction period measures should be formulated in the special construction plan;

b.根据施工图纸结合单位的设备和技术条件,制定出整体移动式模板加工的具体操作方案,并提出材料计划;b. According to the construction drawings combined with the equipment and technical conditions of the unit, formulate a specific operation plan for the overall mobile formwork processing, and propose a material plan;

c.组织技术人员和技工对图纸、相关规范和图集进行有针对性的学习,掌握各细部做法;c. Organize technical personnel and technicians to conduct targeted study on drawings, relevant specifications and atlases, and master the detailed practices;

(3)、场地准备(3), site preparation

a.对施工现场进行清理,对施工现场进行清洁,清除积垢、灰尘、油污和杂物,拆除障碍物;a. Clean up the construction site, clean the construction site, remove scale, dust, oil and sundries, and remove obstacles;

b.了解施工现场周边建筑状况,施工过程中避免影响临近建筑安全;b. Understand the conditions of the surrounding buildings on the construction site, and avoid affecting the safety of adjacent buildings during the construction process;

(4)、材料机具准备(4), material and equipment preparation

a.合理选择机械,保证使用功能齐全;对施工机械和检测设备的性能进行检验,保证施工过程中各项机具设备工作状态良好;a. Reasonable selection of machinery to ensure complete use of functions; inspection of the performance of construction machinery and testing equipment to ensure that various machinery and equipment are in good working condition during the construction process;

b.使用的材料除应有质量证明书外,还应根据现行国家标准的规定做出的复检证明,符合标准后方使用;b. In addition to the quality certificate, the materials used should also be re-inspected according to the provisions of the current national standards and used after meeting the standards;

c.材料进入现场后应对各材料的品种、规格和数量进行核对,并在指定场所堆放保管,以便于后续施工。c. After the materials enter the site, the variety, specification and quantity of each material should be checked, and they should be stacked and kept at the designated place to facilitate subsequent construction.

一次性整体浇筑混凝土后,等混凝土凝固后要对混凝土进行保护,以免混凝土开裂断层;砼浇筑完成后,采用土工布覆盖、洒水保湿养护,养护时间不宜低于12小时;拆模:松开定位螺栓和微调螺栓,拆除定位器;用小锤敲击震动模板,使模板与混凝土脱离;调整悬吊丝杆,使槽内两块模板一上一下后收拢,提升,移除模架;砼表面覆盖土工布,养生时间大于7天。After the concrete is poured as a whole, the concrete should be protected after the concrete is solidified to prevent the concrete from cracking and faulting; after the concrete is poured, it should be covered with geotextile, sprinkled with water for moisturizing and curing, and the curing time should not be less than 12 hours; formwork removal: loosen the positioning Bolts and fine-tuning bolts, remove the locator; tap the vibrating formwork with a small hammer to separate the formwork from the concrete; adjust the suspension screw to make the two formwork in the groove fold up and down, lift, and remove the formwork; the concrete surface Covered with geotextiles, the curing time is more than 7 days.

一种移动模架结构,该移动模架结构适用于上述移动模架结构施工方法,且移动模架结构包括支撑单元1和模板单元2;所述支撑单元1包括主纵梁11、上横梁12、外侧上纵梁13、外侧下纵梁14和连接柱15;所述上横梁12一端垂直固接主纵梁11的侧壁,上横梁12的另一端垂直固接连接柱15的一端;所述连接柱15的另一端垂直固接外侧下纵梁14,连接柱15与上横梁12固接的下方垂直固接外侧上纵梁13,且外侧上纵梁13与外侧下纵梁14平行,外侧上纵梁13与外侧下纵梁14所在平面与主纵梁11平行;所述上横梁12上安置模板单元2;所述模板单元2包括两张电力电缆沟槽模板21、两张排水沟槽模板22、两张通信电缆沟槽模板23和一张边墙外模板24;所述电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24的一端面设有竖向螺杆25,且竖向螺杆25的一端固接在电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24的一端面,竖向螺杆25的另一端贯穿上横梁12并通过螺母251固定在上横梁12的上端面;首先将移动模架一直指定浇注点,使得主纵梁11贴附在墙壁上,然后旋转竖向螺杆25的上螺母251,使得竖向螺杆25在竖直方向上下移动,同时竖向螺杆25的上下移动带动模板上下移动,此时操作工人通过旋转螺母251调节电缆沟槽模板、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24上端的高度,使得模板都处于同一高度,待模板高度调节一致后,浇筑混凝土,待混凝土凝固后,撤掉模板,通过机械或卷扬设备牵引移动模架移至下一施工段;该移动模架将传统施工工艺中分层、多次、多工序浇筑合理优化为移动定位调节、清洁涂油和整体浇筑三道施工工序循环,极大提高了施工工效,基本杜绝了质量缺陷。A mobile formwork structure, the mobile formwork structure is suitable for the above-mentioned construction method of the mobile formwork structure, and the mobile formwork structure includes a support unit 1 and a formwork unit 2; the support unit 1 includes a main longitudinal beam 11 and an upper beam 12. , the outer upper longitudinal beam 13, the outer lower longitudinal beam 14 and the connecting column 15; one end of the upper transverse beam 12 is vertically fixed to the side wall of the main longitudinal beam 11, and the other end of the upper transverse beam 12 is vertically fixed to one end of the connecting column 15; The other end of the connecting column 15 is vertically fixed to the outer side lower longitudinal beam 14, the lower side where the connecting column 15 is fixed to the upper cross beam 12 is vertically fixed to the outer side upper longitudinal beam 13, and the outer upper longitudinal beam 13 is parallel to the outer side lower longitudinal beam 14, The plane where the outer upper longitudinal beam 13 and the outer lower longitudinal beam 14 are located is parallel to the main longitudinal beam 11; the template unit 2 is arranged on the upper beam 12; the template unit 2 includes two power cable groove templates 21, two drainage ditches Slot formwork 22, two communication cable groove formwork 23 and one side wall outer formwork 24; The end face is provided with a vertical screw 25, and one end of the vertical screw 25 is fixed to one end of the power cable groove formwork 21, the drainage groove formwork 22, the communication cable groove formwork 23 and the side wall external formwork 24. The other end of the 25 penetrates the upper beam 12 and is fixed on the upper end face of the upper beam 12 by the nut 251; first, the mobile formwork is always designated as the pouring point, so that the main longitudinal beam 11 is attached to the wall, and then the upper part of the vertical screw 25 is rotated. The nut 251 makes the vertical screw 25 move up and down in the vertical direction, and the vertical movement of the vertical screw 25 drives the template to move up and down. At this time, the operator adjusts the cable groove template, the drainage groove template 22, the communication cable by rotating the nut 251 The height of the upper end of the groove formwork 23 and the outer formwork 24 of the side wall, so that the formwork is at the same height. After the formwork height is adjusted to the same height, pour the concrete. After the concrete solidifies, remove the formwork and move the formwork by mechanical or hoisting equipment. Move to the next construction section; the mobile formwork rationally optimizes the layered, multiple and multi-process pouring in the traditional construction process into three construction process cycles of mobile positioning adjustment, cleaning and oiling and overall pouring, which greatly improves the construction work efficiency. , which basically eliminates quality defects.

作为本发明的一种具体实施方式,所述上横梁12的设有移动单元3;所述移动单元3包括支撑杆31、滚轮32和定位销33;所述支撑杆31的一端固接在上横梁12的侧壁上,支撑杆31量另一端开设通槽311,通槽311的侧壁上开设通孔,通孔内贯穿定位销33,定位销33的外圈转动连接滚轮32的中心位置;通过机械或卷扬设备牵引移动模架移至下一施工段过程中,通过使用滚轮32,使得移动模架在被卷扬设备牵引移动时,更易移动模架的移动。As a specific embodiment of the present invention, the upper beam 12 is provided with a moving unit 3; the moving unit 3 includes a support rod 31, a roller 32 and a positioning pin 33; one end of the support rod 31 is fixed on the upper On the side wall of the beam 12, the other end of the support rod 31 is provided with a through slot 311, the side wall of the through slot 311 is provided with a through hole, the through hole penetrates the positioning pin 33, and the outer ring of the positioning pin 33 rotates to connect the center position of the roller 32 ; During the process of pulling the mobile formwork to the next construction section by mechanical or hoisting equipment, by using the rollers 32, the moving formwork is easier to move when the mobile formwork is pulled and moved by the hoisting equipment.

作为本发明的一种具体实施方式,所述外侧上纵梁13和外侧下纵梁14所在平面设有挡板16;所述挡板16固接在外侧上纵梁13和外侧下纵梁14内侧壁上,挡板16在纵向方向上对称设有两排横向螺杆17;所述横向螺杆17的一端贯穿挡板16并固接在边墙外模板24,横向螺杆17的外圈通过螺母251固接在挡板16的外侧壁上;通过旋转横向螺杆17的螺母251,使得横向螺杆17推动和拉动边墙外模板24距离墙壁的位置,实现对电缆沟槽厚度的控制。As a specific embodiment of the present invention, a baffle plate 16 is provided on the plane where the outer upper longitudinal beam 13 and the outer lower longitudinal beam 14 are located; the baffle plate 16 is fixedly connected to the outer upper longitudinal beam 13 and the outer outer lower longitudinal beam 14 On the inner side wall, the baffle 16 is symmetrically provided with two rows of transverse screws 17 in the longitudinal direction; one end of the transverse screw 17 penetrates the baffle 16 and is fixed to the outer formwork 24 of the side wall, and the outer ring of the transverse screw 17 passes through the nut 251. It is fixed on the outer side wall of the baffle 16; by rotating the nut 251 of the transverse screw 17, the transverse screw 17 pushes and pulls the position of the outer formwork 24 of the side wall away from the wall, so as to control the thickness of the cable groove.

作为本发明的一种具体实施方式,所述电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23之间设有定位单元4;所述定位单元4包括连接板41、定位杆42和微调螺杆43;所述连接板41的一侧开设多个卡槽411,卡槽411个数与电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24个数总和相同,卡槽411的槽口通过螺母251连接微调螺杆43,微调螺杆43的一端固接在电力电缆沟槽模板21、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24的上端面;所述连接板41的下板面固接三个定位杆42,每个定位杆42插入各插入两张电力电缆沟槽模板21、两张排水沟槽模板22和两张通信电缆沟槽模板23之间;通过旋转微调螺杆43的螺母251,螺母251使得微调螺杆43上下移动,实现对对电缆沟槽模板、排水沟槽模板22和通信电缆沟槽模板23进行二次调节,保证电缆沟槽模板、排水沟槽模板22和通信电缆沟槽模板23上端面的齐平度,从而保证浇注后沟槽的质量和美观。As a specific embodiment of the present invention, a positioning unit 4 is provided between the power cable trench template 21, the drainage trench template 22, and the communication cable trench template 23; the positioning unit 4 includes a connecting plate 41, a positioning unit Rod 42 and fine-tuning screw 43; one side of the connecting plate 41 is provided with a plurality of card slots 411, the number of the card slots 411 is the same as the power cable groove template 21, the drainage groove template 22, the communication cable groove template 23 and the side wall The sum of the 24 outer templates is the same, the notch of the card slot 411 is connected to the fine-tuning screw 43 through the nut 251, and one end of the fine-tuning screw 43 is fixed to the power cable groove template 21, the drainage groove template 22, the communication cable groove template 23 and The upper end surface of the outer formwork 24 of the side wall; the lower surface of the connecting plate 41 is fixed with three positioning rods 42, and each positioning rod 42 is inserted into two power cable groove formwork 21 and two drainage groove formwork 22 respectively. and the two communication cable groove templates 23; by rotating the nut 251 of the fine adjustment screw 43, the nut 251 makes the fine adjustment screw 43 move up and down to realize the pairing of the cable groove template, the drainage groove template 22 and the communication cable groove template 23 Carry out secondary adjustment to ensure the flushness of the upper end faces of the cable groove formwork, the drainage groove formwork 22 and the communication cable groove formwork 23, so as to ensure the quality and appearance of the grooves after pouring.

作为本发明的一种具体实施方式,每个个所述定位杆42的长度与所要浇注的电缆沟槽、排水沟槽和通信电缆沟槽深度相同,每个定位杆42的端部对称开设倒角;当定位杆42的端部插入电缆沟槽、排水沟槽和通信电缆沟槽内过程中,需要照顾到每根定位杆42准确插入,但是由于定位杆42的端部为齐平状态,定位杆42会卡在相邻模板之间,为此通过开设倒角,通过倒角将定位杆42引入相邻模板之间,使得每个定位杆42快速且准确插入。As a specific embodiment of the present invention, the length of each positioning rod 42 is the same as the depth of the cable groove, drainage groove and communication cable groove to be poured, and the end of each positioning rod 42 is symmetrically opened and inverted angle; when the end of the positioning rod 42 is inserted into the cable groove, the drainage groove and the communication cable groove, it is necessary to take care of the accurate insertion of each positioning rod 42, but since the end of the positioning rod 42 is in a flush state, The positioning rods 42 will be stuck between the adjacent templates. For this purpose, by opening a chamfer, the positioning rods 42 are introduced between the adjacent templates through the chamfering, so that each positioning rod 42 can be inserted quickly and accurately.

工作原理:首先将移动模架一直指定浇注点,使得主纵梁11贴附在墙壁上,然后旋转竖向螺杆25的上螺母251,使得竖向螺杆25在竖直方向上下移动,同时竖向螺杆25的上下移动带动模板上下移动,此时操作工人通过旋转螺母251调节电缆沟槽模板、排水沟槽模板22、通信电缆沟槽模板23和边墙外模板24上端的高度,使得模板都处于同一高度,待模板高度调节一致后,浇筑混凝土,待混凝土凝固后,撤掉模板,通过机械或卷扬设备牵引移动模架移至下一施工段;该移动模架将传统施工工艺中分层、多次、多工序浇筑合理优化为移动定位调节、清洁涂油和整体浇筑三道施工工序循环,极大提高了施工工效,基本杜绝了质量缺陷;以及过旋转横向螺杆17的螺母251,使得横向螺杆17推动和拉动边墙外模板24距离墙壁的位置,实现对电缆沟槽厚度的控制;同时通过旋转微调螺杆43的螺母251,螺母251使得微调螺杆43上下移动,实现对对电缆沟槽模板、排水沟槽模板22和通信电缆沟槽模板23进行二次调节,保证电缆沟槽模板、排水沟槽模板22和通信电缆沟槽模板23上端面的齐平度,从而保证浇注后沟槽的质量和美观。Working principle: First, the mobile mold base is always designated as the pouring point, so that the main longitudinal beam 11 is attached to the wall, and then the upper nut 251 of the vertical screw 25 is rotated, so that the vertical screw 25 moves up and down in the vertical direction, and at the same time vertically The up and down movement of the screw 25 drives the formwork to move up and down. At this time, the operator adjusts the height of the cable groove formwork, the drainage groove formwork 22, the communication cable groove formwork 23 and the upper end of the side wall external formwork 24 by rotating the nut 251, so that the formwork is all in the upper end. At the same height, after the height of the formwork is adjusted to the same level, pour the concrete. After the concrete is solidified, remove the formwork and move the mobile formwork to the next construction section by pulling the mechanical or hoisting equipment; , The reasonable optimization of multiple and multi-process pouring is three construction process cycles of mobile positioning adjustment, cleaning and oiling and overall pouring, which greatly improves the construction efficiency and basically eliminates quality defects; and over-rotating the nut 251 of the transverse screw 17 makes the The transverse screw 17 pushes and pulls the position of the outer formwork 24 of the side wall from the wall to realize the control of the thickness of the cable groove; at the same time, by rotating the nut 251 of the fine-tuning screw 43, the nut 251 makes the fine-tuning screw 43 move up and down to realize the alignment of the cable groove. The formwork, the drainage groove formwork 22 and the communication cable groove formwork 23 are readjusted to ensure the flushness of the upper end faces of the cable groove formwork, the drainage groove formwork 22 and the communication cable groove formwork 23, so as to ensure the groove after pouring. quality and aesthetics.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above description is only a preferred embodiment of the present invention, but the protection scope of the present invention is not limited to this. The equivalent replacement or change of the inventive concept thereof shall be included within the protection scope of the present invention.

Claims (8)

1. A construction method of a movable formwork structure is characterized in that: the construction method comprises the following steps:
s1: die carrier system processing and manufacturing
According to the field and construction conditions, a frame type formwork is adopted, the length is controlled to be 8-12 m, and walking wheels are installed at the bottom of the formwork frame, so that the walking is convenient to walk; the wall panel and the bottom die of the die frame are integrally processed, namely, the wall panel and the bottom die are L-shaped, so that the wall panel and the bottom die are convenient to mount and dismount, and the overall rigidity of the die plate is effectively improved; the groove wall panel adopts a suspension mode by utilizing a mould frame; the groove middle partition positioner positions the upper edge of the L-shaped template through a clamping groove on a cross beam of the groove middle partition positioner, and the positioner upright post positions the lower edge of the L-shaped template, so that the groove middle partition positioner is convenient and easy to install; the groove outer side die is jointly positioned through a screw rod on the die frame and a clamping groove on a positioner cross beam, so that the verticality of the groove outer side die is ensured;
s2: treatment of contact surfaces
According to the length of the formwork, roughening and cleaning 1-2 contact surfaces with the cycle length at one time to ensure that the fresh concrete surface is over 75 percent, roughening the contact surface of the lining and the groove to ensure good combination with the lining surface and avoid the sliding and displacement of the groove;
s3: drainage blind pipe installation
Through measurement and positioning, leading out a phi 107 longitudinal perforated corrugated pipe and a phi 50 circumferential perforated corrugated pipe to the designed positions in the grooves, tightly binding and sealing the ends by adopting geotextile and binding wires, and installing positioning reinforcing steel bars to fix the pipe positions;
s4: installation of reinforcement
Installing groove side wall reinforcing steel bars according to design, paying attention to the welding quality of top longitudinal grounding reinforcing steel bars, and ensuring the grounding effect;
s5: moving and positioning die carrier
After the last cycle of demolding, the groove mold frame is retracted by a template system, is dragged by a loader or a winch and slowly moves to the next cycle design position, and during the moving process, the position of the mold frame is adjusted by attention to ensure that the distance from the outer side of the mold frame to the outer side wall of the groove is kept at 40 +/-10 cm; transversely moving the template to a designed plane position through a lead screw for suspending the template, and adjusting the elevation of the template to a designed elevation through screwing a nut on the lead screw; installing an intermediate partition positioner and screwing down a positioning bolt; the position of the template is accurately adjusted and controlled through a fine adjustment bolt on the positioner;
s6: mounting and fixing of embedded pipe
Adjusting the positions of a phi 107 longitudinal punching corrugated pipe and a phi 50 circumferential punching corrugated pipe to enable the corrugated pipes to be closely attached to the surface of the template; installing a groove body phi 20 transverse drainage pipe and a phi 100PVC transverse drainage pipe in a side wall through a hole reserved on the template; if the groove is positioned in the grounding electrode section, a grounding terminal is installed according to design requirements;
s7: integral reinforcement and plugging of die carrier
In order to enhance the overall stability of the formwork in the concrete pouring process, reinforcing steel bars can be implanted into the concrete surface of the leveling layer outside the formwork and diagonal braces can be installed for reinforcement; installing an integral end-sealing steel die to ensure the reservation of longitudinal reinforcing steel bars of the side wall and a water-stopping adhesive tape groove at the end of the groove; and (4) coating a release agent, checking and reporting, and preparing to pour concrete.
S8: disposable integral casting concrete
Because the section of the groove is small, in order to avoid concrete pollution on the die carrier, the concrete can not be directly poured into the die by a tank car, the edge of the thin steel plate is combined with the position of the groove to form a 'convex-concave' chute, so that the concrete can be conveniently guided into the die, the concrete in each groove is uniformly and symmetrically poured, and the uniform rising of the concrete surface in the die is ensured; concrete is layered and symmetrically poured and is formed in one step, and the slump is controlled to be 14-16 cm; the pouring process is not too fast, and the mold frame is prevented from floating upwards; the embedded pipe fittings of the reinforcing steel bars, the drain pipes and the grounding terminals are not contacted with the embedded pipe fittings by adopting an inserted vibrating rod or an attached vibrator for tamping.
2. The construction method of the movable formwork structure according to claim 1, wherein: before construction, construction preparation is made so as to deal with problems occurring in the construction process, and the construction preparation is as follows:
(1) personnel organization preparation
The organization personnel carefully learns the specification, is familiar with the design drawing and knows the quality requirement of the project and the monitoring content in the construction; establishing a project management group and a professional construction team group, and completing all levels of auditing and approving procedures;
(2) preparation of the technique
a. Organizing project management and technical personnel to review the design drawings and compiling a special construction scheme, wherein specific safety, quality and construction period measures are made in the special construction scheme;
b. according to construction drawings and equipment and technical conditions of units, a specific operation scheme for processing the integral movable template is worked out, and a material plan is proposed;
c. organizing technicians and technicians to carry out targeted learning on drawings, relevant specifications and drawing sets and master detailed methods;
(3) site preparation
a. Cleaning a construction site, cleaning the construction site, removing scale, dust, oil stains and sundries, and removing obstacles;
b. the conditions of surrounding buildings at the construction site are known, and the influence on the safety of adjacent buildings is avoided in the construction process;
(4) material machine preparation
a. The machinery is reasonably selected, and the use function is ensured to be complete; the performance of the construction machinery and the detection equipment is checked, and the working state of various machines and tools in the construction process is ensured to be good;
b. the used materials are subject to the quality certificate and the retest certificate according to the regulations of the current national standard, and are used after meeting the standard;
c. after the materials enter the site, the variety, the specification and the quantity of each material are checked, and the materials are stacked and stored in a designated place so as to facilitate subsequent construction.
3. The construction method of the movable formwork structure according to claim 1, wherein: after the concrete is integrally poured once, the concrete is protected after the concrete is solidified so as to prevent the concrete from cracking and breaking; after concrete pouring is finished, geotextile is adopted for covering, watering is adopted for moisturizing and maintaining, and the maintaining time is not less than 12 hours; removing the mold: loosening the positioning bolt and the fine adjustment bolt, and dismantling the positioner; knocking and vibrating the template by a small hammer to separate the template from the concrete; adjusting the suspension screw rod to enable the two templates in the groove to be folded up after one template is placed on top of the other template, lifting and removing the die carrier; the concrete surface is covered with geotextile, and the curing time is more than 7 days.
4. A movable mould frame structure is characterized in that: the movable formwork structure is suitable for the construction method of the movable formwork structure in any one of claims 1 to 3, and comprises a supporting unit and a formwork unit; the supporting unit comprises a main longitudinal beam, an upper cross beam, an outer side upper longitudinal beam, an outer side lower longitudinal beam and a connecting column; one end of the upper cross beam is vertically and fixedly connected with the side wall of the main longitudinal beam, and the other end of the upper cross beam is vertically and fixedly connected with one end of the connecting column; the other end of the connecting column is vertically and fixedly connected with an outer side lower longitudinal beam, the lower part of the connecting column fixedly connected with the upper transverse beam is vertically and fixedly connected with an outer side upper longitudinal beam, the outer side upper longitudinal beam is parallel to the outer side lower longitudinal beam, and the plane of the outer side upper longitudinal beam and the plane of the outer side lower longitudinal beam are parallel to the main longitudinal beam; the upper cross beam is provided with a template unit; the template unit comprises two power cable groove templates, two drainage groove templates, two communication cable groove templates and a side wall outer template; the utility model discloses a side wall outer form, including power cable groove template, escape canal groove template, communication cable groove template and side wall outer form, the terminal surface of power cable groove template, escape canal groove template, communication cable groove template and side wall outer form is equipped with vertical screw rod, and the one end rigid coupling of vertical screw rod is at the terminal surface of power cable groove template, escape canal groove template, communication cable groove template and side wall outer form, and the other end of vertical screw rod runs through the entablature and fixes the up end at the entablature through the nut.
5. A mobile formwork structure as claimed in claim 4, wherein: the upper cross beam is provided with a moving unit; the moving unit comprises a supporting rod, a roller and a positioning pin; one end of the supporting rod is fixedly connected to the side wall of the upper cross beam, the other end of the supporting rod is provided with a through groove, the side wall of the through groove is provided with a through hole, a positioning pin penetrates through the through hole, and the outer ring of the positioning pin is rotatably connected with the central position of the roller.
6. A mobile formwork structure as claimed in claim 4, wherein: the planes of the outer side upper longitudinal beam and the outer side lower longitudinal beam are provided with baffle plates; the baffle is fixedly connected to the inner side walls of the outer upper longitudinal beam and the outer lower longitudinal beam, and two rows of transverse screws are symmetrically arranged on the baffle in the longitudinal direction; one end of the transverse screw penetrates through the baffle and is fixedly connected to the side wall outer template, and the outer ring of the transverse screw is fixedly connected to the outer side wall of the baffle through a nut.
7. A mobile formwork structure as claimed in claim 4, wherein: positioning units are arranged among the power cable groove template, the drainage groove template and the communication cable groove template; the positioning unit comprises a connecting plate, a positioning rod and a fine adjustment screw rod; a plurality of clamping grooves are formed in one side of the connecting plate, the number of the clamping grooves is the same as the sum of the number of the power cable groove template, the number of the drainage groove template, the number of the communication cable groove template and the number of the side wall outer templates, notches of the clamping grooves are connected with fine adjustment screws through nuts, and one ends of the fine adjustment screws are fixedly connected to the upper end faces of the power cable groove template, the drainage groove template, the communication cable groove template and the side wall outer templates; the lower plate surface of the connecting plate is fixedly connected with three positioning rods, and each positioning rod is inserted between two power cable groove templates, two drainage groove templates and two communication cable groove templates.
8. The mobile formwork structure defined in claim 7 wherein: the length of each locating rod is the same as the depth of a power cable groove, a drainage groove and a communication cable groove to be poured, and chamfers are symmetrically arranged at the end parts of each locating rod.
CN202011056460.8A 2020-09-30 2020-09-30 Movable formwork structure and construction method thereof Pending CN112064676A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011056460.8A CN112064676A (en) 2020-09-30 2020-09-30 Movable formwork structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011056460.8A CN112064676A (en) 2020-09-30 2020-09-30 Movable formwork structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN112064676A true CN112064676A (en) 2020-12-11

Family

ID=73683513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011056460.8A Pending CN112064676A (en) 2020-09-30 2020-09-30 Movable formwork structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN112064676A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153368A (en) * 2021-04-15 2021-07-23 中铁十七局集团第二工程有限公司 Fixing device of curb ditch template in tunnel
CN113346412A (en) * 2021-04-28 2021-09-03 甘肃路桥建设集团有限公司 Highway tunnel hogging moment truss cable trench template tractor and manufacturing method thereof
CN114017065A (en) * 2021-11-05 2022-02-08 中铁三局集团有限公司 Rapid construction method for cable trough of ditch
CN114182756A (en) * 2021-12-22 2022-03-15 新疆路桥建设集团有限公司 Construction method for simply and movably pouring cable trench by using internal mold support system
CN115354662A (en) * 2022-09-14 2022-11-18 湖北萨莱玛木结构工程有限公司 Dampproofing construction frock of log cabin ground
CN116988815A (en) * 2023-08-08 2023-11-03 广东省高速公路有限公司 An integrated pouring method for highway tunnel trenches

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643968A (en) * 2013-12-10 2014-03-19 中铁二十三局集团第一工程有限公司 Method for rapid construction of double-track tunnel ditch cable channel
CN204266233U (en) * 2014-11-30 2015-04-15 中铁二十局集团第五工程有限公司 A kind of tunnel ditch cable channel construction template positioner
KR101939321B1 (en) * 2018-03-23 2019-01-16 현빈개발 주식회사 Method for constructing linear drain device of bridge
CN208674742U (en) * 2018-08-17 2019-03-29 重庆中科建设(集团)有限公司 Cable trench construction mould bases based on loose tool method
CN212612630U (en) * 2020-09-30 2021-02-26 重庆建工第三建设有限责任公司 Movable formwork structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103643968A (en) * 2013-12-10 2014-03-19 中铁二十三局集团第一工程有限公司 Method for rapid construction of double-track tunnel ditch cable channel
CN204266233U (en) * 2014-11-30 2015-04-15 中铁二十局集团第五工程有限公司 A kind of tunnel ditch cable channel construction template positioner
KR101939321B1 (en) * 2018-03-23 2019-01-16 현빈개발 주식회사 Method for constructing linear drain device of bridge
CN208674742U (en) * 2018-08-17 2019-03-29 重庆中科建设(集团)有限公司 Cable trench construction mould bases based on loose tool method
CN212612630U (en) * 2020-09-30 2021-02-26 重庆建工第三建设有限责任公司 Movable formwork structure

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153368A (en) * 2021-04-15 2021-07-23 中铁十七局集团第二工程有限公司 Fixing device of curb ditch template in tunnel
CN113346412A (en) * 2021-04-28 2021-09-03 甘肃路桥建设集团有限公司 Highway tunnel hogging moment truss cable trench template tractor and manufacturing method thereof
CN114017065A (en) * 2021-11-05 2022-02-08 中铁三局集团有限公司 Rapid construction method for cable trough of ditch
CN114017065B (en) * 2021-11-05 2024-04-05 中铁三局集团有限公司 Quick construction method for ditch cable trough
CN114182756A (en) * 2021-12-22 2022-03-15 新疆路桥建设集团有限公司 Construction method for simply and movably pouring cable trench by using internal mold support system
CN115354662A (en) * 2022-09-14 2022-11-18 湖北萨莱玛木结构工程有限公司 Dampproofing construction frock of log cabin ground
CN115354662B (en) * 2022-09-14 2023-10-27 湖北萨莱玛木结构工程有限公司 Moistureproof construction tool for wooden house foundation
CN116988815A (en) * 2023-08-08 2023-11-03 广东省高速公路有限公司 An integrated pouring method for highway tunnel trenches

Similar Documents

Publication Publication Date Title
CN112064676A (en) Movable formwork structure and construction method thereof
CN103266600B (en) Construction method of occlusion pile of full reinforcement pile
CN111794774A (en) A kind of half-cut single-pressure type Myeongdong tunnel rapid tunnel entry protection structure and construction method
WO2023174439A1 (en) Construction method for large pipe shed guide wall at shallow tunnel portal
CN110629769A (en) Cutting slope prismatic anchor rod frame beam rapid construction method
CN109454746B (en) Concrete pouring device for building construction and construction method thereof
CN110593902A (en) A kind of construction method of inverted arch filling integral pouring
CN112681334A (en) Deep foundation pit side wall concrete pouring construction structure and method
CN113700936A (en) Construction method for laying underground drainage pipeline
CN107905258A (en) Pipe gallery exterior wall concrete construction method
CN112252302A (en) Method for realizing split hoisting of underground continuous wall special-shaped steel reinforcement cage into groove based on BIM
CN216691101U (en) Low side wall of tunnel lining and whole construction formwork of side ditch
CN216949733U (en) Novel reinforced concrete structure inverted cone and molding device
CN110528577A (en) A construction method of cast-in-place aluminum film for underground pipe gallery
CN215594113U (en) Pouring template convenient for construction of narrow space electric power pipe ditch
CN104329118B (en) The integral central of falling convex drainage ditch device in vcehicular tunnel
CN113833033A (en) Anti-seepage anti-floating dismantling-free construction process for building in area close to water area
CN210797663U (en) Post-cast strip structure for bottom plate of underground chamber
CN209741907U (en) A steel grid installation structure for a comprehensive pipe gallery sump pit
CN118623089B (en) Construction process of prestressed steel cylinder concrete pipe
CN207538067U (en) A kind of equipment prefabricated foundation locator
CN220550565U (en) Underground continuous wall system
CN220517112U (en) Continuous prefabricated mold for isolation fence foundation
CN217462178U (en) Fine flat strip distribution structure
CN221589693U (en) Once pouring template supporting and forming structure of ground well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201211