CN110348583A - A kind of unit maintenance progress dynamic management-control method - Google Patents

A kind of unit maintenance progress dynamic management-control method Download PDF

Info

Publication number
CN110348583A
CN110348583A CN201910510582.0A CN201910510582A CN110348583A CN 110348583 A CN110348583 A CN 110348583A CN 201910510582 A CN201910510582 A CN 201910510582A CN 110348583 A CN110348583 A CN 110348583A
Authority
CN
China
Prior art keywords
maintenance
project
plan
time
repair
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910510582.0A
Other languages
Chinese (zh)
Inventor
高丽
张亚武
张健
吕志来
刘念浩
常玉红
牛晓波
李建光
宋旭峰
温国强
郑凯
姜海山
黄正博
郭帅
刘向东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maintenance Branch Of State Grid Xin Yuan Co Ltd
State Grid Corp of China SGCC
Henan University
State Grid Xinyuan Co Ltd
Beijing Xuji Electric Co Ltd
Original Assignee
Maintenance Branch Of State Grid Xin Yuan Co Ltd
State Grid Corp of China SGCC
Henan University
State Grid Xinyuan Co Ltd
Beijing Xuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maintenance Branch Of State Grid Xin Yuan Co Ltd, State Grid Corp of China SGCC, Henan University, State Grid Xinyuan Co Ltd, Beijing Xuji Electric Co Ltd filed Critical Maintenance Branch Of State Grid Xin Yuan Co Ltd
Priority to CN201910510582.0A priority Critical patent/CN110348583A/en
Publication of CN110348583A publication Critical patent/CN110348583A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0633Workflow analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of unit maintenance progress dynamic management-control method, comprising: maintenance deposit project library, power station equipment fortune inspection regulation library;It is numbered according to the title event used when being executed for overhauling project that the content of approved in the maintenance deposit project library generates, to work out pre-planned and annual plan;Fortune overhaul period, frequency and deadline last time in inspection regulation library are transported according to power station equipment, automatic or manual generates repair and maintenance plan;Execute overhauling project implementation, repair and maintenance work order, field operation mobile application;Dynamic control is carried out to unit maintenance progress according to repair and maintenance work order;Wherein the execution of the repair and maintenance work order passes through the repair and maintenance plan manual creation after approval.

