CN110374630A - A kind of construction method of tunnel vault concrete vibrating - Google Patents

A kind of construction method of tunnel vault concrete vibrating Download PDF

Info

Publication number
CN110374630A
CN110374630A CN201910506930.7A CN201910506930A CN110374630A CN 110374630 A CN110374630 A CN 110374630A CN 201910506930 A CN201910506930 A CN 201910506930A CN 110374630 A CN110374630 A CN 110374630A
Authority
CN
China
Prior art keywords
bellows
concrete
lining
tunnel
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910506930.7A
Other languages
Chinese (zh)
Other versions
CN110374630B (en
Inventor
许东升
高超
马宏亮
尹红军
刘刚
龙蛟
刘龙
吴彦双
王蒙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Engineering Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN201910506930.7A priority Critical patent/CN110374630B/en
Publication of CN110374630A publication Critical patent/CN110374630A/en
Application granted granted Critical
Publication of CN110374630B publication Critical patent/CN110374630B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete

Abstract

The invention belongs to lining construction technical field more particularly to a kind of construction method of tunnel vault concrete vibrating, specific steps include: 1. measurements scribing line;2. default bellows;3. installing lining shuttering;4. casting concrete;5. adhesion type vibrates;6. internal vibration;7. bellows is perfused.The construction method of tunnel vault concrete vibrating of the present invention is vibrated the mode matched with internal vibration by using adhesion type, improves quality of vibrating.

Description

A kind of construction method of tunnel vault concrete vibrating
Technical field
The invention belongs to lining construction technical field more particularly to a kind of construction parties of tunnel vault concrete vibrating Method.
Background technique
Hydraulic tunnel majority carries out concrete lining using telescoping steel form, included using telescoping steel form in concreting Attached vibrator vibrated except template.However as the development of hydropower industry, tunnel concrete liner is thick It spends increasing, is only capable of will be close to the concrete material vibration compacting of template using attached vibrator, and can not be by the mixed of periphery Solidifying earth material whole vibration compacting.
With greatly developing for hydropower industry, natural flow station scale is increasing, and Diversion Tunnel diameter is increasing, tunnel Hole lining concrete thickness is also gradually increased, and lining thickness is more than that the tunnel of 60cm is commonplace, and some is even more than 80cm. For the biggish tunnel of lining thickness, spandrel can use poker vibrator and attached vibrator in feed inlet with lower portion Combine and vibrates, it can be closely knit by concrete vibrating;But crown concrete is due to that can not use poker vibrator in feed inlet, only Attached vibrator can be used to vibrate except template, effect of vibrating not can guarantee.If shaken using high-power adhesion type Device is smash, is vibrated effect although can be improved crown concrete material, also be easy to cause lining trolley deformation even to collapse, increases greatly Engineering drawing lessons and security risk are added.
Such as Chinese Patent Application No. are as follows: a kind of tunnel inverted arch concrete lining of the patent disclosure of CN201611078266.3 Sliding formwork and construction method, the surrounding of slip-form template are provided perpendicular to the backplate of slip-form template, and slip-form template and backplate are linked as one Body is provided with reinforcing rib on slip-form template, and the geometry of slip-form template is identical as the shape of tunnel inverted arch, and left feed supplement bucket runs through The left side of slip-form template is set, and right feed supplement bucket runs through the right side that slip-form template is arranged in, is provided with hoist engine on slip-form template And plate vibrator.The construction method of tunnel inverted arch concrete lining sliding formwork includes sliding formwork dragging track position leveling processing, sliding Mould positioning, connects sliding formwork gliding power set, concreting, and the artificial essence of concrete surface is put down.But the invention does not adapt to The construction of vibrating of vault concrete, construction effect can not ensure.
Summary of the invention
In view of the deficiencies of the prior art, it is an object of the present invention to provide a kind of construction parties of tunnel vault concrete vibrating Method is vibrated the mode matched with internal vibration by using adhesion type, improves quality of vibrating.
The technical solution that the present invention solves the problems, such as is to provide a kind of construction method of tunnel vault concrete vibrating, specifically Include the following steps:
Step 1, measurement scribing line:
It crosses along tunnel axis direction in vault center, and along both side each 45-75 ° of position side Hua Liangtiao line, by two Position between bar side line is as vault boundary of works area;
Step 2, bellows is preset:
In vault boundary of works area, along tunnel circumferential direction every 60cm distance 1 Φ 80mm bellows of arrangement, bellows core Apart from lining shuttering 50cm, every bellows runs through the storehouse number of entire 12m long along canal axes direction;
Along bellows, longitudinally every 1.0m installs 20 joint bar of Φ for tunnel crown position corresponding to bellows, and joint bar enters Rock 20cm, joint bar expose distance 10cm of the scar length than bellows and scar;Using Φ 3.5mm iron wire by bellows with Joint bar binding and fixing;
Step 3, lining shuttering is installed:
Lining trolley is run to the hole section for needing lining cutting, lining trolley axis is adjusted, makes platform building cart axis and hole axis Direction is overlapped;Lining trolley jacking device is opened, lining shuttering is shored to lining cutting profile line position;This storehouse end is installed Pre-buried bellows nozzle is pierced by by the lining shuttering at place, the aperture on the lining shuttering of end point;
Step 4, casting concrete:
Using concrete tank from blending station transport concrete material to working face, concrete pump is by concrete material through serving as a contrast Platform building cart feed inlet is delivered in storehouse number, casting concrete, and lining trolley two sides concrete material uniformly rises, and height difference is less than 0.5m;
Step 5, adhesion type vibrates:
Attached vibrator is set on lining trolley, every 2.0m arranges that 6 rings are arranged in a ring, 8, every ring, adds up to 48, It is welded and fixed with lining trolley;The every rising 30cm of casting concrete material is vibrated once using attached vibrator, and vibrator is each One is opened, vibrating time 20s;
Step 6, internal vibration:
For the concrete material of crown range, after the completion of vibrating using attached vibrator, inserting for diameter 30mm is reused Enter formula vibrator and stretch in ripple tube passage and vibrate to peripheral concrete material, effective intubating length is greater than storehouse length;
Step 7, bellows is perfused:
Grout pipe one end connects grouting pump, and the other end is inserted into ripple bottom of the tube, slurry is sent into bellows, grout pipe is with filling The speed of travel of note mortar is slowly extracted outward, closely knit by being perfused in bellows;It is carried out after the completion of a piece bellows perfusion next The perfusion of root bellows;Abovementioned steps are repeated successively to be irrigated all bellowss;
Step 8, demoulding post-processes:
The concrete of lining cutting and the mortar strength of perfusion can be with demouldings after reaching 70%, will be exposed after end head formwork is removed It is cut off in the bellows end of concrete surface using sanding machine, into subsequent cycle.
Further, in step 2, when vault concrete is greater than 80cm, 2~3 layers of bellows are buried.
Further, in step 2, joint bar uses electric hammer pore-creating, anchoring adhesive anchoring.
Further, in step 3, lining trolley is run to before the hole section for needing lining cutting, installs the hole section reinforcing bar, sealing The built-in fittings such as band.
Further, in step 6, internal vibration specific steps are as follows: poker vibrator is pierced by end head formwork certainly Bellows nozzle is inserted directly into bellows tube bottom, opens poker vibrator, is vibrated 20s at tube bottom position, place of being vibrated There is laitance and emerges stopping there is no bubble in concrete material surface;Then it is pulled outwardly 50cm, vibrate 20s again, so anti- Multiple operation, until poker vibrator all pulls out, this root bellows vibrates end;A piece bellows vibrates again after vibrating Next bellows, repeats above operation, the completion until all bellowss all vibrate.
Further, nozzle should be blocked in step 7, after the completion of bellows perfusion mortar tight.
It further, further include that the data of tunnel Internal periphery are acquired using tunnel cross-section instrument in the step 1 Step;Polish processing to the protrusion that can influence lining shuttering in tunnel in favor of the installation of lining shuttering;It is right Depressed section in tunnel carries out the filling of concrete to form gap after preventing lining shuttering from installing.
Further, further include the steps that carrying out pressure monitoring to the concrete poured in the step 4.
Further, in the step 4, casting concrete includes: 300-380 parts of portland cement, aggregate 850-1000 Part, 450-550 parts of sand, 200-220 parts of waterglass, 8-12 parts of glass bead, 50-150 parts of flyash, 40-80 parts of steel fibre, It is third 3-5 parts solidifying, 2-3 parts of high performance water reducing agent of polyocarboxy acid, above-mentioned each ingredient is by mass.
The beneficial effects of the present invention are:
1, the construction method of tunnel vault concrete vibrating of the present invention mainly uses bellows, reinforcing bar, iron wire, water The conventional materials such as mud, sand;It is easy to operate, time-consuming less, construction speed will not be impacted.
2, the construction method of tunnel vault concrete vibrating of the present invention, is not limited by lining concrete thickness, for The biggish vault concrete of lining thickness realizes vibration compacting by burying multilayer corrugated pipe in vault range;And to lining cutting compared with Long storehouse number is operated by the length of the pre-buried bellows of increase and the length of poker vibrator flexible axle to realize.
3, the construction method of tunnel vault concrete vibrating of the present invention uses after the completion of vault concrete vibrating Mortar not less than design concrete grade will be perfused closely knit in pre-buried ripple tube passage, guarantee will not leave in bellows Cavity and influence concrete quality.
4, the construction method of tunnel vault concrete vibrating of the present invention vibrates by using adhesion type and shakes with plug-in type The mode matched is smash, realization vibrates to tunnel vault concrete, improves the quality vibrated.
Detailed description of the invention
Fig. 1 is bellows setting structure schematic diagram in the construction method of tunnel vault concrete vibrating of the present invention;
Fig. 2 be tunnel vault concrete vibrating of the present invention construction method in fill the construction schematic diagram of bellows;
In figure, 1- bellows, 2- lining shuttering, 3- lining trolley, 4- joint bar, 5- attached vibrator, 6- grout pipe, 7- Grouting pump.
Specific embodiment
To better understand the objects, features and advantages of the present invention, with reference to the accompanying drawing and specific real Applying mode, the present invention is further described in detail, it should be noted that in the absence of conflict, the implementation of the application Feature in example and embodiment can be combined with each other.
Embodiment
The construction method of the tunnel vault concrete vibrating, specifically comprises the following steps:
Step 1, measurement scribing line:
By level and laying out instrument equipment, cross along tunnel axis direction in vault center, and along both side each 60 ° of positions Two side lines are drawn, using the position between two side lines as vault boundary of works area.
In the present embodiment, scribing line uses the paint of lance ejection red.
Step 2, bellows 1 is preset:
In vault boundary of works area, along tunnel circumferential direction every in 60cm distance 1 Φ 80mm bellows 1 of arrangement, bellows 1 The heart and 2 distance 50cm of lining shuttering, every bellows 1 run through the storehouse number of entire 12m long along canal axes direction, wherein along tunnel Road circumferential direction refers to that tape measure approaches the data of tunnel house type planar survey every 60cm.
The tunnel crown position corresponding to bellows 1 installs the joint bar 4 of a Φ 20 along the longitudinal every 1.0m of bellows 1, Joint bar 4 enters rock 20cm, and joint bar 4 exposes distance 10cm of the scar length than bellows 1 and scar, and such as: the lining cutting of tunnel crown is thick Degree is 80cm, needs for bellows 1 to be fixed on the position with 2 distance 50cm of lining shuttering, bellows 1 is at a distance from scar 30cm, the then distance that joint bar 4 exposes scar should be 30cm+10cm=40cm, and joint bar 4 uses electric hammer pore-creating, anchoring adhesive anchoring. Bellows 1 and joint bar 4 are bound securely using Φ 3.5mm iron wire, prevent the bellows 1 in crown concrete vibrating from position occurs It moves.To ensure when binding bellows 1 it is penetrating, it is straight, without damage.
When vault concrete is greater than 80cm, 2~3 layers of bellows 1 are buried.
Step 3, lining shuttering 2 is installed:
The built-in fittings such as hole section reinforcing bar, waterstop are installed, lining trolley 3 is run to the hole section for needing lining cutting, adjustment lining 3 axis of platform building cart, is overlapped it with hole axis direction;Open 3 hydraulic top support system of lining trolley, by lining shuttering 2 shore to Lining cutting profile line position.The lining shuttering 2 of this storehouse end point is installed, the lining shuttering 2 of end point is circular ring shape, by lining trolley 3 both ends block securely, tightly.Pre-buried 1 nozzle of bellows is pierced by end point by the aperture on the lining shuttering 2 of end point Lining shuttering 2.
Step 4, casting concrete:
Using concrete tank from blending station transport concrete material to working face, concrete pump is by concrete material through serving as a contrast 3 feed inlet of platform building cart is delivered in storehouse number.In casting process, 3 two sides concrete material of lining trolley is kept uniformly to rise, it is high Difference is no more than 0.5m.
Step 5, adhesion type vibrates:
Lining trolley 3 carries attached vibrator 5, and every 2.0m arranges that a ring, 8, every ring add up to 48, with lining trolley 3 firm weldings.The every rising 30cm of concrete material is vibrated once using attached vibrator 5, and attached vibrator 5 can only be opened every time The attached vibrator 5 for opening an adjacent locations prevents lining trolley 3 from deforming.Vibrating time controls at 20s, place of being vibrated Stop vibrating when concrete material surface laitance occurs and emerges there is no bubble.
Step 6, internal vibration:
For the concrete material of 120 ° of ranges of crown, after the completion of vibrating using attached vibrator 5, plug-in type vibration is reused It smashes device (not shown) and stretches in 1 channel of bellows and vibrate to more than 50cm thickness peripheral concrete material, plug-in type Vibrator diameter 30mm, effective intubating length are greater than storehouse length, at least 12m.
Poker vibrator is inserted directly into from 1 nozzle of bellows for being pierced by end head formwork to 1 tube bottom of bellows, opens and inserts Enter formula vibrator, vibrates 20s at tube bottom position, the concrete material surface at place of being vibrated laitance occurs and there is no bubbles to emerge When stop;Then it is pulled outwardly 50cm, vibrate 20s again, 50cm is so pulled outwardly every time, until poker vibrator is all drawn Out, this root bellows 1 vibrates end;A piece bellows 1 vibrates next bellows 1 again after vibrating, and repeats above operation, The completion until all bellowss 1 all vibrate.
Step 7, bellows 1 is perfused:
6 one end of grout pipe connects grouting pump 7, and the other end is inserted into 1 bottom of bellows, slurry, grout pipe are sent into bellows 1 6 slowly extract outward with the speed of travel of perfusion mortar, closely knit by being perfused in bellows 1;A piece perfusion of bellows 1 is completed laggard Next bellows 1 of row is perfused;Abovementioned steps are repeated successively to be irrigated all bellowss 1.1 perfusion mortar of bellows is completed After should block it is tight.
Step 8, demoulding post-processes:
The concrete of lining cutting and the mortar strength of perfusion can be with demouldings after reaching 70%, will be exposed after end head formwork is removed It is cut off in 1 end of bellows of concrete surface using sanding machine, subsequently into subsequent cycle.
It in the present embodiment, further include that the data of tunnel Internal periphery are adopted using tunnel cross-section instrument in the step 1 The step of collection, is especially acquired vault boundary of works area, understands the flatness of vault boundary of works area;To the energy shadow in tunnel The protrusion rung to lining shuttering polish processing in favor of the installation of lining shuttering;Depressed section in tunnel is carried out The filling of concrete with prevent lining shuttering install after form gap.
Different marking signals is respectively adopted for protrusion and depressed section to be labeled, in order to which the later period is different Processing mode.
In the present embodiment, further include the steps that carrying out pressure monitoring to the concrete poured in the step 4.Pass through pressure Force snesor acquires the pressure of concrete to know the perfusion situation of concrete.
In the present embodiment, in the step 4, casting concrete includes: 300-380 parts of portland cement, aggregate 850- 1000 parts, 450-550 parts of sand, 200-220 parts of waterglass, 8-12 parts of glass bead, 50-150 parts of flyash, steel fibre 40- 80 parts, third 3-5 parts solidifying, 2-3 parts of high performance water reducing agent of polyocarboxy acid, 30-40 parts and 180 parts of shale pottery water, above-mentioned each ingredient By mass.
As an improvement of this embodiment, tunnel bottom be equipped at least 1 Φ 80mm bellows 1, carry out it is slotting Before entering the step of formula is vibrated, first vibrate to the bellows 1 that the bottom in tunnel is equipped with.Wherein, the bottom in tunnel is equipped with Bellows 1 still can be used joint bar binding.
As an improvement of this embodiment, operation of vibrating can be carried out simultaneously using more poker vibrators.
The present invention is not limited to the above embodiments, and the above embodiments and description only describe of the invention Principle, without departing from the spirit and scope of the present invention, various changes and improvements may be made to the invention, these change and change Into all fall within the protetion scope of the claimed invention.The claimed scope of the invention is defined by the following claims.

Claims (9)

1. a kind of construction method of tunnel vault concrete vibrating, which is characterized in that specifically comprise the following steps:
Step 1, measurement scribing line:
It crosses along tunnel axis direction in vault center, and along both side each 45-75 ° of position side Hua Liangtiao line, by two sides Position between sideline is as vault boundary of works area;
Step 2, bellows is preset:
In vault boundary of works area, along tunnel circumferential direction every 60cm distance 1 Φ 80mm bellows of arrangement, bellows core distance Lining shuttering 50cm, every bellows run through the storehouse number of entire 12m long along canal axes direction;
Along bellows, longitudinally every 1.0m installs 20 joint bar of Φ for tunnel crown position corresponding to bellows, and joint bar enters rock 20cm, joint bar expose distance 10cm of the scar length than bellows and scar;Using Φ 3.5mm iron wire by bellows and joint bar Binding and fixing;
Step 3, lining shuttering is installed:
Lining trolley is run to the hole section for needing lining cutting, lining trolley axis is adjusted, makes platform building cart axis and hole axis direction It is overlapped;Lining trolley jacking device is opened, lining shuttering is shored to lining cutting profile line position;This storehouse end point is installed Pre-buried bellows nozzle is pierced by by lining shuttering, the aperture on the lining shuttering of end point;
Step 4, casting concrete:
Using concrete tank from blending station transport concrete material to working face, concrete pump is by concrete material through lining cutting platform Vehicle feed inlet is delivered in storehouse number, casting concrete, and lining trolley two sides concrete material uniformly rises, and height difference is less than 0.5m;
Step 5, adhesion type vibrates:
Attached vibrator is set on lining trolley, and every 2.0m arranges that 6 rings are arranged in a ring, 8, every ring, adds up to 48, with lining Platform building cart is welded and fixed;The every rising 30cm of casting concrete material is vibrated once using attached vibrator, and vibrator is opened every time One, vibrating time 20s;
Step 6, internal vibration:
For the concrete material of crown range, after the completion of vibrating using attached vibrator, the plug-in type of diameter 30mm is reused Vibrator, which stretches in ripple tube passage, vibrates to peripheral concrete material, and effective intubating length is greater than storehouse length;
Step 7, bellows is perfused:
Grout pipe one end connects grouting pump, and the other end is inserted into ripple bottom of the tube, slurry is sent into bellows, grout pipe is with perfusion sand The speed of travel of slurry is slowly extracted outward, closely knit by being perfused in bellows;Next wave is carried out after the completion of a piece bellows perfusion The perfusion of line pipe;Abovementioned steps are repeated successively to be irrigated all bellowss;
Step 8, demoulding post-processes:
The concrete of lining cutting and the mortar strength of perfusion can be with demouldings, after end head formwork is removed, by exposed mixed after reaching 70% It is cut off using sanding machine the bellows end on solidifying soil surface.
2. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 2, When vault concrete is greater than 80cm, 2~3 layers of bellows are buried.
3. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 2, Joint bar uses electric hammer pore-creating, anchoring adhesive anchoring.
4. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 3, Lining trolley is run to before the hole section for needing lining cutting, installs the built-in fittings such as hole section reinforcing bar, waterstop.
5. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 6, Internal vibration specific steps are as follows: be inserted directly into poker vibrator to bellows from the bellows nozzle for being pierced by end head formwork Tube bottom opens poker vibrator, vibrates 20s at tube bottom position, and laitance and not occurs in the concrete material surface at place of being vibrated There is bubble to emerge stopping again;Then it is pulled outwardly 50cm, vibrate 20s again, operates repeatedly, until poker vibrator is whole It pulls out, this root bellows vibrates end;A piece bellows vibrates next bellows again after vibrating, and repeats above operation, The completion until all bellowss all vibrate.
6. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 7, Nozzle should be blocked after the completion of bellows perfusion mortar tight.
7. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 1 Further include the steps that being acquired the data of tunnel Internal periphery using tunnel cross-section instrument;Lining cutting mould can be influenced in tunnel The protrusion of plate polish processing in favor of the installation of lining shuttering;Filling out for concrete is carried out to the depressed section in tunnel It is filled with after preventing lining shuttering from installing and forms gap.
8. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 4 Further include the steps that carrying out pressure monitoring to the concrete poured.
9. the construction method of tunnel vault concrete vibrating according to claim 1, which is characterized in that in the step 4, Casting concrete includes: 300-380 parts of portland cement, 850-1000 parts of aggregate, 450-550 parts of sand, waterglass 200-220 Part, 8-12 parts, II grade 50-150 parts of flyash of glass bead, 40-80 parts of steel fibre, the third 3-5 parts solidifying, poly-carboxylic high-performance diminishing 2-3 parts of agent, above-mentioned each ingredient is by mass.
CN201910506930.7A 2019-06-12 2019-06-12 Construction method for concrete vibration of tunnel vault Active CN110374630B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910506930.7A CN110374630B (en) 2019-06-12 2019-06-12 Construction method for concrete vibration of tunnel vault

