CN110929993A - Engineering project management method and engineering project management system - Google Patents
Engineering project management method and engineering project management system Download PDFInfo
- Publication number
- CN110929993A CN110929993A CN201911061995.1A CN201911061995A CN110929993A CN 110929993 A CN110929993 A CN 110929993A CN 201911061995 A CN201911061995 A CN 201911061995A CN 110929993 A CN110929993 A CN 110929993A
- Authority
- CN
- China
- Prior art keywords
- construction
- task
- constructors
- project
- items
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 37
- 238000010276 construction Methods 0.000 claims abstract description 150
- 238000012795 verification Methods 0.000 claims abstract description 13
- 238000000354 decomposition reaction Methods 0.000 claims abstract description 10
- 238000000034 method Methods 0.000 claims abstract description 9
- 238000012797 qualification Methods 0.000 claims description 30
- 238000012216 screening Methods 0.000 claims description 6
- 238000004364 calculation method Methods 0.000 abstract description 2
- 238000009430 construction management Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 230000001133 acceleration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 238000010200 validation analysis Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06316—Sequencing of tasks or work
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/067—Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/109—Time management, e.g. calendars, reminders, meetings or time accounting
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses an engineering project management method and an engineering project management system, which relate to engineering management and comprise the steps of obtaining a construction plan of an engineering; decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence; calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items; the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors; acquiring a construction request of a constructor for a task item, and verifying the construction request; and binding the constructors and the requested task items after the construction request passes the verification. On the one hand, the construction personnel can know the construction items and the content of the construction items in time, and know the task points and the salaries corresponding to the task items, so that the enthusiasm of the construction personnel can be promoted, on the other hand, the calculation of the salaries of the construction personnel is convenient, the autonomy is high, and the distribution is reasonable.
Description
Technical Field
The present invention relates to engineering project management, and more particularly, to an engineering project management method and an engineering project management system.
Background
With the acceleration of the urbanization process, the urban construction is developed rapidly, the quantity of engineering projects is continuously increased, and more severe requirements are provided for the management of modern engineering projects.
Engineering project management typically includes schedule control, cost control, quality control, contract management, security management, organizational coordination, and risk and information management are also becoming increasingly important.
At present, chinese patent application No. 201810254210.1 discloses a construction management system and method, which includes a progress management module, a manpower management module, a project inspection management module, a material management module, an attendance management module, a logistics management module and a construction manager credit platform module. The construction record machine account management method has the advantages of reducing construction record machine account compiling and statistical checking work, improving working efficiency and ensuring construction quality.
Such a construction management system, while providing construction efficiency, provides room for improvement in how efficiently constructors can allocate and utilize.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide the engineering project management method which has the advantages of reasonable personnel distribution and full utilization.
In order to achieve the purpose, the invention provides the following technical scheme:
an engineering project management method comprises
Obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
By adopting the technical scheme, after a construction plan is obtained, a construction total amount is decomposed by taking a construction period as a reference by utilizing a construction decomposition model, task items which are arranged in a time sequence are generated, then a task point number table suitable for the current project is called, the task items and a certain number of task points are used for calculating constructor salaries, then the task items and the corresponding number of the task points are issued to constructors, construction requests of the constructors for each task item are obtained, the construction requests are verified, and after the verification is passed, the constructors and the task items are bound.
Further, invoking the task point table for the current project includes
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
By adopting the technical scheme, when the task point distribution table is determined, the construction conditions of the project are firstly obtained, the task point distribution table meeting the construction conditions is screened out from the preset library based on the construction conditions, then the selected result of the construction party on the task point distribution table is obtained, and the task point distribution table meeting the construction conditions and meeting the requirements of the construction party is further determined.
Further, the construction request carries identity information and qualification information of the constructors.
By adopting the technical scheme, the construction request comprises the identity information and qualification information of the constructors and is used for verifying the constructors.
Further, the construction request validation includes
The identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
By adopting the technical scheme, the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Aiming at the defects in the prior art, the second purpose of the invention is to provide an engineering project management system which has the advantages of reasonable personnel distribution and full utilization.
In order to achieve the purpose, the invention provides the following technical scheme:
an engineering project management system comprising a processor and a memory, the memory storing a set of instructions for the processor to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
By adopting the technical scheme, after a construction plan is obtained, a construction total amount is decomposed by taking a construction period as a reference by utilizing a construction decomposition model, task items which are arranged in a time sequence are generated, then a task point number table suitable for the current project is called, the task items and a certain number of task points are used for calculating constructor salaries, then the task items and the corresponding number of the task points are issued to constructors, construction requests of the constructors for each task item are obtained, the construction requests are verified, and after the verification is passed, the constructors and the task items are bound.
Further, the set of instructions also includes instructions for the processor to call to implement:
with a task point table adapted to the current project including
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
By adopting the technical scheme, when the task point distribution table is determined, the construction conditions of the project are firstly obtained, the task point distribution table meeting the construction conditions is screened out from the preset library based on the construction conditions, then the selected result of the construction party on the task point distribution table is obtained, and the task point distribution table meeting the construction conditions and meeting the requirements of the construction party is further determined.
Further, the set of instructions also includes instructions for the processor to call to implement:
the construction request carries identity information and qualification information of the constructors.
By adopting the technical scheme, the construction request comprises the identity information and qualification information of the constructors and is used for verifying the constructors.
Further, the set of instructions also includes instructions for the processor to call to implement:
the construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
By adopting the technical scheme, the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
In conclusion, the invention has the following beneficial effects:
1. the construction personnel can know the construction items and the contents thereof in time conveniently, and know the task points and the compensation corresponding to the task items, so that the enthusiasm of the construction personnel can be promoted, the autonomy is high, and the distribution is reasonable;
2. the compensation of constructors is convenient to calculate, only the number of task points is needed to be calculated, and the calculation amount is reduced;
3. the identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Drawings
FIG. 1 is a flow chart illustrating a method for managing an engineering project according to the present invention;
FIG. 2 is a schematic diagram of an engineering project management system according to the present invention.
In the figure: 1. a processor; 2. a memory.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and examples.
The present embodiment is only for explaining the present invention, and it is not limited to the present invention, and those skilled in the art can make modifications of the present embodiment without inventive contribution as needed after reading the present specification, but all of them are protected by patent law within the scope of the claims of the present invention.
Example 1
An engineering project management method, referring to fig. 1, includes steps S101 to S106.
Step S101: and obtaining a construction plan of the project, wherein the construction plan comprises the total construction amount and the construction period of the project.
Each project has a corresponding construction plan, and the construction plan specifically includes the total construction amount and the construction period, that is, how many construction amounts need to be completed in total, and the longest allowable time for completing the construction amounts.
Step S102: and decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence.
And decomposing the construction plan through a preset construction decomposition model to generate task items in a time sequence, wherein the task items are task contents finished by a single constructor or a plurality of constructors.
Step S103: and calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors.
Calling a task point number table suitable for the current project, wherein the task point number table comprises construction conditions of the current project; screening a task point table meeting construction conditions from a preset task point table; and obtaining a selected result aiming at the screened task point number table for calling.
After the task point table is determined, the number of the task points corresponding to each task item is searched and determined in the task point table, and the task point number is used for calculating compensation of constructors.
Step S104: and issuing the task items arranged in the time sequence of the project and the task points corresponding to the task items to constructors.
And then, the task items and the task points corresponding to the task items are released to the constructors, so that the constructors can know the completed specific work content and the corresponding reward conveniently, and further the constructors can be promoted to apply for the task items actively.
Step S105: and acquiring a construction request of a constructor for the task item, and verifying the construction request.
And after the constructor determines the task item suitable for the constructor, obtaining a construction request of the constructor for the selected task item, wherein the construction request carries identity information and qualification information of the constructor. The identity information corresponds to the unique identity of the constructor, and the qualification information is used for distinguishing which construction qualification capability the constructor has.
In addition, the construction request can also be the construction request of a certain construction team, for example, the task item is large and needs to be completed by team cooperation, and after the construction team applies for the construction request, the default degree and the familiarity of constructors are high, so that smooth, stable and efficient construction of a project is facilitated.
Step S106: and binding the constructors and the requested task items after the construction request passes the verification.
The construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item. The identity information of the constructors is verified, illegal application of personnel except the constructors is avoided, the qualification information of the constructors is verified, and the construction qualification of the constructors is strictly controlled and strictly arranged at the distribution source.
Example 2
An engineering project management system, referring to fig. 2, comprising a processor 1 and a memory 2, wherein the memory 2 stores an instruction set for the processor 1 to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
Obtaining the construction conditions of the current project by using a task point number table suitable for the current project; screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
The construction request carries identity information and qualification information of the constructors.
The construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
The above description is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments, and all technical solutions belonging to the idea of the present invention belong to the protection scope of the present invention. It should be noted that modifications and embellishments within the scope of the invention may occur to those skilled in the art without departing from the principle of the invention, and are considered to be within the scope of the invention.
Claims (8)
1. A project management method is characterized in that: comprises that
Obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
2. The project management method of claim 1, wherein: invoking a task point table appropriate for the current project includes
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
3. The project management method of claim 1, wherein: the construction request carries identity information and qualification information of the constructors.
4. The project management method of claim 3, wherein: the construction request is verified to include
The identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
5. An engineering project management system, characterized by: comprising a processor (1) and a memory (2), the memory (2) storing a set of instructions for the processor (1) to call to implement:
obtaining a construction plan of a project, wherein the construction plan comprises the total construction amount and the construction period of the project;
decomposing the construction plan according to a preset construction decomposition model to generate task items arranged in time sequence;
calling a task point table suitable for the current project, wherein the task point table stores task points corresponding to all task items, and the task points are used for calculating compensation of constructors;
the method comprises the steps of issuing task items arranged in time sequence of the project and task points corresponding to the task items to constructors;
acquiring a construction request of a constructor for a task item, and verifying the construction request;
and binding the constructors and the requested task items after the construction request passes the verification.
6. The project management system of claim 5, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
with a task point table adapted to the current project including
Obtaining construction conditions of the current project;
screening a task point table meeting construction conditions from a preset task point table;
and obtaining a selected result aiming at the screened task point number table for calling.
7. The project management system of claim 5, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
the construction request carries identity information and qualification information of the constructors.
8. The project management system of claim 7, wherein: the set of instructions further comprises instructions for the processor (1) to call to implement:
the construction request verification comprises that the identity information of the constructors is the identity information stored in the server and the qualification information of the constructors conforms to the construction qualification of the task item.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911061995.1A CN110929993A (en) | 2019-11-01 | 2019-11-01 | Engineering project management method and engineering project management system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911061995.1A CN110929993A (en) | 2019-11-01 | 2019-11-01 | Engineering project management method and engineering project management system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110929993A true CN110929993A (en) | 2020-03-27 |
Family
ID=69850152
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911061995.1A Pending CN110929993A (en) | 2019-11-01 | 2019-11-01 | Engineering project management method and engineering project management system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110929993A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112488547A (en) * | 2020-12-09 | 2021-03-12 | 黑龙江建筑职业技术学院 | Distribution management system based on engineering project management |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005135363A (en) * | 2003-10-31 | 2005-05-26 | Kudo Kensetsu Kk | Method and program for determining amount of allowance and recording medium having this program recorded therein |
CN105976234A (en) * | 2016-05-04 | 2016-09-28 | 南京邮电大学 | Method for realizing team-based incentive mechanism in mobile crowdsourcing system |
CN106570679A (en) * | 2016-10-27 | 2017-04-19 | 南京邮电大学 | Participant capability based excitation method for crowdsourcing task of group |
CN107918831A (en) * | 2017-11-23 | 2018-04-17 | 深圳拎得清软件有限公司 | BIM Schedule managements method and its system based on browser |
CN108537427A (en) * | 2018-03-29 | 2018-09-14 | 林秀丽 | A kind of business course management method and device |
CN109636183A (en) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | A kind of multiplexing kind recruitment coordinated management method and system based on big data |
CN109754215A (en) * | 2018-12-03 | 2019-05-14 | 上海夫卡实业发展有限公司 | Technological design work management method, platform and the system quickly delivered |
-
2019
- 2019-11-01 CN CN201911061995.1A patent/CN110929993A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005135363A (en) * | 2003-10-31 | 2005-05-26 | Kudo Kensetsu Kk | Method and program for determining amount of allowance and recording medium having this program recorded therein |
CN105976234A (en) * | 2016-05-04 | 2016-09-28 | 南京邮电大学 | Method for realizing team-based incentive mechanism in mobile crowdsourcing system |
CN106570679A (en) * | 2016-10-27 | 2017-04-19 | 南京邮电大学 | Participant capability based excitation method for crowdsourcing task of group |
CN107918831A (en) * | 2017-11-23 | 2018-04-17 | 深圳拎得清软件有限公司 | BIM Schedule managements method and its system based on browser |
CN108537427A (en) * | 2018-03-29 | 2018-09-14 | 林秀丽 | A kind of business course management method and device |
CN109754215A (en) * | 2018-12-03 | 2019-05-14 | 上海夫卡实业发展有限公司 | Technological design work management method, platform and the system quickly delivered |
CN109636183A (en) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | A kind of multiplexing kind recruitment coordinated management method and system based on big data |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112488547A (en) * | 2020-12-09 | 2021-03-12 | 黑龙江建筑职业技术学院 | Distribution management system based on engineering project management |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20040024627A1 (en) | Method and system for delivery of infrastructure components as they related to business processes | |
CN108491254A (en) | A kind of dispatching method and device of data warehouse | |
CN105243335A (en) | Rights management method and apparatus | |
CN105700938A (en) | Multithread processing data method and device | |
Lami et al. | Software sustainability from a process-centric perspective | |
CN107067175A (en) | The management method and system of vehicle | |
CN104463005A (en) | Method for controlling access permissions of electronic document | |
CN112200690A (en) | Ship quality traceability system based on block chain | |
CN112184177A (en) | Project supervision method, device and storage medium | |
CN111444692A (en) | Intelligent environment experiment comprehensive control method, system, computer and storage medium | |
CN107369120A (en) | A kind of smart business's management, service system and enterprise's activity assays | |
CN111125719B (en) | Method, device, computer equipment and readable storage medium for improving code security detection efficiency | |
CN110929993A (en) | Engineering project management method and engineering project management system | |
CN110348583A (en) | A kind of unit maintenance progress dynamic management-control method | |
CN111833025A (en) | Track cost management method, system and storage medium thereof | |
CN105574647A (en) | Active intelligent in-place equipment management system | |
CN108428110A (en) | A kind of acquisition methods of construction-engineering project management information | |
CN117078209A (en) | Method, system and device for managing supervision project and computer storage medium | |
CN111899000A (en) | Engineering data management method, device, computer equipment and storage medium | |
CN111767205A (en) | Online detection method and system supporting task splitting | |
KR101494163B1 (en) | Maintenance history management system for nuclear power plants using bar-code | |
CN112907220B (en) | System, method and device for engineering cost | |
CN110007901A (en) | A kind of development system collecting regimental wind-powered electricity generation monitor supervision platform and its operation method and development approach | |
CN105205652B (en) | Revision method and revision system of ERP (enterprise resource planning) document | |
CN103530232B (en) | A kind of software testing management framework establishment method and device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |