CN108560580B - Earth-retaining wall construction method - Google Patents

Earth-retaining wall construction method Download PDF

Info

Publication number
CN108560580B
CN108560580B CN201810087053.XA CN201810087053A CN108560580B CN 108560580 B CN108560580 B CN 108560580B CN 201810087053 A CN201810087053 A CN 201810087053A CN 108560580 B CN108560580 B CN 108560580B
Authority
CN
China
Prior art keywords
earth
retaining
concrete column
unloads
carrier beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810087053.XA
Other languages
Chinese (zh)
Other versions
CN108560580A (en
Inventor
叶香雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Sheng'an Construction Co.,Ltd.
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201810087053.XA priority Critical patent/CN108560580B/en
Publication of CN108560580A publication Critical patent/CN108560580A/en
Application granted granted Critical
Publication of CN108560580B publication Critical patent/CN108560580B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of earth-retaining wall construction methods, it is characterized in that construction procedure includes: at (1) earth excavation to base plate bottom surface absolute altitude, supporting module simultaneously pours basic board concrete;(2) breast boards is installed;(3) earth-retaining concrete column and concrete capping beam are poured;(4) it pours and unloads carrier beam concrete;(5) it unloads the laying of carrier beam top and unloads support plate;(6) hawser is installed, and is tensed with turnbuckle;(7) construction prestress anchorage cable is straight;(8) clay is filled above support plate unloading, unload and drainage layer is set in the middle part of the argillic horizon of carrier beam top.

Description

Earth-retaining wall construction method
Technical field
The present invention relates to building field, in particular to a kind of earth-retaining wall construction method.
Background technique
Traditional retaining wall uses gravity retaining wall, gravity retaining wall one side higher cost, on the other hand due to opening Digging amount is larger, and the earthwork is easy to appear unstable stance, make gravity retaining wall construction when safety coefficient reduce, ground not Gravity retaining wall is built in good area can increase the burden of ground, and foundation stability allows people to worry, and how large area be avoided to excavate It is the project that engineering staff faces with engineering cost is saved.
Summary of the invention
The purpose of the present invention is to provide a kind of earth-retaining wall construction methods to solve safe construction and to save engineering cost Problem.
The present invention is arranged at 1/3 earth-retaining concrete column height to unload carrier beam and unloads support plate, passes through hawser and retaining wall shape It is integral, active earth pressure is balanced by the native weight unloaded above support plate, reinforces soil body resistant slide by prestress anchorage cable Ability.
Earth-retaining concrete column carries on the back native face to be vertical vertical, and the gradient is arranged towards native face, is 5~10 towards native face and vertical angle Degree, earth-retaining concrete column section is down big up small, and earth-retaining concrete column advantageously reduces active earth pressure towards the native face setting gradient.Gear Earth concrete column be arranged spacing according to retaining wall height determine, here retaining wall height refer to concrete capping beam elevation of top with The distance between ground elevation, when retaining wall height is greater than or equal to 7m, it is 2.5m that spacing, which is arranged, in earth-retaining concrete column;Work as gear When cob wall height is less than 7m and is greater than or equal to 6.5m, earth-retaining concrete column setting spacing is less than or equal to 2.8m and is greater than 2.5m;When retaining wall height is less than 6.5m and is greater than or equal to 6m, earth-retaining concrete column is arranged spacing and is less than or equal to 3.2m And it is greater than 2.8m;When retaining wall height is less than 6m and is greater than or equal to 5.5m, earth-retaining concrete column setting spacing is less than or waits In 3.7m and it is greater than 3.2m;When retaining wall height is less than 5.5m and is greater than or equal to 5m, it is small that spacing is arranged in earth-retaining concrete column In 4.3m and it is greater than 3.7m;When retaining wall height is less than 5m, it is 4.3m that spacing, which is arranged, in earth-retaining concrete column.
Earth-retaining concrete column protrudes into base plate, and base plate is with a thickness of 300~350mm, base plate and earth-retaining concrete column point Two-step pouring, base plate, which stays, sets preformed hole so as to the insertion of earth-retaining concrete column, and base plate buries embedded bar in reserved hole site, Embedded bar is the reinforcing bar that 2 diameters are 25~28mm, and breast boards is arranged towards native side in earth-retaining concrete column, and breast boards is using prefabricated Plate, for breast boards with a thickness of 10~12mm, breast boards is reserved to unload carrier beam and angle steel mounting hole, is arranged in the lower part of earth-retaining concrete column Carrier beam is unloaded, unloading carrier beam setting position is 1/3 earth-retaining concrete column height, and unloading depth of beam is 400~600mm, unloads carrier beam and passes through Angle steel couples with the formation of earth-retaining concrete column, and angle steel is welded with earth-retaining concrete column main reinforcement, unloads carrier beam lower part main reinforcement and angle Steel welding unloads to be laid with above carrier beam and unloads support plate, unloads support plate using prefabricated board, and unloading plate thickness is 10~12mm, is unloaded on the right side of carrier beam Concrete capping beam is arranged so that hawser penetrates in reserved inclined hole at the top of retaining wall, concrete bear down on one depth of beam be 500~ 700mm, hawser upper end, which passes through concrete capping beam, to be reserved inclined hole and is fixed on concrete capping beam upper end with anchorage, under hawser End is fixed on anchorage and unloads carrier beam lower end across unloading carrier beam and reserve inclined hole, and setting turnbuckle adjusts hawser in the middle part of hawser Elasticity, prestress anchorage cable be arranged the gradient be 40~65 degree, here the gradient refer to prestress anchorage cable with level angle, answer in advance Power anchor cable upper end is protruded into the reserved inclined hole of concrete capping beam and is fixed with anchorage.
Construction procedure includes:
(1) at earth excavation to base plate bottom surface absolute altitude, supporting module simultaneously pours basic board concrete, and when supporting module is pre- Stay earth-retaining concrete column pouring hole and embedded embedded bar;
(2) breast boards is installed;
(3) breast boards is arranged complementary modulus plate in angle steel position of mounting hole, pours directly as the right side template of earth-retaining concrete column Build earth-retaining concrete column and concrete capping beam;
(4) it excavates the earthwork on the right side of earth-retaining concrete column and complementary modulus plate is removed, by angle steel and earth-retaining to Liang Dibubiaogaochu is unloaded Concrete column main reinforcement is welded;Then carrier beam lower part main reinforcement will be unloaded and angle steel welds;
(5) it unloads the laying of carrier beam top and unloads support plate;
(6) hawser is installed, and is tensed with turnbuckle;
(7) construction prestress anchorage cable
Anchor cable drilling uses drilled dry, to ensure hole wall adhesive property, if meeting the hole that collapses, should stop to bore immediately, carry out grouting for braced wall Processing, grouting pressure are 0.1~0.2MPa, and after cement mortar initial set, cleaning bottom of hole is crept into again.Height must be used after the completion of drilling Press air that dust in hole and water whole removing portal outer, in order to avoid reduce the adhesion strength of cement mortar and hole wall, wind pressure 0.2 ~0.4MPa;Anchor cable divides free segment and Anchoring part;Free segment steel strand wires coating butter covers PVC hose, PVC after making preservative treatment again Hose diameter is 16mm, and one of guide ring is arranged every 2m to guarantee that steel strand wires are straight in free segment steel strand wires.
Prestressd anchor cable tensioning uses two times tensioning, bankets on breast boards and carries out opening for the first time when filling half It draws, first time tensioning value is 0.22 times of anchorage cable design value of thrust, carries out second again after the completion of unloading and banketing and fill above support plate Secondary tensioning, second of tensioning value are 1.1 times of anchorage cable design value of thrust, prevent the loss of prestress in work progress.Tensioning is arrived It is locked after pre- tensioning value using anchorage.
The Anchoring part slip casting time is to carry out after anchor cable is packed into.Injecting paste material uses cement mortar, and the ratio of mud is 0.4~0.6, Cement-sand ratio is 1:1, and slurry intensity is greater than or equal to 30MPa.Slip casting will be completed once, and centre must not be interrupted, and reach to mortar strength To after 30MPa, anchorage cable stretching can be carried out.Free segment slip casting carries out after second of tensioning.
(8) clay is filled above support plate unloading, clay is 400~500mm using layering hand compaction, lift height, is unloaded Drainage layer is set in the middle part of the argillic horizon of carrier beam top, and drainage layer presss from both sides gravel using sand with a thickness of 0.3m, drainage layer material, in favor of row Water.
The present invention has the advantages that mechanical property is good, safe and reliable, with good application prospect.
Detailed description of the invention
Fig. 1 is retaining wall schematic diagram.
Attached drawing mark: 1, earth-retaining concrete column, 2, breast boards, 3, angle steel, 4, concrete capping beam, 5, hawser, 6, flower Basket screw, 7, prestress anchorage cable, 8, unload support plate, 9, unload carrier beam, 10, base plate.
Specific embodiment
The present embodiment is described in detail below in conjunction with attached drawing.
The present embodiment highly locates setting and unloads carrier beam 9 and to unload support plate 8 in 1/3 earth-retaining concrete column 1, passes through hawser 5 and gear Cob wall forms entirety, balances active earth pressure by the native weight unloaded above support plate 8, reinforces soil by prestress anchorage cable 7 Body resistant slide ability.
It is vertical vertical that earth-retaining concrete column 1, which carries on the back native face, is 8 degree towards native face and vertical angle towards the native face setting gradient, gear 1 section of earth concrete column is down big up small, and earth-retaining concrete column 1 advantageously reduces active earth pressure towards the native face setting gradient.Earth-retaining It is 4.5m that spacing, which is arranged, in concrete column 1.
Earth-retaining concrete column 1 protrudes into base plate 10, and base plate 10 is with a thickness of 320mm, base plate 10 and earth-retaining concrete column 1 It pours in two times, base plate 10, which stays, sets preformed hole so as to the insertion of earth-retaining concrete column 1, and base plate 10 is embedded pre- in reserved hole site Reinforcing bar is buried, embedded bar is the reinforcing bar that 2 diameters are 25mm, and breast boards 2 is arranged towards native side in earth-retaining concrete column 1, and breast boards 2 is adopted With prefabricated board, breast boards 2 is with a thickness of 12mm, and breast boards 2 is reserved to unload 3 mounting hole of carrier beam 9 and angle steel, in earth-retaining concrete column 1 Carrier beam 9 is unloaded in lower part setting, and unloading carrier beam 9 position is arranged is 1/3 earth-retaining concrete column, 1 height, and unloading 9 height of carrier beam is 500mm, unloading Beam 9 is coupled by angle steel 3 with the formation of earth-retaining concrete column 1, and angle steel 3 is welded with 1 main reinforcement of earth-retaining concrete column, unloads carrier beam 9 Lower part main reinforcement and angle steel 3 weld, and unload carrier beam 9 and are laid with above and unload support plate 8, unload support plate 8 using prefabricated board, unload support plate 8 with a thickness of 12mm is unloaded and is reserved inclined hole on the right side of carrier beam 9, so that hawser 5 penetrates, concrete capping beam 4, coagulation soil pressure are arranged at the top of retaining wall 4 height of top beam is 600mm, and 5 upper end of hawser reserves inclined hole across concrete capping beam 4 and is fixed on concrete capping beam with anchorage 4 upper ends, 5 lower end of hawser, which passes through to unload carrier beam 9 and reserve inclined hole and be fixed on anchorage, unloads 9 lower end of carrier beam, and flower is arranged in the middle part of hawser 5 Basket screw 6 adjusts the elasticity of hawser 5, and it is 50 degree that the gradient, which is arranged, in prestress anchorage cable 7, and 7 upper end of prestress anchorage cable is protruded into mixed Solidifying soil pressure top beam 4 is reserved inclined hole and is fixed with anchorage.
Construction procedure includes:
(1) at earth excavation to 10 bottom surface absolute altitude of base plate, supporting module simultaneously pours 10 concrete of base plate, supporting module When reserved 1 pouring hole of earth-retaining concrete column and embedded embedded bar;
(2) breast boards 2 is installed;
(3) complementary modulus is arranged in 3 position of mounting hole of angle steel directly as the right side template of earth-retaining concrete column 1 in breast boards 2 Plate pours earth-retaining concrete column 1 and concrete capping beam 4;
(4) excavate the 1 right side earthwork of earth-retaining concrete column to unloading at 9 elevation of bottom of carrier beam, remove complementary modulus plate, by angle steel 3 with 1 main reinforcement of earth-retaining concrete column is welded;Then 9 lower part main reinforcement of carrier beam will be unloaded to weld with angle steel 3;It pours and unloads 9 concrete of carrier beam;
(5) it unloads the laying of 9 top of carrier beam and unloads support plate 8;
(6) hawser 5 is installed, and is tensed with turnbuckle 6;
(7) construction prestress anchorage cable 7
Anchor cable drilling uses drilled dry, to ensure hole wall adhesive property, if meeting the hole that collapses, should stop to bore immediately, carry out grouting for braced wall Processing, grouting pressure 0.15MPa, after cement mortar initial set, cleaning bottom of hole is crept into again.High pressure must be used empty after the completion of drilling Gas dust in hole and water are all removed portal it is outer, in order to avoid reduce the adhesion strength of cement mortar and hole wall, wind pressure is 0.2~ 0.4MPa;Anchor cable divides free segment and Anchoring part;Free segment steel strand wires coating butter covers PVC hose after making preservative treatment again, and PVC is soft Pipe diameter is 16mm, and one of guide ring is arranged every 2m to guarantee that steel strand wires are straight in free segment steel strand wires.
Prestressd anchor cable tensioning uses two times tensioning, carries out opening for the first time when unloading and banketing above support plate 8 and fill half It draws, first time tensioning value is 0.22 times of anchorage cable design value of thrust, bankets on breast boards 2 and carries out second after the completion of filling again Secondary tensioning, second of tensioning value are 1.1 times of anchorage cable design value of thrust, prevent the loss of prestress in work progress.Tensioning is arrived It is locked after pre- tensioning value using anchorage.
The Anchoring part slip casting time is to carry out after anchor cable is packed into.Injecting paste material uses cement mortar, the ratio of mud 0.5, sand-lime Than for 1:1, slurry intensity is greater than or equal to 30MPa.Slip casting will be completed once, and centre must not be interrupted, and reach to mortar strength After 30MPa, anchorage cable stretching can be carried out.Free segment slip casting carries out after second of tensioning.
(8) clay is filled above support plate 8 unloading, clay is 400~500mm using layering hand compaction, lift height, is unloaded Drainage layer is set in the middle part of 9 top argillic horizon of carrier beam, drainage layer presss from both sides gravel using sand with a thickness of 0.3m, drainage layer material, in favor of Draining.

Claims (1)

1. a kind of earth-retaining wall construction method, it is characterized in that construction procedure includes:
(1) at earth excavation to base plate bottom surface absolute altitude, supporting module simultaneously pours basic board concrete, reserved gear when supporting module Earth concrete column pouring hole and embedded embedded bar;
Setting unloads carrier beam and unloads support plate at 1/3 earth-retaining concrete column height, forms entirety by hawser and retaining wall;Earth-retaining Concrete column carries on the back native face to be vertical vertical, and the gradient is arranged towards native face, is 5~10 degree towards native face and vertical angle, earth-retaining concrete Column section is down big up small;
(2) breast boards is installed;
Breast boards is arranged towards native side in earth-retaining concrete column, and breast boards uses prefabricated board, and breast boards is with a thickness of 10~12mm, breast boards Reserved to unload carrier beam and angle steel mounting hole, in the lower part of earth-retaining concrete column, carrier beam is unloaded in setting;
(3) breast boards is arranged complementary modulus plate in angle steel position of mounting hole, pours gear directly as the right side template of earth-retaining concrete column Earth concrete column and concrete capping beam;
(4) it excavates the earthwork on the right side of earth-retaining concrete column and complementary modulus plate is removed, by angle steel and earth-retaining coagulation to Liang Dibubiaogaochu is unloaded Earth pillar main reinforcement is welded;Then carrier beam lower part main reinforcement will be unloaded and angle steel welds;It pours and unloads carrier beam concrete;
Unloading carrier beam setting position is 1/3 earth-retaining concrete column height, and unloading depth of beam is 400~600mm, unloads carrier beam and passes through angle steel Couple with the formation of earth-retaining concrete column;
(5) it unloads the laying of carrier beam top and unloads support plate;
Support plate is unloaded using prefabricated board, unloading plate thickness is 10~12mm, unloads and reserves inclined hole on the right side of carrier beam, so that hawser penetrates;
(6) hawser is installed, and is tensed with turnbuckle;
Concrete capping beam is set at the top of retaining wall, and concrete bears down on one depth of beam as 500~700mm, and hawser upper end passes through mixed Solidifying soil pressure top beam reserves inclined hole and is fixed on concrete capping beam upper end with anchorage, and hawser lower end, which passes through, unloads the reserved inclined hole use of carrier beam Anchorage, which is fixed on, unloads carrier beam lower end, and turnbuckle is arranged in the middle part of hawser to adjust the elasticity of hawser;
(7) construction prestress anchorage cable
It is 40~65 degree that the gradient, which is arranged, in prestress anchorage cable, and prestress anchorage cable upper end protrudes into concrete capping beam and reserves inclined hole anchorage It is fixed;
Anchor cable divides free segment and Anchoring part;Free segment steel strand wires coating butter covers PVC hose, PVC hose after making preservative treatment again Diameter is 16mm, and one of guide ring is arranged every 2m to guarantee that steel strand wires are straight in free segment steel strand wires;
The Anchoring part slip casting time is to carry out after anchor cable is packed into;Injecting paste material uses cement mortar, and the ratio of mud is 0.4~0.6, sand-lime Than for 1:1, slurry intensity is greater than or equal to 30MPa;Slip casting will be completed once, and centre must not be interrupted, and reach to mortar strength After 30MPa, anchorage cable stretching can be carried out;Free segment slip casting carries out after second of tensioning;
(8) clay is filled above support plate unloading, clay is 400~500mm using layering hand compaction, lift height, unloads carrier beam Drainage layer is set in the middle part of the argillic horizon of top, and drainage layer presss from both sides gravel using sand with a thickness of 0.3m, drainage layer material, in favor of draining.
CN201810087053.XA 2016-04-07 2016-04-07 Earth-retaining wall construction method Active CN108560580B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810087053.XA CN108560580B (en) 2016-04-07 2016-04-07 Earth-retaining wall construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201610288377.0A CN105926667B (en) 2016-04-07 2016-04-07 A kind of retaining wall
CN201810087053.XA CN108560580B (en) 2016-04-07 2016-04-07 Earth-retaining wall construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201610288377.0A Division CN105926667B (en) 2016-04-07 2016-04-07 A kind of retaining wall

Publications (2)

Publication Number Publication Date
CN108560580A CN108560580A (en) 2018-09-21
CN108560580B true CN108560580B (en) 2019-11-05

Family

ID=56835327

Family Applications (4)

Application Number Title Priority Date Filing Date
CN201610288377.0A Active CN105926667B (en) 2016-04-07 2016-04-07 A kind of retaining wall
CN201810087053.XA Active CN108560580B (en) 2016-04-07 2016-04-07 Earth-retaining wall construction method
CN201810087082.6A Active CN108277819B (en) 2016-04-07 2016-04-07 A kind of retaining wall structure
CN201810087125.0A Active CN108277820B (en) 2016-04-07 2016-04-07 The construction method of retaining wall structure

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610288377.0A Active CN105926667B (en) 2016-04-07 2016-04-07 A kind of retaining wall

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201810087082.6A Active CN108277819B (en) 2016-04-07 2016-04-07 A kind of retaining wall structure
CN201810087125.0A Active CN108277820B (en) 2016-04-07 2016-04-07 The construction method of retaining wall structure

Country Status (1)

Country Link
CN (4) CN105926667B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592626B (en) * 2016-11-18 2019-06-18 广东省基础工程集团有限公司 A kind of construction method of the retaining wall structure for superelevation embankment
CN108678001A (en) * 2018-08-08 2018-10-19 上海勘测设计研究院有限公司 A kind of box-type retaining wall
CN108797636A (en) * 2018-09-06 2018-11-13 中铁二院北方勘察设计有限责任公司 A kind of upper font retaining wall structure and its construction method
JP6482715B1 (en) * 2018-10-18 2019-03-13 ケミカルグラウト株式会社 Support structure and support method for anti-side pressure structure
CN109457726B (en) * 2018-12-29 2024-09-17 仵社教 Retaining wall with shear plates and optimal design method thereof
CN110397050B (en) * 2019-08-05 2020-07-14 河北工业大学 Beam-anchor type light drainage retaining wall and construction method thereof
CN115075306B (en) * 2022-07-05 2024-07-23 四川省交通运输发展战略和规划科学研究院 Isolation wall structure for protecting building safety in normal fault and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2197388Y (en) * 1994-05-10 1995-05-17 彭高培 T-shape retaining wall
JP2013136922A (en) * 2011-12-28 2013-07-11 Ohbayashi Corp Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method
CN103452132A (en) * 2013-09-05 2013-12-18 江苏省交通科学研究院股份有限公司 Retaining wall
CN103572775A (en) * 2012-07-30 2014-02-12 深圳市工勘岩土工程有限公司 Semi-assembly type retaining wall of soil filling slope and construction method for semi-assembly type retaining wall

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201212151Y (en) * 2008-07-01 2009-03-25 中铁二院工程集团有限责任公司 Retaining wall foundation structure
CN202730796U (en) * 2012-06-29 2013-02-13 深圳市工勘岩土工程有限公司 Existing retaining wall rib plate type unloading reinforcing structure
CN205557560U (en) * 2016-04-07 2016-09-07 叶香雄 Retaining wall

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2197388Y (en) * 1994-05-10 1995-05-17 彭高培 T-shape retaining wall
JP2013136922A (en) * 2011-12-28 2013-07-11 Ohbayashi Corp Earth retaining wall supporting method, earth retaining wall supporting structure, and underground skeleton constructing method
CN103572775A (en) * 2012-07-30 2014-02-12 深圳市工勘岩土工程有限公司 Semi-assembly type retaining wall of soil filling slope and construction method for semi-assembly type retaining wall
CN103452132A (en) * 2013-09-05 2013-12-18 江苏省交通科学研究院股份有限公司 Retaining wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
衡重式桩板挡墙的应用与研究;刘永春等;《铁道建筑》;20101231(第10期);第73-76页 *

Also Published As

Publication number Publication date
CN108277819B (en) 2019-11-05
CN108277819A (en) 2018-07-13
CN108277820B (en) 2019-11-05
CN105926667B (en) 2018-05-15
CN105926667A (en) 2016-09-07
CN108277820A (en) 2018-07-13
CN108560580A (en) 2018-09-21

Similar Documents

Publication Publication Date Title
CN108560580B (en) Earth-retaining wall construction method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN104032758A (en) Reinforcement construction method for ultrahigh slope in abandoned pit
CN203213136U (en) Caisson and pile combined foundation of consolidated subsoil
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN211898463U (en) Reinforcing device combining micro-steel pipe pile and anchor rod
CN210104758U (en) Foundation pit supporting system of soil nail bored concrete pile anchor cable combination
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN103603369A (en) Construction method of anchor pile counterfort retaining wall
CN109183809A (en) A kind of construction method of Muddy Bottoms clay deep-foundation pit engineering composite support support replacement
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN107366303A (en) Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template
CN212052717U (en) Structure for penetrating karst cave of precast tubular pile
CN201296932Y (en) Segmentation prefabricating sunken outer wall and guide wall thereof
CN207160041U (en) Anchor rod type artificial digging pile
CN207331699U (en) Pit-in-pit reinforced concrete retaining wall composite supporting structure
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
CN109024657A (en) The construction method of Super High Core Walls Structure dell side complex conditions tower crane
CN212405161U (en) Foundation pit supporting system
CN207659988U (en) Crane beam on rock wall for underground power house present situation foundation reinforcing structure
CN109653193B (en) Reverse construction method for underground continuous wall
CN111549794A (en) Miniature supporting method and miniature pile supporting structure suitable for soft foundation treatment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 245400 building 3, Yaoshun Avenue, Haiyang Town, Xiuning County, Huangshan City, Anhui Province

Patentee after: Ye Xiangxiong

Address before: 325025, No. 26, North Sichuan Road, Tianhe street, Wenzhou economic and Technological Development Zone, Wenzhou, Zhejiang

Patentee before: Ye Xiangxiong

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230728

Address after: Room 1704, Zhongtong Building, No. 803 Daqishan Road, Chengnan Street, Tonglu County, Hangzhou City, Zhejiang Province, 310000

Patentee after: Hangzhou Sheng'an Construction Co.,Ltd.

Address before: 245400 building 3, Yaoshun Avenue, Haiyang Town, Xiuning County, Huangshan City, Anhui Province

Patentee before: Ye Xiangxiong