CN111980391A - An integral lifting platform and a construction method for a building exterior facade construction platform - Google Patents

An integral lifting platform and a construction method for a building exterior facade construction platform Download PDF

Info

Publication number
CN111980391A
CN111980391A CN202010859882.2A CN202010859882A CN111980391A CN 111980391 A CN111980391 A CN 111980391A CN 202010859882 A CN202010859882 A CN 202010859882A CN 111980391 A CN111980391 A CN 111980391A
Authority
CN
China
Prior art keywords
steel frame
support
construction
building
boom
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010859882.2A
Other languages
Chinese (zh)
Inventor
杜福祥
任志平
王荔
侯春明
赵长江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Co Ltd
China Construction Third Engineering Bureau Sichuan Construction Equipment Co Ltd
Original Assignee
China Construction Third Engineering Bureau Co Ltd
China Construction Third Engineering Bureau Sichuan Construction Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Co Ltd, China Construction Third Engineering Bureau Sichuan Construction Equipment Co Ltd filed Critical China Construction Third Engineering Bureau Co Ltd
Priority to CN202010859882.2A priority Critical patent/CN111980391A/en
Publication of CN111980391A publication Critical patent/CN111980391A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/34Mobile scaffolds; Scaffolds with mobile platforms characterised by supporting structures provided on the roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses an integral hoisting platform, which utilizes an electric hanging basket as a construction platform main body, can realize extension through a suspension arm, and can adjust the distance between the electric hanging basket and a building vertical surface, so that the electric hanging basket can be installed at one time by using the building vertical surface with a structure without dimension, and the electric hanging basket can be used in various different structural shapes, thereby having simple construction, short period and cost saving. According to the building outer facade construction platform building method, the building outer facade construction platform can be built quickly, the building outer facade construction platform building method is suitable for being applied to various building outer facade structures, the construction period is short, the cost is low, the transfer speed is high, and more construction requirements can be met.

Description

一种整体吊运平台及建筑外立面施工平台的搭建方法An integral lifting platform and a construction method for a building exterior facade construction platform

技术领域technical field

本发明属于建筑施工机械技术领域,具体涉及一种整体吊运平台及建筑外立面施工平台的搭建方法。The invention belongs to the technical field of construction machinery, and in particular relates to a construction method for an integral lifting platform and a building exterior facade construction platform.

背景技术Background technique

随着建筑业的飞速发展,建筑装饰风格更加多样,外立面造型更加复杂,室内挑空结构日益增多,如向建筑楼立面外凸的悬挑台等。在外立面幕墙及装饰施工通常采用吊篮作为施工平台。现有普通吊篮配重多,一般采用外挂固定安装的方式,安装后移动困难。一旦遇到外立面造型复杂的建筑需要多次安拆吊篮,就会导致施工投入较大,且工期较长,还会影响其他工序作业。With the rapid development of the construction industry, the architectural decoration styles are more diverse, the exterior facade modeling is more complex, and the interior void structures are increasing, such as the cantilevered platform that protrudes to the building facade. Hanging baskets are usually used as construction platforms in facade curtain wall and decoration construction. The existing ordinary hanging baskets have many weights, and generally adopt the method of external hanging and fixed installation, which is difficult to move after installation. Once a building with a complex façade needs to be installed and dismantled many times, it will result in a large construction investment, a long construction period, and other processes will be affected.

发明内容SUMMARY OF THE INVENTION

本发明提供一种整体吊运平台及建筑外立面施工平台的搭建方法,以解决现有普通吊篮移动困难的弊病,以解决背景技术中的问题。The present invention provides a method for constructing an integral hoisting platform and a building facade construction platform, so as to solve the disadvantage of the difficulty of moving the existing common hanging baskets and solve the problems in the background technology.

本发明的技术方案如下:一种整体吊运平台,包括钢制框架,所述钢制框架上设有伸缩吊运系统;所述伸缩吊运系统包括吊臂和伸缩机构,所述吊臂通过伸缩机构安装在钢制框架上,通过该伸缩机构实现吊臂向远离钢制框架的方向水平自动伸出或向钢制框架水平自动收回;所述电动吊篮设置在吊臂远离钢制框架的端头处。The technical scheme of the present invention is as follows: an integral hoisting platform includes a steel frame on which a telescopic hoisting system is provided; the telescopic hoisting system includes a boom and a telescopic mechanism, and the boom passes through the The telescopic mechanism is installed on the steel frame, and through the telescopic mechanism, the boom can be automatically extended horizontally in the direction away from the steel frame or retracted horizontally to the steel frame; at the end.

进一步:所述伸缩机构包括支撑箱体,所述支撑箱体内设置有若干个支撑组件;每一个所述支撑组件均包括有支撑杆和支撑滑轮,所述支撑滑轮与所述支撑杆或者支撑箱体转动连接;所述吊臂通过支撑组件与所述支撑箱体通过支撑滑轮滚动支撑,以实现吊臂可以沿着支撑箱体水平往复滑动;所述支撑箱体内还安装有驱动电机,所述驱动电机的输出轴上同轴固定套设有驱动齿轮,所述驱动齿轮与所述吊臂啮合;当驱动电机驱动驱动齿轮旋转时,通过驱动齿轮驱动所述吊臂沿着所述支撑箱体往复滑动。Further: the telescopic mechanism includes a support box, and several support components are arranged in the support box; each of the support components includes a support rod and a support pulley, and the support pulley is connected to the support rod or the support box. The jib is rotatably connected; the boom is rolled and supported with the support box through the support assembly through the support pulley, so that the boom can reciprocate horizontally along the support box; a drive motor is also installed in the support box, and the A drive gear is coaxially fixed on the output shaft of the drive motor, and the drive gear meshes with the suspension arm; when the drive motor drives the drive gear to rotate, the suspension arm is driven by the drive gear along the support box. Slide back and forth.

进一步:所述钢制框架上设有两套吊运系统,两套吊运系统的两个吊臂相互平行;每一个吊臂的端头处均安装有吊索,所述电动吊篮通过两个吊臂上的吊索水平悬挂在吊臂上。Further: the steel frame is provided with two sets of hoisting systems, and the two hoisting arms of the two sets of hoisting systems are parallel to each other; a sling is installed at the end of each hoisting arm, and the electric hanging basket passes through the two sets of hoisting systems. The slings on each jib are suspended horizontally on the jib.

进一步:所述吊臂包括主臂和副臂,所述主臂与所述副臂滑动连接;所述主臂位于靠近钢制框架的一侧并与所述支撑箱体滚动支撑,所述副臂位于靠近电动吊篮的一侧;所述主臂和副臂上均开设有限位孔,通过该限位孔可利用螺栓对主臂和副臂的相对滑动进行锁定。Further: the boom includes a main arm and an auxiliary arm, and the main arm is slidably connected to the auxiliary arm; the main arm is located on the side close to the steel frame and is rolled and supported with the support box, and the auxiliary arm is slidably connected to the auxiliary arm. The arm is located on the side close to the electric hanging basket; the main arm and the auxiliary arm are provided with limit holes, through which the relative sliding of the main arm and the auxiliary arm can be locked with bolts.

进一步:所述钢制框架的底部沿竖向设有可调底座支撑,通过该可调底座支撑以实现钢制框架整体上升或下降。Further: the bottom of the steel frame is vertically provided with an adjustable base support, through which the steel frame can be lifted or lowered as a whole.

进一步:所述钢制框架上设有可调顶撑,通过该可调顶撑上升以实现钢制框架与楼顶面的物理硬接触。Further: the steel frame is provided with an adjustable top support, through which the adjustable top support is raised to realize the physical hard contact between the steel frame and the roof surface of the building.

进一步:所述钢制框架底部设有电动滚轮。Further: the bottom of the steel frame is provided with electric rollers.

一种建筑外立面施工平台的搭建方法,其特征在于,应用了如权利要求6中所述的整体吊运平台,该施工方法的具体施工步骤如下:A method of erecting a construction platform for building facades, characterized in that the integral lifting platform as claimed in claim 6 is applied, and the specific construction steps of the construction method are as follows:

步骤一:制定施工计划,根据高层建筑凸出整体楼面的结构尺寸设计吊臂的整体长度,促使副臂吊挂的电动吊篮能够延伸至高层建筑凸出整体楼面的结构位置,并且可自动吊运平台整体的结构尺寸以及强度能够满足设计要求以及施工安全规范要求;Step 1: Formulate a construction plan, design the overall length of the boom according to the structural dimension of the high-rise building protruding from the overall floor, so that the electric gondola suspended by the jib can extend to the structural position where the high-rise building protrudes from the overall floor, and can The overall structural size and strength of the automatic lifting platform can meet the design requirements and construction safety requirements;

步骤二:将可自动吊运平台拆卸成为零部件以后,通过施工电梯或塔吊安装到高层建筑的任意一个施工段区域内的楼顶的楼层以内,该楼层需具有楼地面和楼顶面,以促使可自动吊运平台的顶撑能够与楼顶面实现物理硬接触;Step 2: After the automatic lifting platform is disassembled into parts, it is installed within the floor of the roof in any construction section area of the high-rise building by the construction elevator or tower crane. To enable the top support of the automatic lifting platform to achieve physical hard contact with the top surface of the building;

步骤三:先调整固定钢制框架的位置,然后固定钢制框架,再按照如下顺序对可自动吊运平台进行安装:钢制框架在楼地面上定位→通过旋转可调底座支撑,促使钢制框架脱离楼地面→通过旋转可调顶撑,使可调顶撑向上延伸并与楼顶面抵紧,以实现钢制框架与楼顶面的物理接触→在钢制框架上安装配重框架,并在配重框架按照设计要求放置配重承板→通过葫芦在钢制框架上安装两套伸缩吊运系统,并利用螺栓贯穿主臂和伏笔上的限位孔,以完成主臂与副臂的相对位置固定→利用塔吊将电动吊篮吊运至两套伸缩吊运系统下方,然后利用吊耳和吊索将电动吊篮水平悬挂至两套伸缩吊运系统上;Step 3: First adjust the position of the fixed steel frame, then fix the steel frame, and then install the automatic lifting platform in the following order: Position the steel frame on the floor → support by rotating the adjustable base to promote the steel frame The frame is separated from the floor of the building → by rotating the adjustable roof support, the adjustable roof support can be extended upwards and pressed against the roof surface of the building to realize the physical contact between the steel frame and the roof surface of the building → install the counterweight frame on the steel frame, And place the counterweight bearing plate on the counterweight frame according to the design requirements → install two sets of telescopic hoisting systems on the steel frame through the hoist, and use the bolt to penetrate the limit hole on the main arm and the foreshadowing to complete the main arm and jib The relative position is fixed → use the tower crane to hoist the electric gondola below the two sets of telescopic hoisting systems, and then use the lifting lugs and slings to horizontally suspend the electric gondola to the two sets of telescopic hoisting systems;

步骤四:对未装载货物的电动吊篮进行提升调试,然后完成伸缩吊运系统的同步调试,吊臂的伸缩测试;逐步在电动吊篮上加载货物,记录电动吊篮每次增加货物时的下降值以及状态,完成整体性测试;Step 4: Lift and debug the unloaded electric gondola, then complete the synchronous debug of the telescopic hoisting system and the telescopic test of the boom; gradually load the electric gondola, and record the amount of cargo added to the electric gondola each time. Drop value and status, complete the overall test;

步骤五:待步骤四完成以后,也即在高层建筑非标准层外立面搭建好了施工平台,该施工平台可通过伸缩吊运系统的吊臂的向前或向后伸缩,以实现施工平台与建筑外立面之间的距离调整,以满足建筑非标准层外立面的施工要求。Step 5: After the completion of Step 4, that is, a construction platform is built on the non-standard façade of the high-rise building. The construction platform can be stretched forward or backward through the boom of the telescopic hoisting system to realize the construction platform. The distance from the building facade is adjusted to meet the construction requirements of the building's non-standard layer facade.

