CN106759455A - A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion - Google Patents
A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion Download PDFInfo
- Publication number
- CN106759455A CN106759455A CN201611103049.5A CN201611103049A CN106759455A CN 106759455 A CN106759455 A CN 106759455A CN 201611103049 A CN201611103049 A CN 201611103049A CN 106759455 A CN106759455 A CN 106759455A
- Authority
- CN
- China
- Prior art keywords
- equipment foundations
- built
- fitting
- tension rib
- equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/44—Foundations for machines, engines or ordnance
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/35—Foundations formed in frozen ground, e.g. in permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Floor Finish (AREA)
Abstract
A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion, is related to conveying electric equipment basis anti-freeze expansion field, and it is poured by Equipment Foundations → and building block fills out pure → flooring and pours three steps and complete;The beneficial effects of the present invention are:Due to aerated blocks(3)Belong to nonrigid material, with porous frangible characteristic, the rigid power of soil freezing heave will not be passed to ground, cause indoor power Equipment Foundations and ground crimp caused by frost heave amplitude is different, secondly concreting ground(7)Inside it is provided with reinforcing bar(4), reinforcing bar(4)With wall lacing wire(5)Fix this and allow for concreting ground(7)As rigid ground, transmission facility is not interfered with, reduce the number of times of large-area power-cuts, it is cost-effective, save artificial.
Description
Technical field
The present invention relates to convey electric equipment basal perimeter terrace anti-freeze expansion field, relate more specifically to a kind of indoor power and set
The method of standby basal perimeter terrace anti-freeze expansion.
Background technology
The indoor equipment basal perimeter terrace that extremely frigid zones install conveying electric equipment can generally occur frost heave in the winter time, cause transmission of electricity
Equipment device damage, it is impossible to normal conveying electricity, maintenance needs large-area power-cuts, once the production and living having a power failure the masses are influenceed,
Maintenance cost is very high, and the influence caused to society is very big.
The content of the invention
For above-mentioned technical problem the invention provides a kind of method of indoor power Equipment Foundations anti-freeze expansion, it is by equipment
Basis pours → and building block filling → flooring pours the completion of three steps;It is the position for installing equipment indoors that the Equipment Foundations are poured
Digging foundation ditch is put, foundation depth ensures to be deeper than frozen soil layer thickness or is connected with equipment room floor, the size and shape of foundation ditch is according to setting
It is standby it needs to be determined that, then use concrete placing installation basis(1), Equipment Foundations(1)It is poured into residual thickness 15cm to 20cm
And cannot be less than 6 times of built-in fitting tension rib diameter, Equipment Foundations(1)The top insertion built-in fitting drawknot of the scope of operation is poured first
Muscle(9), built-in fitting tension rib(9)Overall length is exposed and more than the face of pouring cannot be less than built-in fitting drawknot not less than the 80% of design length
Muscle(9)6 times of diameter, built-in fitting(8)The straight muscle of reinforcement welding tension rib of bottom design requirement, length is straight not less than tension rib
6 times of footpath, in Equipment Foundations(1)Built-in fitting is carried out when pouring building body initial set first(8)Levelling, contraposition, and by built-in fitting tension rib(9)
Upper and lower two parts are welded, and weld bond length is not less than built-in fitting tension rib(9)6 times of bilateral full welds of diameter, the building block is filled out
Fill is by indoor base plate(2)Fill and lead up and tamp at ground -50cm to -70cm in Equipment Foundations periphery backfill;Use aerating
Block(3)Equipment Foundations periphery is filled to terrace and is located to -10cm, it is base plate indoors that the flooring pours(2)Packed layer
On use reinforcing bar(4)With tension rib within the walls(5)Connection, reinforcing bar(4)Longitude and latitude is worked out, and spacing is with 10cm to 20cm between reinforcing bar longitude and latitude
It is advisable, reinforcing bar(4)Diameter be advisable with 8~12mm, then by steel bar layer carry out concreting to -1cm to -2cm locate, according to
Design requirement carries out ground finish coat(7)Treatment, in basic built-in fitting(8)Upper fixed power equipment(6).
The beneficial effects of the present invention are:1st, due to aerated blocks(3)Belong to nonrigid material, with porous frangible spy
Property, the rigid power of soil freezing heave will not be passed to ground, cause indoor power Equipment Foundations with ground because frost heave amplitude is different
Crimp is caused, secondly concreting ground(7)Inside it is provided with reinforcing bar(4), reinforcing bar(4)With wall lacing wire(5)Fix this just
So that concreting ground(7)As rigid ground, transmission facility is not interfered with, reduce the number of times of large-area power-cuts, saved
About cost, saves artificial.2nd, Equipment Foundations are poured at twice, and intense adjustment, very big width can be carried out to equipment basic pre-buried part
Degree improves equipment basic pre-buried part flatness control, reduces equipment basic pre-buried part out-of-flatness and causes equipment fragility connector
Long-term stress causes to damage, and further protection and power equipment reduce the number of times of large-area power-cuts, cost-effective, save people
Work.
Brief description of the drawings
Fig. 1 is schematic structural view of the invention.
Wherein:1st, Equipment Foundations, 2, backfill, 3, aerated blocks, 4, reinforcing bar, 5, tension rib within the walls, 6, power equipment, 7,
Level ground finish coat, 8, built-in fitting, 9, built-in fitting tension rib.
Specific embodiment
Embodiment 1:A kind of method of indoor power Equipment Foundations anti-freeze expansion, it is poured by Equipment Foundations → building block fill out it is pure →
Flooring pours the completion of three steps;The Equipment Foundations pour the position for being to install equipment indoors and dig foundation ditch, and foundation depth is true
Guarantor is deeper than frozen soil layer thickness or is connected with equipment room floor, the size and shape of foundation ditch according to equipment it needs to be determined that, then use
Concrete placing installation basis(1), Equipment Foundations(1)It is poured into residual thickness 15cm to 20cm and cannot be less than built-in fitting drawknot
6 times of muscle diameter, Equipment Foundations(1)The top insertion built-in fitting tension rib of the scope of operation is poured first(9), built-in fitting tension rib
(9)Overall length is exposed and more than the face of pouring cannot be less than built-in fitting tension rib not less than the 80% of design length(9)6 times of diameter, in advance
Embedded part(8)The straight muscle of reinforcement welding tension rib of bottom design requirement, length is not less than 6 times of tension rib diameter, in Equipment Foundations
(1)Built-in fitting is carried out when pouring building body initial set first(8)Levelling, contraposition, and by built-in fitting tension rib(9)Upper and lower two parts are welded
Connect, weld bond length is not less than built-in fitting tension rib(9)6 times of bilateral full welds of diameter, the building block filling is by indoor base plate(2)
Fill and lead up and tamp at ground -50cm to -70cm in Equipment Foundations periphery backfill;Use aerated blocks(3)By Equipment Foundations week
While fill to terrace locating to -10cm, it is base plate indoors that the flooring pours(2)Reinforcing bar is used on packed layer(4)With wall
Interior tension rib(5)Connection, reinforcing bar(4)Longitude and latitude is worked out, and spacing is advisable with 10cm to 20cm between reinforcing bar longitude and latitude, reinforcing bar(4)It is straight
Footpath is advisable with 8~12mm, and steel bar layer then is carried out into concreting locates to -1cm to -2cm, and ground is carried out according to design requirement
Finish coat(7)Treatment, in basic built-in fitting(8)Upper fixed power equipment(6).
The present invention is not only limited to above-mentioned specific embodiment, and persons skilled in the art are according to disclosed by the invention interior
Hold, the present invention can be implemented using other various specific embodiments, therefore, it is every to use design structure of the invention and think of
Road, does the design of some simple changes or change, both falls within the scope of protection of the invention.
Claims (1)
1. a kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion, it is characterised in that:It is poured by Equipment Foundations →
Building block filling → flooring pours the completion of three steps;The Equipment Foundations pour the position for being to install equipment indoors and dig foundation ditch,
Foundation depth ensures to be deeper than frozen soil layer thickness or is connected with equipment room floor that the size and shape of foundation ditch needs really according to equipment
It is fixed, then use concrete placing installation basis(1), Equipment Foundations(1)It is poured into residual thickness 15cm to 20cm and must not be small
In 6 times of built-in fitting tension rib diameter, Equipment Foundations(1)The top insertion built-in fitting tension rib of the scope of operation is poured first(9), in advance
Embedded part tension rib(9)Overall length is exposed and more than the face of pouring cannot be less than built-in fitting tension rib not less than the 80% of design length(9)Directly
6 times of footpath, built-in fitting(8)The straight muscle of reinforcement welding tension rib of bottom design requirement, length is not less than 6 times of tension rib diameter,
In Equipment Foundations(1)Built-in fitting is carried out when pouring building body initial set first(8)Levelling, contraposition, and by built-in fitting tension rib(9)Upper and lower two
Part is welded, and weld bond length is not less than built-in fitting tension rib(9)6 times of bilateral full welds of diameter, building block filling be by
Indoor base plate(2)Fill and lead up and tamp at ground -50cm to -70cm in Equipment Foundations periphery backfill;Use aerated blocks(3)Will
Equipment Foundations periphery is filled to terrace and is located to -10cm, and it is base plate indoors that the flooring pours(2)Steel is used on packed layer
Muscle(4)With tension rib within the walls(5)Connection, reinforcing bar(4)Longitude and latitude is worked out, and spacing is advisable with 10cm to 20cm between reinforcing bar longitude and latitude, steel
Muscle(4)Diameter be advisable with 8~12mm, then by steel bar layer carry out concreting to -1cm to -2cm locate, according to design will
Asking carries out ground finish coat(7)Treatment, in basic built-in fitting(8)Upper fixed power equipment(6).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611103049.5A CN106759455A (en) | 2016-12-05 | 2016-12-05 | A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201611103049.5A CN106759455A (en) | 2016-12-05 | 2016-12-05 | A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106759455A true CN106759455A (en) | 2017-05-31 |
Family
ID=58883778
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201611103049.5A Pending CN106759455A (en) | 2016-12-05 | 2016-12-05 | A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106759455A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3845594A (en) * | 1968-11-04 | 1974-11-05 | Hambro Structural Systems Ltd | Steel joist or composite steel and concrete construction |
CN103541740A (en) * | 2013-10-31 | 2014-01-29 | 同济大学 | Structure system for reducing tunnel lining frost heaving force in cold region |
CN104727339A (en) * | 2015-03-31 | 2015-06-24 | 河北省电力勘测设计研究院 | Electrical equipment foundation two-step type construction method |
CN105350566A (en) * | 2015-12-10 | 2016-02-24 | 国网四川省电力公司乐山供电公司 | Ground pile structure of tower type electric power support |
CN106049214A (en) * | 2016-05-31 | 2016-10-26 | 中国科学院武汉岩土力学研究所 | Bridge and culvert structure transition section anti-frost-heaving structure in cold region |
-
2016
- 2016-12-05 CN CN201611103049.5A patent/CN106759455A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3845594A (en) * | 1968-11-04 | 1974-11-05 | Hambro Structural Systems Ltd | Steel joist or composite steel and concrete construction |
CN103541740A (en) * | 2013-10-31 | 2014-01-29 | 同济大学 | Structure system for reducing tunnel lining frost heaving force in cold region |
CN104727339A (en) * | 2015-03-31 | 2015-06-24 | 河北省电力勘测设计研究院 | Electrical equipment foundation two-step type construction method |
CN105350566A (en) * | 2015-12-10 | 2016-02-24 | 国网四川省电力公司乐山供电公司 | Ground pile structure of tower type electric power support |
CN106049214A (en) * | 2016-05-31 | 2016-10-26 | 中国科学院武汉岩土力学研究所 | Bridge and culvert structure transition section anti-frost-heaving structure in cold region |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104878835B (en) | Strip footing increases basement structure behind house | |
CN108560580B (en) | Earth-retaining wall construction method | |
CA2942801C (en) | Method for installing metal piles in permafrost soil | |
CN209227580U (en) | The tower-crane foundation structure of raft foundation is placed under a kind of | |
CN105464074B (en) | A kind of artificial digging pile high polymer grouting safeguard structure and its construction method | |
CN110984171A (en) | Steel pipe pile grouting combined waist beam anchor rod supporting method | |
RU2392387C2 (en) | Device and method for reinforcement of mast base | |
CN113338361A (en) | Deviation rectifying method for settlement of overlying building caused by subway construction in soft soil stratum | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN109208545B (en) | Construction method of artificial landscape overflow dam with energy dissipation effect | |
CN104988884A (en) | Concrete faced rock-fill dam void deformation monitoring device and installation method thereof | |
CN104328790A (en) | Cast-in-situ sprayed concrete hidden bearing platform and hidden ground beam molding bed | |
CN206385548U (en) | A kind of tandem anchor slab foundation pit support system with Recyclable anchor rope | |
CN105040707A (en) | Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall | |
CN110306989B (en) | Non-open-cut assembled pipe trench excavation supporting and reinforcing method | |
CN110331735A (en) | A kind of tower crane mounting structure for coastal region soft layer | |
CN106759455A (en) | A kind of method of indoor power Equipment Foundations periphery terrace anti-freeze expansion | |
CN205975653U (en) | Independent bearing platform structure of soil child mould construction | |
CN107747317B (en) | Soft rock foundation impervious wall groove bottom sediment treatment method and soft rock foundation impervious wall groove bottom structure | |
CN113846623B (en) | House foundation settlement repairing process and equipment | |
CN108589758A (en) | A kind of foundation structure and construction method of acid-resistance infiltration | |
CN210888953U (en) | Tunnel pile and arch combined primary support system | |
CN111794251B (en) | Expansive soil slope shallow layer reinforcement and service state monitoring and early warning integrated structure system | |
CN204662373U (en) | A kind of deformation monitoring device that comes to nothing for rock | |
CN109183800B (en) | Construction process of preliminary grouting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170531 |