CN207659988U - Crane beam on rock wall for underground power house present situation foundation reinforcing structure - Google Patents

Crane beam on rock wall for underground power house present situation foundation reinforcing structure Download PDF

Info

Publication number
CN207659988U
CN207659988U CN201721547469.2U CN201721547469U CN207659988U CN 207659988 U CN207659988 U CN 207659988U CN 201721547469 U CN201721547469 U CN 201721547469U CN 207659988 U CN207659988 U CN 207659988U
Authority
CN
China
Prior art keywords
wall
rock
present situation
rail support
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721547469.2U
Other languages
Chinese (zh)
Inventor
张春生
何世海
徐建荣
陈建林
钱军
江亚丽
万祥兵
黄可
方丹
应和平
陈鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201721547469.2U priority Critical patent/CN207659988U/en
Application granted granted Critical
Publication of CN207659988U publication Critical patent/CN207659988U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model is related to a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structures.The purpose of this utility model is to provide the low crane beam on rock wall for underground power house present situation foundation reinforcing structure of a kind of construction safety, short construction period, construction investment.The technical solution of the utility model is:A kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:Reinforced concrete native attached wall wall has been poured on the basis of having excavated the Rock Crane Rail Support present situation of formation, and the Rock Crane Rail Support being supported on the basis of the reinforced concrete native attached wall wall top face and Rock Crane Rail Support present situation is poured above reinforced concrete native attached wall wall.The utility model is suitable for underground workshop Rock Crane Rail Support strengthening of foundation under unfavorable geological condition.

Description

Crane beam on rock wall for underground power house present situation foundation reinforcing structure
Technical field
The utility model is related to a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structures.Suitable for unfavorable geology item Underground workshop Rock Crane Rail Support strengthening of foundation under part.
Background technology
In underground workshop bridge machine supporting structure use Rock Crane Rail Support structural shape, it is possible to reduce underground power house across Degree, crane can put into operation ahead of time, can effectively shorten construction period, reduce construction cost, therefore find broad application.Due to The crane wheel load of underground workshop is larger, in unfavorable geologies items such as High Ground Stress Areas, soft stratum, structure surface developments Under part, the molding of Rock Crane Rail Support foundation excavation and rock-mass quality are poor, are influenced by unfavorable geological condition and execution conditions, present situation base Plinth does not often have secondary excavation and permutizer condition, with underground power house it is follow-up it is lower dig, basis will further relax breakage, lead Cause foundation bearing capacity that cannot meet the requirements.Therefore, it is necessary to be reinforced to Rock Crane Rail Support present situation basis after excavation, it is ensured that palisades The bearing capacity of crane girder gives full play to the advantage of Rock Crane Rail Support structure under the premise of ensureing construction safety.
Invention content
The technical problems to be solved in the utility model is:For above-mentioned there are problem, a kind of construction safety, construction week are provided The crane beam on rock wall for underground power house present situation foundation reinforcing structure that phase is short, construction investment is low.
Technical solution used by the utility model is:A kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, It is characterized in that:Reinforced concrete native attached wall wall, reinforced concrete have been poured on the basis of having excavated the Rock Crane Rail Support present situation of formation The palisades being supported on the basis of the reinforced concrete native attached wall wall top face and Rock Crane Rail Support present situation are poured above native attached wall wall Crane girder;
It is connected through attached wall wall top face joint bar between the Rock Crane Rail Support and reinforced concrete native attached wall wall;
The reinforced concrete native attached wall wall is fixed on Rock Crane Rail Support present situation through attached wall wall side joint bar and prestress anchorage cable Basis;
In the Rock Crane Rail Support present situation basis lid weight is carried out using the reinforced concrete native attached wall wall and Rock Crane Rail Support Grouting.
Reinforced concrete native attached wall wall top face is to the inclined inclined-plane of Rock Crane Rail Support present situation base side.
The reinforced concrete native attached wall is preset with connection reinforced concrete native attached wall wall side and Rock Crane Rail Support present situation within the walls The prestress anchorage cable on basis is oriented to steel pipe;The prestress anchorage cable is fixed on described after passing through the prestress anchorage cable to be oriented to steel pipe Rock Crane Rail Support present situation basis.
The prestress anchorage cable design load be 2000kN~2500kN, length be 25m~30m, 10 °~20 ° of the elevation angle, Array pitch is 3.6m~4m.
The reinforced concrete native attached wall wall is connected to its side and Rock Crane Rail Support present situation with being preset in Rock Crane Rail Support The consolidation grouting on basis is oriented to steel pipe, and consolidation grouting is oriented to steel pipe and is drilled with consolidation grouting on the basis of Rock Crane Rail Support present situation Hole site corresponds to.
Consolidation grouting hole aperture is 56mm, and it is 4m~6m to enter rock depth, and array pitch is 2m~2.4m;The consolidation fills The slurries being in the milk in slurry hole are configured using PO42.5R cement, the ratio of mud 1:1 or 0.5:1.
The diameter of attached wall wall side joint bar is 32mm, and length is 6m~9m, protruded length 1.4m, 10 ° of the elevation angle ~20 °, array pitch is 1m~1.2m.
Stir cement and soft soil in deep ground within the scope of the reinforced concrete native attached wall wall is corresponded on the basis of the Rock Crane Rail Support present situation Form concrete spray coating.
A kind of construction method of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:
A, Rock Crane Rail Support present situation base flexible sillar and other residues are removed, high pressure water flushing wash clean is used in combination;
B, intend the Rock Crane Rail Support present situation basis stir cement and soft soil in deep ground shape within the scope of the reinforced concrete native attached wall wall of construction At concrete spray coating;
C, Rock Crane Rail Support present situation basis carry out prestress anchorage cable drilling, reeve, the drilling of attached wall wall side joint bar, Inserted link, slip casting, consolidation grouting hole drilling;
D, the longitudinal reinforcement of reinforced concrete native attached wall wall, transverse steel and lacing wire system peace, longitudinal reinforcement and attached wall wall side Joint bar welds;Corresponding prestress anchorage cable prestressed anchor cable is oriented to steel pipe, and installation consolidation grouting in corresponding consolidation grouting hole is oriented to Steel pipe;
E, the attached wall wall of formwork pouring reinforcement concrete;
F, reinforced concrete native attached wall wall concrete strength removes side form after reaching 75% design strength;
G, tensioning fixation passes through the prestress anchorage cable of prestress anchorage cable guiding steel pipe;
H, progress upper part Rock Crane Rail Support is applied after reinforced concrete native attached wall wall concrete strength reaches 100% design strength Work;
I. steel pipe and the segmentation of consolidation grouting hole from-inner-to-outer are oriented to by consolidation grouting, divide ordered pair Rock Crane Rail Support present situation base The carry out consolidation grouting of plinth.
The reinforced concrete native attached wall wall and Rock Crane Rail Support are jumped storehouse using segmentation and are poured, and the construction joint between storehouse surface should be arranged Keyway and joint bar.
The utility model has the beneficial effects that:Reinforced concrete native attached wall wall is through prestress anchorage cable, attached wall in the utility model Wall side joint bar is fixed on the basis of Rock Crane Rail Support present situation, and reinforced concrete native attached wall wall coordinates consolidation grouting to Rock Crane Rail Support Present situation basis is reinforced, and under conditions of without secondary excavation and displacement, improves the integrality on Rock Crane Rail Support basis, Reducing subsequent relaxation damaged degree, it is ensured that the bearing capacity of Rock Crane Rail Support ensures construction safety, shortens construction period, Reduce construction investment.
Description of the drawings
Fig. 1 is the structure arrangement schematic diagram of the present embodiment.
Specific implementation mode
As shown in Figure 1, the present embodiment is a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, shape is being excavated At Rock Crane Rail Support present situation basis 5 on poured reinforced concrete native attached wall wall 1,1 top of reinforced concrete native attached wall wall has poured The Rock Crane Rail Support 4 being supported on 1 top surface of reinforced concrete native attached wall wall and Rock Crane Rail Support present situation basis 5.
In this example, Rock Crane Rail Support present situation basis 5 is the rock mass basis for having excavated formation, and ranging from Rock Crane Rail Support 4 pushes up 6m~8m below face;1 top surface of reinforced concrete native attached wall wall is to the inclined inclined-plane in basic 5 sides of Rock Crane Rail Support present situation;Palisades are hung Correspond to stir cement and soft soil in deep ground in 1 range of reinforced concrete native attached wall wall on bicycle beam present situation basis 5 and forms concrete spray coating 8.Steel It is 60cm~80cm that the attached wall wall 1 of reinforced concrete, which uses C30 concretings, thickness, is highly 4m~5m, which is equipped within the walls Longitudinal reinforcement 9, transverse steel 10 and the lacing wire 11 of several interconnections.
It is connected through attached wall wall top face joint bar 6 between the Rock Crane Rail Support 4 of the present embodiment and reinforced concrete native attached wall wall 1, it is attached Wall wall top face joint bar 6 is extended by transverse steel 10, and it is 1.0m~1.2m to be inserted into basic 5 depths of Rock Crane Rail Support present situation.
The reinforced concrete native attached wall wall 1 of the present embodiment is fixed on palisades and hangs through attached wall wall side joint bar 7 and prestress anchorage cable 2 Bicycle beam present situation basis 5.
1 side of connection reinforced concrete native attached wall wall and Rock Crane Rail Support present situation base are preset in reinforced concrete native attached wall wall 1 The prestress anchorage cable of plinth 5 is oriented to steel pipe 12, and prestress anchorage cable 2 is fixed on palisades crane after passing through prestress anchorage cable to be oriented to steel pipe 12 Beam present situation basis 5.2 design load of prestress anchorage cable be 2000kN~2500kN, length be 25m~30m, 10 °~20 ° of the elevation angle, Between array pitch be 3.6m~4m.
The diameter of attached wall wall side joint bar 7 is 32mm, and length is 6m~9m, protruded length 1.4m, and 10 ° of the elevation angle~ 20 °, array pitch is 1m~1.2m;The exposed parts of the side joint bar are linked with the welding of longitudinal reinforcement 9.
It is carried out using reinforced concrete native attached wall wall 1 and Rock Crane Rail Support 4 in the Rock Crane Rail Support present situation basis 5 of the present embodiment Lid is in the milk again.
Reinforced concrete native attached wall wall 1 is connected to its side and Rock Crane Rail Support present situation base with being preset in Rock Crane Rail Support 4 The consolidation grouting of plinth 5 is oriented to steel pipe 13, the consolidation that consolidation grouting is oriented to steel pipe 13 and is drilled on Rock Crane Rail Support present situation basis 5 3 position of grout hole corresponds to.
3 aperture of consolidation grouting hole is 56mm, and it is 4m~6m to enter rock depth, and array pitch is 2m~2.4m;In consolidation grouting hole 3 The slurries of grouting are configured using PO42.5R cement, the ratio of mud 1:1 or 0.5:1.
3 0~2m of aperture of consolidation grouting hole is outer segment, is inner segment within hole depth 2m, passes through consolidation grouting hole 3 and consolidation grouting It is oriented to steel pipe 13 to cover Rock Crane Rail Support present situation basis 5 when being in the milk again, the outer segment grouting pressure in consolidation grouting hole 3 is 0.1 ~0.3Mpa, inner segment grouting pressure are 0.3~0.5Mpa.
The construction procedure of the present embodiment is as follows:
A, it removes Rock Crane Rail Support present situation basis 5 and loosens sillar and other residues, high pressure water flushing wash clean is used in combination;
B, the 5 spray CF30 steel fibres of Rock Crane Rail Support present situation basis intended in 1 range of reinforced concrete native attached wall wall of construction are mixed Solidifying soil forms concrete spray coating 8;
C, the drilling of prestress anchorage cable 2 is carried out on Rock Crane Rail Support present situation basis 5, reeve, the brill of attached wall wall side joint bar 7 Hole, inserted link, slip casting, consolidation grouting hole 3 drill;
D, the longitudinal reinforcement 9 of reinforced concrete native attached wall wall 1, transverse steel 10 and the system peace of lacing wire 11, longitudinal reinforcement 9 and attached wall Wall side joint bar 7 welds;2 prestressed anchor cable of corresponding prestress anchorage cable is oriented to steel pipe 12, and corresponding consolidation grouting hole 3 is installed solid Knot grouting is oriented to steel pipe 13;
E, the attached wall wall of formwork pouring reinforcement concrete 1;
F, 1 concrete strength of reinforced concrete native attached wall wall removes side form after reaching 75% design strength;
G, tensioning fixation passes through the prestress anchorage cable 2 of prestress anchorage cable guiding steel pipe 12;
H, 1 concrete strength of reinforced concrete native attached wall wall carries out upper part Rock Crane Rail Support 4 after reaching 100% design strength Construction;
I. steel pipe 13 and the segmentation of 3 from-inner-to-outer of consolidation grouting hole are oriented to by consolidation grouting, divide ordered pair Rock Crane Rail Support existing The carry out consolidation grouting on shape basis 5.
Wherein, reinforced concrete native attached wall wall 1 and Rock Crane Rail Support 4 are jumped storehouse using segmentation and are poured, and the construction joint between storehouse surface is answered Keyway and joint bar are set.
Consolidation grouting hole 3 divides two sequences to construct, I sequence hole and II sequence hole arranged for interval, and in 3 work progress of consolidation grouting hole It should carry out lifting observation, Rock Crane Rail Support 4 and the accumulative deformation permissible value that lifts of reinforced concrete native attached wall wall 1 are 100 μm.

Claims (8)

1. a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:It is hung in the palisades for having excavated formation Reinforced concrete native attached wall wall (1) has been poured in bicycle beam present situation basic (5), and support has been poured above reinforced concrete native attached wall wall (1) Rock Crane Rail Support (4) on the reinforced concrete native attached wall wall (1) top surface and Rock Crane Rail Support present situation basic (5);
It is connected through attached wall wall top face joint bar (6) between the Rock Crane Rail Support (4) and reinforced concrete native attached wall wall (1);
The reinforced concrete native attached wall wall (1) is fixed on Rock Crane Rail Support through attached wall wall side joint bar (7) and prestress anchorage cable (2) Present situation basis (5);
The Rock Crane Rail Support present situation is carried out in basic (5) using the reinforced concrete native attached wall wall (1) and Rock Crane Rail Support (4) Lid is in the milk again.
2. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The steel Attached wall wall (1) top surface of reinforced concrete is to the inclined inclined-plane in basic (5) side of Rock Crane Rail Support present situation.
3. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1 or 2, it is characterised in that:Institute It states and is preset with connection reinforced concrete native attached wall wall (1) side and Rock Crane Rail Support present situation basis in reinforced concrete native attached wall wall (1) (5) prestress anchorage cable is oriented to steel pipe (12);After the prestress anchorage cable (2) passes through the prestress anchorage cable to be oriented to steel pipe (12) It is basic (5) to be fixed on the Rock Crane Rail Support present situation.
4. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 3, it is characterised in that:It is described pre- Stress anchor cable (2) design load is 2000kN~2500kN, and length is 25m~30m, and 10 °~20 ° of the elevation angle, array pitch is 3.6m ~4m.
5. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The steel It is preset in the attached wall wall (1) of reinforced concrete and Rock Crane Rail Support (4) and be connected to its side and Rock Crane Rail Support present situation basis (5) Consolidation grouting is oriented to steel pipe (13), and consolidation grouting is oriented to steel pipe (13) and is drilled with consolidating in Rock Crane Rail Support present situation basic (5) Grout hole (3) position is tied to correspond to.
6. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 5, it is characterised in that:It is described solid Knot grout hole (3) aperture is 56mm, and it is 4m~6m to enter rock depth, and array pitch is 2m~2.4m;It is filled in the consolidation grouting hole (3) The slurries of slurry are configured using PO42.5R cement.
7. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:It is described attached The diameter of wall wall side joint bar (7) is 32mm, and length is 6m~9m, protruded length 1.4m, 10 °~20 ° of the elevation angle, array pitch For 1m~1.2m.
8. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The rock Stir cement and soft soil in deep ground in reinforced concrete native attached wall wall (1) range is corresponded in wall crane girder present situation basic (5) forms coagulation Native spray-up (8).
CN201721547469.2U 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure Active CN207659988U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721547469.2U CN207659988U (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721547469.2U CN207659988U (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure

Publications (1)

Publication Number Publication Date
CN207659988U true CN207659988U (en) 2018-07-27

Family

ID=62947088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721547469.2U Active CN207659988U (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure

Country Status (1)

Country Link
CN (1) CN207659988U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107724423A (en) * 2017-11-17 2018-02-23 中国电建集团华东勘测设计研究院有限公司 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107724423A (en) * 2017-11-17 2018-02-23 中国电建集团华东勘测设计研究院有限公司 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method

Similar Documents

Publication Publication Date Title
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN205742213U (en) Foundation pit supporting construction
CN204000901U (en) The vertical high slope prestressing anchor support of a kind of massif device
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN102828518A (en) Manual hole digging support pile prestress anchor cable anchoring structure and construction method of anchoring structure
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN103572701A (en) Buckling anchor system combined rock anchor
CN103321246A (en) Underground diaphragm wall based foundation pit construction method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN203049443U (en) High level trestle structure arranged on steep bare rock of deepwater torrent unsheathed layer
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN107100164A (en) A kind of long auger guncreting pile construction method
CN109577322A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN111236949B (en) Small-angle cross tunnel construction method