CN111411731A - Vertical hole grouting type building block and construction process thereof - Google Patents

Vertical hole grouting type building block and construction process thereof Download PDF

Info

Publication number
CN111411731A
CN111411731A CN202010357820.1A CN202010357820A CN111411731A CN 111411731 A CN111411731 A CN 111411731A CN 202010357820 A CN202010357820 A CN 202010357820A CN 111411731 A CN111411731 A CN 111411731A
Authority
CN
China
Prior art keywords
building block
groove
building
grouting
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010357820.1A
Other languages
Chinese (zh)
Inventor
宫莉
晏绘华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010357820.1A priority Critical patent/CN111411731A/en
Publication of CN111411731A publication Critical patent/CN111411731A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C1/00Building elements of block or other shape for the construction of parts of buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/42Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities
    • E04B2/44Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities using elements having specially-designed means for stabilising the position; Spacers for cavity walls
    • E04B2/46Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities using elements having specially-designed means for stabilising the position; Spacers for cavity walls by interlocking of projections or inserts with indentations, e.g. of tongues, grooves, dovetails
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/42Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities
    • E04B2/52Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities the walls being characterised by fillings in some of the cavities forming load-bearing pillars or beams
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0202Details of connections
    • E04B2002/0232Undercut connections, e.g. using undercut tongues and grooves
    • E04B2002/0234Angular dovetails
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2002/0295Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements of which the width is equal to the wall thickness

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a vertical hole grouting type building block and a construction process thereof. The invention discloses a building block, which is characterized in that end grooves are arranged at two ends of the building block, holes are reserved in the middle of the building block, after the building block is stacked, bonding mortar or concrete is poured into the end grooves to form mortar or concrete core columns, the building blocks are connected left and right and are strung up and down through the core columns, the construction effect is high, the connection strength between the building blocks, the smoothness, the stability and the shock resistance of the whole building block wall surface are high, the efficiency is improved, the manufacturing cost is saved, the wall body is not hollowly bulged and does not crack, the building block is suitable for flush joint building, furthermore, grouting holes are formed on the bases of the end grooves arranged at two ends of the building block, and the building block is suitable for.

Description

Vertical hole grouting type building block and construction process thereof
Technical Field
The invention belongs to the technical field of building blocks, and particularly relates to a vertical hole grouting type building block and a construction process thereof.
Background
At present, the inner partition wall filling building block is a key field with multiple quality accidents of construction engineering, common quality problems such as cracking, leakage, falling, hollowing and the like are difficult to prevent and treat, the quality of the masonry is influenced by artificial masonry construction, mutual connection of different materials and the like, the construction speed is low, the quality is uneven, the field mixing of the plastering mortar has large pollution, the material consumption is large and the like, and the problems are more and more prominent in contradiction with the current energy conservation and emission reduction, environmental protection, manpower resource shortage and the like in China. Specifically, the method comprises the following steps:
1) conventional blocks (i.e., conventional solid blocks). The traditional solid block construction process is a bonding process, and has the disadvantages of large material consumption, large labor consumption, low labor productivity and large quality factor caused by human interference. High cost, long period and difficult quality guarantee.
2) Traditional hollow blocks. The problems of the hollow blocks with the transverse holes are basically the same as those of the solid blocks, namely the problem of the point 1). When the hollow building blocks with the vertical holes are constructed, the bonding area is far from enough, and the stability and the integrity of the wall body are poor.
3) Autoclaved aerated building blocks. The building block not only has the problems of the traditional solid building block in the construction process, but also has more quality problems of hollowing, cracking and the like because the water absorption rate of the autoclaved aerated (type) building block is overlarge.
4) A light-weight lath. The production of the light batten mainly adopts a production process taking foamed cement as a main material, the batten has large size and construction difficulty, the transportation and installation are inconvenient, the water absorption rate of the foamed cement is high, and the plastering mortar is difficult to form effective firm bonding with the batten. In recent practice, the cracking and deformation of the strip plate reach more than 80 percent.
Disclosure of Invention
The invention discloses a vertical hole grouting type building block and a construction process thereof, which solve the problems in the background technology.
Because the hollow building block is when building by laying bricks or stones, the bonding area of traditional bonding process is little, and the wholeness, stability, the shock resistance of brickwork reduce by a wide margin. According to the invention, the building block is provided with the vertically-penetrating holes, the structural strength of the building block is met by the holes, the manufacturing cost of the building block is reduced, the building block is provided with the vertically-penetrating end grooves and/or grouting holes, and the building blocks are strung by pouring bonding materials such as mortar or concrete into the end grooves and/or grouting holes, so that the stability and integrity of the masonry can be greatly improved, and the seismic performance of the masonry is improved. The structure and the process avoid mortar joints for bonding of the traditional structure and the traditional process, after the building blocks are finished by the stringing process, the wall surface is smooth, painting is not needed, the building speed is high, the traditional building is changed into a simple connection mode of stacking and vertical hole grouting, labor and materials (building blocks and painted mortar materials) are saved, the efficiency is improved, the manufacturing cost is saved, the wall body is not hollow and bloated and does not crack, and the stability, the integrity and the shock resistance of the wall body can be greatly improved.
The specific technical scheme is as follows: the utility model provides a erect hole grout formula building block, the building block up end set up building block upper portion recess, the building block about both ends set up the tip recess, the tank bottom of building block upper portion recess sets up the reserved steel bar groove along the length direction of building block, the middle part of building block vertically run through and seted up the hole, the tip recess be mouthful big groove of closing up at the end, the tip recess in grout.
Furthermore, the middle of the building block is vertically penetrated and provided with a grouting hole, and holes are formed in two sides of the grouting hole.
Furthermore, the building block comprises two parallel building block side plates, a connecting beam is arranged between the two building block side plates, cavities among the connecting beam, the building block side plates and the groove bottom plate of the end groove form holes, and the holes on the left side and the right side of the connecting beam are symmetrically arranged.
Still further, the building block include two parallel building block curb plates, set up two even roof beams between two building block curb plates, two link the roof beam and constitute the grout hole with the cavity between two building block curb plates, the grout hole be located the positive centre of building block, link the roof beam and constitute the hole with the cavity between the tank bottom plate of building block curb plate and tip recess, the hole symmetrical arrangement of the grout hole left and right sides.
Furthermore, one end of the left end and the right end of the building block is provided with a convex connection part, the other end of the building block is provided with a concave connection part, the convex connection part and the concave connection part form a tongue-and-groove, and the tongue-and-groove is positioned on the outer side of the groove at the end part.
Still further, the groove on the upper portion of the building block is an expanding groove arranged along the length direction of the building block, and a plurality of reserved steel bar grooves are arranged at the bottom of the groove on the upper portion of the building block in parallel along the length direction of the building block.
The invention relates to a construction process of a vertical hole grouting type building block, which comprises the following steps:
1) and stacking the building blocks: firstly, stacking a lower layer of building blocks, embedding reinforcing steel bars along a reserved reinforcing steel bar groove after the stacking of the lower layer of building blocks is finished, and then stacking an upper layer of building blocks, wherein end grooves of each layer of building blocks are tightly attached to each other; the end part groove of the upper layer building block is positioned above the grouting hole in the middle of the lower layer building block, the end part groove of the lower layer building block is positioned below the grouting hole in the middle of the upper layer building block, and the stacked upper and lower layer building blocks form a staggered joint;
2) pouring a bonding material into the end groove and/or the grouting hole of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
Further, the left end and the right end of the building block in the step 1) are closely attached and connected with each other through a tongue-and-groove; in the step 2), filling a bonding material and compacting the bonding material into the groove at the end part of the piled building block and/or the grouting hole; the bonding material is bonding mortar or concrete.
The invention discloses another construction process of a vertical hole grouting type building block, which is characterized by comprising the following steps of:
1) and stacking the building blocks: firstly, stacking a lower layer of building blocks, embedding reinforcing steel bars along a reserved reinforcing steel bar groove after the stacking of the lower layer of building blocks is finished, and then stacking an upper layer of building blocks, wherein end grooves of each layer of building blocks are tightly attached to each other; each row of the stacked building blocks are arranged in an up-and-down alignment manner to form a neat seam;
2) pouring a bonding material into the end groove of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
Further, the left end and the right end of the building block in the step 1) are closely attached and connected with each other through a tongue-and-groove; filling the end grooves of the piled blocks with bonding materials and compacting the bonding materials in the step 2); 3-4 layers are stacked and grouted each time, and a column cavity formed by a groove (5) at the end part of the uppermost layer of the building block is not filled; the bonding material is bonding mortar or concrete.
Further, the building blocks are provided with grouting holes, and in the step 2), the bonding materials are poured into the grooves at the end parts of the piled uppermost building blocks, and the grouting holes are filled with the bonding materials and compacted with the bonding materials; 3-4 layers are stacked and grouted each time, and a column cavity and a grouting hole (4) formed by a groove (5) at the end part of the uppermost layer of the building block are not filled; the bonding material forms a bonding stem.
The social and economic effects of the invention are obvious and mainly shown in the following aspects:
1) the cost is low. The wall construction is simple, the painting is not needed, and the cost can be effectively reduced.
2) The labor cost is saved. The traditional bonding between the building blocks is changed into the string bonding, the operation is simple and easy, and more than 80 percent of labor consumption is saved.
The construction speed is high. The traditional masonry among the building blocks is changed into stacking, and the construction speed is more than 5 times of the traditional construction speed.
And the material is saved. The building blocks are seamless, the surface of the wall body is smooth, and the consumption of plastering mortar is saved.
3) The integrity is good. Through reserving grout groove (tip recess) and/or vertical pouring hole between the building block, the bonding slurry of pouring forms (bonds) the stem, and the structural integrity of brickwork is good.
4) The earthquake-resistant performance is excellent. Firstly, the drawknot reinforcing bar of brickwork (being the building block) is placed in the building block upper portion of reserving connects the recess, and the building block curb plate salient position of building block both sides forms powerful boundary constraint to the reinforcing bar, has increased substantially the anti-seismic performance of brickwork. Secondly, a vertically through mortar connecting column (namely a bonding core column) is formed between the building blocks and/or inside the building blocks through the pouring mortar in the vertical holes (the end part grooves and/or the pouring holes) between the upper layer and the lower layer of the building blocks, and the seismic performance of the masonry is further improved.
5) The wall surface formed by the building blocks has good quality. The masonry (namely the building block) is seamless, powder is avoided, and the masonry structure realizes zero hollowing and zero cracking.
6) The construction is simple.
7) The universality is strong. The invention is suitable for all parts of the country, the quantity of newly built buildings in the country every year is large at present, the required internal partition wall building blocks are about 4 hundred million square meters, and the beneficial area is large.
The market of the invention is in urgent need. At present, the existing building blocks in the market have more or less common quality problems in the aspects of wall cracking, hollowing, falling and the like, the development of the building block and the construction process can thoroughly eliminate the quality problems of the internal partition wall building blocks in China, and the vertical hole grouting type building block construction technology has the advantages of low construction cost, excellent performance and good universality.
In addition, the vertical hole grouting construction process is simple and easy to implement during wall construction, and during construction of secondary structures such as constructional columns, end columns and lintels, the process of the secondary structures (columns) is to pour concrete or bonding mortar into holes of building blocks to complete the structural columns; for the (lintel) U-shaped building blocks, the process is that the U-shaped building blocks are arranged in a row, reinforcing steel bars can be directly paved on the building blocks, and concrete is poured into the U-shaped grooves, so that the construction of the lintel is completed.
Drawings
FIG. 1 is a top view block diagram of one embodiment of the block of the present invention;
FIG. 2 is a side view of the structure of FIG. 1;
FIG. 3 is a top view block diagram of another embodiment of the block of the present invention;
in the figure: 1-building block side plate; 2-reserving a steel bar groove; 3-connecting the beam; 4-grouting auxiliary holes; 5-end grooves; 6-holes; 7-tongue and groove; 8-a groove at the upper part of the building block; wherein, the dotted line inner cavity area of the end groove 5 is filled with pouring bonding mortar or concrete.
Detailed Description
Referring to the attached drawings 1 and 3, the vertical hole grouting type building block is characterized in that a groove 8 in the upper portion of the building block is formed in the upper end face of the building block, end portion grooves 5 are formed in the left end and the right end of the building block, a reserved steel bar groove 2 is formed in the groove bottom of the groove 8 in the upper portion of the building block along the length direction of the building block, a hole 6 is vertically formed in the middle of the building block in a penetrating mode, the end portion groove 5 is a narrow groove with a small opening and a large bottom, and grouting is conducted in the end.
Further, referring to fig. 1, a grouting hole 4 is vertically formed in the middle of the building block in a penetrating manner, and holes 6 are formed in two sides of the grouting hole 4.
Furthermore, the building block comprises two parallel building block side plates 1, a connecting beam 3 is arranged between the two building block side plates 1, cavities among the connecting beam 3, the building block side plates 1 and the groove bottom plate of the end groove 5 form holes 6, and the holes 6 on the left side and the right side of the connecting beam 3 are symmetrically arranged.
Still further, the building block include two parallel building block curb plates 1, set up two even roof beams 3 between two building block curb plates 1, two link roof beams 3 and two cavity constitution grout holes 4 between the building block curb plate 1, grout holes 4 be located the positive centre of building block, even roof beam 3 and building block curb plate 1 and the tank bottom plate of tip recess 5 between the cavity constitute hole 6, 6 symmetrical arrangement of the hole of the 4 left and right sides of grout holes.
Still further, one end of the left end and the right end of the building block is provided with a convex connection part, the other end of the building block is provided with a concave connection part, the convex connection part and the concave connection part form a tongue-and-groove 7, and the tongue-and-groove 7 is positioned on the outer side of the end part groove 5.
Still further, the upper groove 8 of the building block is an expanding groove arranged along the length direction of the building block, and a plurality of reserved steel bar grooves 2 are arranged at the bottom of the upper groove 8 of the building block in parallel along the length direction of the building block.
Referring to fig. 1, a process to which an embodiment of the present invention is applied:
a construction process of a vertical hole grouting type building block comprises the following steps:
1) and stacking the building blocks: firstly, stacking a lower layer of building blocks, pre-embedding a steel bar along a reserved steel bar groove 2 after the stacking of the lower layer of building blocks is finished, and then stacking an upper layer of building blocks, wherein end grooves 5 of each layer of building blocks are tightly attached to each other; the end groove 5 of the upper layer building block is positioned above the grouting hole 4 in the middle of the lower layer building block, the end groove 5 of the lower layer building block is positioned below the grouting hole 4 in the middle of the upper layer building block, and the stacked upper and lower layer building blocks form a staggered joint;
2) pouring a bonding material into the end groove 5 and/or the grouting hole 4 of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
Further, the left end and the right end of the building block in the step 1) are closely attached and connected with each other through a tongue-and-groove 7; in the step 2), filling the grooves 5 at the end parts of the piled blocks and/or the grouting holes 4 with bonding materials and compacting the bonding materials; 3-4 layers are stacked and grouted each time, and a column cavity and/or a grouting hole 4 formed by a groove (5) at the end part of the uppermost layer building block is not filled; the bonding material is bonding mortar or concrete.
Referring to fig. 1 and 3, a process to which one embodiment and another embodiment of the present invention are applied:
a construction process of a vertical hole grouting type building block is characterized by comprising the following steps:
1) and stacking the building blocks: firstly, stacking a lower layer of building blocks, pre-embedding a steel bar along a reserved steel bar groove 2 after the stacking of the lower layer of building blocks is finished, and then stacking an upper layer of building blocks, wherein end grooves 5 of each layer of building blocks are tightly attached to each other; each row of the stacked building blocks are arranged in an up-and-down alignment manner to form a neat seam;
2) pouring a bonding material into the end groove 5 of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
Further, the left end and the right end of the building block in the step 1) are closely attached and connected with each other through a tongue-and-groove 7; in the step 2), filling the end grooves 5 of the piled blocks with bonding materials and compacting the bonding materials; 3-4 layers are stacked and grouted each time, and a column cavity formed by a groove (5) at the end part of the uppermost layer of the building block is not filled; the bonding material is bonding mortar or concrete.
Furthermore, the building blocks are provided with grouting holes 4, and in the step 2), the bonding materials are poured into the grooves 5 at the end parts of the piled uppermost building blocks, and the grouting holes 4 are filled with the bonding materials and compacted; 3-4 layers are stacked and grouted each time, and a column cavity and a grouting hole (4) formed by a groove (5) at the end part of the uppermost layer of the building block are not filled; the bonding material forms a bonding stem.
The invention relates to a vertical hole grouting type building block and a building block of a construction process thereof, wherein a hole 6 is formed in the middle of a masonry, a bonding material (bonding mortar or concrete) is poured into an end groove 5 at the end part of the building block and/or a middle grouting hole 4 to form a bonding (material) core column, the transverse and vertical firm connection between the building blocks is realized through the bonding core column, and the grouting solidification formed core column enables two adjacent building blocks to form mutually fastened connection through a closing-up structure of the end groove 5, so that the building blocks are changed into a string from the traditional bonding to be connected into a whole. In order to realize that the surface of the masonry (building block) is smooth and seamless, the upper part of the building block is provided with a groove, namely a groove 8 at the upper part of the building block, the groove 8 at the upper part of the building block is provided with a reserved steel bar groove 2 for embedding (wall surface) steel bars, and an embedding position is reserved for the tie steel bars, so that the performance of the building block in the aspect of earthquake resistance is further improved.
Specifically, referring to fig. 1, the present invention provides an embodiment of the present invention, which is suitable for flush masonry and also suitable for staggered masonry.
Referring to fig. 3, another embodiment of the present invention, the blocks of this embodiment are adapted for flush masonry.
And (4) flush masonry, namely, the building blocks are aligned up and down and are piled up in a Lu shape.
Staggered joint masonry, namely, the building blocks are staggered up and down and piled up in a shape like a Chinese character 'pin'.
The end part groove 5 with a small outer opening and a large inner opening is arranged on the grouted building block, so that the building blocks can not be pulled apart by the bonding core column formed after pouring.
Compared with staggered joint masonry, the flush joint masonry can be realized only by aligning and stacking the end part of the upper-layer building block and the end part of the upper-layer building block. The end of the upper-layer building block which is not required to be constructed in a staggered joint manner finds the lower-layer building block grouting hole 4, and in practice, the end of the upper-layer building block is required to be positioned in the middle of the lower-layer building block grouting hole 4 in order to meet construction requirements, namely, the end grooves 5 of the two upper-layer building blocks are symmetrically arranged on the left side and the right side of the two sides above the middle of the lower-layer building block grouting hole 4. The stacking efficiency of the flush masonry is higher, and the construction masonry is more efficient.
In addition, the building block applied to the invention is formed by pressing the building block side plates 1 and the connecting beams 3 in one step in a factory through machinery, and has the advantages of good wall quality, high strength, convenient construction, shortened construction period, labor saving, material saving and low construction difficulty. The wall surface has no vertical joint and transverse joint formed by traditional building block bonding mortar, the wall surface is flat, the building (block) body does not need to be painted, putty can be directly painted, paint is made, the connection mode of vertical hole grouting is not limited by the building height at one time during construction, and the overall performance and the anti-seismic performance of the wall body are greatly enhanced.
In addition, when the building blocks are applied to the household partition wall, the building blocks with the thickness of 200 mm can be selected, and the cavities (holes 6) in the building blocks are filled with thermal insulation mortar, so that the requirements of the household partition wall for thermal insulation, sound insulation, fire prevention and burglary prevention are met.
The type of the block: the main specifications of the building block are of four types according to different application positions, namely, the thicknesses of the building block are 100 mm, 120 mm, 150 mm and 200 mm. The wall with the thickness of 100 mm and 120 mm is mainly used for building walls of kitchens and toilets, 150 mm is mainly used for filling walls of bedrooms, and 200 mm is mainly used for filling walls of household partitions, external walls and public buildings. Meanwhile, according to the difference of the construction positions, combined with the actual construction site, semi-standard building blocks, end part building blocks, U-shaped building blocks special for lintels and the like are respectively manufactured, the building blocks are formed in a one-step pressing mode in a factory through different dies, and the manufacturing is simple and convenient, and the quality is stable. The production process of the building block comprises the following steps: the existing various brick making (building) devices can be manufactured by only changing a mould. Ideally, the vibration-press molding brick machine is formed by vibration-press molding in a factory at one time, and has the advantages of simple and convenient manufacture and stable quality.
In addition, the construction process aims at the middle building block of the wall body.
For the bottommost building block, all hole parts (the hole 6, the end groove 5 and the grouting hole 4) of the building block are filled with C20 concrete, and the filling depth is not less than 10 cm. The middle building blocks of the wall body are piled with 3-4 layers each time and are grouted, the uppermost building block is not filled, and preferably, the middle of the uppermost building block is grouted. A layer of building blocks (the layer below the beam) is arranged on the uppermost part of the wall body, and holes are formed in the corresponding grouting positions for grouting.
In summary, according to the vertical hole grouting type building block and the construction process thereof disclosed by the invention, the end part grooves 5 are arranged at the end parts of the building blocks, the holes 6 are reserved in the middle parts, after the building blocks are stacked, the end part grooves 5 of the adjacent building blocks are filled with bonding mortar or concrete to form mortar or concrete (bonding) core columns, and the building blocks are connected left and right and are stringed up and down through the core columns. Furthermore, a grouting hole 4 is arranged in the middle for pouring bonding mortar or concrete.
The invention is mainly used for the hollow building block, and because the bonding area of the traditional bonding process is small when the hollow building block is built, the integrity, the stability and the shock resistance of the building body are low. The invention designs the building blocks with holes which are penetrated up and down, column cavities formed by end grooves 5 of adjacent building blocks and/or grouting holes 4; the building blocks are stringed by pouring bonding materials such as mortar or concrete into the column cavity and the grouting holes 4, so that the stability and the integrity of the masonry (block) body can be greatly improved, the anti-seismic performance of the masonry (block) body is improved, the structure and the process abandon the bonding mortar joint of the traditional process, and after the stringing process for the building blocks is completed, the wall surface is smooth, painting is not needed, the masonry speed is high, and the traditional masonry is changed into simple stacking. The connection mode of vertical hole grouting saves manpower, brick building materials and painting materials, improves efficiency, saves manufacturing cost, prevents the wall from hollowing and cracking, and greatly improves the stability, integrity and shock resistance of the wall.

Claims (10)

1. The utility model provides a vertical hole grout formula building block, the building block up end set up building block upper portion recess (8), the building block about both ends set up tip recess (5), the tank bottom of building block upper portion recess (8) sets up reserved steel bar groove (2), its characterized in that along the length direction of building block: the middle part of the building block is vertically penetrated and provided with a hole (6), the end part groove (5) is a closed groove with a small opening and a big bottom, and the end part groove (5) is internally grouted.
2. A vertical bore grouted block as claimed in claim 1, wherein: the middle of the building block is vertically penetrated and provided with a grouting hole (4), and holes (6) are arranged on two sides of the grouting hole (4).
3. The vertical hole grouting type building block according to claim 1, characterized in that the building block comprises two parallel building block side plates (1), a connecting beam (3) is arranged between the two building block side plates (1), cavities among the connecting beam (3), the building block side plates (1) and a groove bottom plate of the end groove (5) form holes (6), and the holes (6) on the left side and the right side of the connecting beam (3) are symmetrically arranged.
4. A vertical hole grouting type building block according to claim 3, characterized in that the building block comprises two parallel building block side plates (1), two connecting beams (3) are arranged between the two building block side plates (1), a grouting hole (4) is formed by a cavity between the two connecting beams (3) and the two building block side plates (1), the grouting hole (4) is positioned in the middle of the building block, a hole (6) is formed by the cavity between the connecting beam (3), the building block side plates (1) and a groove bottom plate of the end groove (5), and the holes (6) on the left side and the right side of the grouting hole (4) are symmetrically arranged.
5. A vertical bore grouted block as claimed in claim 3 or 4, wherein: one end of the left end and the right end of the building block is provided with a convex connection part, the other end of the building block is provided with a concave connection part, the convex connection part and the concave connection part form a tongue-and-groove (7), and the tongue-and-groove (7) is positioned on the outer side of the end part groove (5).
6. The vertical hole grouting type building block according to claim 3 or 4, characterized in that the upper groove (8) of the building block is a flared groove arranged along the length direction of the building block, and a plurality of reserved steel bar grooves (2) are arranged in parallel along the length direction of the building block at the bottom of the upper groove (8) of the building block.
7. A construction process of the vertical hole grouting type building block as claimed in any one of claims 2 to 6, characterized by comprising the following steps:
1) and stacking the building blocks: firstly, stacking the lower-layer building blocks, after stacking the lower-layer building blocks, embedding the steel bars along the reserved steel bar grooves (2), then stacking the upper-layer building blocks, and enabling the end grooves (5) of each layer of building blocks to be attached to each other; the end groove (5) of the upper layer building block is positioned above the grouting hole (4) in the middle of the lower layer building block, the end groove (5) of the lower layer building block is positioned below the grouting hole (4) in the middle of the upper layer building block, and the stacked upper and lower layer building blocks form a staggered joint;
2) pouring a bonding material into the end groove (5) and/or the grouting hole (4) of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
8. A process for constructing a vertical bore grouted block as claimed in any one of claims 1 to 6, comprising the steps of:
1) and stacking the building blocks: firstly, stacking the lower-layer building blocks, after stacking the lower-layer building blocks, embedding the steel bars along the reserved steel bar grooves (2), then stacking the upper-layer building blocks, and enabling the end grooves (5) of each layer of building blocks to be attached to each other; each row of the stacked building blocks are arranged in an up-and-down alignment manner to form a neat seam;
2) pouring a bonding material into the end groove (5) of the uppermost-layer building block stacked in the step 1);
3) and the bonding material forms a bonding core column.
9. The construction process of the vertical-hole grouting type building block according to claim 8, wherein the left end and the right end of the building block in the step 1) are closely attached and connected with each other through a groove and tongue (7); in the step 2), filling the end grooves (5) of the piled blocks with bonding materials and compacting the bonding materials; 3-4 layers are stacked and grouted each time, and a column cavity formed by a groove (5) at the end part of the uppermost layer of the building block is not filled; the bonding material is bonding mortar or concrete.
10. The construction process of the vertical hole grouting type building block according to claim 9, characterized in that the building block is a building block with grouting holes (4), and in the step 2), the end groove (5) of the piled uppermost building block is filled with bonding material, and the grouting holes (4) are filled with bonding material and compacted with bonding material; 3-4 layers are stacked and grouted each time, and a column cavity and a grouting hole (4) formed by a groove (5) at the end part of the uppermost layer of the building block are not filled; the bonding material forms a bonding stem.
CN202010357820.1A 2020-04-29 2020-04-29 Vertical hole grouting type building block and construction process thereof Pending CN111411731A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010357820.1A CN111411731A (en) 2020-04-29 2020-04-29 Vertical hole grouting type building block and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010357820.1A CN111411731A (en) 2020-04-29 2020-04-29 Vertical hole grouting type building block and construction process thereof

Publications (1)

Publication Number Publication Date
CN111411731A true CN111411731A (en) 2020-07-14

Family

ID=71492216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010357820.1A Pending CN111411731A (en) 2020-04-29 2020-04-29 Vertical hole grouting type building block and construction process thereof

Country Status (1)

Country Link
CN (1) CN111411731A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111411732A (en) * 2020-04-29 2020-07-14 宫莉 Construction process for assembling vertical hole grouting type building blocks in flush joint mode

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477708A (en) * 2010-11-26 2012-05-30 李凤 Autoclaved aerated concrete building block
CN103174252A (en) * 2011-12-20 2013-06-26 江西省伟义科技发展有限公司 Self-thermal-insulation earthquake-proof building block and application method
CN205557993U (en) * 2016-04-07 2016-09-07 江苏建筑职业技术学院 Take vertical notes core and steel groove's porous assembled building block of heat preservation
CN205663092U (en) * 2016-04-07 2016-10-26 江苏建筑职业技术学院 Take vertical grouted core's porous assembled building block of heat preservation
CN206737164U (en) * 2017-05-23 2017-12-12 郑州大学 The self heat insulation wall of bridge cut-off built in screed
CN110042973A (en) * 2019-05-17 2019-07-23 宫莉 Vertical core grouting formula lightweight concrete internal partition wall in-filled block
CN111411732A (en) * 2020-04-29 2020-07-14 宫莉 Construction process for assembling vertical hole grouting type building blocks in flush joint mode

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102477708A (en) * 2010-11-26 2012-05-30 李凤 Autoclaved aerated concrete building block
CN103174252A (en) * 2011-12-20 2013-06-26 江西省伟义科技发展有限公司 Self-thermal-insulation earthquake-proof building block and application method
CN205557993U (en) * 2016-04-07 2016-09-07 江苏建筑职业技术学院 Take vertical notes core and steel groove's porous assembled building block of heat preservation
CN205663092U (en) * 2016-04-07 2016-10-26 江苏建筑职业技术学院 Take vertical grouted core's porous assembled building block of heat preservation
CN206737164U (en) * 2017-05-23 2017-12-12 郑州大学 The self heat insulation wall of bridge cut-off built in screed
CN110042973A (en) * 2019-05-17 2019-07-23 宫莉 Vertical core grouting formula lightweight concrete internal partition wall in-filled block
CN111411732A (en) * 2020-04-29 2020-07-14 宫莉 Construction process for assembling vertical hole grouting type building blocks in flush joint mode

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
丁红岩: "《图解砌体工程施工细部做法100讲》", 哈尔滨工业大学出版社, pages: 232 - 151 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111411732A (en) * 2020-04-29 2020-07-14 宫莉 Construction process for assembling vertical hole grouting type building blocks in flush joint mode

Similar Documents

Publication Publication Date Title
CN104358341B (en) Building brickwork and masonry construction method of building brickwork
CN201003216Y (en) Serial energy-saving heat preservation seepage control shearing wall interlocking concrete hollow building block
CN103046665B (en) Insulating mortar strengthening layer rowlock wall with steel wire mesh for setting hose tooth constructional column and manufacturing method thereof
CN103216024A (en) Self-heat-preservation mortar-free block masonry shear wall system and construction method thereof
CN102116061A (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN101285330A (en) Environment protection type structure thermal insulation concrete block, masonry and method for anti-knock domestic architecture
CN102444233A (en) Multifunctional assembling and pouring type templated block, use method and use thereof
CN113006363A (en) Vertical hole grouting type concrete internal partition wall filling building block
CN111155677B (en) Raw soil brick masonry structure with core column and construction method thereof
CN201224941Y (en) Environment protection type structure thermal insulation concrete building block, masonry and anti-vibration residential building
CN103556759A (en) Insulating and bearing shearing wall with cross-shaped embedded columns at central parts and single row of reinforcing bars and method
CN111411731A (en) Vertical hole grouting type building block and construction process thereof
CN111411732A (en) Construction process for assembling vertical hole grouting type building blocks in flush joint mode
CN102767290B (en) Construction method for retention position of constructional column of self-insulation sand aerated concrete block exterior wall
CN115807561B (en) Connection reinforcing structure of hollow decorative flower wall of ultra-high shale clear water brick and construction method thereof
CN202248483U (en) Multifunctional assembling pouring type modularized building block
CN210563378U (en) Assembled plate combined rammed earth wall
CN102127940B (en) Honeycomb structure wall body
CN103556754A (en) Single-line reinforcement thermal insulation bearing shear wall with T-shaped hidden posts at end parts and manufacturing method of shear wall
CN103556755A (en) Single-line reinforcement thermal insulation bearing shear wall with L-shaped hidden posts at end parts and manufacturing method of shear wall
CN103015563B (en) Outer-block inner-masonry building structure system
CN203296209U (en) Self-insulation mortarless block masonry shear wall system
CN203080733U (en) External built-mold and internal masonry building structure system
CN210086629U (en) Vertical hole grouting type light concrete inner partition wall filling building block
CN207003470U (en) A kind of pin-connected panel ecological anchor rod retaining wall structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination