CN111644608A - 一种中间包上水口结构及其安装方法 - Google Patents

一种中间包上水口结构及其安装方法 Download PDF

Info

Publication number
CN111644608A
CN111644608A CN201911152548.7A CN201911152548A CN111644608A CN 111644608 A CN111644608 A CN 111644608A CN 201911152548 A CN201911152548 A CN 201911152548A CN 111644608 A CN111644608 A CN 111644608A
Authority
CN
China
Prior art keywords
nozzle
upper nozzle
feeding port
inclined surface
water feeding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911152548.7A
Other languages
English (en)
Other versions
CN111644608B (zh
Inventor
安泽秋
张启东
王红胜
杨晓山
黄财德
刘延强
赵长亮
马强
袁天祥
何文远
肖华生
王胜东
闫文涛
周绍轩
潘云龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shougang Jingtang United Iron and Steel Co Ltd
Original Assignee
Shougang Jingtang United Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shougang Jingtang United Iron and Steel Co Ltd filed Critical Shougang Jingtang United Iron and Steel Co Ltd
Priority to CN201911152548.7A priority Critical patent/CN111644608B/zh
Publication of CN111644608A publication Critical patent/CN111644608A/zh
Application granted granted Critical
Publication of CN111644608B publication Critical patent/CN111644608B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/50Pouring-nozzles
    • B22D41/52Manufacturing or repairing thereof
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/50Pouring-nozzles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B22CASTING; POWDER METALLURGY
    • B22DCASTING OF METALS; CASTING OF OTHER SUBSTANCES BY THE SAME PROCESSES OR DEVICES
    • B22D41/00Casting melt-holding vessels, e.g. ladles, tundishes, cups or the like
    • B22D41/50Pouring-nozzles
    • B22D41/52Manufacturing or repairing thereof
    • B22D41/54Manufacturing or repairing thereof characterised by the materials used therefor

Abstract

本发明属于中间包技术领域,公开了一种中间包上水口结构及安装方法,中间包上水口结构包括:上水口以及固定在所述上水口外部的水口座砖;所述上水口与所述水口座砖之间填充有铬质火泥,其中,所述铬质火泥中铬质物料与水的配比为100∶21;所述水口座砖外铺设有密实的捣打料,其中,所述捣打料中干质捣打料与水的配比为100∶4;所述上水口的上部外壁设置成向水口内侧倾斜的第一倾面,所述水口座砖的筒腔内壁开设成与所述第一倾面相弥合的第二倾面。本发明提供的中间包上水口结构鞥狗可靠的防止渗钢。

Description

一种中间包上水口结构及其安装方法
技术领域
本发明涉及中间包技术领域,特别涉及一种中间包上水口结构及其安装方法。
背景技术
中间包水口渗钢是指在浇钢过程中,钢水沿着中间包座砖与水口之间的缝隙渗漏到中包下部而凝结的行为,阻挡了中包事故闸板的行程通道,给生产带来安全隐患。
发明内容
本发明提供一种中间包上水口结构及其安装方法,解决现有技术中的中间包水口渗钢的技术问题。
为解决上述技术问题,本发明提供了一种中间包上水口结构,包括:上水口以及固定在所述上水口外部的水口座砖;
所述上水口与所述水口座砖之间填充有铬质火泥,其中,所述铬质火泥中铬质物料与水的配比为100∶21;
所述水口座砖外铺设有密实的捣打料,其中,所述捣打料中干质捣打料与水的配比为100∶4;
所述上水口的上部外壁设置成向水口内侧倾斜的第一倾面,所述水口座砖的筒腔内壁开设成与所述第一倾面相弥合的第二倾面。
进一步地,所述上水口的材质为镁碳材质。
进一步地,所述水口座砖的材质为刚玉材质。
进一步地,所述第一倾面的倾角为5°。
进一步地,所述上水口的内径直径80mm,所述上水口的第一倾面的顶端为163mm,所述上水口的第一倾面的顶端外径177mm;
所述水口座砖的筒腔的第二倾面的底端内径167mm,所述水口座砖的筒腔的第二倾面的顶端内径180mm,所述水口座砖高度180mm。
进一步地,所述铬质火泥的厚度为3mm。
一种中间包上水口结构安装方法,用于砌筑所述的中间包上水口结构;其特征在于,包括:
将铬质火泥均匀涂抹在上水口周围,厚度约3mm;
将上水口座砖顺时针旋进套在上水口外;
将捣打料倒入座砖周围并捣实;
于捣实后的捣打料上面覆盖一层涂抹料,继续捣实抹平。
本申请实施例中提供的一个或多个技术方案,至少具有如下技术效果或优点:
本申请实施例中提供的中间包上水口结构及安装方法,通过优化铬质火泥及捣打料干湿程度,一方面,使得上水口与捣打料的膨胀性能相一致,避免使用过程中因膨胀程度不匹配导致捣打料层与水口分离而产生缝隙;同时,能够充分弥合上水口与座砖之间的缝隙,并且能够配合水口和座砖的膨胀程度,并抵抗钢水的侵蚀,从而防止在两者间出现缝隙避免渗钢。值得说明的是,在上水口和水口座砖间形成相配合的第一倾面和第二倾面,形成非竖直接缝,从结构上延长可能的渗钢路径,还能够提升渗钢阻力;从而整体上有效解决了水口与座砖之间配合不严密形成贯穿的缝隙发生渗透的情况。
附图说明
图1为本发明实施例提供的中间包水口结构的装配状态示意图;
图2为本发明实施例提供的上水口的结构示意图;
图3为本发明实施例提供的水口座砖的结构示意图。
具体实施方式
本申请实施例通过提供一种中间包上水口结构及安装方法,解决现有技术中的中间包水口渗钢的技术问题。
为了更好的理解上述技术方案,下面将结合说明书附图以及具体的实施方式对上述技术方案进行详细说明,应当理解本发明实施例以及实施例中的具体特征是对本申请技术方案的详细的说明,而不是对本申请技术方案的限定,在不冲突的情况下,本申请实施例以及实施例中的技术特征可以相互组合。
参见图1、图2和图3,一种中间包上水口结构,包括:上水口1以及固定在所述上水口1外部的水口座砖2。
值得说明的是,本实施例中,所述上水口1与所述水口座砖2之间填充有铬质火泥,其中,所述铬质火泥中铬质物料与水的配比为100∶21;能够充分弥合上水口与座砖之间的缝隙,并且能够配合水口和座砖的膨胀程度,并抵抗钢水的侵蚀,从而防止在两者间出现缝隙避免渗钢。
本实施例中,所述铬质火泥的厚度为3mm,即可形成良好的弥合效果。
所述水口座砖2外铺设有密实的捣打料,其中,所述捣打料中干质捣打料与水的配比为100∶4;使得上水口与捣打料的膨胀性能相一致,避免使用过程中因膨胀程度不匹配导致捣打料层与水口分离而产生缝隙;从而避免贯穿缝隙渗钢。
本实施例中,还从结构上进行优化,所述上水口1的上部外壁设置成向水口内侧倾斜的第一倾面,所述水口座砖2的筒腔内壁开设成与所述第一倾面相弥合的第二倾面,从而在装配和形成一个倾斜的接触缝隙,一方面延长渗钢路径,削弱渗钢损伤,同时也能够形成非竖直缝隙,提升渗钢阻力进一步削弱渗钢损伤速率。
进一步地,所述第一倾面的倾角为5°,实现稳定的装配的同时也具备较好的结构强度。
本实施例中,所述上水口1的材质为镁碳材质,所述水口座砖2的材质为刚玉材质。所述上水口1的内径直径80mm,所述上水口1的第一倾面的顶端为163mm,所述上水口1的第一倾面的顶端外径177mm;所述水口座砖2的筒腔的第二倾面的底端内径167mm,所述水口座砖2的筒腔的第二倾面的顶端内径180mm,所述水口座砖2高度180mm。
本实施例还提供具体的安装砌筑方法。
一种中间包上水口结构安装方法,用于砌筑所述的中间包上水口结构;其特征在于,包括:
将铬质火泥均匀涂抹在上水口周围,厚度约3mm;具体来说,铬质火泥的厚度是以套上水口座砖2后,上水口端部露出的高度小于等于40mm 的情况下,确定铬质火泥的涂覆厚度。上水口1顶端到水口座砖2的底端的长度约180mm。
将上水口座砖顺时针旋进套在上水口外,并用橡皮锤砸实,以上水口 1的端部露出高度小于等于35mm为标准。
将捣打料倒入座砖周围并捣实;于捣实后的捣打料上面覆盖一层涂抹料,继续捣实抹平。
本申请实施例中提供的一个或多个技术方案,至少具有如下技术效果或优点:
本申请实施例中提供的中间包上水口结构及安装方法,通过优化铬质火泥及捣打料干湿程度,一方面,使得上水口与捣打料的膨胀性能相一致,避免使用过程中因膨胀程度不匹配导致捣打料层与水口分离而产生缝隙;同时,能够充分弥合上水口与座砖之间的缝隙,抵抗钢水的侵蚀,从而防止在两者间出现缝隙避免渗钢。值得说明的是,在上水口和水口座砖间形成相配合的第一倾面和第二倾面,形成非竖直接缝,从结构上延长可能的渗钢路径,还能够提升渗钢阻力;从而整体上有效解决了水口与座砖之间配合不严密形成贯穿的缝隙发生渗透的情况。
最后所应说明的是,以上具体实施方式仅用以说明本发明的技术方案而非限制,尽管参照实例对本发明进行了详细说明,本领域的普通技术人员应当理解,可以对本发明的技术方案进行修改或者等同替换,而不脱离本发明技术方案的精神和范围,其均应涵盖在本发明的权利要求范围当中。

