CN112046707B - 一种半潜式海洋平台合拢高支撑拆除方法 - Google Patents
一种半潜式海洋平台合拢高支撑拆除方法 Download PDFInfo
- Publication number
- CN112046707B CN112046707B CN202010915274.9A CN202010915274A CN112046707B CN 112046707 B CN112046707 B CN 112046707B CN 202010915274 A CN202010915274 A CN 202010915274A CN 112046707 B CN112046707 B CN 112046707B
- Authority
- CN
- China
- Prior art keywords
- pulling
- support
- high support
- semi
- winch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 18
- 229910000831 Steel Inorganic materials 0.000 claims description 21
- 239000010959 steel Substances 0.000 claims description 21
- 238000003466 welding Methods 0.000 claims description 4
- 238000004140 cleaning Methods 0.000 claims description 3
- 238000005520 cutting process Methods 0.000 claims description 3
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000002360 preparation method Methods 0.000 abstract description 3
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B63—SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
- B63B—SHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING
- B63B75/00—Building or assembling floating offshore structures, e.g. semi-submersible platforms, SPAR platforms or wind turbine platforms
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种半潜式海洋平台合拢高支撑拆除方法,本发明通过拉移将高支撑分成两部分拉移出半潜平台底部,然后通过门座式起重机分解拆除,可减少拆除过程中的交叉作业,降低安全风险,同时对海洋平台自身作业的影响较少,在准备充足的情况下,效率较高。
Description
技术领域
本发明涉及船舶及海工产品制造技术领域,特别涉及一种半潜式海洋平台合拢高支撑拆除方法。
背景技术
半潜式海洋平台具有极强的抗风浪能力、优良的运动性能、巨大的甲板面积和装载容量、高效的作业效率等。其结构形式一般包括:上船体、浮体两个及立柱四个,浮体与上船体之间用立柱连接,左右浮体之间一般通过两个横撑管连接。半潜式海洋平台的建造方式一般采用整体上部船体提升浮体滑移、上船体整体吊装、常规搭积木、浮吊吊装上船体等几种常见的建造合拢方式,而常规搭积木的方式尤为有效,技术相对成熟,成本较低,安全风险小等有点,使用尤为广泛。而常规搭积木的方式合拢半潜式海洋平台,需要采用高支撑为上船体的合拢提供搭载定位的平台,高支撑数量较多,尺寸较大,整体强度要求较高。在上船体全部合拢完成、整体强度刚性满足要求后,合拢高支撑方可拆除。
目前,公知的合拢高支撑拆除方法是采用滑车吊点主吊、汽车吊辅助吊装放倒的方式拆除,此方案主要的困难是:
1)半潜平台上船体反底需与设置大量的吊点,用于主吊放倒高支撑,吊点的焊接及拆除对反底油漆破坏较多,影响后期生产进度。
2)合拢高支撑放倒占用场地空间较大,但半潜平台底部空间狭小,高支撑数量较多,在放倒过程中风险较大,极易与其它高支撑或平台结构相碰,同时交叉作业较多,安全风险大。
发明内容
本发明的目的在于提供一种半潜式海洋平台合拢高支撑拆除方法。
本发明采用的技术方案是:
一种半潜式海洋平台合拢高支撑拆除方法,其特征在于:包括以下步骤:
步骤1:根据高支撑拉移路径,将沿线的地面整平,相关突出地筋等清理干净,防止拉移过程中影响连续性;
步骤2:根据高支撑的布置特点,采用钢管或方管、钢丝绳等将高支撑底部和上部连接起来,分两部分做成艏部7组支撑、艉部9组支撑,高支撑下部前端布置拉耳,钢管或方管与高支撑底部之间采用焊接,高支撑顶部已经有走道平台连接,用钢丝绳将整体绑牢加固;
步骤3:在平台艏部布置拉移绞车装置,绞车与地面固定,通过滑车、卸扣、5m*30t钢丝绳与艏部7组高支撑底部拉耳连接,绞车通过滑车、卸扣、30m*50t钢丝绳与拉耳连接,拉耳需与地面固定;
步骤4:将高支撑顶部支墩割断拆除,高支撑与半潜式海洋平台反底脱离;
步骤5:将艏部7组高支撑通过拉移的方式拉出半潜式海洋平台底部后,拆除拉移绞车装置,采用门座式起重机将艏部高支撑分解拆除;
步骤6:绞车与地面固定,通过滑车、卸扣、5m*30t钢丝绳与艏部9组高支撑底部拉耳连接;
步骤7:将艏部9组高支撑整体拉移出半潜式海洋平台底部后,拆除拉移绞车装置,然后采用门座式起重机将艏部高支撑分解拆除。
本发明的优点:通过拉移将高支撑分成两部分拉移出半潜平台底部,然后通过门座式起重机分解拆除,可减少拆除过程中的交叉作业,降低安全风险,同时对海洋平台自身作业的影响较少,在准备充足的情况下,效率较高。
附图说明
下面结合附图和具体实施方式对本发明作进一步详细叙述。
图1为本发明的装置布置图;
图2为本发明图1中I的放大图。
其中:1、半潜式海洋平台;2、艏部7组高支撑;3、艉部9组支撑;4、绞车;5、卸扣;6、30m*50t钢丝绳;7、滑车;8、拉耳;9、50T*5m钢丝绳。
具体实施方式
如图1-2所示,一种半潜式海洋平台合拢高支撑拆除方法,包括以下步骤:
步骤1:根据高支撑拉移路径,将沿线的地面整平,相关突出地筋等清理干净,防止拉移过程中影响连续性;
步骤2:根据高支撑的布置特点,采用钢管或方管、钢丝绳等将高支撑底部和上部连接起来,分两部分做成艏部7组支撑2、艉部9组支撑3,高支撑下部前端布置拉耳8,钢管或方管与高支撑底部之间采用焊接,高支撑顶部已经有走道平台连接,用钢丝绳将整体绑牢加固;
步骤3:在平台艏部布置拉移绞车装置,绞车4与地面固定,通过滑车7、卸扣5、30m*50t钢丝绳6与艏部7组高支撑2底部拉耳8连接,绞车4通过滑车7、卸扣5、30m*50t钢丝绳6与拉耳8连接,拉耳8需与地面固定;
步骤4:将高支撑顶部支墩割断拆除,高支撑与半潜式海洋平台1反底脱离;
步骤5:将艏部7组高支撑2通过拉移的方式拉出半潜式海洋平台1底部后,拆除拉移绞车装置,采用门座式起重机将艏部高支撑2分解拆除;
步骤6:绞车4与地面固定,通过滑车7、卸扣5、50T*5m钢丝绳9与艏部9组高支撑3底部拉耳8连接;
步骤7:将艏部9组高支撑3整体拉移出半潜式海洋平台1底部后,拆除拉移绞车装置,然后采用门座式起重机将艏部高支撑分解拆除。
本发明通过拉移将高支撑分成两部分拉移出半潜平台底部,然后通过门座式起重机分解拆除,可减少拆除过程中的交叉作业,降低安全风险,同时对海洋平台自身作业的影响较少,在准备充足的情况下,效率较高。
Claims (1)
1.一种半潜式海洋平台合拢高支撑拆除方法,其特征在于:包括以下步骤:
步骤1:根据高支撑拉移路径,将沿线的地面整平,突出地筋清理干净,防止拉移过程中影响连续性;
步骤2:根据高支撑的布置特点,采用钢管或方管、钢丝绳将高支撑底部和上部连接起来,分两部分做成艏部7组支撑、艉部9组支撑,高支撑下部前端布置拉耳,钢管或方管与高支撑底部之间采用焊接,高支撑顶部已经有走道平台连接,用钢丝绳将整体绑牢加固;
步骤3:在平台艏部布置拉移绞车装置,绞车与地面固定,通过滑车、卸扣、30m*50t钢丝绳与艏部7组高支撑底部拉耳连接,绞车通过滑车、卸扣、30m*50t钢丝绳与拉耳连接,拉耳需与地面固定;
步骤4:将高支撑顶部支墩割断拆除,高支撑与半潜式海洋平台反底脱离;
步骤5:将艏部7组高支撑通过拉移的方式拉出半潜式海洋平台底部后,拆除拉移绞车装置,采用门座式起重机将艏部高支撑分解拆除;
步骤6:绞车与地面固定,通过滑车、卸扣、50T*5m钢丝绳与艉部9组高支撑底部拉耳连接;
步骤7:将艉部9组高支撑整体拉移出半潜式海洋平台底部后,拆除拉移绞车装置,然后采用门座式起重机将艉部高支撑分解拆除。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010915274.9A CN112046707B (zh) | 2020-09-03 | 2020-09-03 | 一种半潜式海洋平台合拢高支撑拆除方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010915274.9A CN112046707B (zh) | 2020-09-03 | 2020-09-03 | 一种半潜式海洋平台合拢高支撑拆除方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112046707A CN112046707A (zh) | 2020-12-08 |
CN112046707B true CN112046707B (zh) | 2023-09-05 |
Family
ID=73606823
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010915274.9A Active CN112046707B (zh) | 2020-09-03 | 2020-09-03 | 一种半潜式海洋平台合拢高支撑拆除方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112046707B (zh) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1058828A1 (ru) * | 1982-07-14 | 1983-12-07 | Предприятие П/Я Р-6109 | Способ центровки блоков перед их подачей в сборочную зону при строительстве верхнего корпуса полупогружной платформы |
RU2030504C1 (ru) * | 1991-04-23 | 1995-03-10 | Государственный научно-исследовательский и проектный институт по освоению месторождений нефти и газа "Гипроморнефтегаз" | Способ демонтажа опорного блока сквозной морской стационарной платформы |
US6183165B1 (en) * | 1996-05-23 | 2001-02-06 | Wirth Maschinen-Und Bohrgerate-Fabrik Gmbh | Process and device for separation of pipes or columns fixed in the ground |
CN104527924A (zh) * | 2014-12-19 | 2015-04-22 | 大连船舶重工集团海洋工程有限公司 | 半潜式海洋平台上部甲板合拢支撑专用工装 |
CN105836049A (zh) * | 2016-04-26 | 2016-08-10 | 中国海洋石油总公司 | 张力腿平台的陆地整体合拢工艺 |
CN207944358U (zh) * | 2018-03-03 | 2018-10-09 | 中交第二航务工程局有限公司 | 一种海上钢箱梁吊装快速拆卸支墩 |
CN109468955A (zh) * | 2018-11-12 | 2019-03-15 | 湖南金海钢结构有限公司 | 一种大型桁架拆除工装 |
CN110271975A (zh) * | 2019-06-14 | 2019-09-24 | 中国一冶集团有限公司 | 狭小空间下水中钢平台拆除装置 |
CN111148692A (zh) * | 2018-01-22 | 2020-05-12 | 吴植融 | 直筒式平台筒体甲板与上部设施的建造方法及直筒式平台 |
-
2020
- 2020-09-03 CN CN202010915274.9A patent/CN112046707B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1058828A1 (ru) * | 1982-07-14 | 1983-12-07 | Предприятие П/Я Р-6109 | Способ центровки блоков перед их подачей в сборочную зону при строительстве верхнего корпуса полупогружной платформы |
RU2030504C1 (ru) * | 1991-04-23 | 1995-03-10 | Государственный научно-исследовательский и проектный институт по освоению месторождений нефти и газа "Гипроморнефтегаз" | Способ демонтажа опорного блока сквозной морской стационарной платформы |
US6183165B1 (en) * | 1996-05-23 | 2001-02-06 | Wirth Maschinen-Und Bohrgerate-Fabrik Gmbh | Process and device for separation of pipes or columns fixed in the ground |
CN104527924A (zh) * | 2014-12-19 | 2015-04-22 | 大连船舶重工集团海洋工程有限公司 | 半潜式海洋平台上部甲板合拢支撑专用工装 |
CN105836049A (zh) * | 2016-04-26 | 2016-08-10 | 中国海洋石油总公司 | 张力腿平台的陆地整体合拢工艺 |
CN111148692A (zh) * | 2018-01-22 | 2020-05-12 | 吴植融 | 直筒式平台筒体甲板与上部设施的建造方法及直筒式平台 |
CN207944358U (zh) * | 2018-03-03 | 2018-10-09 | 中交第二航务工程局有限公司 | 一种海上钢箱梁吊装快速拆卸支墩 |
CN109468955A (zh) * | 2018-11-12 | 2019-03-15 | 湖南金海钢结构有限公司 | 一种大型桁架拆除工装 |
CN110271975A (zh) * | 2019-06-14 | 2019-09-24 | 中国一冶集团有限公司 | 狭小空间下水中钢平台拆除装置 |
Non-Patent Citations (1)
Title |
---|
大型海洋平台建造总体合拢技术;刘广辉;于雁云;林焰;姜盛坤;杨霖;;船舶工程(第07期) * |
Also Published As
Publication number | Publication date |
---|---|
CN112046707A (zh) | 2020-12-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101100217A (zh) | 一种海上平台整体建造吊装方法及其专用吊机 | |
KR20150084913A (ko) | 부유식 풍력 터빈의 이송 및 설치를 위한 부유 가능한 이송 및 설치 구조, 부유식 풍력 터빈과 그 이송 및 설치의 방법 | |
CN108726359B (zh) | 一种吊机翻身工艺 | |
CN202911923U (zh) | 一种组合式震源船 | |
CN102642601B (zh) | 双体可移动全回转式起重船 | |
CN101804849A (zh) | 用于海上油气开发的半潜式平台的建造方案 | |
CN201534603U (zh) | 海洋工程双体船 | |
CN104805821B (zh) | 海洋油田天然气压缩处理自升式平台 | |
CN111559473B (zh) | 一种散货船艏部总段的吊装方法 | |
CN102582786A (zh) | 深海浮式平台的建造工艺 | |
KR100940795B1 (ko) | 에어백을 이용한 중량구조물의 이동 및 진수방법 | |
CN114715336A (zh) | 适用于深水的海上风电筒型基础运输安装一体化船舶及安装方法 | |
CN112046707B (zh) | 一种半潜式海洋平台合拢高支撑拆除方法 | |
CN109231026B (zh) | 用于海上风电机组关键零部件的吊装装置 | |
CN203112377U (zh) | 一种海上风电机组分体吊装装置 | |
CN106759203A (zh) | 自升式海洋平台桩腿结构安装合拢的方法 | |
CN111409806B (zh) | 发电机移出方法 | |
CN115057369B (zh) | 一种海上风机安装方法 | |
CN108482586B (zh) | 单桩顶升滑移上船工艺 | |
CN108018778B (zh) | 不通航水域的猫道索架设牵引系统及猫道索快速架设方法 | |
CN113482004A (zh) | 一种海上多筒导管架基础及其风电整机码头下水施工方法 | |
CN113374645A (zh) | 一种海上多筒导管架基础风电机组码头组装方法 | |
CN111962543A (zh) | 一种稳桩平台与母船的快速连接与分离工艺 | |
CN219490976U (zh) | 一种u型漂浮式打桩船 | |
CN213707526U (zh) | 一种半潜式起重船的起重机 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240102 Address after: 226100 room 2, No.1, Xin'anjiang Road, Binjiang street, Haimen District, Nantong City, Jiangsu Province Patentee after: China Merchants Bureau Cruise Manufacturing Co.,Ltd. Patentee after: China Merchants Jinling shipping (Jiangsu) Co.,Ltd. Address before: No.2261, Haimen street, Nantong City, Jiangsu Province Patentee before: China Merchants Bureau Cruise Manufacturing Co.,Ltd. |