有益效果:Beneficial effects:

1、本方案提供了一种整体可吊运平台,利用电动吊篮作为施工平台主体,并且可以通过吊臂实现伸缩,调节电动吊篮与楼立面之间的距离,促使电动吊篮能够使用不用尺寸结构的楼立面,一次安装,使用多种不同结构形状的使用,施工简单,周期短,节约成本。1. This scheme provides an integral hoistable platform, which uses the electric gondola as the main body of the construction platform, and can be extended and retracted through the boom to adjust the distance between the electric gondola and the building facade, so that the electric gondola can be used. Building facades with no size structure can be installed at one time and used with a variety of different structural shapes. The construction is simple, the cycle is short, and the cost is saved.

2、钢制框架通过可调底座支撑和可调顶撑,可以在楼顶上稳定安装,也可以在中间楼层稳定,作为单独的钢制框架稳定所使用组合;同时还可以增加配重框架以及配重承板作为辅助,增强吊运平台整体稳定性,提高安全性;2. The steel frame can be stably installed on the roof through adjustable base support and adjustable top support, and can also be stabilized on the middle floor as a combination of a single steel frame stability; at the same time, a counterweight frame and The counterweight bearing plate is used as an auxiliary to enhance the overall stability of the lifting platform and improve safety;

3、吊运平台在不使用时,将可伸缩吊臂进行收缩,可调底座支撑、可调顶撑放松,即可减小整体占地面积,便于存放;3. When the lifting platform is not in use, the retractable boom is retracted, the adjustable base support and the adjustable top support are loosened, which can reduce the overall floor space and facilitate storage;

4、通过电动滚轮即可实现整体可自动吊运平台的移动;4. The movement of the whole automatic lifting platform can be realized through electric rollers;

5、自动吊运平台在使用前,可根据现场实际情况,调节可伸缩吊臂的长度并固定,以适应不同悬挑长度结构的施工需要;5. Before the automatic hoisting platform is used, the length of the retractable boom can be adjusted and fixed according to the actual situation on site to meet the construction needs of structures with different cantilever lengths;

6、本方案提供的一种建筑外立面施工平台的搭建方法,该方法实现快速搭建建筑外立面施工平台,可根据施工需要在不重新拆装设备的情况下,调节施工平台与楼立面之间的水平距离,同时上下移动施工平台,适合应用于多种建筑外立面构造施工,施工周期短、成本低,转移速度快,可满足较多的施工需求。6. This scheme provides a construction method for a building facade construction platform, which realizes the rapid construction of a building facade construction platform, and can adjust the construction platform and the building according to the needs of construction without disassembling and assembling equipment. The horizontal distance between the surfaces, and the construction platform is moved up and down at the same time, it is suitable for the construction of various building facades, with short construction period, low cost, and fast transfer speed, which can meet more construction needs.

附图说明Description of drawings

图1为本发明中吊运平台的立体结构示意图;Fig. 1 is the three-dimensional structure schematic diagram of the hoisting platform in the present invention;

图2为图1的正视结构示意图。FIG. 2 is a schematic front view of the structure of FIG. 1 .

具体实施方式Detailed ways

下面结合附图和实施例对本发明作进一步说明:Below in conjunction with accompanying drawing and embodiment, the present invention will be further described:

如图1和图2所示,本发明公开了一种整体吊运平台,包括钢制框架1。以钢制框架1作为支撑主体,在钢制框架1内安装滚轮驱动电机2a,并在钢制框架1的底部安装有电动滚轮2。滚轮驱动电机2a属于电动滚轮2的一部分,由滚轮驱动电机2a驱动电动滚轮2行驶,以便于对钢制框架1进行移动。As shown in FIG. 1 and FIG. 2 , the present invention discloses an integral lifting platform including a steel frame 1 . The steel frame 1 is used as a supporting body, a roller driving motor 2 a is installed in the steel frame 1 , and an electric roller 2 is installed at the bottom of the steel frame 1 . The roller driving motor 2 a is a part of the electric roller 2 , and the electric roller 2 is driven by the roller driving motor 2 a to travel, so as to move the steel frame 1 .

钢制框架1上安装有配重框架3,配重框架3上可以搁置配重承板4,如本实施例中,就在配重框架3上搁置了配重承板4,进而增加钢制框架1的稳定性。配重框架3的底部还安装有可调底座支撑5。可调底座支撑5沿竖向设置,并且可调底座支撑5与钢制框架1螺纹连接。当钢制框架1通过可调底座支撑5在楼地面上时,通过旋转可调底座支撑5,可以促使钢制框架1整体上升或者下降。A counterweight frame 3 is installed on the steel frame 1, and a counterweight support plate 4 can be placed on the counterweight frame 3. In this embodiment, the counterweight support plate 4 is placed on the counterweight frame 3, and the steel Stability of frame 1. An adjustable base support 5 is also installed on the bottom of the counterweight frame 3 . The adjustable base support 5 is arranged vertically, and the adjustable base support 5 is threadedly connected with the steel frame 1 . When the steel frame 1 is on the floor through the adjustable base support 5, by rotating the adjustable base support 5, the steel frame 1 can be urged to rise or fall as a whole.

所述钢制框架1上设有可调顶撑6,可调顶撑6通过调节螺母7与钢制框架1进行连接,具体为:调节螺母7与钢制框架1转动连接,可调顶撑6与调节螺母7螺纹连接,并且可调顶撑6竖向设置。这样可通过调节螺母7调节可调顶撑6的支撑高度。如图2所示,可调顶撑6向上升起以物理硬接触的方式与楼顶面接触,这样也即实现了钢制框架1与楼顶面的物理硬接触。通过可调底座支撑5和可调顶撑6对钢制框架1的共同作用,相互配合,进而促使钢制框架1能够非常稳定的受到楼顶面和楼地面的作用支撑。需要说明的是:可调底座支撑5与可调顶撑6的安装结构可以是相同的,他们在本案中虽然名称不同,但是所起的作用基本相同,只是在不同方向上对钢制框架1进行稳定支撑。The steel frame 1 is provided with an adjustable top support 6, and the adjustable top support 6 is connected with the steel frame 1 through an adjustment nut 7. Specifically, the adjustment nut 7 is rotatably connected with the steel frame 1, and the adjustable top support 6 is threadedly connected with the adjusting nut 7, and the adjustable top support 6 is arranged vertically. In this way, the supporting height of the adjustable top support 6 can be adjusted by adjusting the nut 7 . As shown in FIG. 2 , the adjustable roof support 6 is lifted upward to contact with the roof surface in a way of physical hard contact, so that the physical hard contact between the steel frame 1 and the roof surface is realized. Through the joint action of the adjustable base support 5 and the adjustable top support 6 on the steel frame 1, the steel frame 1 can be stably supported by the roof surface and the floor surface. It should be noted that the installation structure of the adjustable base support 5 and the adjustable top support 6 can be the same. Although they have different names in this case, their functions are basically the same. for stable support.

钢制框架1上设有伸缩吊运系统;所述伸缩吊运系统包括吊臂8和伸缩机构9,所述吊臂8通过伸缩机构9安装在钢制框架1上,通过该伸缩机构9实现吊臂8向远离钢制框架1的方向水平自动伸出或向钢制框架1水平自动收回;所述电动吊篮设置在吊臂8远离钢制框架1的端头处。The steel frame 1 is provided with a telescopic hoisting system; the telescopic hoisting system includes a boom 8 and a telescopic mechanism 9 , and the boom 8 is installed on the steel frame 1 through the telescopic mechanism 9 , and is realized by the telescopic mechanism 9 The boom 8 is automatically extended horizontally toward the direction away from the steel frame 1 or retracted horizontally toward the steel frame 1 ; the electric gondola is arranged at the end of the boom 8 away from the steel frame 1 .

所述伸缩机构9包括支撑箱体91,所述支撑箱体91内设置有若干个支撑组件;每一个所述支撑组件均包括有支撑杆93和支撑滑轮92,所述支撑滑轮92与所述支撑杆93或者支撑箱体91转动连接;所述吊臂8通过支撑组件与所述支撑箱体91通过支撑滑轮92滚动支撑,以实现吊臂8可以沿着支撑箱体91水平往复滑动;所述支撑箱体91内还安装有驱动电机94,所述驱动电机94的输出轴上同轴固定套设有驱动齿轮95,所述驱动齿轮95与所述吊臂8啮合;当驱动电机94驱动驱动齿轮95旋转时,通过驱动齿轮95驱动所述吊臂8沿着所述支撑箱体91往复滑动。The telescopic mechanism 9 includes a support box 91, and a number of support components are arranged in the support box 91; each of the support components includes a support rod 93 and a support pulley 92, the support pulley 92 and the The support rod 93 or the support box 91 is rotatably connected; the boom 8 is supported by the support assembly and the support box 91 through the support pulley 92 in rolling support, so that the boom 8 can reciprocate horizontally along the support box 91; A drive motor 94 is also installed in the support box 91, and a drive gear 95 is coaxially fixed and sleeved on the output shaft of the drive motor 94, and the drive gear 95 meshes with the hanger arm 8; when the drive motor 94 drives When the drive gear 95 rotates, the suspension arm 8 is driven by the drive gear 95 to slide back and forth along the support box 91 .

需要说明的是:驱动齿轮95与吊臂8的啮合,所采用的的结构可以是在吊臂8上直接开设齿条96,如图2所示齿条96的安装位置,或者在吊臂8上通过加装齿条96以实现。It should be noted that: the driving gear 95 engages with the boom 8, the adopted structure may be to directly open the rack 96 on the boom 8, as shown in FIG. This is achieved by adding a rack 96.

在本优化的实施例中:钢制框架1上设有两套吊运系统,两套吊运系统的两个吊臂8相互平行;每一个吊臂8的端头处均安装有吊耳12,吊耳12上安装吊索10,所述电动吊篮通过两个吊臂8上的吊索10水平悬挂在吊臂8上。In this optimized embodiment: the steel frame 1 is provided with two sets of hoisting systems, and the two hoisting arms 8 of the two sets of hoisting systems are parallel to each other; the ends of each hoisting arm 8 are provided with lifting lugs 12 , a sling 10 is installed on the lifting lug 12 , and the electric suspended basket is horizontally suspended on the jib 8 through the suspenders 10 on the two jib 8 .

所述吊臂8包括主臂81和副臂82,所述主臂81与所述副臂82滑动连接;所述主臂81位于靠近钢制框架1的一侧并与所述支撑箱体91滚动支撑,所述副臂82位于靠近电动吊篮的一侧;所述主臂81和副臂82上均开设有限位孔83,通过该限位孔83可利用螺栓对主臂81和副臂82的相对滑动进行锁定。在选型时,主臂81和副臂82在本案中均旋转为矩管。需要说明的是:主臂81上并非仅能设置一个副臂82,还可以设置多节嵌套的副臂82,这样就可以极大地增加吊臂8的整体长度。The boom 8 includes a main arm 81 and an auxiliary arm 82, the main arm 81 is slidably connected with the auxiliary arm 82; the main arm 81 is located on the side close to the steel frame 1 and is connected to the support box 91 Rolling support, the auxiliary arm 82 is located on the side close to the electric hanging basket; the main arm 81 and the auxiliary arm 82 are both provided with a limit hole 83, through which the main arm 81 and the auxiliary arm can be bolted to the main arm 81 and the auxiliary arm through the limit hole 83. 82 relative sliding to lock. During the selection, the main arm 81 and the auxiliary arm 82 are both rotated as rectangular tubes in this case. It should be noted that not only one jib 82 can be provided on the main arm 81 , but also multiple nested jibs 82 , which can greatly increase the overall length of the boom 8 .

本案中的电动吊篮,为现有技术中常用的施工机械。电动吊篮包括吊笼11a以及固定在吊笼11a上的提升设备11b。提升吊笼11a通过吊索10安装在吊耳12上,而吊耳12则是安装在副臂82远离主臂81的端头处,通过提升设备11b可以实现电动吊篮上下垂直移动,这个垂直移动的功能则是电动吊篮自身利用提升设备11b完成的,吊臂8仅是为其提供一个着力点也即吊点。The electric hanging basket in this case is a commonly used construction machine in the prior art. The electric gondola includes a gondola 11a and a lifting device 11b fixed on the gondola 11a. The lifting cage 11a is installed on the lifting lug 12 through the sling 10, and the lifting lug 12 is installed at the end of the auxiliary arm 82 away from the main arm 81. The electric suspension basket can be moved vertically up and down by the lifting device 11b. This vertical The moving function is accomplished by the electric gondola itself using the lifting device 11b, and the arm 8 only provides a force point, that is, a hanging point.

下面以具体的实施方式以对本案中的吊运平台的工作原理加以说明:The working principle of the hoisting platform in this case will be described below with specific embodiments:

首先是吊运平台的用途,如将吊运平台作为一种高层建筑非标准层外立面施工平台来进行使用,那么先要搭建这个施工平台。搭建这个施工平台的方法如下:The first is the use of the hoisting platform. If the hoisting platform is used as a non-standard layer facade construction platform for high-rise buildings, then this construction platform must be built first. The method of building this construction platform is as follows:

步骤一:制定施工计划,根据高层建筑凸出整体楼面的结构尺寸设计吊臂8的整体长度,促使副臂82吊挂的电动吊篮能够延伸至高层建筑凸出整体楼面的结构位置,并且可自动吊运平台整体的结构尺寸以及强度能够满足设计要求以及施工安全规范要求;Step 1: formulate a construction plan, design the overall length of the boom 8 according to the structural dimension of the high-rise building protruding from the overall floor, so that the electric hanging basket suspended by the auxiliary arm 82 can be extended to the structural position where the high-rise building protrudes from the overall floor, And the overall structural size and strength of the automatic lifting platform can meet the design requirements and the requirements of construction safety regulations;

步骤二:将可自动吊运平台拆卸成为零部件以后,通过施工电梯或塔吊安装到高层建筑的任意一个施工段区域内的楼顶的楼层以内,该楼层需具有楼地面和楼顶面,以促使可自动吊运平台的顶撑能够与楼顶面实现物理硬接触;Step 2: After the automatic lifting platform is disassembled into parts, it is installed within the floor of the roof in any construction section area of the high-rise building by the construction elevator or tower crane. To enable the top support of the automatic lifting platform to achieve physical hard contact with the top surface of the building;

步骤三:先调整固定钢制框架1的位置,然后固定钢制框架1,再按照如下顺序对可自动吊运平台进行安装:钢制框架1在楼地面上定位→通过旋转可调底座支撑5,促使钢制框架1脱离楼地面→通过旋转可调顶撑6,使可调顶撑6向上延伸并与楼顶面抵紧,以实现钢制框架1与楼顶面的物理接触→在钢制框架1上安装配重框架3,并在配重框架3按照设计要求放置配重承板4→通过葫芦在钢制框架1上安装两套伸缩吊运系统,并利用螺栓贯穿主臂81和伏笔上的限位孔83,以完成主臂81与副臂82的相对位置固定→利用塔吊将电动吊篮吊运至两套伸缩吊运系统下方,然后利用吊耳12和吊索10将电动吊篮水平悬挂至两套伸缩吊运系统上;Step 3: First adjust the position of the fixed steel frame 1, then fix the steel frame 1, and then install the automatic lifting platform in the following order: Position the steel frame 1 on the floor → support 5 by rotating the adjustable base , to push the steel frame 1 off the floor of the building → by rotating the adjustable roof support 6, the adjustable roof support 6 is extended upward and pressed against the roof surface of the building, so as to realize the physical contact between the steel frame 1 and the roof surface of the building → in the steel frame Install the counterweight frame 3 on the steel frame 1, and place the counterweight support plate 4 on the counterweight frame 3 according to the design requirements → install two sets of telescopic hoisting systems on the steel frame 1 through the hoist, and use bolts to penetrate the main arm 81 and The limit hole 83 on the foreshadowing is to complete the relative position fixation of the main arm 81 and the auxiliary arm 82 → use the tower crane to lift the electric gondola to the bottom of the two telescopic lifting systems, and then use the lifting lug 12 and the sling 10 to lift the electric The hanging basket is horizontally suspended on two sets of telescopic hoisting systems;

步骤四:对未装载货物的电动吊篮进行提升调试,然后完成伸缩吊运系统的同步调试,吊臂8的伸缩测试;逐步在电动吊篮上加载货物,记录电动吊篮每次增加货物时的下降值以及状态,完成整体性测试;Step 4: Lift and debug the unloaded electric gondola, then complete the synchronous debugging of the telescopic hoisting system and the telescopic test of the boom 8; gradually load the electric gondola, and record each time the electric gondola adds goods The drop value and state of , complete the overall test;

步骤五:待步骤四完成以后,也即在高层建筑非标准层外立面搭建好了施工平台,该施工平台可通过伸缩吊运系统的吊臂8的向前或向后伸缩,以实现施工平台与建筑外立面之间的距离调整,以满足建筑非标准层外立面的施工要求。Step 5: After Step 4 is completed, that is, a construction platform is built on the outer facade of the non-standard layer of the high-rise building. The construction platform can be stretched forward or backward through the boom 8 of the telescopic lifting system to realize construction. The distance between the platform and the building facade is adjusted to meet the construction requirements of the building's non-standard layer facade.

施工平台搭建完成,吊运平台也即可以开始使用。以该吊运平台安装所在的楼层平面为例,通过驱动电机94驱动驱动齿轮95,然后利用驱动齿轮95驱动吊臂8,促使吊臂8牵引着电动吊篮沿着吊臂8的长方向来回移动,可以调整电动吊篮与楼立面之间的距离,这样当高层建筑的某一层凸出于整体楼立面时,则可以通过吊臂8调整电动吊篮与外凸出的如阳台、凸台或者裙楼楼立面等的尺寸适应。在吊运平台不重新安装的情况下,实现电动吊篮作为施工平台的跨立面施工,节约施工工序、时间以及成本。至于电动吊篮的悬空高度,则是通过电动吊篮自身来完成,因此本案中不再赘述。After the construction platform is completed, the lifting platform can be used. Taking the floor plane where the lifting platform is installed as an example, the driving gear 95 is driven by the driving motor 94, and then the boom 8 is driven by the driving gear 95, so that the boom 8 pulls the electric gondola back and forth along the long direction of the boom 8. Move, the distance between the electric gondola and the building facade can be adjusted, so that when a certain floor of a high-rise building protrudes from the overall building facade, the electric gondola can be adjusted through the boom 8 and the protruding outside such as a balcony , bosses or podium facades, etc. are adapted to the size. Under the condition that the lifting platform is not re-installed, the electric hanging basket can be used as the construction platform for the construction across the façade, which saves the construction process, time and cost. As for the suspended height of the electric hanging basket, it is completed by the electric hanging basket itself, so it will not be repeated in this case.

以上所述仅为本发明的较佳实施例而已,并不以本发明为限制,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (8)

1.一种整体吊运平台,其特征在于:包括钢制框架(1),所述钢制框架(1)上设有伸缩吊运系统;所述伸缩吊运系统包括吊臂(8)和伸缩机构(9),所述吊臂(8)通过伸缩机构(9)安装在钢制框架(1)上,通过该伸缩机构(9)实现吊臂(8)向远离钢制框架(1)的方向水平自动伸出或向钢制框架(1)水平自动收回;所述电动吊篮设置在吊臂(8)远离钢制框架(1)的端头处。1. An integral hoisting platform, characterized in that it comprises a steel frame (1), and a telescopic hoisting system is provided on the steel frame (1); the telescopic hoisting system comprises a boom (8) and A telescopic mechanism (9), the boom (8) is mounted on the steel frame (1) through the telescopic mechanism (9), and the boom (8) moves away from the steel frame (1) through the telescopic mechanism (9). The electric hanging basket is arranged at the end of the boom (8) away from the steel frame (1) and automatically extends horizontally or retracts horizontally toward the steel frame (1). 2.根据权利要求1所述的一种整体吊运平台,其特征在于:所述伸缩机构(9)包括支撑箱体(91),所述支撑箱体(91)内设置有若干个支撑组件;每一个所述支撑组件均包括有支撑杆(93)和支撑滑轮(92),所述支撑滑轮(92)与所述支撑杆(93)或者支撑箱体(91)转动连接;所述吊臂(8)通过支撑组件与所述支撑箱体(91)通过支撑滑轮(92)滚动支撑,以实现吊臂(8)可以沿着支撑箱体(91)水平往复滑动;所述支撑箱体(91)内还安装有驱动电机(94),所述驱动电机(94)的输出轴上同轴固定套设有驱动齿轮(95),所述驱动齿轮(95)与所述吊臂(8)啮合;当驱动电机(94)驱动驱动齿轮(95)旋转时,通过驱动齿轮(95)驱动所述吊臂(8)沿着所述支撑箱体(91)往复滑动。2 . An integral lifting platform according to claim 1 , wherein the telescopic mechanism ( 9 ) comprises a support box ( 91 ), and a plurality of support components are arranged in the support box ( 91 ). 3 . ; Each of the support assemblies includes a support rod (93) and a support pulley (92), and the support pulley (92) is rotatably connected with the support rod (93) or the support box (91); the hanging The arm (8) is rolled and supported by the support assembly and the support box (91) through the support pulley (92), so that the boom (8) can reciprocate horizontally along the support box (91); the support box A drive motor (94) is also installed in the (91), and a drive gear (95) is fixedly sleeved on the output shaft of the drive motor (94) coaxially. ) meshes; when the drive motor (94) drives the drive gear (95) to rotate, the suspension arm (8) is driven to reciprocate and slide along the support box (91) through the drive gear (95). 3.根据权利要求2所述的一种整体吊运平台,其特征在于:所述钢制框架(1)上设有两套吊运系统,两套吊运系统的两个吊臂(8)相互平行;每一个吊臂(8)的端头处均通过吊耳(12)安装有吊索(10),所述电动吊篮通过两个吊臂(8)上的吊索(10)水平悬挂在吊臂(8)上。3. An integral hoisting platform according to claim 2, characterized in that: the steel frame (1) is provided with two sets of hoisting systems, and the two hoisting arms (8) of the two sets of hoisting systems parallel to each other; a sling (10) is installed at the end of each boom (8) through a lifting lug (12), and the electric hanging basket is leveled by the slings (10) on the two booms (8). Suspended on the boom (8). 4.根据权利要求1至3中任一项所述的一种整体吊运平台,其特征在于:所述吊臂(8)包括主臂(81)和副臂(82),所述主臂(81)与所述副臂(82)滑动连接;所述主臂(81)位于靠近钢制框架(1)的一侧并与所述支撑箱体(91)滚动支撑,所述副臂(82)位于靠近电动吊篮的一侧;所述主臂(81)和副臂(82)上均开设有限位孔(83),通过该限位孔(83)可利用螺栓对主臂(81)和副臂(82)的相对滑动进行锁定。4. An integral lifting platform according to any one of claims 1 to 3, characterized in that: the boom (8) comprises a main arm (81) and a secondary arm (82), and the main arm (82) (81) is slidably connected with the auxiliary arm (82); the main arm (81) is located on the side close to the steel frame (1) and is rolled and supported with the support box (91). 82) is located on the side close to the electric suspended basket; the main arm (81) and the auxiliary arm (82) are provided with limit holes (83), through which the main arm (81) can be connected to the main arm (81) by bolts ) and the relative sliding of the jib (82) to lock. 5.根据权利要求4所述的一种整体吊运平台,其特征在于:所述钢制框架(1)的底部沿竖向设有可调底座支撑(5),通过该可调底座支撑(5)以实现钢制框架(1)整体上升或下降。5. An integral lifting platform according to claim 4, characterized in that: the bottom of the steel frame (1) is vertically provided with an adjustable base support (5), through which the adjustable base support ( 5) In order to realize the overall rise or fall of the steel frame (1). 6.根据权利要求5所述的一种整体吊运平台,其特征在于:所述钢制框架(1)上设有可调顶撑(6),通过该可调顶撑(6)上升以实现钢制框架(1)与楼顶面的物理硬接触。6. An integral lifting platform according to claim 5, characterized in that: the steel frame (1) is provided with an adjustable top support (6), through which the adjustable top support (6) rises to The physical hard contact between the steel frame (1) and the roof surface of the building is realized. 7.根据权利要求6所述的一种整体吊运平台,其特征在于:所述钢制框架(1)底部设有电动滚轮(2)。7. An integral lifting platform according to claim 6, characterized in that: the bottom of the steel frame (1) is provided with electric rollers (2). 8.一种建筑外立面施工平台的搭建方法,其特征在于,应用了如权利要求6中所述的整体吊运平台,该施工方法的具体施工步骤如下:8. a construction method of building facade construction platform, is characterized in that, has applied the integral lifting platform as described in claim 6, and the concrete construction steps of this construction method are as follows: 步骤一:制定施工计划,根据高层建筑凸出整体楼面的结构尺寸设计吊臂(8)的整体长度,促使副臂(82)吊挂的电动吊篮能够延伸至高层建筑凸出整体楼面的结构位置,并且可自动吊运平台整体的结构尺寸以及强度能够满足设计要求以及施工安全规范要求;Step 1: Make a construction plan, design the overall length of the boom (8) according to the structural dimension of the high-rise building protruding from the overall floor, so that the electric gondola suspended by the jib (82) can be extended to the high-rise building protruding from the overall floor The structural position of the platform, and the overall structural size and strength of the automatic lifting platform can meet the design requirements and construction safety requirements; 步骤二:将可自动吊运平台拆卸成为零部件以后,通过施工电梯或塔吊安装到高层建筑的任意一个施工段区域内的楼顶的楼层以内,该楼层需具有楼地面和楼顶面,以促使可自动吊运平台的顶撑能够与楼顶面实现物理硬接触;Step 2: After the automatic lifting platform is disassembled into parts, it is installed within the floor of the roof in any construction section area of the high-rise building by the construction elevator or tower crane. To enable the top support of the automatic lifting platform to achieve physical hard contact with the top surface of the building; 步骤三:先调整固定钢制框架(1)的位置,然后固定钢制框架(1),再按照如下顺序对可自动吊运平台进行安装:钢制框架(1)在楼地面上定位→通过旋转可调底座支撑(5),促使钢制框架(1)脱离楼地面→通过旋转可调顶撑(6),使可调顶撑(6)向上延伸并与楼顶面抵紧,以实现钢制框架(1)与楼顶面的物理接触→在钢制框架(1)上安装配重框架(3),并在配重框架(3)按照设计要求放置配重承板(4)→通过葫芦在钢制框架(1)上安装两套伸缩吊运系统,并利用螺栓贯穿主臂(81)和伏笔上的限位孔(83),以完成主臂(81)与副臂(82)的相对位置固定→利用塔吊将电动吊篮吊运至两套伸缩吊运系统下方,然后利用吊耳(12)和吊索(10)将电动吊篮水平悬挂至两套伸缩吊运系统上;Step 3: First adjust the position of the fixed steel frame (1), then fix the steel frame (1), and then install the automatic lifting platform in the following order: Position the steel frame (1) on the floor → pass Rotate the adjustable base support (5) to push the steel frame (1) off the floor → by rotating the adjustable top support (6), the adjustable top support (6) is extended upwards and pressed against the top surface of the building to achieve Physical contact between the steel frame (1) and the roof surface → Install the counterweight frame (3) on the steel frame (1), and place the counterweight support plate (4) on the counterweight frame (3) according to the design requirements → Two sets of telescopic hoisting systems are installed on the steel frame (1) through a hoist, and bolts are used to penetrate the main arm (81) and the limit hole (83) on the foreshadowing to complete the main arm (81) and the auxiliary arm (82). ) → use the tower crane to hoist the electric gondola below the two telescopic hoisting systems, and then use the lifting lugs (12) and slings (10) to horizontally suspend the electric gondola to the two sets of telescopic hoisting systems ; 步骤四:对未装载货物的电动吊篮进行提升调试,然后完成伸缩吊运系统的同步调试,吊臂(8)的伸缩测试;逐步在电动吊篮上加载货物,记录电动吊篮每次增加货物时的下降值以及状态,完成整体性测试;Step 4: Lift and debug the unloaded electric gondola, then complete the synchronous debug of the telescopic hoisting system and the telescopic test of the boom (8); gradually load the cargo on the electric gondola, and record each increase of the electric gondola. The drop value and state of the goods, complete the integrity test; 步骤五:待步骤四完成以后,也即在高层建筑非标准层外立面搭建好了施工平台,该施工平台可通过伸缩吊运系统的吊臂(8)的向前或向后伸缩,以实现施工平台与建筑外立面之间的距离调整,以满足建筑非标准层外立面的施工要求。Step 5: After Step 4 is completed, that is, a construction platform is built on the non-standard layer facade of the high-rise building. Realize the adjustment of the distance between the construction platform and the building facade to meet the construction requirements of the building's non-standard layer facade.
CN202010859882.2A 2020-08-24 2020-08-24 An integral lifting platform and a construction method for a building exterior facade construction platform Pending CN111980391A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010859882.2A CN111980391A (en) 2020-08-24 2020-08-24 An integral lifting platform and a construction method for a building exterior facade construction platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010859882.2A CN111980391A (en) 2020-08-24 2020-08-24 An integral lifting platform and a construction method for a building exterior facade construction platform

Publications (1)

Publication Number Publication Date
CN111980391A true CN111980391A (en) 2020-11-24

Family

ID=73443069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010859882.2A Pending CN111980391A (en) 2020-08-24 2020-08-24 An integral lifting platform and a construction method for a building exterior facade construction platform

Country Status (1)

Country Link
CN (1) CN111980391A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727052A (en) * 2021-01-05 2021-04-30 上海建工一建集团有限公司 Horizontal moving hanging basket
CN112942097A (en) * 2021-03-08 2021-06-11 洛阳理工学院 A remove gallows for building bridge railing construction
CN113073834A (en) * 2021-03-02 2021-07-06 湖北桓壹建设工程有限公司 Integral hoisting platform and building method of building outer facade construction platform
CN113323371A (en) * 2021-06-28 2021-08-31 苏雅拉图 Hanging flower basket for construction
CN113957796A (en) * 2021-10-13 2022-01-21 中建四局芜湖建设投资有限公司 Bridge attaches movable construction hanging flower basket
CN114033140A (en) * 2021-11-24 2022-02-11 上海建工集团股份有限公司 Overhanging two-section rotary type external wall construction platform
CN114293754A (en) * 2022-01-20 2022-04-08 李晓宇 Building curtain wall exterior wall decoration operation construction equipment
CN117052154A (en) * 2023-07-21 2023-11-14 德衽建设工程有限公司 Curtain wall installation equipment
CN118221008A (en) * 2024-05-24 2024-06-21 平煤神马建工集团第一建筑工程有限公司 Building material lifting device for super high-rise building construction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203175023U (en) * 2013-04-23 2013-09-04 中国葛洲坝集团股份有限公司 Counter weight type cantilever hanging basket device
CN204012480U (en) * 2014-07-23 2014-12-10 永州市三番机械制造有限公司 A kind of cable pulling hoisting machine
CN206859051U (en) * 2017-06-02 2018-01-09 武汉市市政建设集团有限公司 Hanging basket platform for bridge construction
CN109484979A (en) * 2017-09-12 2019-03-19 中国三冶集团有限公司 A kind of building engineering construction equipment and construction method
CN111155755A (en) * 2020-01-08 2020-05-15 金色建设集团有限公司 Building outer wall hanging flower basket device
CN211007591U (en) * 2019-08-28 2020-07-14 上海市政工程设计研究总院(集团)有限公司 Telescopic suspension device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203175023U (en) * 2013-04-23 2013-09-04 中国葛洲坝集团股份有限公司 Counter weight type cantilever hanging basket device
CN204012480U (en) * 2014-07-23 2014-12-10 永州市三番机械制造有限公司 A kind of cable pulling hoisting machine
CN206859051U (en) * 2017-06-02 2018-01-09 武汉市市政建设集团有限公司 Hanging basket platform for bridge construction
CN109484979A (en) * 2017-09-12 2019-03-19 中国三冶集团有限公司 A kind of building engineering construction equipment and construction method
CN211007591U (en) * 2019-08-28 2020-07-14 上海市政工程设计研究总院(集团)有限公司 Telescopic suspension device
CN111155755A (en) * 2020-01-08 2020-05-15 金色建设集团有限公司 Building outer wall hanging flower basket device

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112727052A (en) * 2021-01-05 2021-04-30 上海建工一建集团有限公司 Horizontal moving hanging basket
CN113073834A (en) * 2021-03-02 2021-07-06 湖北桓壹建设工程有限公司 Integral hoisting platform and building method of building outer facade construction platform
CN112942097A (en) * 2021-03-08 2021-06-11 洛阳理工学院 A remove gallows for building bridge railing construction
CN113323371A (en) * 2021-06-28 2021-08-31 苏雅拉图 Hanging flower basket for construction
CN113957796A (en) * 2021-10-13 2022-01-21 中建四局芜湖建设投资有限公司 Bridge attaches movable construction hanging flower basket
CN114033140A (en) * 2021-11-24 2022-02-11 上海建工集团股份有限公司 Overhanging two-section rotary type external wall construction platform
CN114033140B (en) * 2021-11-24 2023-05-30 上海建工集团股份有限公司 Overhanging double-section rotary type outer wall construction platform
CN114293754A (en) * 2022-01-20 2022-04-08 李晓宇 Building curtain wall exterior wall decoration operation construction equipment
CN117052154A (en) * 2023-07-21 2023-11-14 德衽建设工程有限公司 Curtain wall installation equipment
CN118221008A (en) * 2024-05-24 2024-06-21 平煤神马建工集团第一建筑工程有限公司 Building material lifting device for super high-rise building construction
CN118221008B (en) * 2024-05-24 2024-09-17 平煤神马建工集团第一建筑工程有限公司 Building material lifting device for super high-rise building construction

Similar Documents

Publication Publication Date Title
CN111980391A (en) An integral lifting platform and a construction method for a building exterior facade construction platform
CN201679222U (en) Double mast climbing work platform
CN116588819A (en) A hoisting device for a glass curtain wall plate and its construction method
CN216105701U (en) Hoisting device for engineering reinforcement construction
CN109879179B (en) Assembled steel construction tower crane platform
CN209145256U (en) Prefabricated building special climbing frame
CN111502294B (en) Automatic installation method of movable precast concrete wallboard
CN214995818U (en) Climbing type construction operation platform outside building
CN201560067U (en) Scale beam type lifting device
CN110453836A (en) inclined glass curtain wall mounting system and mounting method
CN221856149U (en) Guide rope type hanging basket
CN220319141U (en) Threading type self-climbing cloth machine
CN210064983U (en) High-rise building electromechanical device installation carrying device
CN219156359U (en) Self-climbing construction crane for elevator steel structure well
CN217439513U (en) Self-lifting high-altitude operation hanging basket
CN209040300U (en) Construction equipment and box construction of prefabricated buildings
CN114014176B (en) Indoor and outdoor universal crane applicable to various building models and hoisting method
CN110626960A (en) Mechanical equipment hoisting frame
CN109231036B (en) Building promotes panel with fixed steady equipment of hanging
CN210341680U (en) Door type corrugated steel web plate installation and overhanging type hanging bracket structure
CN114809577B (en) Self-lifting aerial work hanging basket
CN217602048U (en) An operation device for plastering construction in a well with high safety
CN219567283U (en) A mobile hoisting platform
CN114955903B (en) An integral hoisting device for steel structure roof beams and a construction method thereof
CN215974668U (en) Building construction material lifting device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20201124