Claims (7)

1.一种中间包上水口结构,其特征在于,包括:上水口以及固定在所述上水口外部的水口座砖;
所述上水口与所述水口座砖之间填充有铬质火泥,其中,所述铬质火泥中铬质物料与水的配比为100∶21;
所述水口座砖外铺设有密实的捣打料,其中,所述捣打料中干质捣打料与水的配比为100∶4;
所述上水口的上部外壁设置成向水口内侧倾斜的第一倾面,所述水口座砖的筒腔内壁开设成与所述第一倾面相弥合的第二倾面。
2.如权利要求1所述的中间包上水口结构,其特征在于,所述上水口的材质为镁碳材质。
3.如权利要求1所述的中间包上水口结构,其特征在于,所述水口座砖的材质为刚玉材质。
4.如权利要求1所述的中间包上水口结构,其特征在于,所述第一倾面的倾角为5°。
5.如权利要求4所述的中间包上水口结构,其特征在于:所述上水口的内径直径80mm,所述上水口的第一倾面的顶端为163mm,所述上水口的第一倾面的顶端外径177mm;
所述水口座砖的筒腔的第二倾面的底端内径167mm,所述水口座砖的筒腔的第二倾面的顶端内径180mm,所述水口座砖高度180mm。
6.如权利要求5所述的中间包上水口结构,其特征在于:所述铬质火泥的厚度为3mm。
7.一种中间包上水口结构安装方法,用于砌筑权利要求1所述的中间包上水口结构;其特征在于,包括:
将铬质火泥均匀涂抹在上水口周围,厚度约3mm;
将上水口座砖顺时针旋进套在上水口外;
将捣打料倒入座砖周围并捣实;
于捣实后的捣打料上面覆盖一层涂抹料,继续捣实抹平。
CN201911152548.7A 2019-11-22 2019-11-22 一种中间包上水口结构及其安装方法 Active CN111644608B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911152548.7A CN111644608B (zh) 2019-11-22 2019-11-22 一种中间包上水口结构及其安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911152548.7A CN111644608B (zh) 2019-11-22 2019-11-22 一种中间包上水口结构及其安装方法

Publications (2)

Publication Number Publication Date
CN111644608A true CN111644608A (zh) 2020-09-11
CN111644608B CN111644608B (zh) 2022-01-18

Family

ID=72346405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911152548.7A Active CN111644608B (zh) 2019-11-22 2019-11-22 一种中间包上水口结构及其安装方法

Country Status (1)

Country Link
CN (1) CN111644608B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112517900A (zh) * 2020-11-17 2021-03-19 天工爱和特钢有限公司 一种制粉中间包的水口制作工艺
CN113927026A (zh) * 2021-09-07 2022-01-14 山东钢铁集团日照有限公司 一种双流板坯连铸机防渗钢分体式水口座砖安装方法
CN114378290A (zh) * 2021-12-13 2022-04-22 首钢京唐钢铁联合有限责任公司 一种中间包上水口安装方法

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5619970A (en) * 1979-07-27 1981-02-25 Nippon Steel Corp Repairing method of sliding nozzle
US5314099A (en) * 1987-03-20 1994-05-24 Mannesmann Ag Casting spout for metallurgical vessels
JPH081316A (ja) * 1994-06-20 1996-01-09 Tokyo Yogyo Co Ltd スライディングノズル用上部ノズル
JPH08197237A (ja) * 1995-01-24 1996-08-06 Sumitomo Metal Ind Ltd スライディングゲートの上ノズル
JP2001334361A (ja) * 2000-05-23 2001-12-04 Hitachi Metals Ltd 流下溶湯保護装置
JP2002013878A (ja) * 2000-06-29 2002-01-18 Nkk Corp 羽口受け煉瓦の補修方法
JP2003117639A (ja) * 2001-10-15 2003-04-23 Shinagawa Refract Co Ltd 連続鋳造用ノズル構造
JP2004122214A (ja) * 2002-10-07 2004-04-22 Shinagawa Refract Co Ltd 鋳造用上ノズル
JP2008126258A (ja) * 2006-11-20 2008-06-05 Tokyo Yogyo Co Ltd 断熱スリーブを備えた溶融金属用の鋳造ノズル
CN201442099U (zh) * 2009-07-30 2010-04-28 莱芜钢铁股份有限公司 方坯、矩形坯用塞棒包快换水口装置
CN201579412U (zh) * 2009-12-28 2010-09-15 莱芜钢铁股份有限公司 方坯、矩形坯用中间包氩气密封快换装置
CN102151822A (zh) * 2011-05-24 2011-08-17 莱芜钢铁集团有限公司 一种连铸中间包及其制造方法
CN104107907A (zh) * 2014-07-17 2014-10-22 内蒙古包钢钢联股份有限公司 挡钢圈、设置有挡钢圈的中间包及其安装方法
CN204075191U (zh) * 2014-09-04 2015-01-07 湖州永联耐火材料有限公司 防漏座砖结构
CN204338849U (zh) * 2014-12-22 2015-05-20 武汉钢铁(集团)公司 一种能改善滑板砖侵蚀的中间包水口
CN105436495A (zh) * 2015-11-26 2016-03-30 武汉钢铁(集团)公司 中间包和中间包水口防渗钢安装方法
CN205599913U (zh) * 2016-04-26 2016-09-28 华耐国际(宜兴)高级陶瓷有限公司 一种新型防钢水渗漏的中间包上水口

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5619970A (en) * 1979-07-27 1981-02-25 Nippon Steel Corp Repairing method of sliding nozzle
US5314099A (en) * 1987-03-20 1994-05-24 Mannesmann Ag Casting spout for metallurgical vessels
JPH081316A (ja) * 1994-06-20 1996-01-09 Tokyo Yogyo Co Ltd スライディングノズル用上部ノズル
JPH08197237A (ja) * 1995-01-24 1996-08-06 Sumitomo Metal Ind Ltd スライディングゲートの上ノズル
JP2001334361A (ja) * 2000-05-23 2001-12-04 Hitachi Metals Ltd 流下溶湯保護装置
JP2002013878A (ja) * 2000-06-29 2002-01-18 Nkk Corp 羽口受け煉瓦の補修方法
JP2003117639A (ja) * 2001-10-15 2003-04-23 Shinagawa Refract Co Ltd 連続鋳造用ノズル構造
JP2004122214A (ja) * 2002-10-07 2004-04-22 Shinagawa Refract Co Ltd 鋳造用上ノズル
JP2008126258A (ja) * 2006-11-20 2008-06-05 Tokyo Yogyo Co Ltd 断熱スリーブを備えた溶融金属用の鋳造ノズル
CN201442099U (zh) * 2009-07-30 2010-04-28 莱芜钢铁股份有限公司 方坯、矩形坯用塞棒包快换水口装置
CN201579412U (zh) * 2009-12-28 2010-09-15 莱芜钢铁股份有限公司 方坯、矩形坯用中间包氩气密封快换装置
CN102151822A (zh) * 2011-05-24 2011-08-17 莱芜钢铁集团有限公司 一种连铸中间包及其制造方法
CN104107907A (zh) * 2014-07-17 2014-10-22 内蒙古包钢钢联股份有限公司 挡钢圈、设置有挡钢圈的中间包及其安装方法
CN204075191U (zh) * 2014-09-04 2015-01-07 湖州永联耐火材料有限公司 防漏座砖结构
CN204338849U (zh) * 2014-12-22 2015-05-20 武汉钢铁(集团)公司 一种能改善滑板砖侵蚀的中间包水口
CN105436495A (zh) * 2015-11-26 2016-03-30 武汉钢铁(集团)公司 中间包和中间包水口防渗钢安装方法
CN205599913U (zh) * 2016-04-26 2016-09-28 华耐国际(宜兴)高级陶瓷有限公司 一种新型防钢水渗漏的中间包上水口

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
洪军等: "中包水口渗钢原因分析及对策", 《武钢技术》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112517900A (zh) * 2020-11-17 2021-03-19 天工爱和特钢有限公司 一种制粉中间包的水口制作工艺
CN113927026A (zh) * 2021-09-07 2022-01-14 山东钢铁集团日照有限公司 一种双流板坯连铸机防渗钢分体式水口座砖安装方法
CN114378290A (zh) * 2021-12-13 2022-04-22 首钢京唐钢铁联合有限责任公司 一种中间包上水口安装方法
CN114378290B (zh) * 2021-12-13 2024-03-19 首钢京唐钢铁联合有限责任公司 一种中间包上水口安装方法

Also Published As

Publication number Publication date
CN111644608B (zh) 2022-01-18

Similar Documents

Publication Publication Date Title
CN111644608B (zh) 一种中间包上水口结构及其安装方法
CN208844810U (zh) 一种建筑屋面女儿墙泛水防水构造
CN109024913A (zh) 装配式自保温砌块体系及应用方法
CN209508137U (zh) 一种气密性强的焦炉炉顶结构
CN206554367U (zh) 土木工程用墙板
CN203917892U (zh) 长寿命中间包
CN205476027U (zh) 一种新型加气混凝土保温砌块
CN209349506U (zh) 中间包上水口防渗钢结构
CN206888329U (zh) 一种高强度的蒸压加气砌块
CN110396982A (zh) 一种人工坝体连接结构及施工方法
CN103357831A (zh) 一种中间包多功能稳流冲击桶及其砌筑方法
CN218503334U (zh) 一种铸造高锰钢辙叉浇注钢包用内衬隔热装置
CN201227688Y (zh) 一种钢水罐楦胎砖
CN204828968U (zh) 保温风管穿轻钢龙骨石膏板隔墙的防火结构
CN210396008U (zh) 一种玻化砖铺贴结构
CN205617315U (zh) 一种用于混凝土六方块护坡的锚固装置
CN201588338U (zh) 多孔夹芯胶砂保温砌块
CN205636647U (zh) 一种用于锚固的预制混凝土六方块
CN109401761A (zh) 一种气密性强的焦炉炉顶结构及其施工方法
CN205798426U (zh) 一种连铸机中间包用分离环
CN109719289B (zh) 一种连铸中间包及其中间包座砖
CN105714735B (zh) 一种锚固的预制混凝土六方块护坡方法及其应用装置
CN216787592U (zh) 一种保温楼板结构
CN205799817U (zh) 一种耐磨中框改进结构
CN219415718U (zh) 一种高韧性耐火砖

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant