CN106498950A - Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body - Google Patents

Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body Download PDF

Info

Publication number
CN106498950A
CN106498950A CN201611194154.4A CN201611194154A CN106498950A CN 106498950 A CN106498950 A CN 106498950A CN 201611194154 A CN201611194154 A CN 201611194154A CN 106498950 A CN106498950 A CN 106498950A
Authority
CN
China
Prior art keywords
pile
anchor
lagging
pvc pipe
reinforcement cage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201611194154.4A
Other languages
Chinese (zh)
Other versions
CN106498950B (en
Inventor
王海涛
何永
闫帅
涂兵雄
贾金青
金慧
吴锋
张小浩
吴跃东
申佳玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Jiaotong University
Original Assignee
Dalian Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Jiaotong University filed Critical Dalian Jiaotong University
Priority to CN201611194154.4A priority Critical patent/CN106498950B/en
Publication of CN106498950A publication Critical patent/CN106498950A/en
Application granted granted Critical
Publication of CN106498950B publication Critical patent/CN106498950B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种锚头置于桩身的深基坑桩锚支护体系及其实施方法,所述的支护体系包括护壁桩、锚杆、马鞍形垫块、锚具、PVC管、斜铁和锁口梁;所述的护壁桩内预置PVC管,锚杆的内端穿过PVC管插入到基坑坑壁内、锚杆的外端与锚具固定连接,所述的锚具轴线与水平面具有15°~25°的夹角,并与锚杆倾角保持一致。本发明取消了传统桩锚体系中的腰梁,避免了因腰梁变形引起的预应力损失。本发明将锚杆的力直接传递到护壁桩上,锚杆和护壁桩可以更好的整体协同受力,支护结构的整体性更好,安全可靠。本发明取消了大量的连接缀板、焊条,大大节省了型钢钢材和用电量。本发明避免了繁重而且危险的腰梁安装工作,简化了工序,缩短了工期。

The invention discloses a deep foundation pit pile-anchor support system with an anchor head placed on the pile body and an implementation method thereof. The support system includes a retaining pile, an anchor rod, a saddle-shaped pad, an anchor, a PVC pipe, Inclined iron and locking beam; the PVC pipe is preset in the retaining pile, the inner end of the anchor rod is inserted into the wall of the foundation pit through the PVC pipe, and the outer end of the anchor rod is fixedly connected with the anchorage. The tool axis has an included angle of 15° to 25° with the horizontal plane, and is consistent with the inclination angle of the anchor rod. The invention cancels the waist beam in the traditional pile-anchor system and avoids the loss of prestress caused by the deformation of the waist beam. The invention directly transmits the force of the anchor rod to the wall-protecting pile, and the anchor rod and the wall-protecting pile can better cooperate with force as a whole, and the integrity of the supporting structure is better, and it is safe and reliable. The invention cancels a large number of connecting panels and welding rods, which greatly saves profiled steel materials and electricity consumption. The invention avoids the heavy and dangerous waist beam installation work, simplifies the process and shortens the construction period.

Description

锚头置于桩身的深基坑桩锚支护体系及其实施方法Deep foundation pit pile anchor support system with anchor head placed on pile body and its implementation method

技术领域technical field

本发明属于岩土工程领域,涉及到采用桩锚支护体系施工的深基坑工程,特别涉及到锚头置于桩身的深基坑桩锚支护体系及其实施方法。The invention belongs to the field of geotechnical engineering, and relates to a deep foundation pit engineering constructed with a pile-anchor support system, in particular to a deep foundation pit pile-anchor support system with an anchor head placed on a pile body and an implementation method thereof.

背景技术Background technique

目前在采用桩锚支护体系施工的深基坑工程中,护壁桩和锚杆(索)之间的连接一般采用由工字钢或槽钢做成的腰梁,将锚杆(索)锚固于腰梁之上,通过一定的构造措施与护壁桩连接,来保证整个桩锚支护体系的整体协同受力。因此,腰梁作为锚杆(索)预加力的传力结构,在整个支护体系中发挥着重要的作用。腰梁一般由型钢焊接而成,由于腰梁长度一般很长使得其长细比很大,腰梁变形难以控制,尤其当锚杆(索)施加预应力时腰梁的变形会更大,腰梁的变形直接造成预应力的损失使其难以达到设计值,这使得支护体系的安全系数难以得到保证;腰梁焊接处施工操作条件差,焊缝质量难以保证,易形成薄弱部位,常常发生腰梁整体失稳或脱落,而使支护体系失去作用,导致深基坑失稳坍塌。另外,该方法不仅存在钢材的用量多,而且需有腰梁的定位、安装等多道施工工序,施工困难而且麻烦。因此有待开发一种能解决现有桩锚支护体系中存在的安全性差、造价高、工序多、工期长等缺点的支护体系。At present, in deep foundation pit projects using pile-anchor support system construction, the connection between wall retaining piles and anchor rods (cables) generally adopts waist beams made of I-beam or channel steel to anchor the anchor rods (cables) On the waist beam, it is connected with the retaining wall pile through certain structural measures to ensure the overall coordinated force of the entire pile-anchor support system. Therefore, the waist beam plays an important role in the entire support system as a force-transmitting structure for the pre-stressing of anchor rods (cables). Waist beams are generally welded by section steel. Since the length of the waist beams is generally very long, the slenderness ratio is very large, and the deformation of the waist beams is difficult to control. Especially when the prestress is applied to the anchor rods (cables), the deformation of the waist beams will be greater. The deformation of the beam directly causes the loss of the prestress, making it difficult to reach the design value, which makes it difficult to guarantee the safety factor of the support system; the construction and operation conditions of the waist beam welding are poor, the quality of the weld is difficult to guarantee, and weak parts are easily formed, which often occurs The overall instability or fall of the waist beam makes the support system lose its function, resulting in the instability and collapse of the deep foundation pit. In addition, this method not only requires a large amount of steel materials, but also requires multiple construction procedures such as the positioning and installation of the waist beam, making the construction difficult and cumbersome. Therefore need to develop a kind of supporting system that can solve the shortcomings such as poor safety, high cost, many procedures and long construction period that exist in the existing pile-anchor supporting system.

