CN105887914A - Construction method of high-voltage pole and tower - Google Patents
Construction method of high-voltage pole and tower Download PDFInfo
- Publication number
- CN105887914A CN105887914A CN201610287397.6A CN201610287397A CN105887914A CN 105887914 A CN105887914 A CN 105887914A CN 201610287397 A CN201610287397 A CN 201610287397A CN 105887914 A CN105887914 A CN 105887914A
- Authority
- CN
- China
- Prior art keywords
- foundation
- column
- construction
- reinforcing bar
- model
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
Abstract
A construction method of a high-voltage pole and tower is characterized by comprising the following steps: pit dividing, earthwork digging, steel bar binding and foundation die supporting, installation of column templates, mounting of foundation bolts, measurement of integral foundation torsion and foundation concrete pouring. The construction method performs foundation construction by the steps, can effectively prevent columns from sinking and guarantees alignment of the foundation bolts.
Description
Technical field
The present invention relates to the method for construction of a kind of high pressure shaft tower, belong to technical field of electric power.
Background technology
In high pressure stem tower foundation is constructed, owing to high pressure stem column foot hole is single hole, and foundation bolt is big from weight, uses tradition side
When method carries out foundation construction, column sinks serious, and foundation bolt is difficult to centering.Instruct accordingly, it would be desirable to work out new construction method
Construction.
Summary of the invention
According to above-mentioned requirements, it is an object of the invention to provide the method for construction of a kind of high pressure shaft tower, to ensure the centering of foundation bolt.
For achieving the above object and other relevant purposes, the present invention provides below scheme:
The method of construction of a kind of high pressure shaft tower, comprises the following steps:
A. repetition measurement location:
Before foundation excavation, it is necessary to check the position at the shaft tower center that nail is vertical when design is surveyed eventually according to construction drawing;The most also tackle quilt
Cross over or pass through the most inadequate landform raised points of thing, wire distance to the ground and leap thing that the whole oversight of design is surveyed and important disconnected
Cake carries out repetition measurement and mends survey, final confirmation shaft tower center;
B. earthwork evacuation:
For hard soil and powdery loess step excavation formula foundation pit, controlling base plate of foundation pit width well, foundation depth is in strict accordance with construction
Figure is constructed;For phenomenon of backbreaking, dig part more and answer paver grouting treatment;For the foundation pit that level of ground water is higher, construction
Time configuration pumping equipment extract hole internal water accumulation out, and add the gradient of hollow place wall;
During excavation of foundation pit, monitoring foundation ditch position and shape at any time, foundation ditch excavates and should carry out in time close to when cheating deep size
Hole is deep to be measured, and carries out Leveling and centering after foundation ditch molding;
C. reinforcing bar binding and basis formwork:
Reinforcing bar binding: before reinforcing bar binding, first has to check specification and the quantity of reinforcing bar, completely the same with construction drawing;In order to
Ensure that the spacing of each position reinforcing bar meets design requirement, according to spacing and the present position of reinforcing bar, reinforcing bar is finished with crayon and ties up
Prick labelling;The application iron wire colligation of reinforcing bar cross point is firm;
Basis formwork includes that bed die and step mould, bed die and stepped formwork use integral forming steel form, and each layer template installs additional respectively
Enclose stupefied, template the most first brush interleaving agent, prevent interleaving agent from gluing, drip on reinforcing bar;Due to casting concrete be at column and
Under the weight effect of concrete, ground floor, second layer step medial surface template stress are relatively big, therefore, must enter it during construction
Row is reinforced, and prevents deformation;
Bed die and the concrete mats pier liner of step mould support bed die height or support with the stupefied each angle of ∠ 125 × 10 angle steel torr, press
After assigned position supports, the relevant position cement mortar at the end, hole is fixed, and upright supports angle steel torr is stupefied;In order to prevent column
The pressure that template is big sinks with model of the column on bed die and step die shoe are stupefied, each for model of the column angle guide chain will be hung to hole respectively
Mouthful the most mounted the most stupefied on;
D., model of the column is installed:
Model of the column is arranged on second layer stepped formwork by angle steel torr is stupefied, model of the column by adjustable apical organ in foundation pit walls
Upper enforcement;Model of the column torr is stupefied to be arranged on stepped formwork, owing to model of the column is higher, heavier, in order to prevent model of the column
Sink, affect construction quality and the end face discrepancy in elevation, need column template to carry out
Promote and reinforcement;
E. the laying of foundation bolt:
Before and after on the horizontal, vertical line direction of foundation bolt, two bolt pitch carry out mark with red pen, and vertically become one
Straight line;This labelling to shift to an earlier date ready-made labelling point-blank on model of the column;
F. the measurement of integral basis foundation torsion: if integral basis foundation torsion meets design requirement, then proceed to next step;As do not met,
Above-mentioned steps a, b, c, d and e are modified;
G. foundation concrete is cast:
Before basis is cast, to the check for the first time of detection ruler little progress row;Basis is monitored during casting;Concrete casts lower margin spiral shell
During bolt extension position, to the second time check of detection ruler little progress row;After each basis has been cast, carry out third time size check;
Through repeated detection, key dimension can be controlled and meet the requirements;Then carry out foundation concrete to cast;
H. foundation ditch backfill:
Use soil or husky backfill that former hole digs out, should often backfill certain thickness watering compacting during backfill once;
The auxiliary pile quantity of described point of hole step conclusion is more than 6 on horizontal, vertical circuit.
Preferably, described reinforcing bar binding step, when assembling reinforcement cross point, when colligation muscle is in Φ less than 12, double with 22#
Stock wiring colligation is together;When colligation muscle is in Φ more than 12, by 22# bifilar wiring decussation colligation twice.
Preferably, described basis formwork step in, each for model of the column angle is hung respectively near coal-mine the most mounted the most stupefied on lead
Chain is 1t guide chain.
Preferably, in the step of laying of described foundation bolt, foundation bolt crane hangs.
Preferably, the suspender belt of lifting foundation bolt uses cross colligation.
The invention has the beneficial effects as follows: the present invention uses above-mentioned steps to carry out foundation construction, can effectively prevent the sinking of column,
Ensure the centering of foundation bolt.
Detailed description of the invention
By particular specific embodiment, embodiments of the present invention being described below, those skilled in the art can be taken off by this specification
The content of dew understands other advantages and effect of the present invention easily.
The method of construction of a kind of high pressure shaft tower, comprises the following steps:
A. repetition measurement location:
Before foundation excavation, it is necessary to check the position at the shaft tower center that nail is vertical when design is surveyed eventually according to construction drawing;The most also tackle quilt
Cross over or pass through the most inadequate landform raised points of thing, wire distance to the ground and leap thing that the whole oversight of design is surveyed and important disconnected
Cake carries out repetition measurement and mends survey, final confirmation shaft tower center;
B. earthwork evacuation:
For hard soil and powdery loess step excavation formula foundation pit, controlling base plate of foundation pit width well, foundation depth is in strict accordance with construction
Figure is constructed;For phenomenon of backbreaking, dig part more and answer paver grouting treatment;For the foundation pit that level of ground water is higher, construction
Time configuration pumping equipment extract hole internal water accumulation out, and add the gradient of hollow place wall;
During excavation of foundation pit, monitoring foundation ditch position and shape at any time, foundation ditch excavates and should carry out in time close to when cheating deep size
Hole is deep to be measured, and carries out Leveling and centering after foundation ditch molding;
C. reinforcing bar binding and basis formwork:
Reinforcing bar binding: before reinforcing bar binding, first has to check specification and the quantity of reinforcing bar, completely the same with construction drawing;In order to
Ensure that the spacing of each position reinforcing bar meets design requirement, according to spacing and the present position of reinforcing bar, reinforcing bar is finished with crayon and ties up
Prick labelling;The application iron wire colligation of reinforcing bar cross point is firm;
Basis formwork includes that bed die and step mould, bed die and stepped formwork use integral forming steel form, and each layer template installs additional respectively
Enclose stupefied, template the most first brush interleaving agent, prevent interleaving agent from gluing, drip on reinforcing bar;Due to casting concrete be at column and
Under the weight effect of concrete, ground floor, second layer step medial surface template stress are relatively big, therefore, must enter it during construction
Row is reinforced, and prevents deformation;
Bed die and the concrete mats pier liner of step mould support bed die height or support with the stupefied each angle of ∠ 125 × 10 angle steel torr, by rule
After support well is put in location, the relevant position cement mortar at the end, hole is fixed, and upright supports angle steel torr is stupefied;In order to prevent column mould
The pressure that plate is big sinks with model of the column on bed die and step die shoe are stupefied, hang near coal-mine respectively by each for model of the column angle guide chain
The most mounted the most stupefied on;
D., model of the column is installed:
Model of the column is arranged on second layer stepped formwork by angle steel torr is stupefied, model of the column by adjustable apical organ in foundation pit walls
Upper enforcement;Model of the column torr is stupefied to be arranged on stepped formwork, owing to model of the column is higher, heavier, in order to prevent model of the column
Sink, affect construction quality and the end face discrepancy in elevation, need column template to carry out
Promote and reinforcement;
E. the laying of foundation bolt:
Before and after on the horizontal, vertical line direction of foundation bolt, two bolt pitch carry out mark with red pen, and vertically become one
Straight line;This labelling to shift to an earlier date ready-made labelling point-blank on model of the column;
F. the measurement of integral basis foundation torsion: if integral basis foundation torsion meets design requirement, then proceed to next step;As do not met,
Above-mentioned steps a, b, c, d and e are modified;
G. foundation concrete is cast:
Before basis is cast, to the check for the first time of detection ruler little progress row;Basis is monitored during casting;Concrete casts lower margin spiral shell
During bolt extension position, to the second time check of detection ruler little progress row;After each basis has been cast, carry out third time size check;
Through repeated detection, key dimension can be controlled and meet the requirements;Then carry out foundation concrete to cast;
H. foundation ditch backfill:
Use soil or husky backfill that former hole digs out, should often backfill certain thickness watering compacting during backfill once;
The auxiliary pile quantity of described point of hole step conclusion is more than 6 on horizontal, vertical circuit.
Preferably, described reinforcing bar binding step, when assembling reinforcement cross point, when colligation muscle is in Φ less than 12, double with 22#
Stock wiring colligation is together;When colligation muscle is in Φ more than 12, by 22# bifilar wiring decussation colligation twice.
Preferably, described basis formwork step in, each for model of the column angle is hung respectively near coal-mine the most mounted the most stupefied on lead
Chain is 1t guide chain.
Preferably, in the step of laying of described foundation bolt, foundation bolt crane hangs.
Preferably, the suspender belt of lifting foundation bolt uses cross colligation.
The principle of above-described embodiment only illustrative present invention and effect thereof, not for limiting the present invention.Any it is familiar with this skill
Above-described embodiment all can be modified under the spirit and the scope of the present invention or change by the personage of art.Therefore, such as
All that in art, tool usually intellectual is completed under without departing from disclosed spirit and technological thought etc.
Effect is modified or changes, and must be contained by the claim of the present invention.
Claims (5)
1. the method for construction of a high pressure shaft tower, it is characterised in that: comprise the following steps:
A. repetition measurement location:
Before foundation excavation, it is necessary to check the position at the shaft tower center that nail is vertical when design is surveyed eventually according to construction drawing;The most also tackle quilt
Cross over or pass through the most inadequate landform raised points of thing, wire distance to the ground and leap thing that the whole oversight of design is surveyed and important disconnected
Cake carries out repetition measurement and mends survey, final confirmation shaft tower center;
B. earthwork evacuation:
For hard soil and powdery loess step excavation formula foundation pit, controlling base plate of foundation pit width well, foundation depth is in strict accordance with construction
Figure is constructed;For phenomenon of backbreaking, dig part more and answer paver grouting treatment;For the foundation pit that level of ground water is higher, construction
Time configuration pumping equipment extract hole internal water accumulation out, and add the gradient of hollow place wall;
During excavation of foundation pit, monitoring foundation ditch position and shape at any time, foundation ditch excavates and should carry out in time close to when cheating deep size
Hole is deep to be measured, and carries out Leveling and centering after foundation ditch molding;
C. reinforcing bar binding and basis formwork:
Reinforcing bar binding: before reinforcing bar binding, first has to check specification and the quantity of reinforcing bar, completely the same with construction drawing;In order to
Ensure that the spacing of each position reinforcing bar meets design requirement, according to spacing and the present position of reinforcing bar, reinforcing bar is finished with crayon and ties up
Prick labelling;The application iron wire colligation of reinforcing bar cross point is firm;
Basis formwork includes that bed die and step mould, bed die and stepped formwork use integral forming steel form, and each layer template installs additional respectively
Enclose stupefied, template the most first brush interleaving agent, prevent interleaving agent from gluing, drip on reinforcing bar;Due to casting concrete be at column and
Under the weight effect of concrete, ground floor, second layer step medial surface template stress are relatively big, therefore, must enter it during construction
Row is reinforced, and prevents deformation;
Bed die and the concrete mats pier liner of step mould support bed die height or support with the stupefied each angle of ∠ 125 × 10 angle steel torr, press
After assigned position supports, the relevant position cement mortar at the end, hole is fixed, and upright supports angle steel torr is stupefied;In order to prevent column
The pressure that template is big sinks with model of the column on bed die and step die shoe are stupefied, each for model of the column angle guide chain will be hung to hole respectively
Mouthful the most mounted the most stupefied on;
D., model of the column is installed:
Model of the column is arranged on second layer stepped formwork by angle steel torr is stupefied, model of the column by adjustable apical organ in foundation pit walls
Upper enforcement;Model of the column torr is stupefied to be arranged on stepped formwork, owing to model of the column is higher, heavier, in order to prevent model of the column
Sink, affect construction quality and the end face discrepancy in elevation, need column template to carry out
Promote and reinforcement;
E. the laying of foundation bolt:
Before and after on the horizontal, vertical line direction of foundation bolt, two bolt pitch carry out mark with red pen, and vertically become one
Straight line;This labelling to shift to an earlier date ready-made labelling point-blank on model of the column;
F. the measurement of integral basis foundation torsion: if integral basis foundation torsion meets design requirement, then proceed to next step;As do not met,
Above-mentioned steps a, b, c, d and e are modified;
G. foundation concrete is cast:
Before basis is cast, to the check for the first time of detection ruler little progress row;Basis is monitored during casting;Concrete casts lower margin spiral shell
During bolt extension position, to the second time check of detection ruler little progress row;After each basis has been cast, carry out third time size check;
Through repeated detection, key dimension can be controlled and meet the requirements;Then carry out foundation concrete to cast;
H. foundation ditch backfill:
Use soil or husky backfill that former hole digs out, should often backfill certain thickness watering compacting during backfill once;
The auxiliary pile quantity of described point of hole step conclusion is more than 6 on horizontal, vertical circuit.
The method of construction of a kind of high pressure shaft tower the most as claimed in claim 1, it is characterised in that: described reinforcing bar binding step,
During assembling reinforcement cross point, when colligation muscle is in Φ less than 12, with 22# bifilar wiring colligation together;When colligation muscle Φ 12 with
Time upper, by 22# bifilar wiring decussation colligation twice.
The method of construction of a kind of high pressure shaft tower the most as claimed in claim 1, it is characterised in that: in the formwork step of described basis,
Each for model of the column angle is hung respectively near coal-mine the most mounted the most stupefied on guide chain be 1t guide chain.
The method of construction of a kind of high pressure shaft tower the most as claimed in claim 1, it is characterised in that: laying of described foundation bolt
Step, foundation bolt crane hangs.
The method of construction of a kind of high pressure shaft tower the most as claimed in claim 4, it is characterised in that: the suspender belt of lifting foundation bolt uses ten
Word colligation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610287397.6A CN105887914A (en) | 2016-05-04 | 2016-05-04 | Construction method of high-voltage pole and tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610287397.6A CN105887914A (en) | 2016-05-04 | 2016-05-04 | Construction method of high-voltage pole and tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105887914A true CN105887914A (en) | 2016-08-24 |
Family
ID=56701998
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610287397.6A Pending CN105887914A (en) | 2016-05-04 | 2016-05-04 | Construction method of high-voltage pole and tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105887914A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149703A (en) * | 2017-08-31 | 2018-06-12 | 中国电建集团河南工程有限公司 | Work transmission line basis precast construction method |
CN110080275A (en) * | 2019-05-17 | 2019-08-02 | 河南海鹏送变电工程有限公司 | A kind of power transmission and transformation line installation base construction method |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104294839A (en) * | 2014-11-14 | 2015-01-21 | 句容华源电器设备有限公司 | High-voltage pole tower foundation construction method |
-
2016
- 2016-05-04 CN CN201610287397.6A patent/CN105887914A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104294839A (en) * | 2014-11-14 | 2015-01-21 | 句容华源电器设备有限公司 | High-voltage pole tower foundation construction method |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108149703A (en) * | 2017-08-31 | 2018-06-12 | 中国电建集团河南工程有限公司 | Work transmission line basis precast construction method |
CN108149703B (en) * | 2017-08-31 | 2019-10-18 | 中国电建集团河南工程有限公司 | Work transmission line basis precast construction method |
CN110080275A (en) * | 2019-05-17 | 2019-08-02 | 河南海鹏送变电工程有限公司 | A kind of power transmission and transformation line installation base construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107246006B (en) | The pile-filling method of concrete-pile | |
CN104294839B (en) | A kind of high pressure stem tower foundation construction method | |
CN103205978B (en) | High-permeability zone under-water-level elevator foundation pit open caisson moulding bed construction method | |
CN105089061B (en) | Ultra-deep foundation pit supporting method | |
CN101289866A (en) | Construction method for precasting concrete moulding bed in local pit of base pit engineering under soft foundation | |
CN108560536A (en) | The continuous piling wall construction method of Soil-cement | |
CN104120736A (en) | Construction method of reinforced concrete retaining wall | |
CN104328790B (en) | Cast-in-situ sprayed concrete hidden bearing platform and hidden ground beam molding bed | |
CN105887914A (en) | Construction method of high-voltage pole and tower | |
CN205116202U (en) | Stake of prestressing force side and integrated stand of steel lattice column | |
CN107460886B (en) | Light steel structure assembly and decoration integrated building foundation and construction method thereof | |
CN104264682A (en) | Anchor traction wall protection pile base layer concrete beam support pouring technology | |
CN204282399U (en) | A kind of subway space enclosing structure | |
CN206448285U (en) | Without bottom concrete combined type cofferdam under the conditions of formation geology | |
CN108487281A (en) | A kind of quick sinking construction device of the forced open caisson of piled anchor | |
CN102493485A (en) | Method for building slope protection retaining wall during filling | |
CN106917358A (en) | A kind of cable-stayed bridge main-beam combination constructing method thereof and its counter weight construction system | |
CN109024657B (en) | Construction method of super high-rise core tube deep pit edge tower crane foundation under complex conditions | |
CN105839663B (en) | On turn over bed course collar tie beam and combine vertical anchor tube reinforcing soft soil foundation ditch method | |
JP5601648B2 (en) | Free slope combined with bottom groove | |
CN216515701U (en) | Miniature stake raft board combination foundation structure | |
CN202970006U (en) | L-shaped prefabricated clear water bleacher plate installation construction structure | |
CN206667263U (en) | A kind of foundation pit supporting construction | |
CN206368375U (en) | A kind of electric power pylon basis | |
CN205637707U (en) | Swimming pool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160824 |