CN110552371A - Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method - Google Patents

Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method Download PDF

Info

Publication number
CN110552371A
CN110552371A CN201910815972.9A CN201910815972A CN110552371A CN 110552371 A CN110552371 A CN 110552371A CN 201910815972 A CN201910815972 A CN 201910815972A CN 110552371 A CN110552371 A CN 110552371A
Authority
CN
China
Prior art keywords
lining wall
construction
steel plate
pouring
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910815972.9A
Other languages
Chinese (zh)
Inventor
廖红玉
刘明周
康铀
易新虎
袁哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201910815972.9A priority Critical patent/CN110552371A/en
Publication of CN110552371A publication Critical patent/CN110552371A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention discloses a construction method for eliminating horizontal construction joints of an annular lining wall based on a reverse construction method, wherein when each layer of earthwork is excavated, the construction allowance of a tire membrane is reserved after the lower lining wall layer is excavated to be high, sand is poured and compacted at the bottom of the lining wall after the earthwork at the bottom of the lining wall is initially flat and before a template is installed, a slope with a high outer part and a low inner part is formed by slope repairing, and then an isolation felt and cement mortar are sequentially paved on the sand pouring layer to form a tire membrane; installing a water stop steel plate and embedding a grout supplementing pipe while installing a steel bar framework of the inner lining wall, wherein the upper part of the water stop steel plate is fixed on the upper part and the lower part of the steel bar framework of the inner lining wall through anchoring steel bars and is inserted into the sand-grouting layer, one end of the grout supplementing pipe extends into the sand-grouting layer and is detachably plugged, the other end of the grout supplementing pipe penetrates out of the template in a sealing manner, and grout is supplemented to a gap generated after concrete of the lower inner lining wall is settled through the grout supplementing pipe embedded in the upper inner lining wall, so that a; after the pouring of the interior lining wall is finished, the tire membranes are manually broken. The method eliminates horizontal construction joints.

Description

Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
Technical Field
The invention belongs to the field of municipal construction, and particularly relates to a construction method for eliminating horizontal construction joints of an annular lining wall based on a reverse construction method.
Background
at present, the design and construction of deep foundation pits of municipal water supply and drainage pump houses and the like usually adopt a mode of combining two walls, namely, an underground continuous wall is used as an outer wall, a lining wall of a circular foundation pit for horizontal support is used as an inner wall, the inner wall is of a reinforced concrete structure, reverse construction method construction is usually adopted, namely, the lining wall is constructed layer by layer and step by step from top to bottom according to the design working condition of foundation pit excavation, the construction of the lining wall is immediately carried out every section of excavation, and the lining wall is constructed in sections from top to bottom in the whole, namely, the reverse construction method construction is carried out.
based on the annular inner lining wall of the reverse construction method, a larger horizontal construction joint is easily generated between the lower inner lining wall and the upper inner lining wall due to the contraction action of concrete.
Disclosure of Invention
The invention aims to provide a construction method for eliminating horizontal construction joints of an annular lining wall based on a reverse construction method, which increases the strength, rigidity and stability of a template, improves the pouring quality, saves the use amount of manpower and machinery, strengthens the treatment on the horizontal construction joints, and improves the appearance quality, integrity and waterproofness of the lining wall.
The technical scheme adopted by the invention is as follows:
A construction method for eliminating horizontal construction joints of annular interior lining walls based on a reverse construction method comprises the following steps:
S1, adopting a bed mould as a bottom mould when pouring the lining wall, namely when excavating each layer of earthwork, reserving the construction allowance of the bed mould after excavating the lining wall layer of the next road to be high, pouring sand and compacting at the bottom of the lining wall after the earthwork at the bottom of the lining wall is initially flat and before installing a template, repairing a slope to form a slope surface with a high outside and a low inside, and then sequentially paving an isolation felt and cement mortar on the sand pouring layer to form the bed mould;
s2, after a lining wall is poured, grouting is carried out on a horizontal construction joint, namely, a water stop steel plate is installed and a grouting pipe is embedded while a steel bar framework of the lining wall is installed, the upper part of the water stop steel plate is fixed on the upper part and the lower part of the steel bar framework of the lining wall through anchoring steel bars, a sand filling layer is inserted into the upper part and the lower part of the steel bar framework of the lining wall, one end of the grouting pipe extends into the sand filling layer and is detachably plugged, a penetrating template with the other end sealed is arranged at the other end, the grouting pipes are distributed along the water stop steel plate and are positioned on two sides of the water stop steel plate, grouting is carried out on a gap generated;
and S3, after the pouring of the interior lining wall is finished, manually breaking the tire membranes.
Furthermore, the installation method of the water-stop steel plate comprises the steps of starting to install the water-stop steel plate after the lining wall is bound by the steel bars on the side of the underground diaphragm wall, lofting and marking the position of the water-stop steel plate, welding the anchoring steel bars on the inner side of the lining wall to position the water-stop steel plate, arranging and installing the water-stop steel plate according to the anchoring steel bars, fully welding the anchoring steel bars and the water-stop steel plate on a single side, fully welding the water-stop steel plate and the water-stop steel plate on a double side in an overlapping mode, and welding the anchoring steel bars on the outer side of the lining wall to clamp the.
Furthermore, when the interior lining wall is poured, firstly, the slump is checked, then, a section of string tube is connected to the end of the pump tube and extends into the template, workers are responsible for adjusting the position of the outlet of the string tube, concrete is poured in layers, a certain thickness is poured on each layer, pouring is carried out along one circle from one end, a vibrating pump is inserted to vibrate and compact along with the concrete pouring sequence, and concrete pouring on each layer is continuously carried out until all the interior lining walls on one layer are poured.
Further, when the steel bars on the outer side of the inner lining wall are dense, cement mortar is poured through the chute device.
And further, before the lining wall is poured, the bottom of the upper lining wall is roughened, cleaned and brushed with cement mortar, and then pouring is carried out.
furthermore, before the lining wall is poured, a feed opening is arranged at the top of the template, the upper part of the feed opening is higher than the bottom opening of the lining wall in the upper passage and the distance between the upper part of the feed opening and the wall surface of the lining wall in the upper passage can ensure pouring and vibrating construction, and the redundant concrete at the feed opening is chiseled and repaired before the concrete of the lining wall is initially set.
Furthermore, when the inner lining wall is poured to be large-volume concrete, a cooling water pipe is pre-buried in the inner lining wall, a temperature measuring point is arranged, and the cooling water pipe is installed on a steel bar framework of the inner lining wall.
Furthermore, before the template is installed, the earthwork at the bottom of the template is leveled, and a concrete cushion is arranged to ensure the position and elevation of the template.
The invention has the beneficial effects that:
The bed mould formed by the sand pouring layer, the isolation asphalt felt and the cement mortar is used as the bottom mould, so that the strength, the rigidity and the stability of the template are improved, the slope surface is favorable for the compact pouring of the concrete at the joint of the lining wall and the underground continuous wall, and the pouring quality of the concrete is improved; the connector reserved on the lower wall can be protected by adopting the sand filling layer, the strength of the tire membrane is improved by adopting the isolation felt and the cement mortar, the precipitation of water in concrete is effectively prevented, the accuracy of the mix proportion of the concrete is ensured, the surface of the tire membrane is ensured to be flat, and the linear parallel and regular outside the horizontal construction joint is realized; the process of punching the bottom die to leave the connector and the water stop steel plate is reduced, the tire mold can be easily broken, the use amount of manpower and machinery is saved, the material cost is saved, and the construction progress is accelerated; the treatment to horizontal construction joints is strengthened, and the appearance quality, integrity and waterproofness of the interior lining wall are improved.
Drawings
Fig. 1 is a schematic view of an embodiment of the present invention (for convenience of observation, the reinforcing cage of the interior lining wall, the diagonal tie bars between the tension rods, the anchor bars, and the cooling water pipes are not shown).
Fig. 2 is a schematic view of the installation of the water stop steel plate in the embodiment of the invention.
In the figure: 1-underground diaphragm wall; 2-a connector; 3-water stop steel plate; 4-lining wall in upper road; 5-slurry supplementing pipe; 6-operating the platform; 7-diagonal draw bars; 8-a pull rod; 9-template; 10-vertical reinforcing pipes; 11-horizontal reinforcement pipes; 12-a concrete cushion; 13-isolation linoleum; 14-cement mortar; 15-sand-filling layer; 16-steel reinforcement framework (vertical steel reinforcement) of the inner lining wall; 17-anchoring the reinforcing steel bars.
Detailed Description
The invention is further described below with reference to the figures and examples.
As shown in fig. 1, a construction method for eliminating horizontal construction joints of annular interior lining walls based on a reverse construction method comprises the following steps:
S1, adopting a tire membrane as a bottom mould during pouring of a lining wall, namely reserving a construction allowance of the tire membrane after the lining wall layer of a lower road is dug to be high during each layer of earthwork excavation, pouring sand and compacting at the bottom of the lining wall (in the embodiment, yellow sand with the fineness modulus of 2.4-2.9 and a 10-20cm sand pouring layer 15 are adopted to sprinkle water to enable the sand to naturally settle and compact) after the earthwork at the bottom of the lining wall is initially flat and before a template 9 is installed), repairing a slope to form a slope surface with a high outer part and a low inner part (in the embodiment, the slope surface has a gradient of 5-10%), and then sequentially paving an isolation felt 13 and cement mortar 14 on the sand pouring layer 15 (when reinforcing steel bars on the outer side of the lining wall are compacted, pouring the cement mortar through a chute device, the slope surface height of the cement mortar is controlled at the center of a water stop steel plate, and;
S2, after pouring the lining wall, performing grout filling on the horizontal construction joint, namely installing a water stop steel plate 3 and embedding a grout filling pipe 5 while installing a steel bar framework 16 of the lining wall, wherein the upper part of the water stop steel plate 3 is fixed on the upper part and the lower part of the steel bar framework 16 of the lining wall through an anchoring steel bar 17 (in the embodiment, an elbow steel bar with the diameter of phi 16 is adopted, and the anchoring interval is 2m), a sand filling layer 15 is inserted into the upper part and the lower part of the steel bar framework 16 of the lining wall (the half depth effect is achieved), one end of the grout filling pipe 5 extends into the sand filling layer 15 and is generally detachably plugged through an adhesive tape, a penetrating template 9 with the other end sealed is arranged at the other end, the grout filling pipe 5 is distributed along the water stop steel plate 3 (in the embodiment, the adjacent interval is 8m) and is arranged at two sides of the water stop steel plate 3, and grout filling is performed on, Drilling sampling, pressurized water inspection, seam face gouging inspection and the like, and otherwise, adopting repeated grouting measures to eliminate horizontal construction seams;
and S3, after the pouring of the interior lining wall is finished, manually breaking the tire membranes.
In the invention, the bed mould formed by the sand pouring layer 15, the isolation asphalt felt 13 and the cement mortar 14 is used as the bottom mould, so that the strength, the rigidity and the stability of the template are increased, the slope surface is favorable for the compact pouring of the concrete at the joint of the lining wall and the underground continuous wall 1, and the pouring quality of the concrete is improved; the connector 2 reserved on the lower wall can be protected by adopting the sand filling layer 15, the strength of the tire membrane is improved by adopting the isolation felt 13 and the cement mortar 14, the precipitation of water in concrete is effectively prevented, the accuracy of the mix proportion of the concrete is ensured, the surface of the tire membrane is ensured to be flat, and the linear parallel and neat outside the horizontal construction joint is enabled to be regular; the process of punching the bottom die to leave the connector and the water stop steel plate 3 is reduced, the tire mold can be easily broken, the use amount of manpower and machinery is saved, the material cost is saved, and the construction progress is accelerated; the treatment to horizontal construction joints is strengthened, and the appearance quality, integrity and waterproofness of the interior lining wall are improved.
In this embodiment, before pouring the interior lining wall, the bottom of the upper interior lining wall 4 is roughened, cleaned and brushed with cement mortar, and then poured, so as to improve the combination effect.
In this embodiment, the method for installing the water-stopping steel plate 3 includes, after the lining wall is bound by the ground connection wall side steel bars 16, installing the water-stopping steel plate 3, marking the position of the water-stopping steel plate 3 by lofting (in this embodiment, every 2 meters), welding the anchoring steel bars 17 to the lining wall inner side steel bars 16 (in this embodiment, elbow steel bars with a diameter of phi 16 are used, and the anchoring interval is 2m) to position the water-stopping steel plate 3, then arranging and installing the water-stopping steel plate 3 according to the anchoring steel bars 17, performing single-side full welding on the anchoring steel bars 17 and the water-stopping steel plate 3, performing double-side full welding on the lap joint of the water-stopping steel plate 3 and the water-stopping steel plate 3, and after the lining wall outer side steel bars 16 are installed, welding the anchoring steel bars 17 to the lining wall outer side steel bars 16 to clamp.
In this embodiment, when pouring the interior wall lining, check the slump earlier, then insert one section cluster bobbin in the pump line end and stretch into in the template 9, be responsible for adjusting cluster bobbin exit position by the workman, the concrete is poured in layers, and every layer is pour a certain thickness (in this embodiment, 500mm), begins to pour along the round from one end, and the insertion vibrator pump closely follows the concrete pouring order and vibrates closely, and every layer of concrete pouring keeps going on continuously, and all pouring of one deck interior wall are accomplished.
As shown in fig. 1, in this embodiment, before the lining wall is poured, a blanking opening is provided at the top of the formwork 9 (in this embodiment, the top of the formwork 9 is provided with a blanking opening with a width of 1.2m and a height of 0.5m every 1.2m or so, that is, the width of a single complete formwork 9 is provided), the upper part of the blanking opening is higher than the bottom opening of the lining wall in the upper run (in this embodiment, not less than 20cm) and the distance (not less than 30cm) from the wall surface of the lining wall 4 in the upper run can ensure the pouring and vibrating construction (i.e., ensure the penetration of the pump pipe and the vibrating tool and ensure the horizontal and longitudinal deepest concrete vibration in place), and the excess concrete at the blanking opening is chiseled and repaired (generally, cement mortar is applied) before the concrete of the lining. The setting of feed opening makes pouring and vibration construction convenient, can guarantee the quality and the work efficiency of concrete pouring construction, and feed opening concrete is higher than inside concrete, forms the side pressure, can carry out secondary vibration when the initial set, has guaranteed closely knit.
In this embodiment, when the lining wall is poured to be large-volume concrete, the cooling water pipe is embedded in the lining wall and the temperature measuring point is set, and the cooling water pipe is installed on the steel reinforcement framework of the lining wall.
as shown in fig. 1, in this embodiment, before installing the formwork 9, the bottom earthwork of the formwork is leveled, and a concrete cushion 12 (in this embodiment, the C20 concrete cushion 12 with a width of 30cm and a thickness of 15 cm) is leveled and set, so as to ensure the position and the elevation of the formwork 9 (contour line lofting of the formwork 9 is performed on the concrete cushion 12, and marking is performed to position the formwork).
It will be understood that modifications and variations can be made by persons skilled in the art in light of the above teachings and all such modifications and variations are intended to be included within the scope of the invention as defined in the appended claims.

Claims (8)

1. A construction method for eliminating horizontal construction joints of annular interior lining walls based on a reverse construction method is characterized in that: comprises the steps of (a) carrying out,
S1, adopting a bed mould as a bottom mould when pouring the lining wall, namely when excavating each layer of earthwork, reserving the construction allowance of the bed mould after excavating the lining wall layer of the next road to be high, pouring sand and compacting at the bottom of the lining wall after the earthwork at the bottom of the lining wall is initially flat and before installing a template, repairing a slope to form a slope surface with a high outside and a low inside, and then sequentially paving an isolation felt and cement mortar on the sand pouring layer to form the bed mould;
S2, after a lining wall is poured, grouting is carried out on a horizontal construction joint, namely, a water stop steel plate is installed and a grouting pipe is embedded while a steel bar framework of the lining wall is installed, the upper part of the water stop steel plate is fixed on the upper part and the lower part of the steel bar framework of the lining wall through anchoring steel bars, a sand filling layer is inserted into the upper part and the lower part of the steel bar framework of the lining wall, one end of the grouting pipe extends into the sand filling layer and is detachably plugged, a penetrating template with the other end sealed is arranged at the other end, the grouting pipes are distributed along the water stop steel plate and are positioned on two sides of the water stop steel plate, grouting is carried out on a gap generated;
And S3, after the pouring of the interior lining wall is finished, manually breaking the tire membranes.
2. The reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: the water-stopping steel plate is installed after the lining wall is bound by the steel bars on the side of the underground diaphragm wall, the position of the water-stopping steel plate is marked by lofting, the anchoring steel bars are welded on the steel bars on the inner side of the lining wall until the water-stopping steel plate is positioned, then the water-stopping steel plate is arranged and installed according to the anchoring steel bars, the anchoring steel bars and the water-stopping steel plate are fully welded on one side, the lap joint of the water-stopping steel plate and the water-stopping steel plate is fully welded on the two sides, and after the steel bars on the outer side of the lining wall are installed, the anchoring steel bars are welded on the steel bars on the.
3. The reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: when the lining wall is poured, firstly, the slump is checked, then, a section of string tube is connected to the end of the pump tube and extends into the template, a worker is responsible for adjusting the position of the outlet of the string tube, concrete is poured in layers, each layer is poured with a certain thickness, pouring is carried out along one circle from one end, a vibration pump is inserted to vibrate and compact along with the concrete pouring sequence, and each layer of concrete pouring is kept continuously until the whole lining wall in one layer is poured.
4. The reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: when the reinforcing steel bars on the outer side of the inner lining wall are dense, cement mortar is poured through the chute device.
5. The reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: before the lining wall is poured, the bottom of the upper lining wall is roughened, cleaned and brushed with cement mortar, and then pouring is carried out.
6. the reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: before the lining wall is poured, a feed opening is arranged at the top of the template, the upper part of the feed opening is higher than the bottom opening of the lining wall in the upper passage and the distance between the upper part of the feed opening and the wall surface of the lining wall in the upper passage can ensure pouring and vibrating construction, and the redundant concrete at the feed opening is chiseled and repaired before the concrete of the lining wall is initially set.
7. The reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: when the inner lining wall is poured to be large-volume concrete, cooling water pipes are pre-buried in the inner lining wall, temperature measuring points are arranged, and the cooling water pipes are installed on a steel bar framework of the inner lining wall.
8. the reverse-construction-based annular interior lining wall construction method for eliminating horizontal construction joints according to claim 1, wherein: before the template is installed, the earthwork at the bottom of the template is leveled, a concrete cushion is leveled, and the position and the elevation of the template are guaranteed.
CN201910815972.9A 2019-08-30 2019-08-30 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method Pending CN110552371A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910815972.9A CN110552371A (en) 2019-08-30 2019-08-30 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910815972.9A CN110552371A (en) 2019-08-30 2019-08-30 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method

Publications (1)

Publication Number Publication Date
CN110552371A true CN110552371A (en) 2019-12-10

Family

ID=68738594

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910815972.9A Pending CN110552371A (en) 2019-08-30 2019-08-30 Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method

Country Status (1)

Country Link
CN (1) CN110552371A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945738A (en) * 2020-07-21 2020-11-17 佛山市鸿博盾构物资有限公司 Shaft construction method
CN113585276A (en) * 2021-04-07 2021-11-02 中国建筑一局(集团)有限公司 Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit
CN113756371A (en) * 2021-09-15 2021-12-07 中国二十二冶集团有限公司 Concrete density construction method at horizontal seam of waterproof concrete

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201588207U (en) * 2009-07-21 2010-09-22 中冶天工建设有限公司 Concreting device at construction joints
CN201943086U (en) * 2010-12-29 2011-08-24 中铁四局集团有限公司市政工程分公司 Underground building wall body
CN102733602A (en) * 2011-04-15 2012-10-17 上海建工集团股份有限公司 Hanging-up construction method of air shaft
CN105735344A (en) * 2014-12-08 2016-07-06 中冶天工上海十三冶建设有限公司 Circle ground pit lining wall steel bar colligation support and lining wall reverse building method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201588207U (en) * 2009-07-21 2010-09-22 中冶天工建设有限公司 Concreting device at construction joints
CN201943086U (en) * 2010-12-29 2011-08-24 中铁四局集团有限公司市政工程分公司 Underground building wall body
CN102733602A (en) * 2011-04-15 2012-10-17 上海建工集团股份有限公司 Hanging-up construction method of air shaft
CN105735344A (en) * 2014-12-08 2016-07-06 中冶天工上海十三冶建设有限公司 Circle ground pit lining wall steel bar colligation support and lining wall reverse building method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111945738A (en) * 2020-07-21 2020-11-17 佛山市鸿博盾构物资有限公司 Shaft construction method
CN113585276A (en) * 2021-04-07 2021-11-02 中国建筑一局(集团)有限公司 Mounting and dismounting device and construction method for bottom membrane of reverse lining wall of deep foundation pit
CN113756371A (en) * 2021-09-15 2021-12-07 中国二十二冶集团有限公司 Concrete density construction method at horizontal seam of waterproof concrete

Similar Documents

Publication Publication Date Title
CN103526770B (en) A kind of construction method of high antiseepage anti-floating pile raft structure
CN111075454B (en) Double-arch tunnel five-hole excavation method
CN101725149B (en) Construction method of long open-cut tunnel
CN111733828A (en) Large-section deep foundation pit fender pile and prestressed anchor cable supporting construction technology
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
CN110952456A (en) Pile type bridge construction process
CN110552371A (en) Construction method for eliminating horizontal construction joints of annular lining wall based on reverse construction method
CN110905523A (en) Subway vertical shaft construction method
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN108867690B (en) Reverse construction method for pile plate retaining wall of large foundation pit
CN201943086U (en) Underground building wall body
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN106609508A (en) Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain
WO2023077552A1 (en) Construction method for foundation pit enclosure and earth excavation
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN203594041U (en) Piled raft structure with good resistance to seepage and buoyancy
CN111042569A (en) Construction method for additionally building linear accelerator machine room in limited space of basement of hospital
CN110607805A (en) Cable tunnel construction method
CN114215090A (en) Construction method of raft and compression pile in closed space
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN115898469A (en) Tunnel secondary lining construction method
CN113266019B (en) Construction method of foundation pit steel pipe support system
CN105464128B (en) Prestress anchorage cable assembled pile plate wall protection construction method
CN115030731A (en) Pilot tunnel construction method in cross tunnel engineering

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191210