Description

A kind of unit maintenance progress dynamic management-control method
Technical field
The present embodiments relate to technical field of data processing, in particular to unit maintenance progress dynamic management-control method.
Background technique
Cross-region distribution in hydroelectric power plant, China is wide, unit number of units is more, unit capacity is different, administrative standard disunity, management water Put down that irregular, Safety Risk in Production is high.Hydro power plant is in order to reduce Safety Risk in Production, reduce management level difference, uniformly Administrative standard promotes management level, and the progress of realization is shown to be associated with mobile operation, can real-time query main line progress and subsystem work The executive condition of the performance of industry project and related job file;According to on-site actual situations, dynamic can be carried out to progress Adjustment, realizes the timely prompting function of deviation, the final control for realizing field operation progress.But existing unit maintenance progress Dynamic is managed, and is all by manual control.
Summary of the invention
Aiming at the problem that dynamic control of unit maintenance progress exists in the prior art relying primarily on labor management, one is proposed Kind unit maintenance progress dynamic management-control method, to improve the accuracy of data processing.
To solve the above-mentioned problems, the embodiment of the present invention proposes a kind of unit maintenance progress dynamic management-control method, comprising:
Maintenance deposit project library, power station equipment fortune inspection regulation library;Wherein lay in includes at least one below in project library Data: unit maintenance project essential information, project equipment detail, scale, effect, project necessity, project alternative, project economic With financial compliance, the contents of a project, the unit maintenance project budget;Wherein power station equipment fortune inspection regulation library in include it is below at least A kind of data: device tree, regulation, issue date, more new description, version, reference directive/guide, equipment Maintenance Type, inspection item, item Mesh foundation/source, period check and accept grade, events in operation and process, technique requirement and quality standard, points for attention, quality control Record.
It is generated according to the content of approved in the maintenance deposit project library formal for being used when overhauling project execution Project number, to work out pre-planned and annual plan;Wherein pre-planned and annual plan is described pre-planned and annual plan packet Include at least one data below: year, batch, project name, total cost, plan starting date, plan time of accomplishment;According to Fortune overhaul period, frequency and deadline last time in power station equipment fortune inspection regulation library, automatic or manual generate repair and maintenance meter It draws, wherein repair and maintenance plan includes at least one data below: year, task names, job class, action, meter Draw starting date, plan time of accomplishment, teams and groups, work responsible person;
Execute overhauling project implementation, repair and maintenance work order, field operation mobile application;Wherein overhauling project executes content packet It includes: in maintenance target, main line progress total construction period, node progression time, overhauling project, responsible person, quality standard, examination grade etc. Hold.
Dynamic control is carried out to unit maintenance progress according to repair and maintenance work order;The wherein execution of the repair and maintenance work order By the repair and maintenance plan manual creation after approval, content includes: key operation project, responsible person, checks and accepts grade, operation base This requirement, overhaul process, quality standard, points for attention.
Wherein, the method also includes:
By field operation mobile application, execute through the downloading of job instruction information, displaying, work in repair and maintenance work order It checks and accepts, and upkeep operation progress synchronous with water power Production MIS, cancels in production management system on the line of industry project In backfill.
Wherein, the method also includes:
Implemented by overhauling project, repair and maintenance work order obtains unit maintenance progress multidate information;
Wherein main line progress shows that content includes: unit, unit maintenance main line task, plan on-stream time, plan Time of completion, practical on-stream time, practical completion time, state;
Wherein branch line progress shows that content includes: unit, unit maintenance branch line task, planned start time, plan End time, on-stream time, take-down time, repairing time, the time of reassembling, time of completion.
The advantageous effects of the above technical solutions of the present invention are as follows: the embodiment of the present invention proposes a kind of unit maintenance progress Dynamic management-control method completes maintenance dimension using mobile terminal by combining water power production management system with mobile operation APP The field operations such as data record are protected, realizes that mobile terminal data record is synchronous with production management system, effectively controls safety Production risk, the field operation progress dynamic of realization are managed, and failure rate is reduced, and improve unit reliability of operation, for company's fortune inspection Management standardization, lean provide strong support.
Detailed description of the invention
Fig. 1 is the flow diagram of the embodiment of the present invention.
Specific embodiment
To keep the technical problem to be solved in the present invention, technical solution and advantage clearer, below in conjunction with attached drawing and tool Body embodiment is described in detail.
As shown in Figure 1 it is the unit maintenance progress dynamic management-control method of the embodiment of the present invention, combines water power production management System and mobile application APP.Wherein system flow is maintenance deposit project library, power station equipment fortune in water power production management system Regulation library is examined, pre-planned and annual plan, repair and maintenance plan are worked out, executes overhauling project implementation, repair and maintenance work order, scene Operation mobile application, unit maintenance progress dynamic are managed.
Wherein, the unit maintenance progress dynamic management-control method of the embodiment of the present invention includes:
Maintenance deposit project library, power station equipment fortune inspection regulation library;
Work out pre-planned and annual plan, repair and maintenance plan;
Execute overhauling project implementation, repair and maintenance work order, field operation mobile application;
Unit maintenance progress dynamic is managed.
Wherein, the project information in maintenance power station equipment fortune inspection regulation library includes Power Plant Equipment-tree, regulation, date of issue Phase, more new description, version, reference directive/guide, type (A is repaired, B is repaired, C is repaired, D is repaired), inspection item, project foundation/source, the period, Check and accept grade, events in operation and process, technique requires and quality standard, points for attention, quality control record.
Wherein, the establishment repair and maintenance plan goes into operation including year, task names, job class, action, plan The contents such as date, plan time of accomplishment, teams and groups, work responsible person.Repair and maintenance task can transport inspection regulation function by power station equipment Period, frequency and deadline last time automatically generate in energy, can also manual creation repair and maintenance task.
Wherein, the repair and maintenance work order that executes includes key operation project, responsible person, the examination etc. in job instruction Grade, operation basic demand, overhaul process, quality standard, points for attention.
Wherein, the execution field operation mobile application includes by job instruction information downloading in repair and maintenance work order (task, time started, planned time, responsible person, elemental operation condition etc.) shows, checks and accepts (master on the line of events in operation Job is wanted to check and accept opinion, signer, signature time), and upkeep operation progress synchronous with water power Production MIS.
Wherein, the unit maintenance progress dynamic control information is implemented and repair and maintenance work order function from overhauling project Energy.
Wherein, the unit maintenance progress dynamic control display information includes unit in main line progress, unit maintenance main line Task, plan on-stream time, plan time of completion, practical on-stream time, practical completion time, state;In branch line progress When unit, unit maintenance branch line task, planned start time, planned end time, on-stream time, take-down time, repairing Between, reassemble time, time of completion.
Wherein, unit maintenance progress dynamic control adjustment information include on-stream time, the take-down time, the repairing time, Reassemble time, time of completion.
Specifically: can in real time, effectively grasp the actual progress of control field operation, this hair to solve production management personnel The bright one kind that provides is based on water power production management system unit maintenance progress dynamic management-control method.It is characterized in that, water power produces Management system is combined with mobile operation APP, and wherein its operation flow is (1) maintenance deposit project library, power station equipment fortune inspection rule Cheng Ku;(2) pre-planned and annual plan, repair and maintenance plan are worked out;(3) it executes overhauling project implementation, repair and maintenance work order, show Field operation mobile application (4) unit maintenance progress dynamic is managed.The present invention realizes can real-time query main line progress and subsystem work The executive condition of the performance of industry project and related job file, and according to on-site actual situations, progress can be moved State adjustment, realizes the timely prompting function of deviation, the final control for realizing field operation progress.
Wherein, deposit project library maintenance include: unit maintenance project essential information, project equipment detail, scale, effect, The contents such as project necessity, project alternative, project economic and financial compliance, the contents of a project, the unit maintenance project budget.
Wherein, power station equipment fortune inspection regulation library maintenance includes: device tree, regulation, issue date, more new description, version, draws With directive/guide, type (A is repaired, B is repaired, C is repaired, D is repaired), inspection item, project foundation/source, the period, check and accept grade, events in operation and Process, technique requires and quality standard, points for attention, quality control the contents such as record.
Wherein, it is contemplated that draw and annual plan establishment include: year, batch, project name, total cost, plan starting date, Contents, the unit maintenance contents of a project such as plan time of accomplishment are only capable of the deposit item-function module of source approved.Plan approval After could generate title event number, for overhauling project execute when use.
Wherein, repair and maintenance planning includes: year, task names, job class, action, plan stream day The contents such as phase, plan time of accomplishment, teams and groups, work responsible person.Repair and maintenance task can transport inspection regulation function by power station equipment Middle period, frequency and deadline last time automatically generate, can also manual creation repair and maintenance task.
Wherein, it includes: maintenance target, main line progress total construction period (planned start time, plan knot that overhauling project, which executes content, The beam time), node progression time (go into operation, dismantle, repairing, reassembling, being completed), overhauling project, responsible person, quality standard, examination The contents such as grade.
Wherein, by the repair and maintenance plan manual creation after approval, content includes: main for the execution of repair and maintenance work order Events in operation, responsible person, examination grade, operation basic demand, overhaul process, quality standard, points for attention etc..
Wherein, field operation mobile application is executed through job instruction information downloading (work times in repair and maintenance work order Business, time started, planned time, responsible person, elemental operation condition etc.), show, check and accept (groundwork on the lines of events in operation Project acceptance inspection opinion, signer, signature time), and upkeep operation progress synchronous with water power Production MIS, cancel Backfill in production management system, avoids repeated work, improves the efficiency of job management, is functional module in mobile operation APP, Client can pass through the function of these authorizations of dedicated mobile phone access.
Wherein, unit maintenance progress multidate information is shown from overhauling project implementation, repair and maintenance work order, main line progress Content includes: unit, unit maintenance main line task, plan on-stream time, plan time of completion, practical on-stream time, reality Border time of completion, state;Branch line progress show content include: unit, unit maintenance branch line task, planned start time, Planned end time, on-stream time, take-down time, repairing time, the time of reassembling, time of completion.
Wherein, power plant's production management personnel, new source corporate operations personnel even if not at the scene can also pass through log in water power Unit maintenance progress dynamic control function grasps unit main line progress and branch line progress, in real time to machine in production management system It includes: on-stream time, take-down time, repairing time, the time of reassembling, time of completion that group, which carries out dynamic adjustment,.
The above is a preferred embodiment of the present invention, it is noted that for those skilled in the art For, without departing from the principles of the present invention, it can also make several improvements and retouch, these improvements and modifications It should be regarded as protection scope of the present invention.

Claims (3)

1. a kind of unit maintenance progress dynamic management-control method characterized by comprising
Maintenance deposit project library, power station equipment fortune inspection regulation library;Wherein lay in project library includes at least one data below: Unit maintenance project essential information, project equipment detail, scale, effect, project necessity, project alternative, project economic and wealth Business compliance, the contents of a project, the unit maintenance project budget;It include wherein at least one below in power station equipment fortune inspection regulation library Data: device tree, regulation, issue date, more new description, version, reference directive/guide, equipment Maintenance Type, inspection item, project according to According to/source, period, check and accept grade, events in operation and process, technique requires and quality standard, points for attention, quality control record It is single.
The title event used when being executed for overhauling project generated according to the content of approved in the maintenance deposit project library Number, to work out pre-planned and annual plan;Wherein pre-planned and annual plan be described pre-planned and annual plan include with Under at least one data: year, batch, project name, total cost, plan starting date, plan time of accomplishment;According to power station Fortune overhaul period, frequency and deadline last time in equipment fortune inspection regulation library, automatic or manual generate repair and maintenance plan, Middle repair and maintenance plan includes at least one data below: year, task names, job class, action, plan go into operation Date, plan time of accomplishment, teams and groups, work responsible person;
Execute overhauling project implementation, repair and maintenance work order, field operation mobile application;Wherein overhauling project execution content includes: It overhauls target, main line progress total construction period, node progression time, overhauling project, responsible person, quality standard, check and accept the contents such as grade.
Dynamic control is carried out to unit maintenance progress according to repair and maintenance work order;Wherein the execution of the repair and maintenance work order passes through Repair and maintenance plan manual creation after approval, content include: key operation project, responsible person, check and accept grade, operation and want substantially It asks, overhaul process, quality standard, points for attention.
2. unit maintenance progress dynamic management-control method according to claim 1, which is characterized in that the method also includes:
By field operation mobile application, execute through the downloading of job instruction information, displaying, operation item in repair and maintenance work order It checks and accepts, and upkeep operation progress synchronous with water power Production MIS, cancels in production management system on purpose line Backfill.
3. unit maintenance progress dynamic management-control method according to claim 1, which is characterized in that the method also includes:
Implemented by overhauling project, repair and maintenance work order obtains unit maintenance progress multidate information;
Wherein main line progress shows that content includes: unit, unit maintenance main line task, plan on-stream time, plan completion Time, practical on-stream time, practical completion time, state;
Wherein branch line progress shows that content includes: that unit, unit maintenance branch line task, planned start time, plan terminate Time, on-stream time, take-down time, repairing time, the time of reassembling, time of completion.
CN201910510582.0A 2019-06-13 2019-06-13 A kind of unit maintenance progress dynamic management-control method Pending CN110348583A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910510582.0A CN110348583A (en) 2019-06-13 2019-06-13 A kind of unit maintenance progress dynamic management-control method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910510582.0A CN110348583A (en) 2019-06-13 2019-06-13 A kind of unit maintenance progress dynamic management-control method

Publications (1)

Publication Number Publication Date
CN110348583A true CN110348583A (en) 2019-10-18

Family

ID=68181952

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910510582.0A Pending CN110348583A (en) 2019-06-13 2019-06-13 A kind of unit maintenance progress dynamic management-control method

Country Status (1)

Country Link
CN (1) CN110348583A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495356A (en) * 2023-12-18 2024-02-02 成都秦川物联网科技股份有限公司 Intelligent gas pipeline maintenance method based on man-machine linkage and Internet of things system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102915479A (en) * 2012-09-25 2013-02-06 陕西陕煤黄陵矿业有限公司 Power plant asset management system
CN103366259A (en) * 2013-07-30 2013-10-23 国家电网公司 Method for planning inspection project in hydroelectric production management system
CN105809575A (en) * 2016-03-29 2016-07-27 国家电网公司 Mobile operation system and method for water and electricity production management
CN107798488A (en) * 2017-11-24 2018-03-13 国网内蒙古东部电力有限公司 A kind of grid maintenance engineering Stores Management System
US20180165658A1 (en) * 2016-12-09 2018-06-14 Yokogawa Electric Corporation Device asset management apparatus, device asset management method, and non-transitory computer readable storage medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102915479A (en) * 2012-09-25 2013-02-06 陕西陕煤黄陵矿业有限公司 Power plant asset management system
CN103366259A (en) * 2013-07-30 2013-10-23 国家电网公司 Method for planning inspection project in hydroelectric production management system
CN105809575A (en) * 2016-03-29 2016-07-27 国家电网公司 Mobile operation system and method for water and electricity production management
US20180165658A1 (en) * 2016-12-09 2018-06-14 Yokogawa Electric Corporation Device asset management apparatus, device asset management method, and non-transitory computer readable storage medium
CN107798488A (en) * 2017-11-24 2018-03-13 国网内蒙古东部电力有限公司 A kind of grid maintenance engineering Stores Management System

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘红超 等: ""集团级一体化、大集中水电生产管理信息系统的设计与实现"", 《水电自动化与大坝监测》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117495356A (en) * 2023-12-18 2024-02-02 成都秦川物联网科技股份有限公司 Intelligent gas pipeline maintenance method based on man-machine linkage and Internet of things system
CN117495356B (en) * 2023-12-18 2024-03-26 成都秦川物联网科技股份有限公司 Intelligent gas pipeline maintenance method based on man-machine linkage and Internet of things system

Similar Documents

Publication Publication Date Title
CN104951905A (en) Equipment dynamic ledger management system
CN103268531B (en) A kind of energy diode platform for energy centre
CN107368951A (en) A kind of power grid enterprises' technological transformation Overhaul Quality management and control honesty Warning System and its operation method
CN106372302A (en) Tower crane automatic model selection and optimization system and method based on BIM (Building Information Modeling) technology
CN110555609A (en) Hydropower station field standardized operation management and control system and method
Senaratne et al. Evaluation of application of lean principles to precast concrete bridge beam production process
CN107169894A (en) Real estate operation management system based on SAP
CN110348583A (en) A kind of unit maintenance progress dynamic management-control method
CN110363402A (en) A kind of factory personnel dispatching method based on grouping strategy
CN105574647A (en) Active intelligent in-place equipment management system
CN104599061A (en) Method for calculating project amount of road bridge engineering project
CN201974848U (en) Management system for comprehensively arranging and executing maintenance plan of production equipment
CN110929993A (en) Engineering project management method and engineering project management system
CN102622678A (en) System for managing tobacco production infrastructures
CN106021571A (en) Method and device for generating oil production engineering scheme
CN105139114A (en) Automatic compiling method for annual operation mode of power grid in district or county
CN111444698A (en) Building project management method and system
Cao et al. Applied research of activity-based costing under ERP environment
Handa et al. Downgrading construction incidents
CN106097160A (en) The foundation of electricity power engineering technological transformation maintenance specialized engineering amount list counts system
Ye et al. The cost control of communication construction projects: Case study of Zhejiang post and telecommunication construction corporation
Energy et al. Cost-benefit analysis
Yanjin Application of MS-Project in Scientific Research Project Management
CN117875616A (en) Maintenance management method and system for equipment of electric power construction enterprise
Topchiy Information Support for Industrial Area Redevelopment Projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191018