CN110080275A - A kind of power transmission and transformation line installation base construction method - Google Patents
A kind of power transmission and transformation line installation base construction method Download PDFInfo
- Publication number
- CN110080275A CN110080275A CN201910414986.XA CN201910414986A CN110080275A CN 110080275 A CN110080275 A CN 110080275A CN 201910414986 A CN201910414986 A CN 201910414986A CN 110080275 A CN110080275 A CN 110080275A
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- power transmission
- template
- installation base
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
The invention discloses a kind of power transmission and transformation line installation base construction methods, it is related to project of transmitting and converting electricity technical field, the present invention is the following steps are included: excavation of foundation pit, prick muscle formwork, basis is poured to be backfilled with demoulding, in excavation of foundation pit step, according to foundation pit size, foundation pit four side edge contour line is drawn on ground, several guide piles are inserted perpendicularly into along every contour line, spacing is a between every adjacent two guide pile of the same side, a=30-50cm, every guide pile bottom is b beyond pre- foundation pit bottom depth of digging, b=20-40cm, it is dug down when excavation along the square region that guide pile is crowded around, foundation pit until digging out predefined size, the present invention has working specification, the small advantage of the foundation pit Size Error dug out.
Description
Technical field
The present invention relates to project of transmitting and converting electricity technical fields, construct more particularly to a kind of power transmission and transformation line installation base
Method.
Background technique
Project of transmitting and converting electricity refers to that the project of transmitting and converting electricity constructions of various voltage class, debugging, power grid operation management, building are built
It builds and the testing of materials, steel tower and its attachment processing and remote large-tonnage lifting forwarding etc..Project of transmitting and converting electricity and people
Production and living it is closely related, with the development of society, people to project of transmitting and converting electricity constantly more stringent requirements are proposed.Power transmission and transformation
The various technologies applied in engineering include that stringing technology, pylon steelframe displacement technique, route aseptic technic and high-voltage dc transmission become
Power technology.
In power transmission and transformation line construction technology process, including foundation construction, ground connection are buried, tower erection, whole bar, lead frame
If wherein foundation construction is the foundation pit for needing to dig out pole and tower foundation according to Center stake and auxiliary pile measurement point with installation etc. is grounded,
Assembling reinforcement and installation template in foundation pit, are then poured concrete in template, and molding obtains basic stand column, then form removal
And other components, it then carries out being grounded burial and construction process in next step again, needs to carry out in strict accordance with job specfication when digging foundation pit,
Foundation pit is generally rectangular hole, and foundation pit walls have certain verticality requirement, and are at present to first pass through when digging foundation pit in construction method
Manually or mechanically after digging to hole bottom, then foundation pit walls verticality is measured, requires again to mend the place of protrusion according to verticality and dig it
It reams, not only construction efficiency is low for this method, but also the foundation pit size dug out be easy to cause large error, is unsatisfactory for construction and wants
It asks.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to: in order to solve the above technical problem, the present invention provides a kind of power transmission and transformation lines to install base
Ground construction method.
The present invention specifically uses following technical scheme to achieve the goals above:
A kind of power transmission and transformation line installation base construction method, comprising the following steps: excavation of foundation pit, bundle muscle formwork, basis are poured
It builds and is backfilled with demoulding, in excavation of foundation pit step, according to foundation pit size, draw foundation pit four side edge contour line on ground, along
Every contour line is inserted perpendicularly into several guide piles, and spacing is a, a=30- between every adjacent two guide pile of the same side
50cm, every guide pile bottom are b beyond pre- foundation pit bottom depth of digging, b=20-40cm, along the side that guide pile is crowded around when excavation
Shape region is dug down, the foundation pit until digging out predefined size.
Further, the silt dug out in Excavation Process is needed far near coal-mine 1m or more, foundation depth tolerance
For+100mm, -50mm.
Further, the bundle muscle formwork specifically includes the following steps:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom on pad brick
There are the spacing of 5-8cm between plate muscle and foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened,
Foundation pit walls set up support rod and push against all templates.
Further, the basis pour specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from mould
Pouring operation is carried out at the top of plate, the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column water seasoning, when maintenance on the outside of template
Add overcover, irrigation times should ensure that concrete surface is wet.
Further, in step bl is determined, concrete formulation includes: 390-395 parts of cement, rubble based on its parts by weight of raw materials
1235-1240 parts, 635-640 parts of sand and 180-190 parts of water.
Further, demoulding backfill specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column after disassembly is residual
Slag;
C2: adding overcover in basic stand column exposed parts, then the backfilled with earth in foundation pit, until backfill height and ground
It flushes, is buried basic stand column lower end.
Beneficial effects of the present invention are as follows:
1, it before digging foundation pit, according to foundation pit size after its edge contour marks, is inserted perpendicularly into along every contour line
Several guide piles, every adjacent positioned pilespacing is from reasonable Arrangement, and it is more than pre- one section of foundation pit of digging that every guide pile, which needs to protrude into underground,
Distance, such foundation pit guarantee that guide pile will not fall when digging to bottom, and the square region surrounded when digging foundation pit along guide pile is down
Digging avoids construction error caused by directly digging down with artificial intuition, has standardized construction method, can once dig out satisfaction and hang down
The foundation pit that straight degree requires, meets construction requirement, and be integrally improved construction efficiency.
Detailed description of the invention
Fig. 1 is guide pile position view in a kind of power transmission and transformation line installation base construction method of the present invention;
Fig. 2 is the structural schematic diagram after basic stand column moulding by casting.
Appended drawing reference: 1- guide pile, 2- basic stand column.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not
For limiting the present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is logical
The component for the embodiment of the present invention being often described and illustrated herein in the accompanying drawings can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed
The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art
Member's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or
Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any
This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive
Property include so that include a series of elements process, method, article or equipment not only include those elements, but also
Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described
There is also other identical elements in the process, method, article or equipment of element.
Feature and performance of the invention are described in further detail with reference to embodiments.
Embodiment 1
As shown in Fig. 1 to 2, the present embodiment provides a kind of power transmission and transformation line installation base construction methods, comprising the following steps:
Excavation of foundation pit, bundle muscle formwork, basis pour and backfill with demoulding, in excavation of foundation pit step, according to foundation pit size, draw on ground
Foundation pit four side edge contour line, is inserted perpendicularly into several guide piles along every contour line, positioned at the same side per adjacent two positioning
Spacing is a, a=30-50cm between stake, and every guide pile bottom is b, b=20-40cm beyond pre- foundation pit bottom depth of digging, and is excavated
When dug down along the square region that guide pile is crowded around, the foundation pit until digging out predefined size.
Further, the silt dug out in Excavation Process is needed far near coal-mine 1m or more, foundation depth tolerance
For+100mm, -50mm.
Further, the bundle muscle formwork specifically includes the following steps:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom on pad brick
There are the spacing of 5-8cm between plate muscle and foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened,
Foundation pit walls set up support rod and push against all templates.
Further, the basis pour specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from mould
Pouring operation is carried out at the top of plate, the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column water seasoning, when maintenance on the outside of template
Add overcover, irrigation times should ensure that concrete surface is wet.
Further, in step bl is determined, concrete formulation includes: 390-395 parts of cement, rubble based on its parts by weight of raw materials
1235-1240 parts, 635-640 parts of sand and 180-190 parts of water.
Further, demoulding backfill specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column after disassembly is residual
Slag;
C2: adding overcover in basic stand column exposed parts, then the backfilled with earth in foundation pit, until backfill height and ground
It flushes, is buried basic stand column lower end.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention
It encloses and is subject to claims, it is all to change with equivalent structure made by specification and accompanying drawing content of the invention, similarly
It should be included within the scope of the present invention.
Claims (6)
1. a kind of power transmission and transformation line installation base construction method, comprising the following steps: excavation of foundation pit, bundle muscle formwork, basis pour
It is backfilled with demoulding, which is characterized in that in excavation of foundation pit step, according to foundation pit size, draw foundation pit four side edge wheel on ground
Profile is inserted perpendicularly into several guide piles (1) along every contour line, positioned at the same side per adjacent two guide pile (1) between
Away from for a, a=30-50cm, every guide pile (1) bottom is b beyond pre- foundation pit bottom depth of digging, b=20-40cm, when excavation along
The square region that guide pile (1) is crowded around is dug down, the foundation pit until digging out predefined size.
2. a kind of power transmission and transformation line installation base construction method according to claim 1, which is characterized in that in excavation of foundation pit
The silt dug out in the process is needed far near coal-mine 1m or more, and foundation depth tolerance is+100mm, -50mm.
3. a kind of power transmission and transformation line installation base construction method according to claim 1, which is characterized in that the bundle muscle branch
Mold the following steps are included:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom plate muscle on pad brick
There are the spacing of 5-8cm between foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened, in foundation pit
Ledge sets support rod and pushes against all templates.
4. a kind of power transmission and transformation line installation base construction method according to claim 3, which is characterized in that pour on the basis
Build specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from template top
Portion carries out pouring operation, and the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column (2) water seasoning, when maintenance on the outside of template plus
Overcover, irrigation times should ensure that concrete surface is wet.
5. a kind of power transmission and transformation line installation base construction method according to claim 4, which is characterized in that in step B1
In, concrete formulation includes: 390-395 parts of cement, 1235-1240 parts of rubble, 635-640 parts of sand based on its parts by weight of raw materials
With 180-190 parts of water.
6. a kind of power transmission and transformation line installation base construction method according to claim 4, which is characterized in that the demoulding is returned
Fill out specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column (2) after disassembly is residual
Slag;
C2: in basic stand column (2), exposed parts add overcover, then the backfilled with earth in foundation pit, until backfill height and ground
It flushes, is buried basic stand column (2) lower end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910414986.XA CN110080275A (en) | 2019-05-17 | 2019-05-17 | A kind of power transmission and transformation line installation base construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910414986.XA CN110080275A (en) | 2019-05-17 | 2019-05-17 | A kind of power transmission and transformation line installation base construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110080275A true CN110080275A (en) | 2019-08-02 |
Family
ID=67420819
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910414986.XA Pending CN110080275A (en) | 2019-05-17 | 2019-05-17 | A kind of power transmission and transformation line installation base construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110080275A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115012427A (en) * | 2022-06-20 | 2022-09-06 | 广东电网有限责任公司 | Outdoor transformer substation construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101446088A (en) * | 2008-11-11 | 2009-06-03 | 中国电力科学研究院 | Construction method for pole and tower foundation in Gobi Desert gravelly soil area |
US20110158751A1 (en) * | 2009-12-29 | 2011-06-30 | Kyowa Co., Ltd. | Method for constructing a foundation for a wind power generation system |
CN104074199A (en) * | 2014-06-17 | 2014-10-01 | 杭州华能大坝安全工程技术有限公司 | Underwater bearing platform construction method |
CN105887914A (en) * | 2016-05-04 | 2016-08-24 | 国网新疆电力公司哈密供电公司 | Construction method of high-voltage pole and tower |
-
2019
- 2019-05-17 CN CN201910414986.XA patent/CN110080275A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101446088A (en) * | 2008-11-11 | 2009-06-03 | 中国电力科学研究院 | Construction method for pole and tower foundation in Gobi Desert gravelly soil area |
US20110158751A1 (en) * | 2009-12-29 | 2011-06-30 | Kyowa Co., Ltd. | Method for constructing a foundation for a wind power generation system |
CN104074199A (en) * | 2014-06-17 | 2014-10-01 | 杭州华能大坝安全工程技术有限公司 | Underwater bearing platform construction method |
CN105887914A (en) * | 2016-05-04 | 2016-08-24 | 国网新疆电力公司哈密供电公司 | Construction method of high-voltage pole and tower |
Non-Patent Citations (1)
Title |
---|
叶建云等: "《斜置式插入钢管基础施工的定位测量与控制》", 《电力建设》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115012427A (en) * | 2022-06-20 | 2022-09-06 | 广东电网有限责任公司 | Outdoor transformer substation construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11143027B2 (en) | Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof | |
CN107059920B (en) | Loess formation piping lane construction technology | |
CN110984210A (en) | Iron frame foundation of power transmission line and construction method | |
CN103374923A (en) | Method for prefabricating and mounting underwater pier | |
CN112064676A (en) | Movable formwork structure and construction method thereof | |
CN109403367A (en) | A kind of assembled case change basis and its component on site construction method | |
CN106988339B (en) | Sandy gravel stratum piping lane construction technology | |
CN101597888A (en) | Construction method of municipal drainage culvert sinking trough | |
KR20070115112A (en) | Construction method for utility-pipe conduit | |
CN110080275A (en) | A kind of power transmission and transformation line installation base construction method | |
CN104153403A (en) | Construction method for reverse construction method cast-in-place pile static load test pile | |
CN204825867U (en) | As composite pile structure of secretly digging garage stand | |
CN110306396A (en) | A kind of assembly concrete road surface and construction method | |
CN103669400A (en) | Typical construction method for prefabricated tube bank | |
CN109826224A (en) | A kind of sinking well protection wall digging foundation and its construction method for desert region iron tower of power transmission line | |
CN104727339A (en) | Electrical equipment foundation two-step type construction method | |
CN211691431U (en) | Detachable pipe group construction accurate positioning template combined system | |
CN113585276A (en) | Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit | |
CN202280073U (en) | Precast assembly type equipment foundation | |
CN110344439B (en) | Construction method of rear retaining wall drain hole | |
CN209353364U (en) | A kind of assembled case change basis | |
CN216949733U (en) | Novel reinforced concrete structure inverted cone and molding device | |
CN115595979A (en) | Construction method for treating karst cave by bridge pile foundation under geological condition of strong development of karst | |
CN113106994A (en) | Wide waterproof plate laying method for cover-excavation top-down subway station | |
CN209723014U (en) | A kind of sinking well protection wall digging foundation for desert region iron tower of power transmission line |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190802 |