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910506930.7A CN110374630B (en) 2019-06-12 2019-06-12 Construction method for concrete vibration of tunnel vault

Publications (2)

Publication Number Publication Date
CN110374630A true CN110374630A (en) 2019-10-25
CN110374630B CN110374630B (en) 2021-02-26

Family

ID=68250163

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910506930.7A Active CN110374630B (en) 2019-06-12 2019-06-12 Construction method for concrete vibration of tunnel vault

Country Status (1)

Country Link
CN (1) CN110374630B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486054A (en) * 2019-09-10 2019-11-22 山东建筑大学 A kind of steel pipe concrete bracket filling concrete system and its method for filling
CN111274708A (en) * 2020-02-14 2020-06-12 哈尔滨工程大学 Method for predicting penetration distance of multiple-injection spraying of marine diesel engine
CN113738402A (en) * 2021-09-18 2021-12-03 湖北祖德水利水电工程有限公司 Support system and method for hydraulic tunnel construction
CN114633341A (en) * 2022-03-30 2022-06-17 江西工业贸易职业技术学院 Be used for precast building assembly to use concrete vibrator
CN114633341B (en) * 2022-03-30 2024-04-26 江西工业贸易职业技术学院 Be used for precast concrete vibrator for building assembly

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005213868A (en) * 2004-01-29 2005-08-11 Maeda Corp Vibrator system for concrete compaction and lining concrete compaction method for tunnel
JP2015183462A (en) * 2014-03-25 2015-10-22 鹿島建設株式会社 Concrete compaction apparatus and concrete compaction method
CN106640135A (en) * 2016-12-08 2017-05-10 中铁十四局集团第二工程有限公司 Automatic vibrating system used in tunnel secondary lining concrete applying and vibrating method
CN107448217A (en) * 2017-09-25 2017-12-08 中铁十七局集团第工程有限公司 A kind of practical tunnel lining trolley vibrating system
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN109707409A (en) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 A kind of tunnel double-lining concrete vibrating system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005213868A (en) * 2004-01-29 2005-08-11 Maeda Corp Vibrator system for concrete compaction and lining concrete compaction method for tunnel
JP2015183462A (en) * 2014-03-25 2015-10-22 鹿島建設株式会社 Concrete compaction apparatus and concrete compaction method
CN106640135A (en) * 2016-12-08 2017-05-10 中铁十四局集团第二工程有限公司 Automatic vibrating system used in tunnel secondary lining concrete applying and vibrating method
CN107448217A (en) * 2017-09-25 2017-12-08 中铁十七局集团第工程有限公司 A kind of practical tunnel lining trolley vibrating system
CN108194136A (en) * 2017-12-31 2018-06-22 中铁十九局集团第二工程有限公司 Lining construction method
CN109026065A (en) * 2018-07-25 2018-12-18 中铁十六局集团有限公司 A kind of Tunnel Second Lining zero-fault construction method
CN109707409A (en) * 2019-01-11 2019-05-03 中铁十一局集团第四工程有限公司 A kind of tunnel double-lining concrete vibrating system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110486054A (en) * 2019-09-10 2019-11-22 山东建筑大学 A kind of steel pipe concrete bracket filling concrete system and its method for filling
CN111274708A (en) * 2020-02-14 2020-06-12 哈尔滨工程大学 Method for predicting penetration distance of multiple-injection spraying of marine diesel engine
CN111274708B (en) * 2020-02-14 2022-04-29 哈尔滨工程大学 Method for predicting penetration distance of multiple-injection spraying of marine diesel engine
CN113738402A (en) * 2021-09-18 2021-12-03 湖北祖德水利水电工程有限公司 Support system and method for hydraulic tunnel construction
CN113738402B (en) * 2021-09-18 2024-04-09 湖北祖德水利水电工程有限公司 Supporting system and method for hydraulic tunnel construction
CN114633341A (en) * 2022-03-30 2022-06-17 江西工业贸易职业技术学院 Be used for precast building assembly to use concrete vibrator
CN114633341B (en) * 2022-03-30 2024-04-26 江西工业贸易职业技术学院 Be used for precast concrete vibrator for building assembly

Also Published As

Publication number Publication date
CN110374630B (en) 2021-02-26

Similar Documents

Publication Publication Date Title
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN110374630A (en) A kind of construction method of tunnel vault concrete vibrating
CN111074943A (en) Construction method for integrally casting inspection well shaping steel mould in situ
CN102937027A (en) Construction method of edge top arch and bottom arch of concrete pouring tunnel
CN103643971B (en) Tunnel invert sizing end mould rapid constructing method
CN107059920A (en) Loess formation piping lane construction technology
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN104131502A (en) Construction method for widening road in rapid erection manner
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
CN108560536A (en) The continuous piling wall construction method of Soil-cement
CN109372019A (en) Cable duct original position rest construction method
CN106988339B (en) Sandy gravel stratum piping lane construction technology
CN108487016B (en) Construction method for irregular and accurate elevation concrete pavement of test field
CN110761808A (en) Large-section loess tunnel supporting system and supporting construction method
CN211258631U (en) Loess tunnel basement reinforcement construction structure based on high pressure jet grouting pile
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN110004787A (en) Pier storage yard road concrete surface construction method
CN107989049A (en) A kind of construction method of frame bank protection
CN207974149U (en) Pre-buried skeleton strength core masonry cable duct
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN211038656U (en) Large-section loess tunnel supporting system
CN113481775A (en) Construction method for foam concrete backfilling embankment in karst region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant