CN103366259A - Method for planning inspection project in hydroelectric production management system - Google Patents

Method for planning inspection project in hydroelectric production management system Download PDF

Info

Publication number
CN103366259A
CN103366259A CN2013103226359A CN201310322635A CN103366259A CN 103366259 A CN103366259 A CN 103366259A CN 2013103226359 A CN2013103226359 A CN 2013103226359A CN 201310322635 A CN201310322635 A CN 201310322635A CN 103366259 A CN103366259 A CN 103366259A
Authority
CN
China
Prior art keywords
project
overhauling
plant
maintenance
nonstandard
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103226359A
Other languages
Chinese (zh)
Inventor
冯伊平
李华
荆岫岩
刘红超
李国和
张亚武
宋旭峰
张健
宋湘辉
常玉红
李冬华
温国强
陈清水
李国东
黄正博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Beijing Xuji Electric Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Xinyuan Co Ltd
Beijing Xuji Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Xinyuan Co Ltd, Beijing Xuji Electric Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN2013103226359A priority Critical patent/CN103366259A/en
Publication of CN103366259A publication Critical patent/CN103366259A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a method for planning an inspection project in a hydroelectric production management system. The method comprises inspection reserve project planning, inspection reserve project declaration, inspection annular plan, inspection project change, inspection project working plan, inspection project monthly report and inspection project annual summary. By virtue of the method disclosed by the invention, the management level of the inspection project planning by a hydroelectric company can be improved, the management work of the system inspection project by a hydroelectric company is standardized, the equipment inspection quality and the running reliability are improved, the production cost is reasonably controlled, and the safe, stable and economical running of power generating facilities and equipment is ensured.

Description

Water power production management system overhauling project method of planning
Technical field
The invention belongs to water power production management system field, particularly a kind of water power production management system overhauling project method of planning.
Background technology
That China hydroelectric power plant's cross-region distributes is wide, the unit number of units is many, unit capacity differs, administrative standard disunity, management level mixed, Safety Risk in Production are high.Water power company is in order to reduce Safety Risk in Production, to dwindle management level difference, the unified management standard, promoting management level, carry out hydroelectric power plant's production management system overhauling project planning management, to reach standardization, standardization and the lean requirement of hydroelectric power plant's management.
Summary of the invention
Fundamental purpose of the present invention is to provide a kind of water power production management system overhauling project method of planning, to promote the water power company fortune inspection efficiency of management, standard water power company system overhaul Project Management, improve Plant maintenance quality and operational reliability, rationally the production control cost guarantees safe, stable, the economical operation of power generating equipment, equipment.
To achieve these goals, the present invention by the following technical solutions, a kind of water power production management system overhauling project method of planning, comprise: the establishment of maintenance deposit project, the project application of maintenance deposit, overhauling project annual plan, the overhauling project change, the overhauling project work program, overhauling project monthly magazine, overhauling project annual summary.
Project information in the described maintenance deposit project establishment comprises that bullets, item description, year, year investment, specialty segmentation, maintenance type, project status, power plant are called for short.
The flow process of the described maintenance deposit project application is, plant project establishment people writes the deposit project of next year overhauling, plant project and gathers the people and gather that the deposit project of next year overhauling, plant project person approving are examined project, plant project is examined project Approved by approval project, the project person approving of company.
The flow process of described overhauling project annual plan is, plant project establishment people writes that annual plan is examined in next year overhauling project plan, plant project person approving, plant project is examined power plant's annual plan Approved by approval annual plan, the project person approving of company.
The flow process of described overhauling project change is, plant project establishment people writes that overhauling project changed content in the current year, plant project person approving are examined the project changed content, plant project is examined the project changed content Approved by approval project changed content, the project person approving of company.
The flow process of described overhauling project work program is, plant project establishment people writes that overhauling project work program in the current year, plant project person approving are examined the overhauling project work program, plant project is examined the overhauling project work program Approved by approval overhauling project work program, the project person approving of company.
The flow process of described overhauling project monthly magazine is, plant project establishment people writes that this month overhauling project monthly magazine, plant project person approving are examined the overhauling project monthly magazine, plant project is examined the overhauling project monthly magazine Approved by approval overhauling project monthly magazine, the project person approving of company.
The flow process of described overhauling project annual summary is, plant project establishment people write the current year overhauling project sum up, plant project person approving examines the overhauling project annual summary, plant project is examined the overhauling project annual summary Approved by approval overhauling project annual summary, the project person approving of company.
Further, the overhauling project planning management is the application program of a B/S framework, is a functional module of water power production management system, and the client can access by the browser mode function of these mandates.
Further, overhauling project refers to as recovering and improve the general level of the health and the reliability of production facility, equipment, eliminate facility, equipment deficiency, hidden danger or the fault that takes place frequently, partial structurtes or the part of facility, equipment checked, repairs, improves and do not consist of the engineering project of new capital assets.
Further, the establishment of maintenance deposit project realizes that the hydroelectric power plant is to functions such as newly-increased, the deletion of maintenance deposit project, modification, inquiries; Deposit project establishment is detailed by bulleted list, project, the nonstandard project of unit maintenance, four Shipping Options Pages of msu message form.Wherein bulleted list has been realized the query function of deposit project, can inquire about according to conditions such as bullets, item description, item types, specialty segmentation, year, state, power plant.Choose a list-item or a newly-increased maintenance deposit project, can switch to the detailed Shipping Options Page of project, this Shipping Options Page shows the details of maintenance deposit project.The inquiry of the nonstandard project under the unit maintenance project that the nonstandard item label page or leaf of unit maintenance is realized choosing, newly-increased, deletion and modify feature.The msu message Shipping Options Page shows the audit opinion of this maintenance deposit project.
Further, newly-increased, the deletion of maintenance deposit project, preserve operation and realize by the toolbar button in the establishment of maintenance deposit project.State and the state in the nonstandard project of unit maintenance in the maintenance deposit project all are the rough draft state when newly-built, and its state of change is approved or cancellation in maintenance deposit project application workflow.When maintenance deposit project status was approved, this record can not be revised and delete; When maintenance deposit project status is cancellation or rough draft, can revise and delete.
Further, the project application of maintenance deposit realizes the workflow examination and approval of hydroelectric power plant's maintenance deposit project, comprise declare tabulation, the project of declaring is detailed, declare reply situation, approval information, five Shipping Options Pages of relevant documentation.In some optional embodiments, maintenance deposit project application flow process as shown in Figure 2, minute five service links are respectively that plant project establishment people writes the deposit project of next year overhauling, plant project and gathers the people and gather that the deposit project of next year overhauling, plant project person approving are examined project, plant project is examined project Approved by approval project, the project person approving of company.
Further, declare the tabulation Shipping Options Page and realize that maintenance deposit project gathers the inquiry of tabulation, declaring tabulation is the summary record of a plurality of maintenance deposit projects, comprises at least a maintenance deposit project, can repeatedly overhaul declaring of deposit project in 1 year.A summary record is exactly the running example of a workflow, the suggestions made after examination of workflow are in the approval information Shipping Options Page, it is the suggestion of examining for a summary record, each maintenance deposit project can have one or more audit opinions in addition, is the msu message of the project of laying in for single maintenance in person approving's review process.
Further, the detailed Shipping Options Page of the project of declaring divides up and down two parts, upper part show declare choose in the tabulation declare the record details, lower part shows that this declares the unit maintenance that comprises in the record, nonstandard project, nonstandard bulleted list below 300,000 more than 300,000.
Further, unit maintenance tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, the selection of realization unit maintenance project and nonstandard project, removes and examine function.And the option button below the unit maintenance tabulation carries out the selection of unit maintenance project.Click option button ejects next year, and state is the unit maintenance deposit bulleted list window of rough draft and cancellation, and select by the mode of choosing record, after clicking the confirming button in the pop-up window, the record of selecting is shown in the unit maintenance tabulation, and the project that occurs in the unit maintenance tabulation can not show in pop-up window.Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit project.Click the detailed button of project in the unit maintenance tabulation, can eject the detailed window of maintenance deposit project.
Further, nonstandard item label page or leaf is comprised of the tabulation of nonstandard project list and option button more than 300,000 more than 300,000, realize nonstandard project more than 300,000 selection, remove and audit function.Nonstandard item label page or leaf below 300,000 is comprised of the tabulation of nonstandard project list below 300,000 and option button, realize nonstandard project below 300,000 selection, remove and audit function.Click the detailed button of the project in (or following) nonstandard bulleted list more than 300,000, can eject the detailed content window of this nonstandard project.
Further, declare reply situation Shipping Options Page and divide up and down two parts, upper part show declare choose in the tabulation declare the record details, lower part shows that this declares the unit maintenance reply that comprises in the record, nonstandard project reply, nonstandard project 300,000 below are given an written reply and tabulated 300,000 or more.Comprise the detailed button of project in each reply tabulation, click the detailed button of project of certain project, eject the Entry Details window, comprise the suggestions made after examination Shipping Options Page in the window, this Shipping Options Page is realized the suggestions made after examination typing of single maintenance deposit project.
Further, unit maintenance reply tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, realizes the reply audit function of unit maintenance project and nonstandard project.The reply content comprise reply annual charge (ten thousand yuan), reply maintenance grade, reply plan on-stream time, reply plan time of completion, reply plan time (my god).Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit project.
Further, nonstandard project is given an written reply the reply audit function that Shipping Options Page is realized nonstandard project more than 300,000 more than 300,000.Nonstandard project reply Shipping Options Page below 300,000 is realized the reply audit function of nonstandard project below 300,000.The reply content comprise reply annual charge (ten thousand yuan), reply plan on-stream time, reply plan time of completion, reply plan time (my god).
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to maintenance deposit project information replenishes.Upload button below the document attachment tabulation, realize uploading of local file.
Further, the overhauling project annual plan realize the hydroelectric power plant the annual overhaul project scheduling establishment and examine process, comprise that list of schedules, turnaround plan report, plan reply situation, approval information, five Shipping Options Pages of relevant documentation.In some optional embodiments, overhauling project annual plan flow process as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that annual plan is examined in next year overhauling project plan, plant project person approving, plant project is examined power plant's annual plan Approved by approval annual plan, the project person approving of company.
Further, the list of schedules Shipping Options Page is realized the inquiry that the annual overhaul project scheduling gathers, and list of schedules is the summary record of a plurality of overhauling project plans, comprises at least an overhauling project plan, can carry out declaring of an overhauling project plan in 1 year.A summary record is exactly the running example of a workflow, the suggestions made after examination of workflow are in the approval information Shipping Options Page, it is the suggestion of examining for a summary record, each overhauling project can have one or more audit opinions in addition, is for the msu message of single overhauling project in person approving's review process.
Further, turnaround plan reports Shipping Options Page to divide up and down two parts, the details of the plan summary record of choosing in the upper part Showplan tabulation, lower part show the unit maintenance that comprises in this plan summary record, nonstandard project, nonstandard bulleted list below 300,000 more than 300,000.
Further, unit maintenance tabulation Shipping Options Page is comprised of unit maintenance tabulation and the nonstandard bulleted list of unit maintenance, realizes selection, deletion and the modify feature of unit maintenance project and nonstandard project.And the option button below the unit maintenance tabulation carries out the selection of unit maintenance project.Click the option button and eject the next year unit maintenance deposit bulleted list window of state for ratifying, and select by the mode of choosing record, after clicking the confirming button in the pop-up window, the record of selecting is copied in the unit maintenance tabulation, and the project that occurs in the unit maintenance tabulation can not show in pop-up window.Show the detailed tabulation of nonstandard project of unit maintenance project below the unit maintenance tabulation, choose the unit maintenance project, the nonstandard bulleted list of unit can show all nonstandard projects of this unit project.
Further, flow process is in plant project establishment people and works out next year overhauling project programming phase, in the window that the detailed button of click project ejects, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book can be revised, and audit opinion tabulation Shipping Options Page is read-only.Flow process is in the person approving and examines the stage, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book are read-only, and the audit opinion Shipping Options Page is revisable, below audit opinion is tabulated newly-increased button are arranged, click newly-increased button, increase an audit opinion.
Further, nonstandard item label page or leaf is comprised of nonstandard project list tabulation and option button more than 300,000 more than 300,000, realizes selection, deletion and the modify feature of nonstandard project more than 300,000.Nonstandard item label page or leaf below 300,000 is comprised of nonstandard project list tabulation and option button below 300,000, realizes selection, deletion and the modify feature of nonstandard project below 300,000.
Further, plan reply situation Shipping Options Page divides up and down two parts, the plan record details of choosing in the upper part Showplan tabulation, lower part show that this declares the unit maintenance reply that comprises in the record, nonstandard project reply, nonstandard project 300,000 below are given an written reply and tabulated 300,000 or more.
Further, unit maintenance reply tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, realizes the reply audit function of unit maintenance project and nonstandard project.Comprise reply annual charge (ten thousand yuan), reply maintenance grade, reply plan on-stream time, reply plan time of completion, reply plan time (my god).Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit project.
Further, in the window that the detailed button of click project ejects, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book, when flow process is in power plant establishment people and works out next year overhauling project plan, these four Shipping Options Pages can be write, and in other audit links of flow process, these four Shipping Options Pages are read-only.Flow process is in the person approving and examines the stage, and the audit opinion Shipping Options Page is revisable, below audit opinion is tabulated newly-increased button is arranged, and clicks newly-increased button, increases an audit opinion.
Further, (or following) nonstandard item label page or leaf is realized the reply audit function of (or following) nonstandard project more than 300,000 more than 300,000.The reply content comprise reply annual charge (ten thousand yuan), reply plan on-stream time, reply plan time of completion, reply plan time (my god).
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to overhauling project annual plan information replenishes.Upload button below the document attachment tabulation, realize uploading of local file.
Further, the overhauling project change realizes that the hydroelectric power plant carries out the change of expense, duration and newly-increased, the cancellation of annual overhaul project to the annual overhaul project of approved, the employing working flow mode is carried out the establishment of annual overhaul project change and is examined process, workflow is examined link with the overhauling project annual plan, and function comprises that change tabulation, change project report, change reply situation, approval information, five Shipping Options Pages of relevant documentation.
Further, change tabulation Shipping Options Page is realized the aggregate query of overhauling project changed content, a change tabulation comprises at least a change project and reports, the change project has unit maintenance, nonstandard project, nonstandard project below 300,000 more than 300,000, and that the change type of project has is newly-increased, cancellation, revise.
Further, the change project reports Shipping Options Page to comprise that unit maintenance is tabulated, nonstandard bulleted list, nonstandard bulleted list below 300,000 more than 300,000, below each tabulation modification project, cancellation of project, three buttons of new projects are arranged, realize respectively revising off-the-shelf item, cancellation off-the-shelf item, newly-increased deposit project to formal plan.
Further, click the following modification project button of unit maintenance tabulation, eject the annual unit maintenance bulleted list window of having ratified, choose record, click confirming button, the change project of choosing is copied in the unit maintenance tabulation.Click the following cancellation of project button of unit maintenance tabulation, eject the annual unit maintenance bulleted list window of having ratified, choose record, click confirming button, the change project of choosing is copied in the unit maintenance tabulation, the cancellation of project content information all is read-only, and change type is deletion, and after changing budget (ten thousand yuan) is 0.Click the following new projects button of unit maintenance tabulation, eject the annual unit maintenance deposit bulleted list window of having ratified, choose record, click confirming button, the deposit project information of choosing is copied in the unit maintenance tabulation, the new projects content information except change type be read-only, other all can be write, the change type of new projects is for newly-increased.
Further, nonstandard project and 300,000 following nonstandard bulleted lists and unit maintenance bulleted list function class all are to carry out the project alter operation by the modification project under tabulating, cancellation of project, three buttons of new projects seemingly more than 300,000; On displaying contents, unit maintenance is many maintenance grade and unit, 300,000 or more and more than the following nonstandard project position, other guide is all consistent.
Further, change reply situation Shipping Options Page displaying contents and change project report the Shipping Options Page displaying contents similar, are used for the person approving and carry out the audit of change project.Comprise unit maintenance reply, nonstandard project reply and 300,000 following nonstandard projects are given an written reply three tabulations 300,000 or more, do not revise project, cancellation of project, new projects button below the tabulation, list content is consistent with the list content of project change reporting.Difference is that the list content in the project change reporting Shipping Options Page does not comprise reply information, the list content of change reply situation Shipping Options Page comprises reply information, do not comprise plan information, as giving an written reply planned time, give an written reply concluding time, the duration of reply, giving an written reply the annual amount of money (ten thousand yuan).Increase newly, remove in the project change reporting or revise a project, after the preservation, change reply situation content is just consistent with project change reporting content.
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to the overhauling project modification information replenishes.Upload button below the document attachment tabulation, realize uploading of local file.
Further, when the overhauling project changing process finishes, operation below can carrying out: the unit project that circulation will be changed, nonstandard project, nonstandard project below 300,000 more than 300,000, for newly-increased overhauling project, directly copy whole project information to the approved planning item, for revising overhauling project, the overhauling project information updating of revising is arrived the planning item of corresponding (bullets is identical, year is identical, power plant is identical) approved, for cancellation of project, change the planning item state of corresponding approved into cancellation, yearly budget changes 0 into.
Further, the overhauling project work program realize hydroelectric power plant's approved the plan of annual overhaul project work establishment and examine process, comprise list of schedules, job, three Shipping Options Pages of approval information.In some optional embodiments, overhauling project work program flow process as shown in Figure 3, minute four service links are respectively that plant project establishment people writes overhauling project work program in the current year, plant project person approving's examination plan, plant project and examines power plant's work program Approved by approval work program, the project person approving of company.
Further, the list of schedules Shipping Options Page is realized the inquiry that the plan of annual overhaul project work gathers, list of schedules is the summary record of a plurality of overhauling project work programs, is that the turnaround plan in the end of the year of approved is repaiied project, can carry out the establishment of an overhauling project work program in 1 year and examine.A summary record is exactly the running example of a workflow, and the suggestions made after examination of workflow are the suggestions of examining for a summary record in the approval information Shipping Options Page.
Further, the job Shipping Options Page divides up and down two parts, the details of the plan summary record of choosing in the tabulation of upper part Showplan, lower part shows unit standards project and 300,000 above nonstandard bulleted lists, have the detailed button of project in the tabulation, bullets, project name, the Project design time, dotted-line time, the project kickoff time, the project time of completion, the project clearing time, the project leader, wherein various PROJECT TIME all are the numerals of 1-12, expression 1-12 month, click the Entry Details button, the overhauling project details window in ejection and the overhauling project annual plan.
Further, after the project scheduling was newly-built, when preserving for the first time, system can generate unit maintenance project and 300,000 above nonstandard bulleted list data automatically, and each milestone phase points time that the user only need to revise each overhauling project gets final product.
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, newly-increased, the deletion of overhauling project work program, preserve operation and realize by the Main Toolbar button in the establishment of overhauling project work program.Overhauling project work program state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project work program workflow.
Further, the overhauling project monthly magazine is realized the overhauling project responsible official of hydroelectric power plant by monthly implementation status of filling in the annual overhaul planning item of approved, comprise the tabulation of project monthly magazine, project monthly magazine in detail, approval information, four Shipping Options Pages of relevant documentation.In some optional embodiments, overhauling project monthly magazine flow process as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that this month overhauling project monthly magazine, plant project person approving are examined the project monthly magazine, plant project is examined the plant project monthly magazine Approved by approval project monthly magazine, the project person approving of company.
Further, project monthly magazine tabulation Shipping Options Page is realized the inquiry that monthly overhauling project job schedule gathers, the tabulation of project monthly magazine is the summary record of a plurality of overhauling project job schedules, the turnaround plan in the end of the year that is approved is repaiied project, after the annual plan approval, carry out the establishment of an overhauling project monthly magazine at the bottom of every month and examine.A summary record is exactly the running example of a workflow, and the suggestions made after examination of workflow are the suggestions of examining for a summary record in the approval information Shipping Options Page.
Further, the detailed Shipping Options Page of project monthly magazine divides up and down two parts, the details of the monthly summary record of overhauling project of choosing in the tabulation of upper part display items display monthly magazine, lower part shows unit standards project and 300,000 above nonstandard bulleted lists, have the detailed button of project in the tabulation, bullets, project name, yearly budget (ten thousand yuan), this month, finished (ten thousand yuan), total (ten thousand yuan), the Project design time, dotted-line time, the project kickoff time, the project time of completion, the project clearing time, wherein various PROJECT TIME all are the numerals of 1-12, expression 1-12 month, click the Entry Details button, the details of display items display monthly magazine below list box, details have been Duoed vivid progress and situation description than the content in the tabulation.
Further, after the project monthly magazine is newly-built, when preserving for the first time, system can generate unit maintenance project and 300,000 above nonstandard bulleted list data automatically, each milestone phase points time and this month that the user only need to revise each overhauling project, finish (ten thousand yuan), vivid progress and situation explanation and get final product, and wherein to total (ten thousand yuan) be read-only to project, and system can add up automatically, value is finished for upper month to date adds this month, need not fill in.
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, the overhauling project monthly magazine increases, deletes, preserves operation newly by the realization of the Main Toolbar button in the overhauling project monthly magazine.Overhauling project monthly magazine state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project monthly magazine workflow.
Further, the overhauling project annual summary realizes that the hydroelectric power plant according to the maintenance situation summary in the current year of annual overhaul summary template completion, comprises annual summary tabulation, annual summary, three Shipping Options Pages of approval information.In some optional embodiments, overhauling project annual summary flow process as shown in Figure 3, minute four service links, be respectively plant project establishment people write the current year overhauling project sum up, plant project person approving examines the overhauling project annual summary, plant project is examined power plant's overhauling project annual summary Approved by approval overhauling project annual summary, the project person approving of company.
Further, annual summary tabulation Shipping Options Page is realized the inquiry of overhauling project annual summary, and the overhauling project annual summary record of a power plant is exactly the running example of a workflow, and the suggestions made after examination of workflow are in the approval information Shipping Options Page.
Further, the annual summary Shipping Options Page divides up and down two parts, upper part shows the record details of choosing in the tabulation of overhauling project annual summary, lower part shows maintenance annual summary document template and annual summary lists of documents, have document code in the tabulation, document title, upper successor, uplink time, delete button, wherein document code and document title are hyperlink, clickable hyperlinks, eject the profile download window, be used for downloading document, below list box, show and add the annex button, click and add the annex button, eject local document and upload window, local file is uploaded onto the server.
Further, overhaul the following interpolation annex button of annual summary document template tabulation and the delete button in the annual summary document template only for administrator role as seen, other roles are invisible, are used for the keeper and safeguard up-to-date maintenance annual summary template.
Further, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the circulation button of click Main Toolbar ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Further, the overhauling project annual summary increases, deletes, preserves operation newly by the Main Toolbar button realization of overhauling project annual summary.Overhauling project annual summary state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project annual summary workflow.
Good effect of the present invention is:
By the present invention, employing comprises the establishment of maintenance deposit project, the project application of maintenance deposit, overhauling project annual plan, overhauling project change, overhauling project work program, overhauling project monthly magazine, overhauling project annual summary, solved in the water power production management system the overhauling project problem of management, thereby lifting water power company fortune inspection management level have been reached, set up fortune inspection administrative evaluation mechanism, to reach standardization, standardization and the lean requirement of hydroelectric power plant's management, for company's fortune inspection management standardization, lean provide strong support.
Description of drawings
Following accompanying drawing is used to provide a further understanding of the present invention, and illustrative examples of the present invention and explanation thereof are used for explaining the present invention, do not consist of improper restriction of the present invention.In the accompanying drawings:
Fig. 1 is functional schematic of the present invention;
Fig. 2 is maintenance deposit project application auditing flow figure;
Fig. 3 is overhauling project annual plan auditing flow figure;
Embodiment
Need to prove, in the situation that do not conflict, embodiment and the feature among the embodiment among the application can make up mutually, and unless explicitly call for, independent assembly and function are optional, and the order of operation can change.The part of some embodiments and feature can be included in or replace part and the feature of other embodiments.The scope of embodiment of the present invention comprises the gamut of claims, and all obtainable equivalents of claims.Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with example.
Fig. 1 is the functional schematic of water power production management system overhauling project method of planning of the present invention.
As shown in Figure 1, the plan of water power overhauling project comprises:
(1) maintenance deposit project establishment: realize increase, deletion, modification and the inquiry of hydroelectric power plant's single maintenance deposit project, comprise that bulleted list, project are detailed, the nonstandard project of unit maintenance, four Shipping Options Pages of msu message;
(2) the maintenance deposit project application: adopt the mode of workflow to realize that the hydroelectric power plant is packaged as a plurality of maintenance deposit projects the process of examining of the maintenance deposit project application, comprise declare tabulation, the project of declaring is detailed, declare reply situation, approval information, five Shipping Options Pages of relevant documentation.Only having state is that the maintenance deposit project of ratifying could be used in the maintenance annual plan;
(3) overhauling project annual plan: adopt the mode of workflow realize the hydroelectric power plant the annual overhaul project scheduling establishment and examine process, comprise that list of schedules, turnaround plan report, plan reply situation, approval information, five Shipping Options Pages of relevant documentation.During establishment maintenance annual plan, select in the annual overhaul deposit project library of approved, after the annual plan approval, maintenance deposit project has just become formal overhauling project.The overhauling project annual plan of hydroelectric power plant 1 year establishment is once generally carried out in the September, examine approval after, as the title event plan, if later change is arranged, walk the overhauling project changing process;
(4) overhauling project change: adopt the mode of workflow realize the hydroelectric power plant annual overhaul project of approved is carried out the change of expense, duration and annual overhaul project newly-increased, cancellation establishment and examine process, comprise that list of schedules, turnaround plan report, plan reply situation, approval information, five Shipping Options Pages of relevant documentation
(5) overhauling project work program: adopt the mode of workflow to realize the establishment of the information such as each milestone phase points time of annual overhaul planning item of hydroelectric power plant's approved and project leader and examine process, comprise Work List, job, three Shipping Options Pages of approval information.
(6) overhauling project monthly magazine: adopt the mode of workflow to realize the overhauling project responsible official of hydroelectric power plant by the process of examining of the implementation status of the monthly annual overhaul planning item of filling in approved, comprise the tabulation of project monthly magazine, project monthly magazine in detail, approval information, relevant documentation.
(7) overhauling project annual summary: adopt the mode of workflow to realize that the hydroelectric power plant sums up the process of examining that the maintenance situation in template completion current year is summed up according to annual overhaul, comprise annual summary tabulation, annual summary, three Shipping Options Pages of approval information.
Preferably, the bulleted list information in the establishment of described maintenance deposit project comprise bullets, item description, year, year investment (ten thousand yuan), specialty segmentation (water conservancy project, water machine, once, secondary, information, other), maintenance type (unit maintenance project, nonstandard project, nonstandard project below 300,000 300,000 or more), project status (approved, cancellation, rough draft), power plant's abbreviation etc.The detailed Shipping Options Page content of project comprises the bit organization title, bullets, item description, item types is (on the limit, limit is lower), position encoded, location name, the maintenance type, the specialty segmentation, project segmentation (unit, synergic system, hydraulic structure, other), year, year investment (ten thousand yuan), the maintenance purpose (improves the safety and environmental protection level, improve productive capacity, the raising equipment general level of the health, reduce energy consumption), (the A level maintenance of maintenance grade, the maintenance of B level, the maintenance of C level, the maintenance of D level), planned start time, the plan concluding time, plan time, historical hidden danger defective, unit operation information, this equipment mainly overhauls situation former years, item source (hidden danger, defective, planning, counter arranging), hidden danger/defective numbering, existing problems and the analysis of causes, re-set target and performance analysis, the previous work progress, technical scheme, the project annex, project budget book (comprises the unit maintenance budget, the project estimation book, the bill of materials), the establishment people, the establishment time.Have nonstandard bullets, nonstandard item description, year investment (ten thousand yuan), position encoded, location expression, state (approved, cancellation, rough draft) in the nonstandard bulleted list.The nonstandard project detailed content of unit maintenance has nonstandard bullets, nonstandard item description, annual investment, Position Number, location expression, state, establishment people, establishment time, specialty segmentation, this equipment mainly to overhaul situation, historical hidden danger defective, item source, hidden danger/defective numbering, existing problems and the analysis of causes, re-set target and performance analysis, technical scheme, unit maintenance prerun, the bill of materials former years.Have audit numbering, person approving, audit opinion, audit time in the msu message Shipping Options Page.
Preferably, newly-increased, the deletion of maintenance deposit project, preserve operation and realize by the toolbar button in the establishment of maintenance deposit project.State and the state in the nonstandard project of unit maintenance in the maintenance deposit project all are the rough draft state when newly-built, and its state of change is approved or cancellation in maintenance deposit project application workflow.When maintenance deposit project status was approved, this record can not be revised and delete; When maintenance deposit project status is cancellation or rough draft, can revise and delete.
Preferably, the time of putting into operation, historical hidden danger defective, unit operation information and this equipment in the maintenance deposit project mainly overhaul situation former years, and behind chosen position, system can inquire about the relevant information of this position automatically, and Query Result is filled into corresponding contents.Mainly overhaul situation former years such as historical hidden danger defective and this equipment, system queries goes out historical hidden danger defect information all under this position and historical maintenance situation, and describe and the description of hidden danger numbering+hidden danger is presented in the historical hidden danger defective text box line by line by defective numbering+defective, the description of overhauling project numbering+overhauling project is presented at line by line this equipment and mainly overhauls in the situation text box former years, makes things convenient for the user to judge the necessity of this overhauling project.
Preferably, maintenance deposit project application flow process as shown in Figure 2, minute five service links are respectively that plant project establishment people writes the deposit project of next year overhauling, plant project and gathers the people and gather that the deposit project of next year overhauling, plant project person approving are examined project, plant project is examined project Approved by approval project, the project person approving of company.
Preferably, in the project application of described maintenance deposit declare list content comprise declare numbering, declare descriptions, year, state (rough draft, power plant examine, company examines, approved), work out the people, give an written reply the people, power plant's abbreviation.Declaring tabulation is the summary record of a plurality of maintenance deposit projects, comprises at least a maintenance deposit project, can repeatedly overhaul declaring of deposit project in 1 year.A summary record is exactly the running example of a workflow, the suggestions made after examination of workflow are in the approval information Shipping Options Page, it is the suggestion of examining for a summary record, each maintenance deposit project can have one or more audit opinions in addition, is the msu message of the project of laying in for single maintenance in person approving's review process.
Preferably, the detailed Shipping Options Page of the project of declaring divides up and down two parts, upper part show declare choose in the tabulation declare the record details, in have and declare numbering, declare description, year, the establishment people, the establishment time, the person approving, state, the all items budget adds up to (ten thousand yuan), the standards project budget adds up to (ten thousand yuan), nonstandard budget adds up to (ten thousand yuan) more than 300,000, nonstandard budget below 300,000 adds up to (ten thousand yuan), wherein all items budget adds up to four total entries such as (ten thousand yuan) according to the automatic statistics of lower part content, and lower part shows that this declares the unit maintenance that comprises in the record, nonstandard project more than 300,000, nonstandard bulleted list below 300,000.
Preferably, unit maintenance tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, the selection of realization unit maintenance project and nonstandard project, removes and examine function.The unit maintenance list content comprise the detailed button of project, bullets, project name, unit, maintenance grade, annual charge (ten thousand yuan), planned start time, plan concluding time, plan time (my god), remove button, and carry out the selection of unit maintenance project by the option button of tabulating following.Click option button ejects next year, and state is the unit maintenance deposit bulleted list window of rough draft and cancellation, and select by the mode of choosing record, after clicking the confirming button in the pop-up window, the record of selecting is shown in the unit maintenance tabulation, and the project that occurs in the unit maintenance tabulation can not show in pop-up window.Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, list content have project name, unit, maintenance grade, budget (ten thousand yuan), plan starting date, plan completion date of construction, plan time (my god).Choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit maintenance project.Safeguard in the nonstandard item label page or leaf of unit maintenance of nonstandard project detail corresponding to unit maintenance project in the establishment of maintenance deposit project.
Click the detailed button of project in the unit maintenance tabulation, can eject the detailed window of maintenance deposit project, comprise five Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion in this window.Preferably, project essential information Shipping Options Page comprises organization name, bullets, item description, item types is (on the limit, limit is lower), position encoded, location name, the maintenance type, the specialty segmentation, project segmentation (unit, synergic system, hydraulic structure, other), year, year investment (ten thousand yuan), the maintenance purpose (improves the safety and environmental protection level, improve productive capacity, the raising equipment general level of the health, reduce energy consumption), (the A level maintenance of maintenance grade, the maintenance of B level, the maintenance of C level, the maintenance of D level), planned start time, the plan concluding time, plan time, historical hidden danger defective, unit operation information, this equipment mainly overhauls situation former years, the establishment people, the establishment time, the project annex; Project necessity Shipping Options Page comprises item source (hidden danger, defective, planning, counter arranging), hidden danger/defective numbering, existing problems and the analysis of causes; The project alternative Shipping Options Page comprises re-set target and performance analysis, previous work progress, technical scheme; Project budget book label page or leaf comprises unit maintenance budget, project estimation book, three Shipping Options Pages of the bill of materials; The audit opinion Shipping Options Page comprises project overview information and audit opinion tabulation, and project overview information comprises bullets, item description, reply maintenance grade, reply planned start time, reply plan concluding time, the investment of reply year (ten thousand yuan), state; The audit opinion tabulation was comprised of audit numbering, person approving, audit opinion, audit time, showed the audit opinion that the person approving fills in.
Preferably, the initial value of reply maintenance grade, reply planned start time, reply plan concluding time, reply year investment (ten thousand yuan) is the value of scheduled overhaul grade, planned start time, plan concluding time, program year investment (ten thousand yuan).Can revise when the person approving examines, after the modification, the reply value can not change along with planned value, otherwise when the establishment of maintenance deposit project, the reply value can change along with planned value.
Preferably, flow process is in power plant establishment people establishment and next year lays in project or power plant and gather the people and gather when next year laying in project, in the window that the detailed button of click project ejects, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book can be revised, and audit opinion tabulation Shipping Options Page is read-only.Flow process is in the person approving and examines the stage, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book are read-only, and the audit opinion Shipping Options Page is revisable, below audit opinion is tabulated newly-increased button are arranged, click newly-increased button, increase an audit opinion.The contents such as the reply start time in the audit opinion Shipping Options Page, reply concluding time, reply investment (ten thousand yuan), state are revisable in person approving's audit stage in addition.
Preferably, (or following) nonstandard item label page or leaf is comprised of the tabulation of (or following) more than 300,000 nonstandard project list and option button more than 300,000, realize (or following) nonstandard project more than 300,000 selection, remove and modify feature.Have in (or following) nonstandard bulleted list more than 300,000 the detailed button of project, bullets, project name, position, annual charge (ten thousand yuan), plan on-stream time, plan time of completion, plan time (my god), remove button.Click more than 300,000 the button that removes in (or following) nonstandard bulleted list, this rower can be designated as deletion, click again the save button in the Main Toolbar, this record will be removed, be that this does not gather this nonstandard project, but nonstandard project information can not deleted, and again click project is selected button, this nonstandard project can occur again in the nonstandard bulleted list window of ejection.Click the detailed button of the project in (or following) nonstandard bulleted list more than 300,000, can eject the detailed content window of this nonstandard project, this window comprises the Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion, and each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, declare reply situation Shipping Options Page and divide up and down two parts, upper part show declare choose in the tabulation declare the record details, in have and declare numbering, declare description, year, the establishment people, the establishment time, the person approving, state, all reply project budgets add up to (ten thousand yuan), standards project reply budget adds up to (ten thousand yuan), nonstandard reply budget adds up to (ten thousand yuan) more than 300,000, nonstandard reply budget below 300,000 adds up to (ten thousand yuan), and wherein all reply project budgets add up to four total entries such as (ten thousand yuan) automatically to add up according to following reply content.Lower part shows that this declares the unit maintenance reply that comprises in the record, nonstandard project reply, nonstandard project 300,000 below are given an written reply and tabulated 300,000 or more.
Preferably, unit maintenance reply tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, realizes the reply audit function of unit maintenance project and nonstandard project.The unit maintenance list content comprise the detailed button of project, bullets, project name, unit, reply maintenance grade, reply annual charge (ten thousand yuan), reply planned start time, reply plan concluding time, reply duration (my god).Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit project.The detailed list content of the nonstandard project of unit have project name, unit, maintenance grade, budget (ten thousand yuan), plan starting date, plan completion date of construction, plan time (my god).Click the detailed button of project in the unit maintenance tabulation, can eject the detailed window of maintenance deposit project, comprise five Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion in this window, each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, (or following) nonstandard project is given an written reply the reply audit function that Shipping Options Page is realized nonstandard project more than 300,000 more than 300,000.Have in (or following) nonstandard bulleted list more than 300,000 the detailed button of project, bullets, project name, position, reply annual charge (ten thousand yuan), reply plan on-stream time, reply plan time of completion, reply plan time (my god).Click the detailed button of the project in (or following) nonstandard bulleted list more than 300,000, can eject the detailed content window of this nonstandard project, this window comprises the Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion, and each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.The circulation window divide four parts, above first show current procedure links and flow process theme; Second portion adopts the mode of individual event frame to show executable operation (as reporting company home office to examine, reject to the establishment people and revise) and fills in suggestions made after examination; Third part shows the suggestions made after examination tabulation circulated, and the suggestions made after examination tabulation comprises nodename, approver, examines the time, suggestions made after examination; The 4th partial display is determined, is cancelled and redistributes button.When clicking confirming button, with workflow next link to selection; When clicking cancel button, close current workflow window; When button is redistributed in click, open one and redistribute the task window, this window can be selected personnel and fill in p.m.entry, behind the selection personnel, clicks confirming button and namely current task is transmitted to the personnel that choose.
Preferably, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to maintenance deposit project information replenishes.The document attachment tabulation has document title, document description, upper successor, uplink time, checks the annex button, deletes the annex button, uploads button below document attachment is tabulated, and realizes uploading of local file.
Preferably, overhauling project annual plan flow process as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that annual plan is examined in next year overhauling project plan, plant project person approving, plant project is examined power plant's annual plan Approved by approval annual plan, the project person approving of company.
Preferably, the list of schedules content in the described overhauling project annual plan comprises that plan numbering, plan are described, year, state (rough draft, power plant examine, company examines, approved), establishment people, the reply people of company, power plant be called for short.List of schedules is the summary record of a plurality of overhauling project plans, comprises at least an overhauling project plan, can carry out declaring of an overhauling project plan in 1 year.A summary record is exactly the running example of a workflow, the suggestions made after examination of workflow are in the approval information Shipping Options Page, it is the suggestion of examining for a summary record, each overhauling project plan can have one or more audit opinions in addition, is for the msu message of single overhauling project plan in person approving's review process.
Preferably, turnaround plan reports Shipping Options Page to divide up and down two parts, the details of the plan summary record of choosing in the tabulation of upper part Showplan, the planned numbering of content, plan is described, year, the establishment people, the establishment time, the person approving, state, the all items budget adds up to (ten thousand yuan), the standards project budget adds up to (ten thousand yuan), nonstandard budget adds up to (ten thousand yuan) more than 300,000, nonstandard budget below 300,000 adds up to (ten thousand yuan), wherein all items budget adds up to four total entries such as (ten thousand yuan) automatically to add up according to the lower part content, and lower part shows the unit maintenance that comprises in this plan summary record, nonstandard project more than 300,000, nonstandard bulleted list below 300,000.
Preferably, unit maintenance tabulation Shipping Options Page is comprised of unit maintenance tabulation and the nonstandard bulleted list of unit maintenance, realizes selection, deletion and the modify feature of unit maintenance project and nonstandard project.The unit maintenance list content comprise the detailed button of project, bullets, project name, unit, maintenance grade, annual charge (ten thousand yuan), plan starting date, plan completion date of construction, plan time (my god), delete button, and carry out the selection of unit maintenance project by the option button of tabulating following.Click the option button and eject the next year unit maintenance deposit bulleted list window of state for ratifying, and select by the mode of choosing record, after clicking the confirming button in the pop-up window, the record of selecting is copied in the unit maintenance tabulation, and the project that occurs in the unit maintenance tabulation can not show in pop-up window.Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the nonstandard bulleted list of unit can show all nonstandard projects of this unit maintenance project.Click the detailed button of project in the unit maintenance tabulation, can eject the detailed window of maintenance deposit project, comprise five Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion in this window, each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, the overhauling project information in the project application of maintenance deposit and the overhauling project information in the overhauling project annual plan are different two entities (table), and still two entities have essentially identical content.When the overhauling project annual plan is worked out, project is laid in the maintenance of selecting to have ratified, can with maintenance deposit project information complete copy in the annual plan overhauling project, in annual plan, revise overhauling project information, can't be synchronized in the maintenance deposit project.In the project application of maintenance deposit, revise in addition maintenance deposit project information, be equivalent to directly in the establishment of maintenance deposit project, revise project information, because the Entry Details in the project application of maintenance deposit is exactly the Entry Details in the establishment of maintenance deposit project.
Preferably, flow process is in plant project establishment people and works out next year overhauling project programming phase, in the window that the detailed button of click project ejects, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book can be revised, and audit opinion tabulation Shipping Options Page is read-only.Flow process is in the person approving and examines the stage, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book are read-only, and the audit opinion Shipping Options Page is revisable, below audit opinion is tabulated newly-increased button are arranged, click newly-increased button, increase an audit opinion.The contents such as the reply start time in the audit opinion Shipping Options Page, reply concluding time, reply investment (ten thousand yuan), state are revisable in person approving's audit stage in addition.
Preferably, (or following) nonstandard item label page or leaf is comprised of (or following) more than 300,000 nonstandard project list tabulation and option button more than 300,000, realizes selection, deletion and the modify feature of (or following) nonstandard project more than 300,000.Have in (or following) nonstandard bulleted list more than 300,000 the detailed button of project, bullets, project name, position, annual charge (ten thousand yuan), plan on-stream time, plan time of completion, plan time (my god), delete button.Click the delete button in (or following) nonstandard bulleted list more than 300,000, this rower can be designated as deletion, click again the save button in the Main Toolbar, this record will be deleted, be that this does not gather this nonstandard project, but nonstandard project information can not deleted, and selects button in the click project, this nonstandard project can occur again in the nonstandard bulleted list window of ejection.Click the detailed button of the project in (or following) nonstandard bulleted list more than 300,000, can eject the detailed content window of this nonstandard project, this window comprises the Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion, and each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, plan reply situation Shipping Options Page divides up and down two parts, the plan record details of choosing in the tabulation of upper part Showplan, the planned numbering of content, declare description, year, the establishment people, the establishment time, the person approving, state, all reply project budgets add up to (ten thousand yuan), standards project reply budget adds up to (ten thousand yuan), nonstandard reply budget adds up to (ten thousand yuan) more than 300,000, nonstandard reply budget below 300,000 adds up to (ten thousand yuan), wherein all reply project budgets add up to four total entries such as (ten thousand yuan) according to the automatic statistics of following reply content, and lower part shows that this declares the unit maintenance reply that comprises in the record, nonstandard project reply more than 300,000, nonstandard project reply tabulation below 300,000.
Preferably, unit maintenance reply tabulation Shipping Options Page is comprised of unit maintenance tabulation and the detailed tabulation of the nonstandard project of unit maintenance, realizes the reply audit function of unit maintenance project and nonstandard project.The unit maintenance list content comprise the detailed button of project, bullets, project name, unit, reply maintenance grade, reply annual charge (ten thousand yuan), reply starting date, reply completion date of construction, reply duration (my god).Show the detailed tabulation of the nonstandard project of unit below the unit maintenance tabulation, choose the unit maintenance project, the detailed tabulation of the nonstandard project of unit can show all nonstandard projects of this unit project.The detailed list content of the nonstandard project of unit have reply numbering, project name, reply maintenance grade, reply budget (ten thousand yuan), reply starting date, reply completion date of construction, reply duration (my god).Click the detailed button of project in the unit maintenance tabulation, can eject the detailed window of maintenance deposit project, comprise five Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion in this window, each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, in the window that the detailed button of click project ejects, the Shipping Options Page contents such as project essential information, project necessity, project alternative, project budget book, when flow process is in power plant establishment people and works out next year overhauling project plan, these four Shipping Options Pages can be write, and in other audit links of flow process, these four Shipping Options Pages are read-only.Flow process is in the person approving and examines the stage, and the audit opinion Shipping Options Page is revisable, below audit opinion is tabulated newly-increased button is arranged, and clicks newly-increased button, increases an audit opinion.The contents such as the maintenance of the reply in audit opinion Shipping Options Page grade, reply planned start time, reply plan concluding time, reply investment (ten thousand yuan), state are revisable in person approving's audit stage in addition.
Preferably, nonstandard project is given an written reply the reply audit function that Shipping Options Page is realized nonstandard project more than 300,000 more than 300,000.Have in the nonstandard bulleted list more than 300,000 the detailed button of project, bullets, project name, position, reply annual charge (ten thousand yuan), reply plan on-stream time, reply plan time of completion, reply plan time (my god).Click the detailed button of the project in the nonstandard bulleted list more than 300,000, can eject the detailed content window of this nonstandard project, this window comprises the Shipping Options Pages such as project essential information, project necessity, project alternative, project budget book, audit opinion, and each Shipping Options Page particular content is referring to the detailed button explanation of project in the top click unit maintenance tabulation.
Preferably, the reply of nonstandard project below 300,000 Shipping Options Page realizes that the bundling of nonstandard project below 300,000 examines function.Only show a combined data during i.e. nonstandard project reply below 300,000, only need to determine reply total expenses (ten thousand yuan).Have reply numbering, project name, state, reply total expenses (ten thousand yuan) below 300,000 in the nonstandard bulleted list.
Preferably, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Preferably, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to overhauling project annual plan information replenishes.The document attachment tabulation has document title, document description, upper successor, uplink time, checks the annex button, deletes the annex button, uploads button below document attachment is tabulated, and realizes uploading of local file.
Preferably, the similar overhauling project annual plan of overhauling project changing process, as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that overhauling project changed content in the current year, plant project person approving are examined the project changed content, plant project is examined the project changed content Approved by approval project changed content, the project person approving of company.
Preferably, the change tabulation mark in the described overhauling project change comprises that plan numbering, plan description, year, state, reply people, power plant are called for short.A change tabulation comprises at least a maintenance change project and reports, and the change project has unit maintenance, nonstandard project, nonstandard project 300,000 below 300,000 or more, and that the change type of project has is newly-increased, cancel, modification.
Preferably, the change project reports Shipping Options Page to comprise that unit maintenance is tabulated, nonstandard bulleted list, nonstandard bulleted list below 300,000 more than 300,000, below each tabulation modification project, cancellation of project, three buttons of new projects are arranged, realize respectively revising off-the-shelf item, cancellation off-the-shelf item, newly-increased deposit project to formal plan.
Preferably, the unit maintenance list content comprises and checks details button, change type, bullets, project name, unit, maintenance grade, yearly budget, plan starting date, plan completion date of construction, plan time.Click the details button of checking in the tabulation, the details of display items display below the tabulation, comprise change type, bullets, item description, item types, the project segmentation, nonstandard item types, unit, the maintenance grade, planned start time, the plan concluding time, plan time, the maintenance purpose, assign budget (ten thousand yuan) beginning of the year, after changing budget (ten thousand yuan), the project verification reason, the contents of a project, remarks etc., planned start time wherein, the plan concluding time, after changing budget (ten thousand yuan) is revisable, other are read-only, revise planned start time and plan concluding time, reply start time and reply concluding time in the change reply situation can change.Again click in the tabulation and check details button, the following details content of tabulation will be closed.
Preferably, click the following modification project button of unit maintenance tabulation, eject the annual unit maintenance bulleted list window of having ratified, choose record, click confirming button, the change project of choosing is copied in the unit maintenance tabulation.Click the following cancellation of project button of unit maintenance tabulation, eject the annual unit maintenance bulleted list window of having ratified, choose record, click confirming button, the change project of choosing is copied in the unit maintenance tabulation, the cancellation of project content information all is read-only, and change type is deletion, and after changing budget (ten thousand yuan) is 0.Click the following new projects button of unit maintenance tabulation, eject the annual unit maintenance deposit bulleted list window of having ratified, choose record, click confirming button, the deposit project information of choosing is copied in the unit maintenance tabulation, the new projects content information except change type be read-only, other all can be write, the change type of new projects is for newly-increased.
Preferably, nonstandard bulleted list and unit maintenance bulleted list function class all are to carry out the project alter operation by the modification project under tabulating, cancellation of project, three buttons of new projects seemingly more than 300,000; On displaying contents, unit maintenance is many maintenance grade and unit, 300,000 or more more than the nonstandard project position, other guide is all consistent.Nonstandard bulleted list below 300,000 is realized the change of nonstandard project bundling expense below 300,000, by the modification project of tabulating following, eject nonstandard Grand total of the project list window below 300,000, choose record, click confirming button, the nonstandard Grand total of the project below 300,000 of choosing is copied to below 300,000 in the nonstandard bulleted list, and finish by revising master budget (ten thousand yuan) value that nonstandard Project Cost changes below 300,000.Nonstandard project change below 300,000 is cancellation and new projects button not.
Preferably, change reply situation Shipping Options Page displaying contents and change of plan report the Shipping Options Page displaying contents similar, are used for the person approving and carry out the audit of change project.Comprise unit maintenance, nonstandard project and 300,000 following three tabulations of nonstandard project more than 300,000, do not revise project, cancellation of project, new projects button below the tabulation, list content is consistent with the list content of project change reporting.Difference is that the list content in the project change reporting Shipping Options Page does not comprise reply information, the list content of change reply situation Shipping Options Page comprises reply information, do not comprise plan information, as giving an written reply planned time, give an written reply concluding time, the duration of reply, giving an written reply the annual amount of money (ten thousand yuan).Increase newly, remove in the project change reporting or revise a project, after the preservation, change reply situation Shipping Options Page related content is just consistent with content in the project change reporting Shipping Options Page.
Preferably, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Preferably, the relevant documentation Shipping Options Page is used for submitting to and checking document attachment, is that to the overhauling project modification information replenishes.The document attachment tabulation has document title, document description, upper successor, uplink time, checks the annex button, deletes the annex button, uploads button below document attachment is tabulated, and realizes uploading of local file.
Preferably, when the overhauling project changing process finishes, operation below can carrying out: the unit project that circulation will be changed, nonstandard project, nonstandard project 300,000 below 300,000 or more, for the overhauling project that increases newly, directly copy the annual overhaul project that whole project information arrives approved; For revising overhauling project, the overhauling project information updating of revising is arrived the overhauling project of corresponding (bullets is identical, year is identical, power plant is identical) approved; For cancellation of project, change the overhauling project state of corresponding approved into cancellation, yearly budget changes 0 into.
Preferably, the overhauling project work program flows similar overhauling project annual plan, journey as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that overhauling project work program in the current year, plant project person approving are examined the overhauling project work program, plant project is examined the overhauling project work program Approved by approval overhauling project work program, the project person approving of company.
Preferably, the list of schedules content in the described overhauling project work program comprises that plan numbering, plan are described, year, state (rough draft, power plant examine, company examines, approved), establishment people, the reply people of company, power plant be called for short.List of schedules is the summary record of a plurality of overhauling project work programs, is that the turnaround plan in the end of the year of approved is repaiied project, can carry out the establishment of an overhauling project work program in 1 year and examine.A summary record is exactly the running example of a workflow, and the suggestions made after examination of workflow are the suggestions of examining for a summary record in the approval information Shipping Options Page.
Preferably, the job Shipping Options Page divides up and down two parts, the details of the plan summary record of choosing in the tabulation of upper part Showplan, and the planned numbering of content, plan description, year, establishment people, establishment time, person approving, power plant are called for short, state.Lower part shows unit standards project and 300,000 above nonstandard bulleted lists, have the detailed button of project, bullets, project name, Project design time, dotted-line time, project kickoff time, project time of completion, project clearing time, project leader in the tabulation, wherein various PROJECT TIME all are the numerals of 1-12, expression 1-12 month, click the Entry Details button, the overhauling project details window in ejection and the overhauling project annual plan.
Preferably, after the project scheduling was newly-built, when preserving for the first time, system can generate unit maintenance project and 300,000 above nonstandard bulleted list data automatically, and each milestone phase points time that the user only need to revise each overhauling project gets final product.
Preferably, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Preferably, newly-increased, the deletion of overhauling project work program, preserve operation and realize by the Main Toolbar button in the establishment of overhauling project work program.Overhauling project work program state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project work program workflow.
Preferably, the similar overhauling project annual plan of overhauling project monthly magazine flow process, as shown in Figure 3, minute four service links are respectively that plant project establishment people writes that this month overhauling project monthly magazine, plant project person approving are examined the overhauling project monthly magazine, plant project is examined the overhauling project monthly magazine Approved by approval overhauling project monthly magazine, the project person approving of company.
Preferably, the project monthly magazine list content in the described overhauling project monthly magazine comprises that year, monthly, state (rough draft, power plant examine, company examines, approved), establishment people, establishment time, the reply people of company, power plant are called for short.The tabulation of project monthly magazine is the summary record of a plurality of overhauling project job schedules, after the annual plan approval, carries out the establishment of an overhauling project monthly magazine at the bottom of every month and examines.A summary record is exactly the running example of a workflow, and the suggestions made after examination of workflow are the suggestions of examining for a summary record in the approval information Shipping Options Page.
Preferably, the detailed Shipping Options Page of project monthly magazine divides up and down two parts, the details of the monthly summary record of overhauling project of choosing in the upper part display items display monthly magazine tabulation, in have be called for short in year, monthly, establishment people, establishment time, person approving, power plant, state.Lower part shows unit standards project and 300,000 above nonstandard bulleted lists, have the detailed button of project in the tabulation, bullets, project name, yearly budget (ten thousand yuan), this month, finished (ten thousand yuan), total (ten thousand yuan), the Project design time, dotted-line time, the project kickoff time, the project time of completion, the project clearing time, wherein various PROJECT TIME all are the numerals of 1-12, expression 1-12 month, click the Entry Details button, the details of display items display monthly magazine below list box, details have been Duoed vivid progress and situation description than the content in the tabulation.
Preferably, after the project monthly magazine is newly-built, when preserving for the first time, system can automatically generate unit maintenance project and 300,000 above nonstandard bulleted list data, can generate simultaneously the related content of progress last month, and each milestone phase points time and this month that the user only need to revise each overhauling project finish (ten thousand yuan), vivid progress and situation explanation and get final product, wherein to total (ten thousand yuan) be read-only to project, system is statistics automatically, is worth for upper month to date adds this month and finishes, and need not fill in.
Preferably, the suggestions made after examination of record during the circulation of approval information Shipping Options Page flow for displaying, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Preferably, the overhauling project monthly magazine increases, deletes, preserves operation newly by the realization of the Main Toolbar button in the overhauling project monthly magazine.Overhauling project monthly magazine state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project monthly magazine workflow.
Preferably, the similar overhauling project annual plan of overhauling project annual summary flow process, as shown in Figure 3, minute four service links, be respectively plant project establishment people write the current year overhauling project sum up, plant project person approving examines the overhauling project annual summary, plant project is examined the overhauling project annual summary Approved by approval overhauling project annual summary, the project person approving of company.
Preferably, the annual summary list content in the described overhauling project annual summary comprises year, sum up to describe, state (rough draft, power plant examine, company examines, approved), establishment people, establishment time, the reply people of company, power plant be called for short.The overhauling project annual summary record of a power plant is exactly the running example of a workflow, and the suggestions made after examination of workflow are in the approval information Shipping Options Page.
Preferably, the annual summary Shipping Options Page divides up and down two parts, and upper part shows the record details of choosing in the tabulation of overhauling project annual summary, in have year, sum up describe, establishment people, establishment time, person approving, power plant are called for short, state.Lower part shows maintenance annual summary document template and annual summary lists of documents, have document code, document title, upper successor, uplink time, delete button in the tabulation, wherein document code and document title are hyperlink, clickable hyperlinks ejects the profile download window, is used for downloading document, below list box, show and add the annex button, click and add the annex button, eject local document and upload window, local file is uploaded onto the server.
Preferably, overhaul the following interpolation annex button of annual summary document template tabulation and the delete button in the annual summary document template only for administrator role as seen, other roles are invisible, are used for the keeper and safeguard up-to-date maintenance annual summary template.
Preferably, the approval information tabulation comprises nodename, flow process theme, approver, examines the contents such as time, suggestions made after examination.Wherein nodename and flow process theme configured in advance in the flow scheme design device is good, clicks the circulation button of Main Toolbar, ejects the workflow window.In the circulation window, select next link, and the typing approval information, click confirming button, with workflow next link to selection.
Preferably, the overhauling project annual summary increases, deletes, preserves operation newly by the Main Toolbar button realization of overhauling project annual summary.Overhauling project annual summary state all is the rough draft state when newly-built, and its state of change is the states such as power plant's audit, power plant ratify, company examines, closes in overhauling project annual summary workflow.

Claims (8)

1. a water power production management system overhauling project method of planning is characterized in that, comprising: the establishment of maintenance deposit project, the project application of maintenance deposit, overhauling project annual plan, overhauling project change, the overhauling project work program, overhauling project monthly magazine, overhauling project annual summary.
2. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the project information in the described maintenance deposit project establishment comprises that bullets, item description, year, year investment, specialty segmentation, maintenance type, project status, power plant are called for short.
3. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of the described maintenance deposit project application is, plant project establishment people writes the deposit project of next year overhauling, plant project and gathers the people and gather that the deposit project of next year overhauling, plant project person approving are examined project, plant project is examined project Approved by approval project, the project person approving of company.
4. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of described overhauling project annual plan is, plant project establishment people writes that annual plan is examined in next year overhauling project plan, plant project person approving, plant project is examined power plant's annual plan Approved by approval annual plan, the project person approving of company.
5. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of described overhauling project change is, plant project establishment people writes that overhauling project changed content in the current year, plant project person approving are examined the project changed content, plant project is examined the project changed content Approved by approval project changed content, the project person approving of company.
6. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of described overhauling project work program is, plant project establishment people writes that overhauling project work program in the current year, plant project person approving are examined the overhauling project work program, plant project is examined the overhauling project work program Approved by approval overhauling project work program, the project person approving of company.
7. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of described overhauling project monthly magazine is, plant project establishment people writes that this month overhauling project monthly magazine, plant project person approving are examined the overhauling project monthly magazine, plant project is examined the overhauling project monthly magazine Approved by approval overhauling project monthly magazine, the project person approving of company.
8. according to water power production management system overhauling project method of planning claimed in claim 1, it is characterized in that, the flow process of described overhauling project annual summary is, plant project establishment people write the current year overhauling project sum up, plant project person approving examines the overhauling project annual summary, plant project is examined the overhauling project annual summary Approved by approval overhauling project annual summary, the project person approving of company.
CN2013103226359A 2013-07-30 2013-07-30 Method for planning inspection project in hydroelectric production management system Pending CN103366259A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103226359A CN103366259A (en) 2013-07-30 2013-07-30 Method for planning inspection project in hydroelectric production management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103226359A CN103366259A (en) 2013-07-30 2013-07-30 Method for planning inspection project in hydroelectric production management system

Publications (1)

Publication Number Publication Date
CN103366259A true CN103366259A (en) 2013-10-23

Family

ID=49367551

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103226359A Pending CN103366259A (en) 2013-07-30 2013-07-30 Method for planning inspection project in hydroelectric production management system

Country Status (1)

Country Link
CN (1) CN103366259A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104504518A (en) * 2014-12-19 2015-04-08 深圳市燃气集团股份有限公司 ERP (Enterprise Resource Planning) system based reserve project data processing method and system
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN105278524A (en) * 2015-11-10 2016-01-27 国家电网公司 Open type hydroelectric generating set fault diagnosis system
CN106096915A (en) * 2016-06-08 2016-11-09 国网安徽省电力公司检修公司 A kind of engineering project data handling system
CN107798488A (en) * 2017-11-24 2018-03-13 国网内蒙古东部电力有限公司 A kind of grid maintenance engineering Stores Management System
CN108389026A (en) * 2017-12-28 2018-08-10 广州建软科技股份有限公司 A kind of power failure planning management system and method
CN109358587A (en) * 2018-11-05 2019-02-19 国电南京自动化股份有限公司 A kind of Condition-based Maintenance of Hydroelectric Sets decision-making technique and system
CN110109875A (en) * 2017-12-27 2019-08-09 北京福田戴姆勒汽车有限公司 The data connecting method and system of Engineering Change Management information system
CN110348583A (en) * 2019-06-13 2019-10-18 河南大学 A kind of unit maintenance progress dynamic management-control method
CN110555609A (en) * 2019-08-26 2019-12-10 国网新源控股有限公司 Hydropower station field standardized operation management and control system and method
CN111435496A (en) * 2019-01-14 2020-07-21 上海汽车集团股份有限公司 Knowledge and project management method and device

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104504518A (en) * 2014-12-19 2015-04-08 深圳市燃气集团股份有限公司 ERP (Enterprise Resource Planning) system based reserve project data processing method and system
CN105278524B (en) * 2015-11-10 2018-10-26 国家电网公司 A kind of style of opening Approach for Hydroelectric Generating Unit Fault Diagnosis system
CN105278524A (en) * 2015-11-10 2016-01-27 国家电网公司 Open type hydroelectric generating set fault diagnosis system
CN106096915A (en) * 2016-06-08 2016-11-09 国网安徽省电力公司检修公司 A kind of engineering project data handling system
CN107798488A (en) * 2017-11-24 2018-03-13 国网内蒙古东部电力有限公司 A kind of grid maintenance engineering Stores Management System
CN110109875A (en) * 2017-12-27 2019-08-09 北京福田戴姆勒汽车有限公司 The data connecting method and system of Engineering Change Management information system
CN108389026A (en) * 2017-12-28 2018-08-10 广州建软科技股份有限公司 A kind of power failure planning management system and method
CN109358587A (en) * 2018-11-05 2019-02-19 国电南京自动化股份有限公司 A kind of Condition-based Maintenance of Hydroelectric Sets decision-making technique and system
CN111435496A (en) * 2019-01-14 2020-07-21 上海汽车集团股份有限公司 Knowledge and project management method and device
CN111435496B (en) * 2019-01-14 2023-10-03 上海汽车集团股份有限公司 Knowledge and project management method and device
CN110348583A (en) * 2019-06-13 2019-10-18 河南大学 A kind of unit maintenance progress dynamic management-control method
CN110555609A (en) * 2019-08-26 2019-12-10 国网新源控股有限公司 Hydropower station field standardized operation management and control system and method

Similar Documents

Publication Publication Date Title
CN103366259A (en) Method for planning inspection project in hydroelectric production management system
CN111815282B (en) Information system engineering supervision project guidance management system
CN111815283B (en) Information system engineering supervision enterprise business management system
Clark et al. Improving US Endangered Species Act recovery plans: key findings and recommendations of the SCB recovery plan project
Chorafas Enterprise architecture and new generation information systems
Asuncion et al. An end-to-end industrial software traceability tool
CN111815281B (en) Information system project supervision project bid management system
CN102117444A (en) System for comprehensive arrangement and execution management of production equipment maintenance plan
Squicciarini et al. A value chain statistical definition of construction and the performance of the sector
KR20080019581A (en) Cost element managing system
Gottfried Precarious work in Japan: Old forms, new risks?
Bakri et al. Addressing the issues of maintenance management in SMEs: towards sustainable and lean maintenance approach
CN102938096B (en) A kind of implementation method of the power plant registration information declaration system of dynamic configuration
Mutikanga et al. Postaward construction and contract management of engineering, procurement, and construction hydropower projects: Two case studies from Uganda
Balk et al. PPT: a COTS integration case study
Cadot et al. Incentives and obstacles to growth: Lessons from manufacturing case studies in Madagascar
CN201974848U (en) Management system for comprehensively arranging and executing maintenance plan of production equipment
Spraakman The impact of enterprise resource planning systems on management accounting: Some Canadian evidence and suggestions for future research
Arabzad et al. Improving project management process in municipality based on SWOT analysis
Burleson An analysis of multiskilled labor strategies in construction
Rundle et al. Effective front-end strategies to reduce waste on construction projects
Kuchta et al. The influence of culture on accounting systems
Bradbury How the XRB uses research in setting accounting and assurance standards
Esher Agile Methodology Tailoring Under CMMI®
Thimm ICT support for collaborative environmental compliance management in SMEs—The CCPro approach

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20131023

RJ01 Rejection of invention patent application after publication