CN110080275A - A kind of power transmission and transformation line installation base construction method - Google Patents

A kind of power transmission and transformation line installation base construction method Download PDF

Info

Publication number
CN110080275A
CN110080275A CN201910414986.XA CN201910414986A CN110080275A CN 110080275 A CN110080275 A CN 110080275A CN 201910414986 A CN201910414986 A CN 201910414986A CN 110080275 A CN110080275 A CN 110080275A
Authority
CN
China
Prior art keywords
foundation pit
power transmission
template
installation base
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910414986.XA
Other languages
Chinese (zh)
Inventor
王振帮
胡海周
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Haipeng Power Transmission And Transfer Engineering Co Ltd
Original Assignee
Henan Haipeng Power Transmission And Transfer Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Haipeng Power Transmission And Transfer Engineering Co Ltd filed Critical Henan Haipeng Power Transmission And Transfer Engineering Co Ltd
Priority to CN201910414986.XA priority Critical patent/CN110080275A/en
Publication of CN110080275A publication Critical patent/CN110080275A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a kind of power transmission and transformation line installation base construction methods, it is related to project of transmitting and converting electricity technical field, the present invention is the following steps are included: excavation of foundation pit, prick muscle formwork, basis is poured to be backfilled with demoulding, in excavation of foundation pit step, according to foundation pit size, foundation pit four side edge contour line is drawn on ground, several guide piles are inserted perpendicularly into along every contour line, spacing is a between every adjacent two guide pile of the same side, a=30-50cm, every guide pile bottom is b beyond pre- foundation pit bottom depth of digging, b=20-40cm, it is dug down when excavation along the square region that guide pile is crowded around, foundation pit until digging out predefined size, the present invention has working specification, the small advantage of the foundation pit Size Error dug out.

Description

A kind of power transmission and transformation line installation base construction method
Technical field
The present invention relates to project of transmitting and converting electricity technical fields, construct more particularly to a kind of power transmission and transformation line installation base Method.
Background technique
Project of transmitting and converting electricity refers to that the project of transmitting and converting electricity constructions of various voltage class, debugging, power grid operation management, building are built It builds and the testing of materials, steel tower and its attachment processing and remote large-tonnage lifting forwarding etc..Project of transmitting and converting electricity and people Production and living it is closely related, with the development of society, people to project of transmitting and converting electricity constantly more stringent requirements are proposed.Power transmission and transformation The various technologies applied in engineering include that stringing technology, pylon steelframe displacement technique, route aseptic technic and high-voltage dc transmission become Power technology.
In power transmission and transformation line construction technology process, including foundation construction, ground connection are buried, tower erection, whole bar, lead frame If wherein foundation construction is the foundation pit for needing to dig out pole and tower foundation according to Center stake and auxiliary pile measurement point with installation etc. is grounded, Assembling reinforcement and installation template in foundation pit, are then poured concrete in template, and molding obtains basic stand column, then form removal And other components, it then carries out being grounded burial and construction process in next step again, needs to carry out in strict accordance with job specfication when digging foundation pit, Foundation pit is generally rectangular hole, and foundation pit walls have certain verticality requirement, and are at present to first pass through when digging foundation pit in construction method Manually or mechanically after digging to hole bottom, then foundation pit walls verticality is measured, requires again to mend the place of protrusion according to verticality and dig it It reams, not only construction efficiency is low for this method, but also the foundation pit size dug out be easy to cause large error, is unsatisfactory for construction and wants It asks.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to: in order to solve the above technical problem, the present invention provides a kind of power transmission and transformation lines to install base Ground construction method.
The present invention specifically uses following technical scheme to achieve the goals above:
A kind of power transmission and transformation line installation base construction method, comprising the following steps: excavation of foundation pit, bundle muscle formwork, basis are poured It builds and is backfilled with demoulding, in excavation of foundation pit step, according to foundation pit size, draw foundation pit four side edge contour line on ground, along Every contour line is inserted perpendicularly into several guide piles, and spacing is a, a=30- between every adjacent two guide pile of the same side 50cm, every guide pile bottom are b beyond pre- foundation pit bottom depth of digging, b=20-40cm, along the side that guide pile is crowded around when excavation Shape region is dug down, the foundation pit until digging out predefined size.
Further, the silt dug out in Excavation Process is needed far near coal-mine 1m or more, foundation depth tolerance For+100mm, -50mm.
Further, the bundle muscle formwork specifically includes the following steps:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom on pad brick There are the spacing of 5-8cm between plate muscle and foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened, Foundation pit walls set up support rod and push against all templates.
Further, the basis pour specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from mould Pouring operation is carried out at the top of plate, the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column water seasoning, when maintenance on the outside of template Add overcover, irrigation times should ensure that concrete surface is wet.
Further, in step bl is determined, concrete formulation includes: 390-395 parts of cement, rubble based on its parts by weight of raw materials 1235-1240 parts, 635-640 parts of sand and 180-190 parts of water.
Further, demoulding backfill specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column after disassembly is residual Slag;
C2: adding overcover in basic stand column exposed parts, then the backfilled with earth in foundation pit, until backfill height and ground It flushes, is buried basic stand column lower end.
Beneficial effects of the present invention are as follows:
1, it before digging foundation pit, according to foundation pit size after its edge contour marks, is inserted perpendicularly into along every contour line Several guide piles, every adjacent positioned pilespacing is from reasonable Arrangement, and it is more than pre- one section of foundation pit of digging that every guide pile, which needs to protrude into underground, Distance, such foundation pit guarantee that guide pile will not fall when digging to bottom, and the square region surrounded when digging foundation pit along guide pile is down Digging avoids construction error caused by directly digging down with artificial intuition, has standardized construction method, can once dig out satisfaction and hang down The foundation pit that straight degree requires, meets construction requirement, and be integrally improved construction efficiency.
Detailed description of the invention
Fig. 1 is guide pile position view in a kind of power transmission and transformation line installation base construction method of the present invention;
Fig. 2 is the structural schematic diagram after basic stand column moulding by casting.
Appended drawing reference: 1- guide pile, 2- basic stand column.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not For limiting the present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is logical The component for the embodiment of the present invention being often described and illustrated herein in the accompanying drawings can be arranged and be designed with a variety of different configurations.
Therefore, the detailed description of the embodiment of the present invention provided in the accompanying drawings is not intended to limit below claimed The scope of the present invention, but be merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art Member's every other embodiment obtained without making creative work, shall fall within the protection scope of the present invention.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive Property include so that include a series of elements process, method, article or equipment not only include those elements, but also Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described There is also other identical elements in the process, method, article or equipment of element.
Feature and performance of the invention are described in further detail with reference to embodiments.
Embodiment 1
As shown in Fig. 1 to 2, the present embodiment provides a kind of power transmission and transformation line installation base construction methods, comprising the following steps: Excavation of foundation pit, bundle muscle formwork, basis pour and backfill with demoulding, in excavation of foundation pit step, according to foundation pit size, draw on ground Foundation pit four side edge contour line, is inserted perpendicularly into several guide piles along every contour line, positioned at the same side per adjacent two positioning Spacing is a, a=30-50cm between stake, and every guide pile bottom is b, b=20-40cm beyond pre- foundation pit bottom depth of digging, and is excavated When dug down along the square region that guide pile is crowded around, the foundation pit until digging out predefined size.
Further, the silt dug out in Excavation Process is needed far near coal-mine 1m or more, foundation depth tolerance For+100mm, -50mm.
Further, the bundle muscle formwork specifically includes the following steps:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom on pad brick There are the spacing of 5-8cm between plate muscle and foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened, Foundation pit walls set up support rod and push against all templates.
Further, the basis pour specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from mould Pouring operation is carried out at the top of plate, the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column water seasoning, when maintenance on the outside of template Add overcover, irrigation times should ensure that concrete surface is wet.
Further, in step bl is determined, concrete formulation includes: 390-395 parts of cement, rubble based on its parts by weight of raw materials 1235-1240 parts, 635-640 parts of sand and 180-190 parts of water.
Further, demoulding backfill specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column after disassembly is residual Slag;
C2: adding overcover in basic stand column exposed parts, then the backfilled with earth in foundation pit, until backfill height and ground It flushes, is buried basic stand column lower end.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention It encloses and is subject to claims, it is all to change with equivalent structure made by specification and accompanying drawing content of the invention, similarly It should be included within the scope of the present invention.

Claims (6)

1. a kind of power transmission and transformation line installation base construction method, comprising the following steps: excavation of foundation pit, bundle muscle formwork, basis pour It is backfilled with demoulding, which is characterized in that in excavation of foundation pit step, according to foundation pit size, draw foundation pit four side edge wheel on ground Profile is inserted perpendicularly into several guide piles (1) along every contour line, positioned at the same side per adjacent two guide pile (1) between Away from for a, a=30-50cm, every guide pile (1) bottom is b beyond pre- foundation pit bottom depth of digging, b=20-40cm, when excavation along The square region that guide pile (1) is crowded around is dug down, the foundation pit until digging out predefined size.
2. a kind of power transmission and transformation line installation base construction method according to claim 1, which is characterized in that in excavation of foundation pit The silt dug out in the process is needed far near coal-mine 1m or more, and foundation depth tolerance is+100mm, -50mm.
3. a kind of power transmission and transformation line installation base construction method according to claim 1, which is characterized in that the bundle muscle branch Mold the following steps are included:
A1: assembling reinforcement: several pieces of pad bricks first are laid with as protective layer at foundation pit bottom, bind bottom plate muscle, bottom plate muscle on pad brick There are the spacing of 5-8cm between foundation pit walls, and column muscle is then bound on bottom plate muscle;
A2: template installation: template uses rigid material, and template is installed to four side of column muscle one by one and is mutually fastened, in foundation pit Ledge sets support rod and pushes against all templates.
4. a kind of power transmission and transformation line installation base construction method according to claim 3, which is characterized in that pour on the basis Build specifically includes the following steps:
B1: it according to concrete proportioning by raw material using mechanical stirring or artificial stirring, prepares it after concrete from template top Portion carries out pouring operation, and the concrete being stirred continuously in template in casting process makes it uniformly;
B2: starting after casting in 12 hours to molding basic stand column (2) water seasoning, when maintenance on the outside of template plus Overcover, irrigation times should ensure that concrete surface is wet.
5. a kind of power transmission and transformation line installation base construction method according to claim 4, which is characterized in that in step B1 In, concrete formulation includes: 390-395 parts of cement, 1235-1240 parts of rubble, 635-640 parts of sand based on its parts by weight of raw materials With 180-190 parts of water.
6. a kind of power transmission and transformation line installation base construction method according to claim 4, which is characterized in that the demoulding is returned Fill out specifically includes the following steps:
C1: template is dismantled after pouring completion 48 hours in basis, and the concrete removed on basic stand column (2) after disassembly is residual Slag;
C2: in basic stand column (2), exposed parts add overcover, then the backfilled with earth in foundation pit, until backfill height and ground It flushes, is buried basic stand column (2) lower end.
CN201910414986.XA 2019-05-17 2019-05-17 A kind of power transmission and transformation line installation base construction method Pending CN110080275A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910414986.XA CN110080275A (en) 2019-05-17 2019-05-17 A kind of power transmission and transformation line installation base construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910414986.XA CN110080275A (en) 2019-05-17 2019-05-17 A kind of power transmission and transformation line installation base construction method

Publications (1)

Publication Number Publication Date
CN110080275A true CN110080275A (en) 2019-08-02

Family

ID=67420819

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910414986.XA Pending CN110080275A (en) 2019-05-17 2019-05-17 A kind of power transmission and transformation line installation base construction method

Country Status (1)

Country Link
CN (1) CN110080275A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115012427A (en) * 2022-06-20 2022-09-06 广东电网有限责任公司 Outdoor transformer substation construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
US20110158751A1 (en) * 2009-12-29 2011-06-30 Kyowa Co., Ltd. Method for constructing a foundation for a wind power generation system
CN104074199A (en) * 2014-06-17 2014-10-01 杭州华能大坝安全工程技术有限公司 Underwater bearing platform construction method
CN105887914A (en) * 2016-05-04 2016-08-24 国网新疆电力公司哈密供电公司 Construction method of high-voltage pole and tower

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446088A (en) * 2008-11-11 2009-06-03 中国电力科学研究院 Construction method for pole and tower foundation in Gobi Desert gravelly soil area
US20110158751A1 (en) * 2009-12-29 2011-06-30 Kyowa Co., Ltd. Method for constructing a foundation for a wind power generation system
CN104074199A (en) * 2014-06-17 2014-10-01 杭州华能大坝安全工程技术有限公司 Underwater bearing platform construction method
CN105887914A (en) * 2016-05-04 2016-08-24 国网新疆电力公司哈密供电公司 Construction method of high-voltage pole and tower

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
叶建云等: "《斜置式插入钢管基础施工的定位测量与控制》", 《电力建设》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115012427A (en) * 2022-06-20 2022-09-06 广东电网有限责任公司 Outdoor transformer substation construction method

Similar Documents

Publication Publication Date Title
US11143027B2 (en) Rectangular working well with preset pipe jacking hole and sliding back wall in water-rich stratum and construction method thereof
CN107059920B (en) Loess formation piping lane construction technology
CN110984210A (en) Iron frame foundation of power transmission line and construction method
CN103374923A (en) Method for prefabricating and mounting underwater pier
CN112064676A (en) Movable formwork structure and construction method thereof
CN109403367A (en) A kind of assembled case change basis and its component on site construction method
CN106988339B (en) Sandy gravel stratum piping lane construction technology
CN101597888A (en) Construction method of municipal drainage culvert sinking trough
KR20070115112A (en) Construction method for utility-pipe conduit
CN110080275A (en) A kind of power transmission and transformation line installation base construction method
CN104153403A (en) Construction method for reverse construction method cast-in-place pile static load test pile
CN204825867U (en) As composite pile structure of secretly digging garage stand
CN110306396A (en) A kind of assembly concrete road surface and construction method
CN103669400A (en) Typical construction method for prefabricated tube bank
CN109826224A (en) A kind of sinking well protection wall digging foundation and its construction method for desert region iron tower of power transmission line
CN104727339A (en) Electrical equipment foundation two-step type construction method
CN211691431U (en) Detachable pipe group construction accurate positioning template combined system
CN113585276A (en) Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit
CN202280073U (en) Precast assembly type equipment foundation
CN110344439B (en) Construction method of rear retaining wall drain hole
CN209353364U (en) A kind of assembled case change basis
CN216949733U (en) Novel reinforced concrete structure inverted cone and molding device
CN115595979A (en) Construction method for treating karst cave by bridge pile foundation under geological condition of strong development of karst
CN113106994A (en) Wide waterproof plate laying method for cover-excavation top-down subway station
CN209723014U (en) A kind of sinking well protection wall digging foundation for desert region iron tower of power transmission line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190802