CN107724423A - Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method - Google Patents

Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method Download PDF

Info

Publication number
CN107724423A
CN107724423A CN201711144840.5A CN201711144840A CN107724423A CN 107724423 A CN107724423 A CN 107724423A CN 201711144840 A CN201711144840 A CN 201711144840A CN 107724423 A CN107724423 A CN 107724423A
Authority
CN
China
Prior art keywords
wall
rock
present situation
rail support
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711144840.5A
Other languages
Chinese (zh)
Inventor
张春生
何世海
徐建荣
陈建林
钱军
江亚丽
万祥兵
黄可
方丹
应和平
陈鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201711144840.5A priority Critical patent/CN107724423A/en
Publication of CN107724423A publication Critical patent/CN107724423A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0241Retaining or protecting walls comprising retention means in the backfill the retention means being reinforced earth elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0046Production methods using prestressing techniques
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Mining & Mineral Resources (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The present invention relates to a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method.It is an object of the invention to provide the low crane beam on rock wall for underground power house present situation foundation reinforcing structure of a kind of construction safety, short construction period, construction investment and its construction method.The technical scheme is that:A kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:Reinforced concrete native attached wall wall has been poured on the basis of the Rock Crane Rail Support present situation of formation has been excavated, the Rock Crane Rail Support being supported on the basis of the reinforced concrete native attached wall wall top face and Rock Crane Rail Support present situation is poured above reinforced concrete native attached wall wall.The present invention is applied to underground workshop Rock Crane Rail Support strengthening of foundation under unfavorable geological condition.

Description

Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method
Technical field
The present invention relates to a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method.Suitable for not Underground workshop Rock Crane Rail Support strengthening of foundation under good geological conditions.
Background technology
Bridge machine supporting structure uses Rock Crane Rail Support structural shape in underground workshop, it is possible to reduce underground power house across Degree, crane can put into operation ahead of time, can effectively shorten construction period, reduce construction cost, therefore find broad application.Due to The crane wheel load of underground workshop is larger, in unfavorable geology bars such as High Ground Stress Areas, soft stratum, structure surface developments Under part, the shaping of Rock Crane Rail Support foundation excavation and rock-mass quality are poor, are influenceed by unfavorable geological condition and execution conditions, present situation base Plinth does not often possess secondary excavation and permutizer condition, and follow-up lower with underground power house is dug, and basis will further relax breakage, lead Foundation bearing capacity is caused to meet to require.Therefore, it is necessary to Rock Crane Rail Support present situation basis after excavation is reinforced, it is ensured that palisades The bearing capacity of crane girder, on the premise of construction safety is ensured, give full play to the advantage of Rock Crane Rail Support structure.
The content of the invention
The technical problem to be solved in the present invention is:Problem be present for above-mentioned, there is provided a kind of construction safety, construction period The crane beam on rock wall for underground power house present situation foundation reinforcing structure short, construction investment is low and its construction method.
The technical solution adopted in the present invention is:A kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is special Sign is:Reinforced concrete native attached wall wall, reinforced concrete native attached have been poured on the basis of the Rock Crane Rail Support present situation of formation has been excavated The palisades crane being supported on the basis of the reinforced concrete native attached wall wall top face and Rock Crane Rail Support present situation is poured above wall wall Beam;
It is connected between the Rock Crane Rail Support and reinforced concrete native attached wall wall through attached wall wall top face joint bar;
The reinforced concrete native attached wall wall is fixed on Rock Crane Rail Support present situation through attached wall wall side joint bar and prestress anchorage cable Basis;
In the Rock Crane Rail Support present situation basis lid weight is carried out using the reinforced concrete native attached wall wall and Rock Crane Rail Support Grouting.
The reinforced concrete native attached wall wall top face is to the inclined inclined-plane of Rock Crane Rail Support present situation base side.
The reinforced concrete native attached wall is preset with connection reinforced concrete native attached wall wall side and Rock Crane Rail Support present situation within the walls The prestress anchorage cable on basis is oriented to steel pipe;The prestress anchorage cable be oriented to through the prestress anchorage cable after steel pipe be fixed on it is described Rock Crane Rail Support present situation basis.
The prestress anchorage cable design load is 2000kN~2500kN, and length is 25m~30m, 10 °~20 ° of the elevation angle, Array pitch is 3.6m~4m.
The reinforced concrete native attached wall wall connects its side and Rock Crane Rail Support present situation with being preset with Rock Crane Rail Support The consolidation grouting on basis is oriented to steel pipe, and consolidation grouting is oriented to steel pipe and the consolidation grouting being drilled with the basis of Rock Crane Rail Support present situation Hole site is corresponding.
Consolidation grouting hole aperture is 56mm, and it is 4m~6m to enter rock depth, and an array pitch is 2m~2.4m;The consolidation fills The slurries being in the milk in slurry hole are configured using PO42.5R cement, the ratio of mud 1:1 or 0.5:1.
The diameter of the attached wall wall side joint bar is 32mm, and length is 6m~9m, protruded length 1.4m, 10 ° of the elevation angle ~20 °, an array pitch is 1m~1.2m.
Stir cement and soft soil in deep ground in the range of the reinforced concrete native attached wall wall is corresponded on the basis of the Rock Crane Rail Support present situation Form concrete spray coating.
A kind of construction method of crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:
A, Rock Crane Rail Support present situation base flexible sillar and other residues are removed, and with high pressure water flushing wash clean;
B, the Rock Crane Rail Support present situation basis stir cement and soft soil in deep ground shape in the range of the reinforced concrete native attached wall wall of construction is intended Into concrete spray coating;
C, carry out the drilling of prestress anchorage cable on Rock Crane Rail Support present situation basis, reeve, the drilling of attached wall wall side joint bar, Inserted link, slip casting, consolidation grouting hole drilling;
D, the longitudinal reinforcement of reinforced concrete native attached wall wall, transverse steel and lacing wire system peace, longitudinal reinforcement and attached wall wall side Joint bar welds;Corresponding prestress anchorage cable prestressed anchor cable is oriented to steel pipe, and corresponding consolidation grouting hole installation consolidation grouting is oriented to Steel pipe;
E, the attached wall wall of formwork pouring reinforcement concrete;
F, reinforced concrete native attached wall wall concrete strength removes side form after reaching 75% design strength;
G, tensioning fixation is oriented to the prestress anchorage cable of steel pipe through prestress anchorage cable;
H, reinforced concrete native attached wall wall concrete strength, which reaches, carries out portion's Rock Crane Rail Support thereon after 100% design strength and applies Work;
I. steel pipe and the segmentation of consolidation grouting hole from-inner-to-outer are oriented to by consolidation grouting, divide ordered pair Rock Crane Rail Support present situation base The carry out consolidation grouting of plinth.
The reinforced concrete native attached wall wall and Rock Crane Rail Support are jumped storehouse using segmentation and poured, and the construction joint between the face of storehouse should be set Keyway and joint bar.
The beneficial effects of the invention are as follows:Reinforced concrete native attached wall wall is inserted through prestress anchorage cable, attached wall wall side in the present invention Muscle is fixed on the basis of Rock Crane Rail Support present situation, and reinforced concrete native attached wall wall coordinates consolidation grouting to Rock Crane Rail Support present situation basis Reinforced, under conditions of without secondary excavation and displacement, the integrality on Rock Crane Rail Support basis is improved, after reducing Continuous relaxation damaged degree, it is ensured that the bearing capacity of Rock Crane Rail Support, ensure construction safety, shorten construction period, reduce engineering Investment.
Brief description of the drawings
Fig. 1 is the structure arrangement schematic diagram of the present embodiment.
Embodiment
As shown in figure 1, the present embodiment is a kind of crane beam on rock wall for underground power house present situation foundation reinforcing structure, shape is being excavated Into Rock Crane Rail Support present situation basis 5 on poured reinforced concrete native attached wall wall 1, the top of reinforced concrete native attached wall wall 1 has poured The Rock Crane Rail Support 4 being supported on the top surface of reinforced concrete native attached wall wall 1 and Rock Crane Rail Support present situation basis 5.
In this example, Rock Crane Rail Support present situation basis 5 is the rock mass basis for having excavated formation, and scope is that Rock Crane Rail Support 4 pushes up 6m~8m below face;The top surface of reinforced concrete native attached wall wall 1 is to the inclined inclined-plane in basic 5 sides of Rock Crane Rail Support present situation;Palisades are hung Correspond to stir cement and soft soil in deep ground in the range of reinforced concrete native attached wall wall 1 on bicycle beam present situation basis 5 and form concrete spray coating 8.Steel The attached wall wall 1 of reinforced concrete uses C30 concretings, and thickness is 60cm~80cm, is highly 4m~5m, the attached wall is provided with the walls Longitudinal reinforcement 9, transverse steel 10 and the lacing wire 11 of some interconnections.
It is connected between the Rock Crane Rail Support 4 of the present embodiment and reinforced concrete native attached wall wall 1 through attached wall wall top face joint bar 6, it is attached Wall wall top face joint bar 6 is extended by transverse steel 10 to be formed, and basic 5 depths of insertion Rock Crane Rail Support present situation are 1.0m~1.2m.
The reinforced concrete native attached wall wall 1 of the present embodiment is fixed on palisades and hung through attached wall wall side joint bar 7 and prestress anchorage cable 2 Bicycle beam present situation basis 5.
The side of connection reinforced concrete native attached wall wall 1 and Rock Crane Rail Support present situation base are preset with reinforced concrete native attached wall wall 1 The prestress anchorage cable of plinth 5 is oriented to steel pipe 12, and prestress anchorage cable 2 is fixed on palisades crane after being oriented to steel pipe 12 through prestress anchorage cable Beam present situation basis 5.The design load of prestress anchorage cable 2 is 2000kN~2500kN, and length is 25m~30m, 10 °~20 ° of the elevation angle, Between array pitch be 3.6m~4m.
The diameter of attached wall wall side joint bar 7 is 32mm, and length is 6m~9m, protruded length 1.4m, and 10 ° of the elevation angle~ 20 °, an array pitch is 1m~1.2m;The exposed parts of the side joint bar link with the welding of longitudinal reinforcement 9.
Carried out in the Rock Crane Rail Support present situation basis 5 of the present embodiment using reinforced concrete native attached wall wall 1 and Rock Crane Rail Support 4 Lid is in the milk again.
Reinforced concrete native attached wall wall 1 connects its side and Rock Crane Rail Support present situation base with being preset with Rock Crane Rail Support 4 The consolidation grouting of plinth 5 is oriented to steel pipe 13, and consolidation grouting is oriented to steel pipe 13 and the consolidation being drilled with Rock Crane Rail Support present situation basis 5 The position correspondence of grout hole 3.
The aperture of consolidation grouting hole 3 is 56mm, and it is 4m~6m to enter rock depth, and an array pitch is 2m~2.4m;In consolidation grouting hole 3 The slurries of grouting are configured using PO42.5R cement, the ratio of mud 1:1 or 0.5:1.
0~the 2m of aperture of consolidation grouting hole 3 is outer section, is inner segment within hole depth 2m, passes through consolidation grouting hole 3 and consolidation grouting It is oriented to steel pipe 13 to cover Rock Crane Rail Support present situation basis 5 when being in the milk again, the outer section grouting pressure in consolidation grouting hole 3 is 0.1 ~0.3Mpa, inner segment grouting pressure are 0.3~0.5Mpa.
The construction procedure of the present embodiment is as follows:
A, remove Rock Crane Rail Support present situation basis 5 and loosen sillar and other residues, and with high pressure water flushing wash clean;
B, intend the spray CF30 steel fibres of Rock Crane Rail Support present situation basis 5 in the range of the reinforced concrete native attached wall wall 1 of construction to mix Solidifying soil forms concrete spray coating 8;
C, carry out the drilling of prestress anchorage cable 2 on Rock Crane Rail Support present situation basis 5, reeve, the brill of attached wall wall side joint bar 7 Hole, inserted link, slip casting, consolidation grouting hole 3 drill;
D, the longitudinal reinforcement 9 of reinforced concrete native attached wall wall 1, transverse steel 10 and the system peace of lacing wire 11, longitudinal reinforcement 9 and attached wall Wall side joint bar 7 welds;The corresponding prestressed anchor cable of prestress anchorage cable 2 is oriented to steel pipe 12, and corresponding consolidation grouting hole 3 is installed solid Knot grouting is oriented to steel pipe 13;
E, the attached wall wall 1 of formwork pouring reinforcement concrete;
F, the concrete strength of reinforced concrete native attached wall wall 1 removes side form after reaching 75% design strength;
G, tensioning fixation is oriented to the prestress anchorage cable 2 of steel pipe 12 through prestress anchorage cable;
H, the concrete strength of reinforced concrete native attached wall wall 1 carries out portion's Rock Crane Rail Support 4 thereon after reaching 100% design strength Construction;
I. steel pipe 13 and the segmentation of the from-inner-to-outer of consolidation grouting hole 3 are oriented to by consolidation grouting, divide ordered pair Rock Crane Rail Support to show The carry out consolidation grouting on shape basis 5.
Wherein, reinforced concrete native attached wall wall 1 and Rock Crane Rail Support 4 are jumped storehouse using segmentation and poured, and the construction joint between the face of storehouse should Keyway and joint bar are set.
Consolidation grouting hole 3 divides two sequences to construct, I sequence hole and II sequence hole arranged for interval, and in the work progress of consolidation grouting hole 3 It should carry out lifting observation, Rock Crane Rail Support 4 and the accumulative deformation permissible value that lifts of reinforced concrete native attached wall wall 1 are 100 μm.

Claims (10)

  1. A kind of 1. crane beam on rock wall for underground power house present situation foundation reinforcing structure, it is characterised in that:Hung in the palisades for having excavated formation Reinforced concrete native attached wall wall (1) has been poured on bicycle beam present situation basis (5), support has been poured above reinforced concrete native attached wall wall (1) Rock Crane Rail Support (4) on reinforced concrete native attached wall wall (1) top surface and Rock Crane Rail Support present situation basic (5);
    It is connected between the Rock Crane Rail Support (4) and reinforced concrete native attached wall wall (1) through attached wall wall top face joint bar (6);
    The reinforced concrete native attached wall wall (1) is fixed on Rock Crane Rail Support through attached wall wall side joint bar (7) and prestress anchorage cable (2) Present situation basis (5);
    The Rock Crane Rail Support present situation is carried out in basic (5) using the reinforced concrete native attached wall wall (1) and Rock Crane Rail Support (4) Lid is in the milk again.
  2. 2. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The steel Attached wall wall (1) top surface of reinforced concrete is to the inclined inclined-plane in basic (5) side of Rock Crane Rail Support present situation.
  3. 3. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1 or 2, it is characterised in that:Institute State and connection reinforced concrete native attached wall wall (1) side and Rock Crane Rail Support present situation basis are preset with reinforced concrete native attached wall wall (1) (5) prestress anchorage cable is oriented to steel pipe (12);After the prestress anchorage cable (2) is oriented to steel pipe (12) through the prestress anchorage cable It is basic (5) to be fixed on the Rock Crane Rail Support present situation.
  4. 4. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 3, it is characterised in that:It is described pre- Stress anchor cable (2) design load is 2000kN~2500kN, and length is 25m~30m, and 10 °~20 ° of the elevation angle, an array pitch is 3.6m ~4m.
  5. 5. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The steel It is preset with the attached wall wall (1) of reinforced concrete and Rock Crane Rail Support (4) and connect its side and Rock Crane Rail Support present situation basis (5) Consolidation grouting is oriented to steel pipe (13), and consolidation grouting is oriented to steel pipe (13) with being drilled with consolidating in Rock Crane Rail Support present situation basic (5) Tie grout hole (3) position correspondence.
  6. 6. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 5, it is characterised in that:It is described solid It is 56mm to tie grout hole (3) aperture, and it is 4m~6m to enter rock depth, and an array pitch is 2m~2.4m;Filled in the consolidation grouting hole (3) The slurries of slurry are configured using PO42.5R cement, the ratio of mud 1:1 or 0.5:1.
  7. 7. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:It is described attached The diameter of wall wall side joint bar (7) is 32mm, and length is 6m~9m, protruded length 1.4m, 10 °~20 ° of the elevation angle, an array pitch For 1m~1.2m.
  8. 8. crane beam on rock wall for underground power house present situation foundation reinforcing structure according to claim 1, it is characterised in that:The rock Stir cement and soft soil in deep ground in the range of the reinforced concrete native attached wall wall (1) is corresponded on wall crane girder present situation basis (5) and forms coagulation Native spray-up (8).
  9. A kind of 9. construction party of crane beam on rock wall for underground power house present situation foundation reinforcing structure described in claim 1~8 any one Method, it is characterised in that:
    A, remove Rock Crane Rail Support present situation basic (5) and loosen sillar and other residues, and with high pressure water flushing wash clean;
    B, basic (5) stir cement and soft soil in deep ground of Rock Crane Rail Support present situation in the range of the reinforced concrete native attached wall wall (1) of construction is intended Form concrete spray coating (8);
    C, the drilling of prestress anchorage cable (2) is carried out on Rock Crane Rail Support present situation basis (5), is reeved, attached wall wall side joint bar (7) Drilling, inserted link, slip casting, consolidation grouting hole (3) drilling;
    D, the longitudinal reinforcement (9) of reinforced concrete native attached wall wall (1), transverse steel (10) and lacing wire (11) system peace, longitudinal reinforcement (9) Welded with attached wall wall side joint bar (7);Corresponding prestress anchorage cable (2) prestressed anchor cable is oriented to steel pipe (12), corresponding consolidation Grout hole (3) installation consolidation grouting is oriented to steel pipe (13);
    E, the attached wall wall (1) of formwork pouring reinforcement concrete;
    F, reinforced concrete native attached wall wall (1) concrete strength removes side form after reaching 75% design strength;
    G, tensioning fixation is oriented to the prestress anchorage cable (2) of steel pipe (12) through prestress anchorage cable;
    H, reinforced concrete native attached wall wall (1) concrete strength carries out portion's Rock Crane Rail Support (4) thereon after reaching 100% design strength Construction;
    I. the segmentation of steel pipe (13) and consolidation grouting hole (3) from-inner-to-outer is oriented to by consolidation grouting, divides ordered pair Rock Crane Rail Support to show The carry out consolidation grouting on shape basis (5).
  10. 10. construction method according to claim 9, it is characterised in that:The reinforced concrete native attached wall wall (1) and palisades are hung Bicycle beam (4) is jumped storehouse using segmentation and poured, and the construction joint between the face of storehouse should set keyway and joint bar.
CN201711144840.5A 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method Pending CN107724423A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711144840.5A CN107724423A (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711144840.5A CN107724423A (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method

Publications (1)

Publication Number Publication Date
CN107724423A true CN107724423A (en) 2018-02-23

Family

ID=61216356

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711144840.5A Pending CN107724423A (en) 2017-11-17 2017-11-17 Crane beam on rock wall for underground power house present situation foundation reinforcing structure and its construction method

Country Status (1)

Country Link
CN (1) CN107724423A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424880A (en) * 2020-04-30 2020-07-17 中国葛洲坝集团第三工程有限公司 Novel bearing platform structure for crane beam of bridge crane of underground factory building and construction method of bearing platform structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089023A (en) * 2015-04-14 2015-11-25 中国电建集团贵阳勘测设计研究院有限公司 Improving method for concrete floor of hydropower house and structure of concrete floor
CN205062775U (en) * 2015-10-10 2016-03-02 中国电建集团贵阳勘测设计研究院有限公司 Into factory's traffic hole structure is crossed to power station underground factory building rock -wall crane girder
CN106567405A (en) * 2015-10-10 2017-04-19 中国电建集团贵阳勘测设计研究院有限公司 Underground powerhouse palisade crane beam overbreak reinforcement structure and construction method thereof
CN207659988U (en) * 2017-11-17 2018-07-27 中国电建集团华东勘测设计研究院有限公司 Crane beam on rock wall for underground power house present situation foundation reinforcing structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089023A (en) * 2015-04-14 2015-11-25 中国电建集团贵阳勘测设计研究院有限公司 Improving method for concrete floor of hydropower house and structure of concrete floor
CN205062775U (en) * 2015-10-10 2016-03-02 中国电建集团贵阳勘测设计研究院有限公司 Into factory's traffic hole structure is crossed to power station underground factory building rock -wall crane girder
CN106567405A (en) * 2015-10-10 2017-04-19 中国电建集团贵阳勘测设计研究院有限公司 Underground powerhouse palisade crane beam overbreak reinforcement structure and construction method thereof
CN207659988U (en) * 2017-11-17 2018-07-27 中国电建集团华东勘测设计研究院有限公司 Crane beam on rock wall for underground power house present situation foundation reinforcing structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111424880A (en) * 2020-04-30 2020-07-17 中国葛洲坝集团第三工程有限公司 Novel bearing platform structure for crane beam of bridge crane of underground factory building and construction method of bearing platform structure

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN101614125B (en) Construction method of V-level surrounding rock tunnel
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN106498950B (en) Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN102828518A (en) Manual hole digging support pile prestress anchor cable anchoring structure and construction method of anchoring structure
CN105442605B (en) Extract PHC and be reused in deep foundation pit supporting construction method
CN108035754A (en) A kind of roadway bolt anchor cable combination supporting method
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN103321246A (en) Underground diaphragm wall based foundation pit construction method
CN103572701A (en) Buckling anchor system combined rock anchor
CN106065628B (en) Based on the major diameter running water pipe security protection construction method faced forever with reference to theory
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN201172830Y (en) Anchor rod static-pressing pile foundation in tower crane
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN108316328A (en) A kind of pressurization sinking device and its construction method for open caisson construction
CN109056710B (en) Hard stratum steel pipe pile and construction method thereof
CN108797323B (en) Steel trestle suitable for hard stratum
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
CN111236949B (en) Small-angle cross tunnel construction method
CN201296932Y (en) Segmentation prefabricating sunken outer wall and guide wall thereof
CN207659988U (en) Crane beam on rock wall for underground power house present situation foundation reinforcing structure
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180223