CN104727339A - Electrical equipment foundation two-step type construction method - Google Patents

Electrical equipment foundation two-step type construction method Download PDF

Info

Publication number
CN104727339A
CN104727339A CN201510146776.9A CN201510146776A CN104727339A CN 104727339 A CN104727339 A CN 104727339A CN 201510146776 A CN201510146776 A CN 201510146776A CN 104727339 A CN104727339 A CN 104727339A
Authority
CN
China
Prior art keywords
embedded part
foundation
construction
concrete
dowel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510146776.9A
Other languages
Chinese (zh)
Other versions
CN104727339B (en
Inventor
张伟钊
张尚华
赵东成
冯舜凯
李盼义
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.
Original Assignee
Hebei Electric Power Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Electric Power Design and Research Institute filed Critical Hebei Electric Power Design and Research Institute
Priority to CN201510146776.9A priority Critical patent/CN104727339B/en
Publication of CN104727339A publication Critical patent/CN104727339A/en
Application granted granted Critical
Publication of CN104727339B publication Critical patent/CN104727339B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses an electrical equipment foundation two-step type construction method used for construction of an electrical equipment foundation. The method includes the processes of foundation lower body construction and embedded part foundation construction. The foundation lower body construction includes the following steps that A1, a foundation pit slot of electrical equipment is dug, and a foundation reinforcement frame is placed in the foundation pit slot; A2, the connecting mode of the equipment is designed, and anti-drawing connection or common connection is designed according to actual requirements. The embedded part foundation construction includes the following steps that A3, concrete is poured into the foundation pit slot for the first time, and joint preformed holes are reserved; B1, the specific positions of embedded parts are determined; B2, embedded part anchor bars are arranged according to actual requirements; B3, concrete is poured for the second time. The accuracy and the flatness technological level of main electrical equipment embedded parts of a transformer substation can be improved, the degree of dependence of construction on manufacturer data is reduced, and the construction time of the equipment foundation embedded parts is shortened.

Description

Power equipment basis two-step construction method
Technical field
The present invention relates to the construction method, particularly a kind of construction for power equipment basis on basis.
Background technology
In China's power construction, electric equipments such as main transformer, GIS/HGIS power distribution equipment etc. have that build is large, the feature such as load is heavy, basic embedded part is many, strict to the planeness of equipment basic pre-buried, positioning accuracy request.The many employings of conventional base embedded part construction technology by embedded part after the location leveling of basic end face, whole way of watering together with basis again, its idiographic flow is for after plant equipment data puts in place, carry out embedded part design and foundation pattern design, carry out the work such as basic excavation, cushion construction, reinforcing bar binding, embedded part location, template support, the maintenance of concrete monobloc cast, completion acceptance subsequently successively.
But this disposable mode completing construction is usually subject to equipment vendors' physical resource and the embedded part situation that puts in place restricts, if manufacturer information is complete or embedded part is not in place, just cannot constructs, delay the duration.Because power equipment type is many, more than bid batch, the reason such as construction period is more nervous, conventional embedded part technique is subject to various factors restriction, the more difficult requirement meeting workmanship and progress.Therefore, for better meeting power engineering construction quality and schedule requirement, in power engineering construction, take a kind of novel rational design technology project to seem particularly important and urgent.
Summary of the invention
The technical issues that need to address of the present invention are to provide the construction method on power equipment basis, and Reasonable adjustment job order, shortens the equipment set-up time.
For solving the problems of the technologies described above, the technical solution used in the present invention is:
Power equipment basis two-step construction method, comprise basic infrastructure main body construction and the construction of embedded part part basis, basic infrastructure main body comprises foundation pit groove, basic infrastructure concrete and reinforcement foundation framework, and basic infrastructure main body construction comprises the following steps,
A1, shape and size according to power equipment basis in engineering in the past, dig the foundation pit groove of power equipment, place reinforcement foundation framework in foundation pit groove;
The connected mode on A2, design power equipment and basis, when 80% or the basis of power equipment pulling out load and be greater than power equipment own wt, when producing tensile stress, arrange anti-punching shear bar in foundation pit groove; In other situations, adopt generic connectivity mode;
A3, in foundation pit groove cast first time concrete, and spare interface preformed hole: when all embedded part cross-sectional areas are greater than 10% of basic top surface area, first time pouring concrete end face 0.3m lower than the end face of reinforcement foundation framework, first time, pouring concrete end face entirety was as interface preformed hole; When all embedded part cross-sectional areas are less than or equal to 10% of basic top surface area, the end face of first time pouring concrete end face arrival reinforcement foundation framework, 0.3 meter of dark interface preformed hole is set, the edge 300mm ~ 600mm wider than required access embedded part edge of interface preformed hole needing to access the position of embedded part;
The construction of embedded part part basis comprises the following steps,
B1, embedded part are located, the exact position of become more meticulous to embedded part location, measurement and correction built-in fitting;
B2, embedded part access, access embedded part dowel, and when adopting anti-punching shear bar in steps A 2, embedded part dowel adopts curved anchor pattern tension dowel, and is connected with the anti-punching shear bar spot welding described in steps A 2 by embedded part dowel; When adopting generic connectivity to design in steps A 2, embedded part dowel adopts the common dowel of straight anchor pattern, embedded part is arranged on first time pouring concrete end face;
B3, second time fluid concrete, on power equipment basis, embedded part installs, then on first time pouring concrete end face fluid concrete within the scope of 0.3m.
Further improvement of the present invention is: the anti-punching shear bar described in steps A 2 is HPB300 reinforcing bar, and diameter is 6 ~ 10cm, and setting space is 150 ~ 300mm.
Further improvement of the present invention is: the common dowel of straight anchor pattern described in step B1 is that corner point type supports straight anchor dowel, and the anchorage length in concrete secondary LIFT is 250 ~ 290mm; Described curved anchor pattern tension dowel is 8 equidistant curved anchor dowels, and the anchorage length in concrete secondary LIFT is 40 times of bar diameters.
Further improvement of the present invention is: the concrete that in step B3, second time fluid concrete is used is the C30 pea gravel concreten of interpolation 0.08% ~ 0.10% anti-crack fiber.
Owing to adopting technique scheme, the beneficial effect that the present invention produces is:
Power equipment basis of the present invention two-step construction method can improve precision and the planeness technological level of transformer station's main electric power equipment built-in fitting, the basic infrastructure main body constructions such as foundation trench excavation, concreting, backfill compaction are not by the restriction of Bidding Invition, producer's data, reduce the degree of dependence of construction to producer's data, can go into operation in advance by optimized integration, save the duration, reduce construction costs.
Basic infrastructure main body construction of the present invention and embedded part part basis are constructed the separately construction of two steps, Reasonable adjustment job order, if basic infrastructure main body construction can be constructed in advance when equipment embedded part does not put in place, by the time equipment embedded part carries out embedded part construction after putting in place again, improve operating efficiency, can not some difficultly affect progress because of equipment grade not in place, avoid scene " work holdup " phenomenon, reduce engineering cost.
First time pouring concrete end face of the present invention 0.3m lower than the end face of reinforcement foundation framework, can ensure to bury space underground for distinct device provides reserved, even if make certain adjustment when embedded part is constructed to embedded part position also can ensure to bury underground, improve the compatibility of basic infrastructure main body, based on sub-body construction can construct in advance and provide guarantee.
Anti-punching shear bar of the present invention can strengthen the intensity of basic infrastructure main body, improves the stability on basis, the infringement that the active force that minimizing is pulled out brings equipment Foundations.
Tension dowel of the present invention can bear the uplift force of equipment, improves the connective stability of embedded part and plant bottom case,
The heat of hydration that concrete second pouring can effectively avoid concrete in mass to produce, avoids the generation of external crack.And due to the concrete scale of construction less, better can control construction quality, reach the requirement of clear-water concrete, improve the planeness becoming power equipment built-in fitting.
Accompanying drawing explanation
Fig. 1 is steps flow chart schematic diagram of the present invention;
Foundation structure schematic diagram in Fig. 2 basic infrastructure main body construction of the present invention process;
Fig. 3 the present invention walks foundation structure schematic diagram in embedded part part basis work progress processed;
In the accompanying drawings: 1, foundation pit groove, 2, first time pouring concrete end face, 3, reinforcement foundation framework, 4, second time pouring concrete end face, 5, embedded part, 6, embedded part dowel.
Detailed description of the invention
Power equipment basis two-step construction method, comprise basic infrastructure main body construction and the construction of embedded part part basis, basic infrastructure main body comprises foundation pit groove 1, basic infrastructure concrete and reinforcement foundation framework 3, and basic infrastructure main body construction comprises the following steps,
A1, shape and size according to this power equipment basis in engineering in the past, dig the foundation pit groove 1 of this power equipment, placement reinforcement foundation framework 3 foundation pit groove 1 in;
The connected mode of A2, designing apparatus, when equipment pulling out when load is greater than 80% of equipment own wt, anti-punching shear bar is set in foundation pit groove 1, when equipment is easily subject to earthquake, wind effect substrate generation tensile stress, in foundation pit groove 1, also anti-punching shear bar is set; In other situations, anti-punching shear bar is not set, adopts generic connectivity design;
A3, in foundation pit groove 1 first time fluid concrete, design interface preformed hole: when all embedded part 5 cross-sectional areas are greater than 10% of basic top surface area, first time pouring concrete end face 2 0.3m lower than the end face of reinforcement foundation framework 3, first time, pouring concrete end face 2 entirety was as interface preformed hole; When all embedded part 5 cross-sectional areas are less than or equal to 10% of basic top surface area, pouring concrete end face 2 is higher than the end face of reinforcement foundation framework 3 for the first time, 0.3 meter of dark interface preformed hole is set, the edge 300mm ~ 600mm wider than required access embedded part 5 edge of interface preformed hole needing to access the position of embedded part 5; First time pouring concrete end face 2 0.3m lower than the end face of reinforcement foundation framework 3, can ensure to bury space underground for distinct device provides reserved, space is imbedded in the reserved of some equipment needs at least 0.1 meter, what some equipment needed 0.2 meter reservedly imbeds space, even if reserved 0.3 meter ensures that making certain adjustment when embedded part is constructed to embedded part 5 position also can ensure to bury underground, improve the compatibility of basic infrastructure main body, based on sub-body construction can construct in advance and provide guarantee
Embedded part construction comprises the following steps,
B1, embedded part are located, the exact position of become more meticulous to embedded part 5 location, repeated measurement and correction built-in fitting 5;
B2, embedded part access, access embedded part dowel 6, and when adopting anti-punching shear bar in steps A 2, embedded part dowel 6 adopts curved anchor pattern tension dowel, and is connected with the anti-punching shear bar spot welding described in steps A 2 by embedded part dowel 6; When adopting generic connectivity to design in steps A 2, embedded part dowel 6 adopts the common dowel of straight anchor pattern, embedded part 5 is placed on pouring concrete end face 2 for the first time;
B3, second time fluid concrete, on power equipment basis, embedded part 5 installs, then to carry out on first time pouring concrete end face 2 fluid concrete within the scope of 0.3m.
Anti-punching shear bar described in steps A 2 is HPB300 reinforcing bar, and diameter is 6 ~ 10cm, and setting space is 150 ~ 300cm.
The common dowel of straight anchor pattern described in step B1 is that corner point type supports straight anchor dowel, and the anchorage length in concrete secondary LIFT is 250 ~ 290mm; Described curved anchor pattern tension dowel is 8 equidistant curved anchor dowels, and the anchorage length in concrete secondary LIFT is 40 times of bar diameters.
The concrete that in step B3, second time fluid concrete is used is the C30 pea gravel concreten of interpolation 0.08% ~ 0.10% anti-crack fiber.
Below in conjunction with embodiment, the present invention is described in further details:
Embodiment 1
The basic built-in fitting work progress of 500KVGIS outgoing line interval comprises the following steps,
Basic infrastructure main body construction comprises the following steps,
A1, can determine 500KVGIS outgoing line interval width about 2.7 meters according to the appearance and size of 500KVGIS outgoing line interval in similar engineering in the past, the foundation pit groove 1 digging this power equipment is about 3 meters, placement reinforcement foundation framework 3 foundation pit groove 1 in;
The connected mode of A2, design 500KVGIS outgoing line interval, 500KVGIS outgoing line interval pulls out load is greater than equipment own wt 80%, in foundation pit groove 1, anti-punching shear bar is set;
A3, in foundation pit groove 1 first time fluid concrete, design interface preformed hole: the embedded part cross-sectional area of 500KVGIS outgoing line interval is greater than 10% of basic top surface area, so first time pouring concrete end face 2 0.3m lower than the end face of reinforcement foundation framework 3, first time, pouring concrete end face 2 entirety was as interface preformed hole;
Embedded part construction comprises the following steps,
B1, embedded part are located, and to become more meticulous location to the embedded part 5 of 500KVGIS outgoing line interval, measure and the exact position of correction built-in fitting 5, first time pouring concrete end face built-in fitting 5 is reserved position;
B2, embedded part access, and in 500KVGIS outgoing line interval, embedded part 5 adopts resistance to plucking dowel, and embedded part dowel 6 adopts curved anchor pattern tension dowel, and is connected with the anti-punching shear bar spot welding described in steps A 3;
B3, fluid concrete, on 500KVGIS outgoing line interval basis, built-in fitting 5 installs, and through electric specialty personnel and supervising engineer confirm errorless after, then to carry out on first time pouring concrete end face fluid concrete within the scope of 0.3m.
Embodiment 2
The basic built-in fitting work progress at 500KVGIS bus interval comprises the following steps,
Basic infrastructure main body construction comprises the following steps,
A1,500KVGIS bus interval shape and size can be determined according to the appearance and size of 500KVGIS outgoing line interval in similar engineering in the past, dig the foundation pit groove 1 of this power equipment, placement reinforcement foundation framework 3 foundation pit groove 1 in;
The connected mode at A2, design 500KVGIS bus interval, 500KVGIS bus interval is pulled out load is less than equipment own wt 80%, in foundation pit groove 1, anti-punching shear bar is not set, adopts generic connectivity mode;
A3, in foundation pit groove 1 first time fluid concrete, design interface preformed hole: embedded part 5 cross-sectional area at 500KVGIS bus interval is less than 10% of basic top surface area, so first time pouring concrete end face 2 higher than the low 0.3m of end face of reinforcement foundation framework 3,0.3 meter of dark interface shrinkage pool is set in the position of required spare interface, it is wide that embedded part 5 size is about the long 200mm of 700mm, the size 500mm wider than 500KVGIS bus interval embedded part of interface preformed hole, namely long is 1200mm, and wide is 700mm
Embedded part construction comprises the following steps,
B1, embedded part are located, and to become more meticulous location to the embedded part at 500KVGIS bus interval, measure and the exact position of correction built-in fitting, first time pouring concrete end face 2 built-in fitting 5 is reserved position
B2, embedded part access, and when in 500KVGIS bus interval, embedded part adopts generic connectivity to design, embedded part dowel 6 adopts the common dowel of straight anchor pattern, the embedded part at 500KVGIS bus interval are placed on pouring concrete end face 2 for the first time;
B3, fluid concrete, complete at 500KVGIS bus interval basis installation of embedded parts, and through electric specialty personnel and supervising engineer confirm errorless after, then to carry out on basic end face fluid concrete within the scope of 0.3m.
Precision and the planeness technological level that can improve transformer station's main electric power equipment built-in fitting of the present invention, the basic infrastructure main body constructions such as foundation trench excavation, concreting, backfill compaction are not by the restriction of Bidding Invition, producer's data, reduce the degree of dependence of construction to producer's data, can go into operation in advance by optimized integration, save the duration, reduce construction costs.

Claims (4)

1. power equipment basis two-step construction method, it is characterized in that: comprise basic infrastructure main body construction and the construction of embedded part part basis, basic infrastructure main body comprises foundation pit groove (1), basic infrastructure concrete and reinforcement foundation framework (3), and basic infrastructure main body construction comprises the following steps
A1, shape and size according to power equipment basis in engineering in the past, dig the foundation pit groove (1) of power equipment, placement reinforcement foundation framework (3) foundation pit groove (1) in;
The connected mode on A2, design power equipment and basis, when 80% or the basis of power equipment pulling out load and be greater than power equipment own wt, when producing tensile stress, arrange anti-punching shear bar in foundation pit groove (1); In other situations, adopt generic connectivity mode;
A3, in foundation pit groove (1) cast first time concrete, and spare interface preformed hole: when all embedded parts (5) cross-sectional area is greater than 10% of basic top surface area, first time pouring concrete end face (2) 0.3m lower than the end face of reinforcement foundation framework (3), first time pouring concrete end face (2) is overall as interface preformed hole; When all embedded parts (5) cross-sectional area is less than or equal to 10% of basic top surface area, the end face of first time pouring concrete end face (2) arrival reinforcement foundation framework (3), needing the position accessing embedded part (5), 0.3 meter of dark interface preformed hole is set, the edge 300mm ~ 600mm wider than required access embedded part edge of interface preformed hole;
The construction of embedded part part basis comprises the following steps,
B1, embedded part are located, the exact position of become more meticulous to embedded part (5) location, measurement and correction built-in fitting (5);
B2, embedded part access, access embedded part dowel (6), and when adopting anti-punching shear bar in steps A 2, embedded part dowel (6) adopts curved anchor pattern tension dowel, and is connected with the anti-punching shear bar spot welding described in steps A 2 by embedded part dowel (6); When adopting generic connectivity to design in steps A 2, embedded part dowel (6) adopts the common dowel of straight anchor pattern, embedded part (5) is arranged on first time pouring concrete end face (2);
B3, second time fluid concrete, on power equipment basis, embedded part installs, then goes up fluid concrete within the scope of 0.3m in first time pouring concrete end face (2).
2. power equipment basis according to claim 1 two-step construction method, it is characterized in that: the anti-punching shear bar described in steps A 2 is HPB300 reinforcing bar, diameter is 6 ~ 10cm, and setting space is 150 ~ 300mm.
3. power equipment basis according to claim 1 two-step construction method, is characterized in that: the common dowel of straight anchor pattern described in step B1 is that corner point type supports straight anchor dowel, and the anchorage length in concrete secondary LIFT is 250 ~ 290mm; Described curved anchor pattern tension dowel is 8 equidistant curved anchor dowels, and the anchorage length in concrete secondary LIFT is 40 times of bar diameters.
4. power equipment basis according to claim 1 two-step construction method, is characterized in that: the concrete that in step B3, second time fluid concrete is used is the C30 pea gravel concreten of interpolation 0.08% ~ 0.10% anti-crack fiber.
CN201510146776.9A 2015-03-31 2015-03-31 Power equipment basis two-step construction method Active CN104727339B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510146776.9A CN104727339B (en) 2015-03-31 2015-03-31 Power equipment basis two-step construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510146776.9A CN104727339B (en) 2015-03-31 2015-03-31 Power equipment basis two-step construction method

Publications (2)

Publication Number Publication Date
CN104727339A true CN104727339A (en) 2015-06-24
CN104727339B CN104727339B (en) 2016-07-06

Family

ID=53451701

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510146776.9A Active CN104727339B (en) 2015-03-31 2015-03-31 Power equipment basis two-step construction method

Country Status (1)

Country Link
CN (1) CN104727339B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759455A (en) * 2016-12-05 2017-05-31 国网青海省电力公司西宁供电公司 A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion
CN107700520A (en) * 2017-09-01 2018-02-16 南阳理工学院 A kind of anti-corrosion architectural electricity cabinet construction installation method
CN108867686A (en) * 2017-07-24 2018-11-23 武汉炼化工程设计有限责任公司 A kind of pump foundation secondary grout layer anti-drop structure and its casting process
CN111287212A (en) * 2020-02-15 2020-06-16 广州市芳村建筑工程有限公司 Two-step construction method for power equipment foundation

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5941530A (en) * 1982-08-31 1984-03-07 Toshiba Corp Installation of foundation bolt for apparatus setting
JPH08302710A (en) * 1995-04-28 1996-11-19 Tokyo Gas Co Ltd Machine base for installation equipment and constructing method thereof
JPH1060913A (en) * 1996-08-14 1998-03-03 Sumitomo Metal Ind Ltd Installation method for machine equipment
CN101881031A (en) * 2010-02-11 2010-11-10 中国二十二冶集团有限公司 Adjustable grouting material base plate device and installation method thereof
CN102134879A (en) * 2011-01-12 2011-07-27 陕西建工集团第六建筑工程有限公司 Embedding accuracy control construction method for embedded part of overlong equipment foundation platform
CN202380479U (en) * 2011-12-14 2012-08-15 河南省电力勘测设计院 Cast-in-situ connecting device for 220-kilovolt transformer station equipment bracket and blinding layer foundation
CN104179191A (en) * 2013-05-28 2014-12-03 中广核工程有限公司 Construction method of large-equipment base in nuclear power plant
CN204023605U (en) * 2014-07-10 2014-12-17 内蒙古电力勘测设计院有限责任公司 The fixed structure of ground embedded part

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5941530A (en) * 1982-08-31 1984-03-07 Toshiba Corp Installation of foundation bolt for apparatus setting
JPH08302710A (en) * 1995-04-28 1996-11-19 Tokyo Gas Co Ltd Machine base for installation equipment and constructing method thereof
JPH1060913A (en) * 1996-08-14 1998-03-03 Sumitomo Metal Ind Ltd Installation method for machine equipment
CN101881031A (en) * 2010-02-11 2010-11-10 中国二十二冶集团有限公司 Adjustable grouting material base plate device and installation method thereof
CN102134879A (en) * 2011-01-12 2011-07-27 陕西建工集团第六建筑工程有限公司 Embedding accuracy control construction method for embedded part of overlong equipment foundation platform
CN202380479U (en) * 2011-12-14 2012-08-15 河南省电力勘测设计院 Cast-in-situ connecting device for 220-kilovolt transformer station equipment bracket and blinding layer foundation
CN104179191A (en) * 2013-05-28 2014-12-03 中广核工程有限公司 Construction method of large-equipment base in nuclear power plant
CN204023605U (en) * 2014-07-10 2014-12-17 内蒙古电力勘测设计院有限责任公司 The fixed structure of ground embedded part

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106759455A (en) * 2016-12-05 2017-05-31 国网青海省电力公司西宁供电公司 A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion
CN108867686A (en) * 2017-07-24 2018-11-23 武汉炼化工程设计有限责任公司 A kind of pump foundation secondary grout layer anti-drop structure and its casting process
CN107700520A (en) * 2017-09-01 2018-02-16 南阳理工学院 A kind of anti-corrosion architectural electricity cabinet construction installation method
CN111287212A (en) * 2020-02-15 2020-06-16 广州市芳村建筑工程有限公司 Two-step construction method for power equipment foundation

Also Published As

Publication number Publication date
CN104727339B (en) 2016-07-06

Similar Documents

Publication Publication Date Title
CN209636847U (en) A kind of adjustable tower crane built-in fitting accurate positioning tool
CN104234385B (en) Construction method of installation after a kind of terrace heavy steel plate built-in fitting
CN102758451B (en) Concrete cable channel construction process
CN103643971B (en) Tunnel invert sizing end mould rapid constructing method
CN104727339B (en) Power equipment basis two-step construction method
CN101672007A (en) Constructing method of precast pier footing for bridge
CN105421222A (en) Socket and spigot joint type connection structure for bridge prefabricated pier stand column and bearing platform and splicing method of socket and spigot joint type connection structure
CN102493487B (en) Method for constructing foundation slab embedded with concrete supports
CN110424455A (en) The underground confined space is without fertile slot structure side wall big steel form plate system and construction method
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN108582465A (en) After pour canopy, precast reinforced concrete frame beam and after pour canopy manufacturing method
CN205223840U (en) Bridge prefabrication pier stand and cushion cap socket joint formula connection structure
CN104153451A (en) Construction method for installing concrete pipeline through prefabricated supporting block
CN208759772U (en) Canopy and its precast reinforced concrete frame beam are poured after one kind
CN103510537A (en) Construction method combining tower crane foundation and building basement floor
CN208884563U (en) A kind of bolted assembling type base
CN110093929A (en) A kind of underground engineering is along practice construction method and structure
CN110578329A (en) device and method for controlling tunnel deformation by using cable anchors and ground anchoring beams
CN109281408B (en) Comprehensive pipe gallery embedded part and fixing method thereof
CN206554428U (en) A kind of precast stair connecting node
CN101608456B (en) Method for controlling foundation crack of extra-high voltage combined electrical apparatus GIS equipment
CN104453937A (en) Pre-embedding device and method of tunnel vault ground terminals
CN210459229U (en) Support assembled in deep basal pit and trade and prop construction frock
CN211948447U (en) Foundation pit supporting device
CN103352568A (en) Method for building constructional column on foundation pad

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 050031 No. 6 Jianbei Street, Chang'an District, Shijiazhuang City, Hebei Province

Patentee after: China Electric Power Construction Group Hebei electric survey and Design Research Institute Co., Ltd.

Address before: 050031 No. 6 Jianbei Street, Chang'an District, Shijiazhuang City, Hebei Province

Patentee before: Hebei Province Power Surveying Design & Research Institute