发明内容Contents of the invention

本发明要解决的技术问题:提供锚头置于桩身的深基坑桩锚支护体系及其实施方法,以解决在桩锚支护体系中存在的因腰梁变形而引起的预应力损失问题,以及安全性差、造价高、工序多、工期长等缺点,达到提高桩锚支护体系整体安全性,降低造价,并简化施工工序和缩短工期的目的。The technical problem to be solved by the present invention is to provide a deep foundation pit pile-anchor support system and its implementation method in which the anchor head is placed on the pile body, so as to solve the prestress loss caused by the deformation of the waist beam existing in the pile-anchor support system Problems, as well as shortcomings such as poor safety, high cost, many processes, and long construction period, achieve the purpose of improving the overall safety of the pile-anchor support system, reducing cost, simplifying the construction process and shortening the construction period.

本发明的技术方案为:锚头置于桩身的深基坑桩锚支护体系,至少包括护壁桩、锚杆、马鞍形垫块、锚具、PVC管、斜铁和锁口梁;The technical solution of the present invention is: a deep foundation pit pile-anchor support system in which the anchor head is placed on the pile body, at least including retaining piles, anchor rods, saddle-shaped pads, anchors, PVC pipes, inclined irons and locking beams;

所述的护壁桩内预置PVC管,锚杆的内端穿过PVC管插入到基坑坑壁内、锚杆的外端与锚具固定连接,在锚具与护壁桩之间设置斜铁和马鞍形垫块;所述的基坑坑壁喷射混凝土面层,两个相邻的护壁桩之间的基坑坑壁内设置土钉和排水孔;两个相邻的护壁桩之间的基坑坑壁上设置钢筋网;所述的锚具轴线与水平面具有15°~25°的夹角,并与锚杆倾角保持一致。The PVC pipe is preset in the wall retaining pile, the inner end of the anchor rod is inserted into the wall of the foundation pit through the PVC pipe, the outer end of the anchor rod is fixedly connected with the anchorage, and an inclined iron is arranged between the anchorage and the retaining wall pile. and saddle-shaped pads; the sprayed concrete surface layer of the foundation pit wall, and soil nails and drainage holes are set in the foundation pit wall between two adjacent retaining piles; between two adjacent retaining piles The reinforcement mesh is arranged on the wall of the foundation pit; the axis of the anchorage has an included angle of 15°-25° with the horizontal plane, and is consistent with the inclination angle of the anchor rod.

进一步地,所述的锚杆轴线与护壁桩中心线在一个垂直面内。Further, the axis of the anchor rod is in a vertical plane with the center line of the retaining pile.

进一步地,所述的锚杆用锚索代替。Further, the anchor rod is replaced by an anchor cable.

进一步地,所述的两个相邻的护壁桩之间的基坑坑壁内的土钉竖向间距为1.4-1.6m,排水孔横向间距和竖向间距为1.4-1.6m。Further, the vertical spacing of the soil nails in the wall of the foundation pit between two adjacent retaining piles is 1.4-1.6m, and the horizontal spacing and vertical spacing of the drainage holes are 1.4-1.6m.

进一步地,所述的PVC管内径与锚孔孔径保持一致。Further, the inner diameter of the PVC pipe is consistent with the diameter of the anchor hole.

进一步地,所述的护壁桩顶部设置锁口梁。Further, a locking beam is arranged on the top of the retaining pile.

进一步地,所述的锚杆有多个,分别沿护壁桩垂直方向的多个预置PVC管插入到基坑坑壁内。Further, there are multiple anchor rods, and multiple preset PVC pipes along the vertical direction of the retaining pile are respectively inserted into the wall of the foundation pit.

锚头置于桩身的深基坑桩锚支护体系的实施方法,包括以下步骤:The implementation method of the deep foundation pit pile-anchor support system with the anchor head placed on the pile body comprises the following steps:

A、制作护壁桩钢筋笼A. Making reinforcement cages for retaining piles

制作护壁桩钢筋笼时,钢筋笼内在锚杆设计深度处预置两端以木塞封口的PVC管,PVC管通过铁丝与钢筋笼可靠连接,保证PVC管与锚杆设计角度保持一致;钢筋笼预置PVC管处应做箍筋加密处理,护壁桩配筋具有方向性,钢筋笼安放时应严格按图纸标注的方向施工。When making reinforcement cages for wall retaining piles, PVC pipes sealed at both ends with wooden plugs are preset in the reinforcement cages at the design depth of the anchor rods. The PVC pipes are reliably connected to the reinforcement cages through iron wires to ensure that the design angles of the PVC pipes and the anchor rods are consistent; The pre-installed PVC pipes should be treated with stirrup encryption, and the reinforcement of the wall protection piles has directionality. When placing the reinforcement cage, it should be constructed strictly according to the direction marked on the drawing.

B、预制马鞍形垫块B. Prefabricated saddle block

马鞍形垫块通过预制获得,其材料采用钢材或混凝土,预制时保证其马鞍处弧度与所采用的护壁桩圆弧曲率保持一致以保证两者可完美契合。当地质条件较差,锚杆需要施加较大预应力时,混凝土材质马鞍形垫块在预制时应选用高标号水泥并配钢筋。The saddle-shaped pad is obtained through prefabrication, and its material is steel or concrete. During prefabrication, the curvature of the saddle is guaranteed to be consistent with the curvature of the arc of the retaining pile used to ensure a perfect fit between the two. When the geological conditions are poor and a large prestress is required for the anchor bolt, the saddle block made of concrete should be prefabricated with high-grade cement and steel bars.

C、清理场地C. to clean up

清理场地,挖除表面松动土层,对护壁桩桩孔进行测量定位、放样。Clean up the site, excavate the loose soil layer on the surface, measure, position and set out the pile holes of the retaining piles.

D、挖桩孔D. Digging pile holes

按照步骤C定好的护壁桩孔位进行挖孔至设计深度。Excavate the holes to the design depth according to the hole position of the retaining pile determined in step C.

E、吊装钢筋笼E. Hoisting reinforcement cage

吊装钢筋笼,护壁桩配筋具有方向性,钢筋笼安放时应严格按图纸标注的方向施工。When hoisting the reinforcement cage, the reinforcement of the retaining wall pile has directionality, and the reinforcement cage should be placed in strict accordance with the direction marked on the drawing.

F、浇筑护壁桩混凝土F. Pouring concrete for wall retaining piles

向安装好钢筋笼的桩孔内浇筑混凝土,并及时养护。Pour concrete into the pile holes where the reinforcement cages have been installed, and maintain them in time.

G、施做锁口梁G. Make lock beam

具备锁口梁施工条件后,进行护壁桩桩间土挖除及护壁桩桩头截除工作,及时提供锁口梁施工工作面,绑扎、安放钢筋笼,支模,浇筑混凝土,并及时养护。After the construction conditions of the lock beam are met, the soil between the retaining piles and the head of the retaining pile are excavated, and the construction work surface of the lock beam is provided in time, the binding, the placement of the steel cage, the formwork, the pouring of concrete, and timely maintenance.

H、安装锚杆H. Install the anchor rod

具备基坑开挖施工条件后,沿护壁桩开挖基坑至锚杆设计深度下方一定深度,找到预置PVC管打通木塞并钻取锚孔;锚孔内安设锚杆并注浆,养护;待水泥砂浆达到设计强度后安装马鞍形垫块及斜铁对锚杆进行张拉锁定。After the foundation pit excavation construction conditions are met, excavate the foundation pit along the retaining piles to a certain depth below the design depth of the anchor rod, find the preset PVC pipe to get through the wooden plug and drill the anchor hole; install the anchor rod in the anchor hole and inject grout, Maintenance: After the cement mortar reaches the design strength, install saddle-shaped pads and inclined irons to tension and lock the anchor rod.

I、处理基坑坑壁表面I. Treatment of the surface of the foundation pit wall

为防止桩间土脱落塌方,向桩间土内打土钉,挂钢筋网,喷射混凝土面层;基坑坑壁表面设置排水孔,孔后做碎石反滤层。In order to prevent the soil between the piles from falling off and collapsing, soil nails are drilled into the soil between the piles, steel mesh is hung, and the concrete surface is sprayed; drainage holes are set on the surface of the foundation pit wall, and a gravel filter layer is made behind the holes.

J、结束J. end

重复步骤H-J,直至完成桩锚支护体系的施工。Repeat steps H-J until the construction of the pile-anchor support system is completed.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

1、安全可靠。本发明取消了传统桩锚体系中的腰梁,避免了因腰梁变形引起的预应力损失。本发明是将锚杆(索)的力直接传递到护壁桩上,锚杆(索)和护壁桩可以更好的整体协同受力,支护结构的整体性更好,安全可靠。而传统的桩锚支护体系中必须通过钢腰梁才能将锚杆(索)的力传递到护壁桩上,土压力达到一定值后,腰梁会发生局部失稳和整体失稳而导致整个支护结构体系的破坏。1. Safe and reliable. The invention cancels the waist beam in the traditional pile anchor system, and avoids the loss of prestress caused by the deformation of the waist beam. The present invention directly transmits the force of the anchor rod (cable) to the retaining wall pile, and the anchor rod (cable) and the retaining wall pile can better cooperate with force as a whole, and the integrity of the supporting structure is better, and it is safe and reliable. However, in the traditional pile-anchor support system, the force of the anchor rod (cable) must be transmitted to the retaining wall pile through the steel waist beam. Destruction of the supporting structure system.

2、造价低。本发明的连接结构取消了传统桩锚支护体系中使用腰梁的连接方式,取消了大量的连接缀板、焊条,大大节省了型钢钢材和用电量。2. Low cost. The connection structure of the present invention cancels the waist beam connection method used in the traditional pile-anchor support system, cancels a large number of connecting panels and welding rods, and greatly saves steel materials and electricity consumption.

3、工序少、工期短。本发明由于取消了传统桩锚体系中的腰梁,节省了大量复杂的焊接工作,更重要是避免了繁重而且危险腰梁的安装工作,简化了施工工序,缩短了施工工期。3. Few processes and short construction period. Because the invention cancels the waist beam in the traditional pile anchor system, it saves a lot of complicated welding work, and more importantly, it avoids the heavy and dangerous installation work of the waist beam, simplifies the construction process, and shortens the construction period.

附图说明Description of drawings

图1为本发明连接结构的平面示意图。Fig. 1 is a schematic plan view of the connection structure of the present invention.

图2为本发明连接结构详图。Fig. 2 is a detailed diagram of the connection structure of the present invention.

图3为本发明钢筋笼预置PVC管示意图。Fig. 3 is a schematic diagram of pre-installed PVC pipes in steel cages of the present invention.

图4为本发明桩间土支护立面图。Fig. 4 is the vertical view of soil support between piles of the present invention.

图5为本发明桩间土支护平面图。Fig. 5 is a plan view of soil support between piles of the present invention.

图6为本发明实例基坑剖面示意图。Fig. 6 is a schematic cross-sectional view of the foundation pit of the example of the present invention.

图7为本发明基坑立面图。Fig. 7 is an elevation view of the foundation pit of the present invention.

图中:1、护壁桩;2、锚杆;3、马鞍形垫块;4、锚具;5、PVC管;6、斜铁;7、锁口梁;8、混凝土面层;9、土钉;10、钢筋网;11、植筋;12、排水孔;13、钢筋笼。In the figure: 1. Retaining pile; 2. Anchor rod; 3. Saddle pad; 4. Anchorage; 5. PVC pipe; 6. Slanted iron; 7. Lock beam; 8. Concrete surface; Nails; 10, steel mesh; 11, planting bars; 12, drainage holes; 13, steel cages.

具体实施方式detailed description

下面结合附图和具体实施例对本发明的特点进一步说明:Below in conjunction with accompanying drawing and specific embodiment, feature of the present invention is further described:

如图1-7所示,锚头置于桩身的深基坑桩锚支护体系,至少包括护壁桩1、锚杆2、马鞍形垫块3、锚具4、PVC管5、斜铁6和锁口梁7;As shown in Figure 1-7, the deep foundation pit pile anchor support system with the anchor head placed on the pile body includes at least wall retaining pile 1, anchor rod 2, saddle-shaped pad 3, anchorage 4, PVC pipe 5, and inclined iron 6 and lock beam 7;

所述的护壁桩1内预置PVC管5,锚杆2的内端穿过PVC管5插入到基坑坑壁内、锚杆2的外端与锚具4固定连接,在锚具4与护壁桩1之间设置斜铁6和马鞍形垫块3;所述的基坑坑壁喷射混凝土面层8,两个相邻的护壁桩1之间的基坑坑壁内设置土钉9和排水孔12;两个相邻的护壁桩1之间的基坑坑壁上设置钢筋网10;所述的锚具4轴线与水平面具有15°~25°的夹角,并与锚杆2倾角保持一致。The PVC pipe 5 is preset in the wall retaining pile 1, the inner end of the anchor rod 2 is inserted into the wall of the foundation pit through the PVC pipe 5, the outer end of the anchor rod 2 is fixedly connected with the anchorage 4, and the anchorage 4 and the Slant iron 6 and saddle-shaped spacer 3 are arranged between the retaining piles 1; the sprayed concrete surface layer 8 on the wall of the foundation pit is set, and soil nails 9 and Drain holes 12; steel mesh 10 is set on the wall of the foundation pit between two adjacent retaining piles 1; the axis of the anchor 4 has an included angle of 15° to 25° with the horizontal plane, and has an angle of inclination with the anchor rod 2 be consistent.

进一步地,所述的锚杆2轴线与护壁桩1中心线在一个垂直面内。Further, the axis of the anchor rod 2 and the centerline of the retaining pile 1 are in a vertical plane.

进一步地,所述的锚杆2用锚索代替。Further, the anchor rod 2 is replaced by an anchor cable.

进一步地,所述的两个相邻的护壁桩1之间的基坑坑壁内的土钉9竖向间距为1.4-1.6m,排水孔12横向间距和竖向间距为1.4-1.6m。Further, the vertical distance between the soil nails 9 in the foundation pit wall between two adjacent retaining piles 1 is 1.4-1.6m, and the horizontal and vertical distances between the drainage holes 12 are 1.4-1.6m.

进一步地,所述的PVC管5内径与锚孔孔径保持一致。Further, the inner diameter of the PVC pipe 5 is consistent with the diameter of the anchor hole.

进一步地,所述的护壁桩1顶部设置锁口梁7。Further, a locking beam 7 is arranged on the top of the wall retaining pile 1 .

进一步地,所述的锚杆2有多个,分别沿护壁桩1垂直方向的多个预置PVC管5插入到基坑坑壁内。Further, there are multiple anchor rods 2, and multiple preset PVC pipes 5 along the vertical direction of the retaining pile 1 are respectively inserted into the wall of the foundation pit.

锚头置于桩身的深基坑桩锚支护体系的实施方法,包括以下步骤:The implementation method of the deep foundation pit pile-anchor support system with the anchor head placed on the pile body comprises the following steps:

A、制作护壁桩1的钢筋笼13A, make the reinforcement cage 13 of retaining pile 1

制作护壁桩1的钢筋笼13时,钢筋笼13内在锚杆2设计深度处预置两端以木塞封口的PVC管5,PVC管5通过铁丝与钢筋笼13可靠连接,保证PVC管5与锚杆2设计角度保持一致;钢筋笼13内预置PVC管5处应做箍筋加密处理,护壁桩1配筋具有方向性,钢筋笼13安放时应严格按图纸标注的方向施工。When making the reinforcing cage 13 of retaining wall pile 1, the PVC pipe 5 that both ends are sealed with wooden plugs is preset at the design depth of the anchor rod 2 in the reinforcing cage 13, and the PVC pipe 5 is reliably connected with the reinforcing cage 13 by iron wire, so as to ensure that the PVC pipe 5 and the reinforcing cage 13 are reliably connected. The design angles of the anchor rods 2 should be kept consistent; the 5 places where the PVC pipes are preset in the reinforcement cage 13 should be treated with stirrup encryption, and the reinforcement of the retaining wall pile 1 has directionality, and the reinforcement cage 13 should be placed in strict accordance with the direction marked on the drawing.

B、预制马鞍形垫块3B. Prefabricated saddle block 3

马鞍形垫块3通过预制获得,其材料采用钢材或混凝土,预制时保证其马鞍处弧度与所采用的护壁桩1圆弧曲率保持一致以保证两者可完美契合。当地质条件较差,锚杆2需要施加较大预应力时,混凝土材质马鞍形垫块3在预制时选用高标号水泥并配钢筋。The saddle-shaped spacer 3 is obtained through prefabrication, and its material is steel or concrete. During prefabrication, the curvature of the saddle is guaranteed to be consistent with the arc curvature of the retaining pile 1 adopted to ensure that the two can fit perfectly. When the geological conditions are poor and the anchor rod 2 needs to be applied with a large prestress, the concrete saddle block 3 is prefabricated with high-grade cement and reinforced.

C、清理场地C. to clean up

清理场地,挖除表面松动土层,对护壁桩1桩孔进行测量定位、放样。Clean up the site, excavate the loose soil layer on the surface, measure, position and set out the pile hole of the retaining pile 1.

D、挖桩孔D. Digging pile holes

按照步骤C定好的护壁桩1孔位进行挖孔至设计深度。According to step C, dig the hole position of retaining pile 1 to the design depth.

E、吊装钢筋笼13E. Hoisting reinforcement cage 13

吊装钢筋笼13,护壁桩1配筋具有方向性,钢筋笼13安放时应严格按图纸标注的方向施工。When hoisting the reinforcement cage 13, the reinforcement of the wall retaining pile 1 has directionality. When the reinforcement cage 13 is placed, it should be constructed strictly according to the direction marked on the drawing.

F、浇筑护壁桩1混凝土F. Pouring concrete for wall retaining pile 1

向安装好钢筋笼13的桩孔内浇筑混凝土,并及时养护。Concrete is poured in the pile hole that steel cage 13 is installed, and maintenance in time.

G、施做锁口梁7G. Make lock beam 7

具备锁口梁7施工条件后,进行护壁桩1桩间土挖除及护壁桩1桩头截除工作,及时提供锁口梁7施工工作面,绑扎、安放钢筋笼13,支模,浇筑混凝土,并及时养护。After the construction conditions of the locking beam 7 are met, excavate the soil between the retaining pile 1 and cut off the pile head of the retaining pile 1, provide the construction work surface of the locking beam 7 in time, bind and place the steel cage 13, set up the formwork, and pour concrete , and timely maintenance.

H、安装锚杆2H. Install anchor rod 2

具备基坑开挖施工条件后,沿护壁桩1开挖基坑至锚杆2设计深度下方,找到预置PVC管5打通木塞并钻取锚孔;锚孔内安设锚杆2并注浆,养护;待水泥砂浆达到设计强度后安装马鞍形垫块3及斜铁6对锚杆2进行张拉锁定。After the foundation pit excavation construction conditions are met, excavate the foundation pit along the retaining pile 1 to the design depth of the anchor rod 2, find the preset PVC pipe 5 to get through the wooden plug and drill the anchor hole; install the anchor rod 2 in the anchor hole and inject After the cement mortar reaches the design strength, install the saddle-shaped block 3 and the inclined iron 6 to tension and lock the anchor rod 2.

I、处理基坑坑壁表面I. Treatment of the surface of the foundation pit wall

为防止桩间土脱落塌方,向桩间土内打土钉9,挂钢筋网10,喷射混凝土面层8;基坑坑壁表面设置排水孔12,孔后做碎石反滤层。In order to prevent the soil between the piles from falling off and collapsing, soil nails 9 are drilled in the soil between the piles, steel mesh 10 is hung, and the surface layer of sprayed concrete is 8; drainage holes 12 are arranged on the surface of the foundation pit wall, and a gravel filter layer is made behind the holes.

J、结束J. end

重复步骤H-J,直至完成桩锚支护体系的施工。Repeat steps H-J until the construction of the pile-anchor support system is completed.

工程实例:Engineering example:

对地质条件较差的深基坑工程,通常采用桩锚支护体系。如图6-7所示,本例基坑深12.4m,采用的护壁桩1桩长15m、桩径0.8m、桩间距1.6m,分别在距桩顶5.0m、7.5m位置处布置两排锚杆2,锚杆2倾角15°。For deep foundation pit projects with poor geological conditions, pile-anchor support systems are usually used. As shown in Figure 6-7, the depth of the foundation pit in this example is 12.4m, and the wall retaining pile 1 used is 15m long, 0.8m in pile diameter, and 1.6m in pile spacing, and two rows are arranged at positions 5.0m and 7.5m away from the pile top Anchor rod 2, the inclination angle of anchor rod 2 is 15°.

充分做好施工准备工作,工作面整平,挖除表面松动土层,对护壁桩1桩孔进行测量定位。Fully prepare for the construction, level the working surface, excavate the loose soil layer on the surface, and measure and position the 1 pile hole of the retaining pile.

如图3所示,对孔位放线定位后进行挖孔作业,同时进行钢筋笼13的制作,钢筋笼13主筋采用HRB400级钢筋,fy=400MPa;箍筋采用HPB300级钢筋,Fy=300MPa;制作护壁桩1的钢筋笼13时,钢筋笼13内在锚杆2设计深度处预置两端以木塞封口的PVC管5,所用PVC管5内径130mm,与锚孔设计直径一致,PVC管5通过铁丝与钢筋笼13可靠连接,保证PVC管5与锚杆2设计角度保持一致;钢筋笼13预置PVC管5处应做箍筋加密处理。待上述两步完成后将钢筋笼13吊装入孔施做护壁桩1,护壁桩1配筋具有方向性,钢筋笼13安放时应严格按图纸标注的方向施工。护壁桩1混凝土强度等级C30,钢筋保护层厚度35mm。As shown in Figure 3, carry out the digging operation after setting out the hole position, and carry out the making of reinforcement cage 13 at the same time, the main reinforcement of reinforcement cage 13 adopts HRB400 grade reinforcement, fy=400MPa; Stirrup adopts HPB300 grade reinforcement, Fy=300MPa; When making the reinforcement cage 13 of the retaining pile 1, the PVC pipe 5 with both ends sealed with wooden plugs is preset in the design depth of the anchor rod 2 in the reinforcement cage 13, and the used PVC pipe 5 has an inner diameter of 130mm, which is consistent with the design diameter of the anchor hole. The reliable connection between the iron wire and the reinforcement cage 13 ensures that the design angles of the PVC pipe 5 and the anchor rod 2 are consistent; After the above two steps are completed, the steel cage 13 is hoisted into the hole and used as the retaining pile 1. The reinforcement of the retaining pile 1 has directionality. When the reinforcement cage 13 is placed, it should be constructed strictly according to the direction marked on the drawing. Wall retaining pile 1 has a concrete strength grade of C30, and the thickness of the reinforcement protective layer is 35mm.

待具备锁口梁7施工条件后,进行护壁桩1桩间土挖除及桩头截除工作,及时提供锁口梁7施工工作面,进行锁口梁7钢筋笼13的绑扎、安放,浇筑混凝土,混凝土强度等级C30,钢筋保护层厚度35mm。混凝土浇筑完12h以内对所有外露混凝土面用麻袋进行覆盖并浇水养护,每天浇水次数以能保持混凝土表面始终处于湿润状态为宜,养护时间不少于7天。After the construction conditions of the interlocking beam 7 are met, excavation of the soil between the retaining piles 1 and the cutting off of the pile head shall be carried out, and the construction work surface of the interlocking beam 7 shall be provided in time, and the binding, placement and pouring of the reinforcing cage 13 of the interlocking beam 7 shall be carried out. Concrete, concrete strength grade C30, steel bar cover thickness 35mm. Within 12 hours after concrete pouring, cover all exposed concrete surfaces with sacks and water them for curing. The number of waterings per day is appropriate to keep the concrete surface always in a wet state, and the curing time is not less than 7 days.

如图1-2所示,待具备基坑土方开挖条件后沿护壁桩1开挖基坑至锚杆2设计深度下方0.5m处,找到预置PVC管5打通木塞并钻取锚孔,安装锚杆2、注浆、养护,待水泥砂浆达到设计强度后安装马鞍形垫块3及斜铁6对锚杆2进行张拉锁定。钢绞线采用1×7七股,公称直径17.8mm,抗拉强度1860MPa。锚孔灌注水泥砂浆强度等级M30。As shown in Figure 1-2, after the earthwork excavation conditions for the foundation pit are met, excavate the foundation pit along the retaining pile 1 to a place 0.5m below the design depth of the anchor rod 2, find the preset PVC pipe 5 to get through the wooden plug and drill the anchor hole , Install anchor rod 2, grouting, maintenance, install saddle-shaped block 3 and inclined iron 6 to tension and lock anchor rod 2 after the cement mortar reaches the design strength. The steel strand adopts 1×7 seven strands, the nominal diameter is 17.8mm, and the tensile strength is 1860MPa. Anchor holes are filled with cement mortar of strength grade M30.

如图4-5所示,待锚杆2施做完成进行护壁桩1桩间土的支护,桩间土采用土钉9挂6.5@200×200钢筋网10,土钉9采用HRB400级钢筋,fy=400MPa,面层喷射C20细石混凝土,厚度50mm。网片制作宜优先使用焊接工艺,钢筋网10搭接不应小于300mm,网片应采用植筋11如:膨胀螺栓或其它方式与护壁桩1连接牢固;基坑坑壁表面设置排水孔12,排水孔12采用Φ100PVC管,间距为1.5m×1.5m,向外倾斜4%,孔后做碎石反滤层。As shown in Figure 4-5, after the installation of the anchor rod 2 is completed, the soil between the retaining pile 1 is supported. The soil between the piles uses soil nails 9 to hang 6.5@200×200 steel mesh 10, and the soil nails 9 use HRB400 steel bars , fy=400MPa, the surface layer is sprayed with C20 fine stone concrete, and the thickness is 50mm. Welding process should be preferred for mesh production. The overlap of steel mesh 10 should not be less than 300mm. The mesh should be planted with reinforcement 11, such as: expansion bolts or other methods are firmly connected with retaining pile 1; drainage holes 12 are set on the surface of the foundation pit wall, Drainage hole 12 adopts Φ100PVC pipe, the spacing is 1.5m×1.5m, and the outward slope is 4%, and the gravel reverse filter layer is used behind the hole.

以同样的方法向下开挖并支护,直至设计深度。Excavate and support downwards in the same way to the design depth.

对于本领域技术人员而言,显然本发明不限于上述示范性实施例的细节,而且在不背离本发明的精神或基本特征的情况下,能够以其它的具体形式实现本发明。因此,无论从哪一点来看,均应将实例看作是示范性的,而且是非限制性的,本发明的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本发明内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。It will be apparent to those skilled in the art that the invention is not limited to the details of the above-described exemplary embodiments, but that the invention can be embodied in other specific forms without departing from the spirit or essential characteristics of the invention. Therefore, the examples should be regarded in all points of view as exemplary and not restrictive, the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that the scope of the invention will fall within the scope of the claims. All changes within the meaning and range of equivalent elements are embraced in the present invention. Any reference sign in a claim should not be construed as limiting the claim concerned.

以上所述,仅为本发明的较佳实施例,并不限制本发明,凡是依据本发明的技术实质对以上实施例所做的任何细微修改、等同替换和改进,均应包括在本发明技术方案的保护范围之内。The above is only a preferred embodiment of the present invention, and does not limit the present invention. Any minor modifications, equivalent replacements and improvements made to the above embodiments according to the technical essence of the present invention should be included in the technical aspects of the present invention. within the scope of protection of the program.

Claims (8)

1. anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:At least include lagging pile (1), anchor pole (2), Shape of a saddle cushion block (3), anchorage (4), pvc pipe (5), wedge (6) and fore shaft beam (7);
In described lagging pile (1) preset pvc pipe (5), the inner of anchor pole (2) is inserted in foundation ditch crater wall through pvc pipe (5), The outer end of anchor pole (2) is fixedly connected with anchorage (4), arranges wedge (6) and shape of a saddle pad between anchorage (4) and lagging pile (1) Block (3);Arrange in described foundation ditch crater wall gunite concrete surface layer (8), the foundation ditch crater wall between two adjacent lagging piles (1) Soil nailing (9) and osculum (12);Bar-mat reinforcement (10) is set in the foundation ditch crater wall between two adjacent lagging piles (1);Described Anchorage (4) axis has 15 °~25 ° of angle with horizontal plane, and is consistent with anchor pole (2) inclination angle.
2. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described anchor Bar (2) axis is with lagging pile (1) centrage in a vertical.
3. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described anchor Bar (2) is replaced with anchor cable.
4. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described two Soil nailing (9) level interval in foundation ditch crater wall between individual adjacent lagging pile (1) is 1.4-1.6m, between osculum (12) is horizontal Away from level interval be 1.4-1.6m.
5. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described Pvc pipe (5) internal diameter is consistent with anchor hole aperture.
6. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described shield Fore shaft beam (7) is set at the top of wall stake (1).
7. anchor head according to claim 1 is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Described anchor Bar (2) has multiple, and the multiple preset pvc pipe (5) along lagging pile (1) vertical direction is inserted in foundation ditch crater wall respectively.
8. anchor head is placed in the implementation of the Pile-Anchor Supporting for Deep Excavation system of pile body, it is characterised in that:Comprise the following steps:
A, the steel reinforcement cage (13) for making lagging pile (1)
During steel reinforcement cage (13) of making lagging pile (1), at anchor pole (2) projected depth of steel reinforcement cage (13) inherence, preset two ends are with stopper The pvc pipe (5) of sealing, pvc pipe (5) are reliably connected with steel reinforcement cage (13) by iron wire, it is ensured that pvc pipe (5) is designed with anchor pole (2) Angle is consistent;In steel reinforcement cage (13), stirrup encryption should be done by preset pvc pipe (5) place, and lagging pile (1) arrangement of reinforcement has direction Property, steel reinforcement cage (13) should strictly press the direction construction of drawings marked when laying;
B, prefabricated shape of a saddle cushion block (3)
Shape of a saddle cushion block (3) by prefabricated acquisition, its material using steel or concrete, ensure when prefabricated at its saddle radian with Lagging pile (1) circular arc curvature for being adopted be consistent with ensure both can perfection agree with;When geological conditions poor, anchor pole (2) When needing to apply more high-prestressed, concrete material shape of a saddle cushion block (3) from high-mark cement and matches somebody with somebody reinforcing bar when prefabricated;
C, place cleaning
Place cleaning, excavates surface and loosens soil layer, measure positioning, setting-out to lagging pile (1) stake holes;
D, digging stake holes
Lagging pile (1) hole position that sets according to step C carries out borehole to projected depth;
E, lifting steel reinforcement cage (13)
There is directivity, steel reinforcement cage (13) should strictly press drawings marked when laying for lifting steel reinforcement cage (13), lagging pile (1) arrangement of reinforcement Construct in direction;
F, pour lagging pile (1) concrete
The casting concrete into the stake holes for install steel reinforcement cage (13), and conserve in time;
G, perform fore shaft beam (7)
After possessing fore shaft beam (7) execution conditions, carry out lagging pile (1) inter-pile soil and excavate and the amputation work of lagging pile (1) pile crown, and When fore shaft beam (7) construction working face is provided, colligation, lay steel reinforcement cage (13), formwork, casting concrete, and conserving in time;
H, installation anchor pole (2)
After possessing excavation condition, below lagging pile (1) excavation pit to anchor pole (2) projected depth, find preset Pvc pipe (5) is got through stopper and drills through anchor hole;Anchor pole (2) slip casting is installed in anchor hole, is conserved;Treat that cement mortar reaches design strong Installing shape of a saddle cushion block (3) and wedge (6) after degree carries out tensioning fixation to anchor pole (2);
I, process Foundation Pit wall surface
For preventing inter-pile soil from coming off landslide, soil nailing (9) is beaten into inter-pile soil, hang bar-mat reinforcement (10), gunite concrete surface layer (8); Foundation Pit wall surface arranges osculum (12), does rubble loaded filter behind hole;
J, end
Repeat step H-J, until complete the construction of pile-anchor supporting system.
CN201611194154.4A 2016-12-21 2016-12-21 Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body Active CN106498950B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611194154.4A CN106498950B (en) 2016-12-21 2016-12-21 Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611194154.4A CN106498950B (en) 2016-12-21 2016-12-21 Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body

Publications (2)

Publication Number Publication Date
CN106498950A true CN106498950A (en) 2017-03-15
CN106498950B CN106498950B (en) 2018-11-30

Family

ID=58333588

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611194154.4A Active CN106498950B (en) 2016-12-21 2016-12-21 Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body

Country Status (1)

Country Link
CN (1) CN106498950B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222017A (en) * 2018-02-02 2018-06-29 江苏工程职业技术学院 A kind of H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108487255A (en) * 2018-02-02 2018-09-04 江苏工程职业技术学院 Modified H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108867690A (en) * 2018-09-30 2018-11-23 中冶建工集团有限公司 The reverse construction of peg board barricade of big foundation pit
CN108999199A (en) * 2018-10-12 2018-12-14 深圳市工勘岩土集团有限公司 Combined type foundation pit supporting method
CN110185045A (en) * 2019-07-05 2019-08-30 马鞍山十七冶工程科技有限责任公司 A kind of foundation pit support device
CN110453690A (en) * 2019-09-10 2019-11-15 山东建筑大学 A recyclable foundation pit pile anchor support structure and construction method
CN110984169A (en) * 2019-11-13 2020-04-10 中冶天工集团有限公司 Protective net used between cast-in-place pile piles and installation method thereof
CN114059557A (en) * 2021-12-15 2022-02-18 中国电建集团北京勘测设计研究院有限公司 Excavation supporting method for vertical side slope of foundation pit of hydropower station with deep covering layer
CN114809014A (en) * 2022-05-16 2022-07-29 兰州理工大学 Construction method of pile-anchor combined support structure with unloading pipe shed
CN115478543A (en) * 2022-10-26 2022-12-16 北京房地集团有限公司 Foundation pit supporting structure of manual hole digging pile and construction method
CN119195124A (en) * 2024-11-15 2024-12-27 重庆市轨道交通设计研究院有限责任公司 A construction method of embedded anchor structure for reducing foundation pit excavation volume

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268770A (en) * 2002-03-18 2003-09-25 Rita Sogo Kikaku:Kk Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
CN1970893A (en) * 2006-07-13 2007-05-30 大连理工大学 Connecting structure for use in piled anchor supporting system and its construction method
KR20110129657A (en) * 2010-05-26 2011-12-02 이득근 Mud wall using frame structure and construction method of mud wall using the same
CN202323962U (en) * 2011-12-10 2012-07-11 中国建筑西南勘察设计研究院有限公司 Composite supporting structure of drainage pipe pile and soil nailing wall
CN204753604U (en) * 2015-06-11 2015-11-11 西安科技大学 A excavation supporting system for expanding soil district
CN205502023U (en) * 2016-03-17 2016-08-24 中勘冶金勘察设计研究院有限责任公司 Native protector between foundation ditch stake
CN205662920U (en) * 2016-06-08 2016-10-26 四川省建筑科学研究院 Take secret assembled precast pile in anchor rope hole
CN206408630U (en) * 2016-12-21 2017-08-15 大连交通大学 Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003268770A (en) * 2002-03-18 2003-09-25 Rita Sogo Kikaku:Kk Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
CN1970893A (en) * 2006-07-13 2007-05-30 大连理工大学 Connecting structure for use in piled anchor supporting system and its construction method
KR20110129657A (en) * 2010-05-26 2011-12-02 이득근 Mud wall using frame structure and construction method of mud wall using the same
CN202323962U (en) * 2011-12-10 2012-07-11 中国建筑西南勘察设计研究院有限公司 Composite supporting structure of drainage pipe pile and soil nailing wall
CN204753604U (en) * 2015-06-11 2015-11-11 西安科技大学 A excavation supporting system for expanding soil district
CN205502023U (en) * 2016-03-17 2016-08-24 中勘冶金勘察设计研究院有限责任公司 Native protector between foundation ditch stake
CN205662920U (en) * 2016-06-08 2016-10-26 四川省建筑科学研究院 Take secret assembled precast pile in anchor rope hole
CN206408630U (en) * 2016-12-21 2017-08-15 大连交通大学 Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108487255A (en) * 2018-02-02 2018-09-04 江苏工程职业技术学院 Modified H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108222017B (en) * 2018-02-02 2019-11-26 江苏工程职业技术学院 A kind of H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108487255B (en) * 2018-02-02 2019-11-26 江苏工程职业技术学院 Modified H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108222017A (en) * 2018-02-02 2018-06-29 江苏工程职业技术学院 A kind of H profile steel anchor pole composite pile-prefabricated board wall base pit enclosure construction method
CN108867690A (en) * 2018-09-30 2018-11-23 中冶建工集团有限公司 The reverse construction of peg board barricade of big foundation pit
CN108999199A (en) * 2018-10-12 2018-12-14 深圳市工勘岩土集团有限公司 Combined type foundation pit supporting method
CN110185045B (en) * 2019-07-05 2024-04-16 中国十七冶集团有限公司 Foundation pit supporting device
CN110185045A (en) * 2019-07-05 2019-08-30 马鞍山十七冶工程科技有限责任公司 A kind of foundation pit support device
CN110453690A (en) * 2019-09-10 2019-11-15 山东建筑大学 A recyclable foundation pit pile anchor support structure and construction method
CN110453690B (en) * 2019-09-10 2021-09-10 山东建筑大学 Recyclable foundation pit pile anchor supporting structure and construction method
CN110984169A (en) * 2019-11-13 2020-04-10 中冶天工集团有限公司 Protective net used between cast-in-place pile piles and installation method thereof
CN114059557A (en) * 2021-12-15 2022-02-18 中国电建集团北京勘测设计研究院有限公司 Excavation supporting method for vertical side slope of foundation pit of hydropower station with deep covering layer
CN114809014A (en) * 2022-05-16 2022-07-29 兰州理工大学 Construction method of pile-anchor combined support structure with unloading pipe shed
CN114809014B (en) * 2022-05-16 2023-09-01 兰州理工大学 Construction method of pile-anchor combined support structure with unloading pipe shed
CN115478543A (en) * 2022-10-26 2022-12-16 北京房地集团有限公司 Foundation pit supporting structure of manual hole digging pile and construction method
CN115478543B (en) * 2022-10-26 2023-10-20 北京房地集团有限公司 Artificial hole digging pile foundation pit supporting structure and construction method
CN119195124A (en) * 2024-11-15 2024-12-27 重庆市轨道交通设计研究院有限责任公司 A construction method of embedded anchor structure for reducing foundation pit excavation volume

Also Published As

Publication number Publication date
CN106498950B (en) 2018-11-30

Similar Documents

Publication Publication Date Title
CN106498950B (en) Anchor head is placed in the implementation method of the Pile-Anchor Supporting for Deep Excavation system of pile body
CN102678134B (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN104032758B (en) Extra-high reinforced construction method in discarded pit
CN105041333B (en) It is a kind of first to fill out the method for digging method processing Tunnel Landslide afterwards
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN205742213U (en) Foundation pit supporting construction
CN102828518B (en) Construction method of prestressed anchor cable anchoring structure of manual hole digging support pile
CN210163913U (en) Asymmetric double-row pile-anchor rod combined supporting structure
CN106013191A (en) Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN107965325B (en) A kind of small interval shallow tunnel just branch arch replacement construction method
CN104196014A (en) Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN111560962A (en) Backfill area foundation pit supporting structure and construction method thereof
CN105155550A (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
CN104452784A (en) Composite bolt pile used for slope strengthening and construction technique of composite bolt pile
CN108625356A (en) A kind of prefabricated prestressed underground continuous wall and its construction method
CN109209389A (en) Hazy tunnel construction method
CN210104758U (en) A foundation pit support system of soil-nailed cast-in-place pile and anchor-cable combination
CN104631440A (en) Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN108547625B (en) TBM cutterhead method for dismounting in a kind of tunnel
CN104612719B (en) The anti-collapse processing method in a kind of soft rock tunnel hole
CN206800370U (en) It is a kind of to excavate the continuous side wall supporting and retaining system protective construction in underground without fertile groove

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant