CN110929993A - Engineering project management method and engineering project management system - Google Patents

Engineering project management method and engineering project management system Download PDF

Info

Publication number
CN110929993A
CN110929993A CN201911061995.1A CN201911061995A CN110929993A CN 110929993 A CN110929993 A CN 110929993A CN 201911061995 A CN201911061995 A CN 201911061995A CN 110929993 A CN110929993 A CN 110929993A
Authority
CN
China
Prior art keywords
construction
task
constructors
project
items
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911061995.1A
Other languages
Chinese (zh)
Inventor
郭小林
刘洪伟
赵晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guoyi Tiancheng Construction Engineering Technology Co Ltd
Original Assignee
Guoyi Tiancheng Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guoyi Tiancheng Construction Engineering Technology Co Ltd filed Critical Guoyi Tiancheng Construction Engineering Technology Co Ltd
Priority to CN201911061995.1A priority Critical patent/CN110929993A/en
Publication of CN110929993A publication Critical patent/CN110929993A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/067Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/109Time management, e.g. calendars, reminders, meetings or time accounting
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses an engineering project management method and an engineering project management system, which relate to engineering management and comprise the steps of obtaining a construction plan of an engineering; decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence; calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items; the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors; acquiring a construction request of a constructor for a task item, and verifying the construction request; and binding the constructors and the requested task items after the construction request passes the verification. On the one hand, the construction personnel can know the construction items and the content of the construction items in time, and know the task points and the salaries corresponding to the task items, so that the enthusiasm of the construction personnel can be promoted, on the other hand, the calculation of the salaries of the construction personnel is convenient, the autonomy is high, and the distribution is reasonable.

Description

Engineering project management method and engineering project management system
Technical Field
The present invention relates to engineering project management, and more particularly, to an engineering project management method and an engineering project management system.
Background
With the acceleration of the urbanization process, the urban construction is developed rapidly, the quantity of engineering projects is continuously increased, and more severe requirements are provided for the management of modern engineering projects.
Engineering project management typically includes schedule control, cost control, quality control, contract management, security management, organizational coordination, and risk and information management are also becoming increasingly important.
At present, chinese patent application No. 201810254210.1 discloses a construction management system and method, which includes a progress management module, a manpower management module, a project inspection management module, a material management module, an attendance management module, a logistics management module and a construction manager credit platform module. The construction record machine account management method has the advantages of reducing construction record machine account compiling and statistical checking work, improving working efficiency and ensuring construction quality.
Such a construction management system, while providing construction efficiency, provides room for improvement in how efficiently constructors can allocate and utilize.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide the engineering project management method which has the advantages of reasonable personnel distribution and full utilization.
In order to achieve the purpose, the invention provides the following technical scheme:
an engineering project management method comprises
Obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
By adopting the technical scheme, after a construction plan is obtained, a construction total amount is decomposed by taking a construction period as a reference by utilizing a construction decomposition model, task items which are arranged in a time sequence are generated, then a task point number table suitable for the current project is called, the task items and a certain number of task points are used for calculating constructor salaries, then the task items and the corresponding number of the task points are issued to constructors, construction requests of the constructors for each task item are obtained, the construction requests are verified, and after the verification is passed, the constructors and the task items are bound.
Further, invoking the task point table for the current project includes
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
By adopting the technical scheme, when the task point distribution table is determined, the construction conditions of the project are firstly obtained, the task point distribution table meeting the construction conditions is screened out from the preset library based on the construction conditions, then the selected result of the construction party on the task point distribution table is obtained, and the task point distribution table meeting the construction conditions and meeting the requirements of the construction party is further determined.
Further, the construction request carries identity information and qualification information of the constructors.
By adopting the technical scheme, the construction request comprises the identity information and qualification information of the constructors and is used for verifying the constructors.
Further, the construction request validation includes
The identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
By adopting the technical scheme, the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Aiming at the defects in the prior art, the second purpose of the invention is to provide an engineering project management system which has the advantages of reasonable personnel distribution and full utilization.
In order to achieve the purpose, the invention provides the following technical scheme:
an engineering project management system comprising a processor and a memory, the memory storing a set of instructions for the processor to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
By adopting the technical scheme, after a construction plan is obtained, a construction total amount is decomposed by taking a construction period as a reference by utilizing a construction decomposition model, task items which are arranged in a time sequence are generated, then a task point number table suitable for the current project is called, the task items and a certain number of task points are used for calculating constructor salaries, then the task items and the corresponding number of the task points are issued to constructors, construction requests of the constructors for each task item are obtained, the construction requests are verified, and after the verification is passed, the constructors and the task items are bound.
Further, the set of instructions also includes instructions for the processor to call to implement:
with a task point table adapted to the current project including
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
By adopting the technical scheme, when the task point distribution table is determined, the construction conditions of the project are firstly obtained, the task point distribution table meeting the construction conditions is screened out from the preset library based on the construction conditions, then the selected result of the construction party on the task point distribution table is obtained, and the task point distribution table meeting the construction conditions and meeting the requirements of the construction party is further determined.
Further, the set of instructions also includes instructions for the processor to call to implement:
the construction request carries identity information and qualification information of the constructors.
By adopting the technical scheme, the construction request comprises the identity information and qualification information of the constructors and is used for verifying the constructors.
Further, the set of instructions also includes instructions for the processor to call to implement:
the construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
By adopting the technical scheme, the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
In conclusion, the invention has the following beneficial effects:
1. the construction personnel can know the construction items and the contents thereof in time conveniently, and know the task points and the compensation corresponding to the task items, so that the enthusiasm of the construction personnel can be promoted, the autonomy is high, and the distribution is reasonable;
2. the compensation of constructors is convenient to calculate, only the number of task points is needed to be calculated, and the calculation amount is reduced;
3. the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Drawings
FIG. 1 is a flow chart illustrating a method for managing an engineering project according to the present invention;
FIG. 2 is a schematic diagram of an engineering project management system according to the present invention.
In the figure: 1. a processor; 2. a memory.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and examples.
The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications of the present embodiment without inventive contribution as needed after reading the present specification, but all of them are protected by patent law within the scope of the claims of the present invention.
Example 1
An engineering project management method, referring to fig. 1, includes steps S101 to S106.
Step S101: and obtaining a construction plan of the project, wherein the construction plan comprises the total construction amount and the construction period of the project.
Each project has a corresponding construction plan, and the construction plan specifically includes the total construction amount and the construction period, that is, how many construction amounts need to be completed in total, and the longest allowable time for completing the construction amounts.
Step S102: and decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence.
And decomposing the construction plan through a preset construction decomposition model to generate task items in a time sequence, wherein the task items are task contents finished by a single constructor or a plurality of constructors.
Step S103: and calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors.
Calling a task point number table suitable for the current project, wherein the task point number table comprises construction conditions of the current project; screening a task point table meeting construction conditions from a preset task point table; and obtaining a selected result aiming at the screened task point number table for calling.
After the task point table is determined, the number of the task points corresponding to each task item is searched and determined in the task point table, and the task point number is used for calculating compensation of constructors.
Step S104: and issuing the task items arranged in the time sequence of the project and the task points corresponding to the task items to constructors.
And then, the task items and the task points corresponding to the task items are released to the constructors, so that the constructors can know the completed specific work content and the corresponding reward conveniently, and further the constructors can be promoted to apply for the task items actively.
Step S105: and acquiring a construction request of a constructor for the task item, and verifying the construction request.
And after the constructor determines the task item suitable for the constructor, obtaining a construction request of the constructor for the selected task item, wherein the construction request carries identity information and qualification information of the constructor. The identity information corresponds to the unique identity of the constructor, and the qualification information is used for distinguishing which construction qualification capability the constructor has.
In addition, the construction request can also be the construction request of a certain construction team, for example, the task item is large and needs to be completed by team cooperation, and after the construction team applies for the construction request, the default degree and the familiarity of constructors are high, so that smooth, stable and efficient construction of a project is facilitated.
Step S106: and binding the constructors and the requested task items after the construction request passes the verification.
The construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item. The identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Example 2
An engineering project management system, referring to fig. 2, comprising a processor 1 and a memory 2, wherein the memory 2 stores an instruction set for the processor 1 to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
Obtaining the construction conditions of the current project by using a task point number table suitable for the current project; screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
The construction request carries identity information and qualification information of the constructors.
The construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
The above description is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments, and all technical solutions belonging to the idea of the present invention belong to the protection scope of the present invention. It should be noted that modifications and embellishments within the scope of the invention may occur to those skilled in the art without departing from the principle of the invention, and are considered to be within the scope of the invention.

Claims (8)

1. A project management method is characterized in that: comprises that
Obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
2. The project management method of claim 1, wherein: invoking a task point table appropriate for the current project includes
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
3. The project management method of claim 1, wherein: the construction request carries identity information and qualification information of the constructors.
4. The project management method of claim 3, wherein: the construction request is verified to include
The identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
5. An engineering project management system, characterized by: comprising a processor (1) and a memory (2), the memory (2) storing a set of instructions for the processor (1) to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
6. The project management system of claim 5, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
with a task point table adapted to the current project including
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
7. The project management system of claim 5, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
the construction request carries identity information and qualification information of the constructors.
8. The project management system of claim 7, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
the construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
CN201911061995.1A 2019-11-01 2019-11-01 Engineering project management method and engineering project management system Pending CN110929993A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911061995.1A CN110929993A (en) 2019-11-01 2019-11-01 Engineering project management method and engineering project management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911061995.1A CN110929993A (en) 2019-11-01 2019-11-01 Engineering project management method and engineering project management system

Publications (1)

Publication Number Publication Date
CN110929993A true CN110929993A (en) 2020-03-27

Family

ID=69850152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911061995.1A Pending CN110929993A (en) 2019-11-01 2019-11-01 Engineering project management method and engineering project management system

Country Status (1)

Country Link
CN (1) CN110929993A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112488547A (en) * 2020-12-09 2021-03-12 黑龙江建筑职业技术学院 Distribution management system based on engineering project management

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005135363A (en) * 2003-10-31 2005-05-26 Kudo Kensetsu Kk Method and program for determining amount of allowance and recording medium having this program recorded therein
CN105976234A (en) * 2016-05-04 2016-09-28 南京邮电大学 Method for realizing team-based incentive mechanism in mobile crowdsourcing system
CN106570679A (en) * 2016-10-27 2017-04-19 南京邮电大学 Participant capability based excitation method for crowdsourcing task of group
CN107918831A (en) * 2017-11-23 2018-04-17 深圳拎得清软件有限公司 BIM Schedule managements method and its system based on browser
CN108537427A (en) * 2018-03-29 2018-09-14 林秀丽 A kind of business course management method and device
CN109636183A (en) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 A kind of multiplexing kind recruitment coordinated management method and system based on big data
CN109754215A (en) * 2018-12-03 2019-05-14 上海夫卡实业发展有限公司 Technological design work management method, platform and the system quickly delivered

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005135363A (en) * 2003-10-31 2005-05-26 Kudo Kensetsu Kk Method and program for determining amount of allowance and recording medium having this program recorded therein
CN105976234A (en) * 2016-05-04 2016-09-28 南京邮电大学 Method for realizing team-based incentive mechanism in mobile crowdsourcing system
CN106570679A (en) * 2016-10-27 2017-04-19 南京邮电大学 Participant capability based excitation method for crowdsourcing task of group
CN107918831A (en) * 2017-11-23 2018-04-17 深圳拎得清软件有限公司 BIM Schedule managements method and its system based on browser
CN108537427A (en) * 2018-03-29 2018-09-14 林秀丽 A kind of business course management method and device
CN109754215A (en) * 2018-12-03 2019-05-14 上海夫卡实业发展有限公司 Technological design work management method, platform and the system quickly delivered
CN109636183A (en) * 2018-12-12 2019-04-16 上海荷福人工智能科技(集团)有限公司 A kind of multiplexing kind recruitment coordinated management method and system based on big data

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112488547A (en) * 2020-12-09 2021-03-12 黑龙江建筑职业技术学院 Distribution management system based on engineering project management

Similar Documents

Publication Publication Date Title
US20040024627A1 (en) Method and system for delivery of infrastructure components as they related to business processes
CN108491254A (en) A kind of dispatching method and device of data warehouse
CN105243335A (en) Rights management method and apparatus
CN105700938A (en) Multithread processing data method and device
Lami et al. Software sustainability from a process-centric perspective
CN107067175A (en) The management method and system of vehicle
CN104463005A (en) Method for controlling access permissions of electronic document
CN112200690A (en) Ship quality traceability system based on block chain
CN112184177A (en) Project supervision method, device and storage medium
CN111444692A (en) Intelligent environment experiment comprehensive control method, system, computer and storage medium
CN107369120A (en) A kind of smart business's management, service system and enterprise's activity assays
CN111125719B (en) Method, device, computer equipment and readable storage medium for improving code security detection efficiency
CN110929993A (en) Engineering project management method and engineering project management system
CN110348583A (en) A kind of unit maintenance progress dynamic management-control method
CN111833025A (en) Track cost management method, system and storage medium thereof
CN105574647A (en) Active intelligent in-place equipment management system
CN108428110A (en) A kind of acquisition methods of construction-engineering project management information
CN117078209A (en) Method, system and device for managing supervision project and computer storage medium
CN111899000A (en) Engineering data management method, device, computer equipment and storage medium
CN111767205A (en) Online detection method and system supporting task splitting
KR101494163B1 (en) Maintenance history management system for nuclear power plants using bar-code
CN112907220B (en) System, method and device for engineering cost
CN110007901A (en) A kind of development system collecting regimental wind-powered electricity generation monitor supervision platform and its operation method and development approach
CN105205652B (en) Revision method and revision system of ERP (enterprise resource planning) document
CN103530232B (en) A kind of software testing management framework establishment method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination