CN112184177A - Project supervision method, device and storage medium - Google Patents

Project supervision method, device and storage medium Download PDF

Info

Publication number
CN112184177A
CN112184177A CN202011092925.5A CN202011092925A CN112184177A CN 112184177 A CN112184177 A CN 112184177A CN 202011092925 A CN202011092925 A CN 202011092925A CN 112184177 A CN112184177 A CN 112184177A
Authority
CN
China
Prior art keywords
plan
stage
identification information
project
personal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011092925.5A
Other languages
Chinese (zh)
Other versions
CN112184177B (en
Inventor
刘海
龚付坤
余忠
张学咏
姚传宝
胡正华
郭伟
牛犇
陈康
刘邦
甘新涛
李昌学
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Original Assignee
Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Tianheng Engineering Construction Consulting Management Co ltd filed Critical Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Priority to CN202011092925.5A priority Critical patent/CN112184177B/en
Publication of CN112184177A publication Critical patent/CN112184177A/en
Application granted granted Critical
Publication of CN112184177B publication Critical patent/CN112184177B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/186Templates
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/44Arrangements for executing specific programs
    • G06F9/451Execution arrangements for user interfaces

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Geometry (AREA)
  • Strategic Management (AREA)
  • Software Systems (AREA)
  • Human Resources & Organizations (AREA)
  • Artificial Intelligence (AREA)
  • Audiology, Speech & Language Pathology (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Health & Medical Sciences (AREA)
  • Computer Hardware Design (AREA)
  • Computational Linguistics (AREA)
  • General Health & Medical Sciences (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Computational Mathematics (AREA)
  • Civil Engineering (AREA)
  • Human Computer Interaction (AREA)
  • Data Mining & Analysis (AREA)
  • Mathematical Analysis (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides a project supervision method, which comprises the following steps: configuring identification information of each participating party company at each stage in the whole process project management and operation authority corresponding to each participating party company; editing the main plan of the A stage and the personal expansion plan corresponding to the A stage, and pushing the personal work task at the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; setting the name and the planning time range of the milestone node; showing the comparison between the actual progress and the planned progress; editing the personal work task and creating a new personal work task; and editing the preset work item template. By adopting the project supervision method, the project can be supervised from the whole process and multiple stages, so that each participating unit can conveniently overall plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.

Description

Project supervision method, device and storage medium
Technical Field
The present invention relates to the field of software technologies, and in particular, to a method, an apparatus, and a storage medium for project supervision.
Background
In the traditional project management, project plans of all stages of a project are respectively made by all participating units, and the defects that all participating units cannot collaboratively manage and control the whole project in time and cannot comprehensively manage the project exist.
Disclosure of Invention
The embodiment of the invention provides a project supervision method, equipment and a storage medium, which are used for project management, can supervise projects from the whole process and multiple stages, are convenient for various participating units to comprehensively plan the projects and master the overall progress condition of the projects; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
In a first aspect, the present invention provides a method of project supervision, the method of project supervision comprising displaying an interface, the method of project supervision comprising: configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company comprises: the system comprises construction party identification information, supervision party identification information and surveyor identification information, wherein the operation authority comprises checking authority and modifying authority. Editing the main plan and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone terminal at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; the A stage is any stage of the plurality of stages; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan includes personal work tasks created based on the A-phase master plan. Setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the plurality of planning nodes in the master plan. Showing the comparison between the actual progress and the planned progress; the actual progress is the actual completion condition of the plurality of plan nodes; the planned schedule is a planned completion of the number of planned nodes. Editing the personal work task and creating a new personal work task; the personal work task is the minimum execution unit of work and comprises a work package task and a common task; the work package tasks are tasks of presetting a work item template according to the national building construction quality safety standard, and comprise quality inspection, safety civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the general task is a task without a standard check item. And editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, the number of detection areas, the number of in-group detection points and the like.
In one possible design, the number of phases includes a decision phase, a survey design phase, a bid and tender phase, a construction phase, and an as built acceptance phase, the method comprising: configuring the viewing permission of the identification information of the construction party in the decision stage; configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage; configuring the viewing permission of the constructor identification information in the bidding stage; configuring the viewing authority of the construction party identification information in the construction stage; and configuring the viewing permission of the construction party identification information in the completion acceptance stage.
In one possible design, the method includes: configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage; and configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage.
In one possible design, the method includes: configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage; configuring the viewing authority and the modifying authority of the construction party identification information in the completion acceptance stage; configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage; and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
In one possible design, the method includes: the method comprises the following steps: importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system; importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system; importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system; importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system; -importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
In one possible design, the method includes: filling a preset work item template of the work package task at a mobile phone end; displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task; according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported; and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
In one possible design, the method includes: and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
In one possible design, the method includes: when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart; and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
In one possible design, the method includes: and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
In one possible design, the method of project supervision further comprises: performing identity authentication on user account information of the method for logging in the project supervision; checking a registration application of a user; setting a performance integral value corresponding to each task; managing personal data, company data, project data and task data; binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering; and automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
One or more technical solutions in the embodiments of the present invention at least have one or more of the following technical effects:
in the technical scheme of the embodiment of the invention, identification information of each participating party company at each stage in the whole process project management and operation authority corresponding to each participating party company are configured; editing the main plan and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; setting the name and the planning time range of the milestone node; and displaying the comparison of the actual progress and the planned progress; and editing the personal work task and creating a new personal work task; and the work package editing module is used for editing the preset work item template according to the national building construction quality safety standard. By adopting the project supervision method, the project can be supervised from the whole process and multiple stages, so that each participating unit can conveniently overall plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
Drawings
FIG. 1 is a schematic block flow diagram of a method of project supervision in an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a computer device in an embodiment of the present invention.
Fig. 3 is a schematic structural diagram of a computer-readable storage medium in an embodiment of the present invention.
Detailed Description
The technical solutions of the present invention are described in detail below with reference to the drawings and specific embodiments, and it should be understood that the specific features in the embodiments and examples of the present invention are described in detail in the technical solutions of the present application, and are not limited to the technical solutions of the present application, and the technical features in the embodiments and examples of the present application may be combined with each other without conflict.
The embodiment of the invention provides a project supervision method, which can supervise a project from the whole process and multiple stages, is convenient for each participating unit to comprehensively plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management. The examination system can be applied to engineering project management. The project supervision method is applied to a plurality of project management service terminals and a plurality of project management mobile terminals, wherein the project management service terminals are used for a platform manager to check registered enterprise information or the manager to perform plan management, task management and graph model management on projects. The project management server is also used for the general user to carry out plan management and task management on the project. And the project management mobile terminal is used for adding personal tasks or executing tasks by engineering project personnel and filling according to the work item template.
The embodiment of the invention divides the operation roles in the project management server into a platform manager, an enterprise manager and a general user, which are respectively introduced below.
A platform administrator: which has the authority of the platform management module. The platform administrator can perform the following operations in the project management service end: and screening and searching the personnel of the enterprise through or deleting the registered enterprise information.
The administrator: the system has the authority of an information configuration module, a plan management module, a task management module, a work package editing module and a graph model management module. The administrator can perform the following operations in the project management service end: creating a project, inputting information of the project, adding a company of a participating party and configuring authority; assigning tasks to personnel of the participating companies; binding a project two-dimensional design and construction drawing and a three-dimensional BIM model with a unit project; maintaining a main plan of a project and creating individual work tasks; view individual job tasks in question; and editing the preset work item template.
The general user: it has the authority of a plan management module and a task management module. The general user can perform the following operations at the project management service end: maintaining a main plan of a project and creating individual work tasks; to view the individual work tasks in question.
Example one
Referring to fig. 1, a method of project supervision is described, including:
s101, configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company comprises: the system comprises construction party identification information, supervision party identification information and surveyor identification information, wherein the operation authority comprises checking authority and modifying authority.
S102, editing a main plan of the A stage and a personal expansion plan of the A stage, and pushing personal work tasks of the time point to a mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; the A stage is any stage of the plurality of stages; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan includes personal work tasks created based on the A-phase master plan.
S103, setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the plurality of planning nodes in the master plan.
S104, displaying the comparison between the actual progress and the planned progress; the actual progress is the actual completion condition of the plurality of plan nodes; the planned schedule is a planned completion of the number of planned nodes.
S105, editing the personal work task and creating a new personal work task; the personal work task is the minimum execution unit of work and comprises a work package task and a common task; the work package tasks are tasks of presetting a work item template according to the national building construction quality safety standard, and comprise quality inspection, safety civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the general task is a task without a standard check item.
S106, editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control points, sample case diagrams, sample case videos, detection area types, detection area quantity, the number of in-group measurement points and the like.
In the embodiment of the invention, the identification information of each participating party company in each stage in the whole process project management and the operation authority corresponding to each participating party company are configured; editing the main plan and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone terminal at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; setting the name and the planning time range of the milestone node; showing the comparison between the actual progress and the planned progress; editing the personal work task and creating a new personal work task; and editing the preset work item template according to the national building construction quality safety standard. By adopting the project supervision method, the project can be supervised from the whole process and multiple stages, so that each participating unit can conveniently overall plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
Optionally, in some embodiments of the invention, the number of phases includes a decision phase, a survey design phase, a bid-in phase, a construction phase and an as-built acceptance phase, the method further comprising:
configuring the viewing permission of the identification information of the construction party in the decision stage; configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage; configuring the viewing permission of the constructor identification information in the bidding stage; configuring the viewing authority of the construction party identification information in the construction stage; and configuring the viewing permission of the construction party identification information in the completion acceptance stage.
Optionally, in some embodiments of the present invention, the method further includes: configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage; and configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage.
Optionally, in some embodiments of the present invention, the method further includes: configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage; configuring the viewing authority and the modifying authority of the construction party identification information in the completion acceptance stage; configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage; and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
Optionally, in some embodiments of the present invention, the method further includes: importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system; importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system; importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system; importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system; -importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
Optionally, in some embodiments of the present invention, the method further includes: filling a preset work item template of the work package task at a mobile phone end; displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task; according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported; and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
Optionally, in some embodiments of the present invention, the method further includes: and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
Optionally, in some embodiments of the present invention, the method further includes: when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart; and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
Optionally, in some embodiments of the present invention, the method further includes: and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
Optionally, in some embodiments of the present invention, the method for project supervision further includes:
performing identity authentication on user account information of the method for logging in the project supervision;
checking a registration application of a user;
setting a performance integral value corresponding to each task;
managing personal data, company data, project data and task data;
binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering;
and automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
Example two
In another aspect, the present embodiment provides a computer apparatus, as shown in fig. 2, including a memory 310, a processor 320, and a computer program 311 stored in the memory 310 and executable on the processor 320, wherein the processor 320 executes the computer program 311 to implement the following steps:
configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company at least comprises the following steps: construction side identification information, supervision side identification information, reconnaissance side identification information, design side identification information, the operation authority includes: viewing permissions and modifying permissions;
editing an A-stage main plan and an A-stage personal expansion plan, and pushing personal work tasks at the time points to a mobile phone end at the time points corresponding to the plans according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
showing the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
editing the personal work task and creating a new personal work task; the personal work tasks comprise a work package task and a common task; the work package tasks comprise quality inspection, safe civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without a standard check item;
and editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity and the number of the in-group detection points.
In particular, when the processor 320 executes the computer program 311, any one of the first embodiment can be implemented.
Since the computer device described in this embodiment is a device for implementing a method for improving machine code security in the first embodiment of this application, a person skilled in the art can understand a specific implementation manner of the computer device of this embodiment and various variations thereof based on the method described in the first embodiment of this application, and therefore, a detailed description of how the server implements the method in the embodiment of this application is omitted here. The equipment used by those skilled in the art to implement the methods in the embodiments of the present application is within the scope of the present application.
Based on the same inventive concept, the application provides a storage medium corresponding to the third embodiment.
EXAMPLE III
The present embodiment provides a computer-readable storage medium 400, as shown in fig. 3, on which a computer program 411 is stored, which computer program 411, when being executed by a processor, realizes the steps of:
configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company at least comprises the following steps: construction side identification information, supervision side identification information, reconnaissance side identification information, design side identification information, the operation authority includes: viewing permissions and modifying permissions;
editing an A-stage main plan and an A-stage personal expansion plan, and pushing personal work tasks at the time points to a mobile phone end at the time points corresponding to the plans according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
showing the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
editing the personal work task and creating a new personal work task; the personal work tasks comprise a work package task and a common task; the work package tasks comprise quality inspection, safe civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without a standard check item;
and editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity and the number of the in-group detection points.
In a specific implementation, when the computer program 411 is executed by a processor, any one of the first embodiment may be implemented.
As will be appreciated by one skilled in the art, embodiments of the present application may be provided as a method, system, or computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, and the like) having computer-usable program code embodied therein.
The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the application. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
The above description is only exemplary of the present invention and should not be taken as limiting the scope of the present invention, and any modifications, equivalents, improvements, etc. that are within the spirit and principle of the present invention should be included in the present invention.

Claims (10)

1. A project supervision method is applied to a project management platform, and is characterized by comprising the following steps:
configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company at least comprises the following steps: construction side identification information, supervision side identification information, reconnaissance side identification information, design side identification information, the operation authority includes: viewing permissions and modifying permissions;
editing an A-stage main plan and an A-stage personal expansion plan, and pushing personal work tasks at the time points to a mobile phone end at the time points corresponding to the plans according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
showing the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
editing the personal work task and creating a new personal work task; the personal work tasks comprise a work package task and a common task; the work package tasks comprise quality inspection, safe civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without a standard check item;
and editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity and the number of the in-group detection points.
2. The method of project supervision according to claim 1, wherein the plurality of phases include a decision phase, a survey design phase, a bid and ask phase, a construction phase and an as-built acceptance phase, wherein the configuring identification information of each of the participant companies of each phase in the full process project management and the operating rights corresponding to each of the participant companies specifically comprises:
configuring the viewing permission of the identification information of the construction party in the decision stage;
configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage;
configuring the viewing permission of the constructor identification information in the bidding stage;
configuring the viewing authority of the construction party identification information in the construction stage;
configuring the viewing authority of the construction party identification information in the completion acceptance stage;
configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage;
configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage;
configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage;
configuring viewing authority and modifying authority included in the completion acceptance stage of the construction party identification information;
configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage;
and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
3. The method for project supervision according to claim 2, wherein the editing of the a-phase master plan and the a-phase personal development plan, and the pushing of the personal work task at the time point to the mobile phone end at the time point corresponding to the plan according to the a-phase master plan and the a-phase personal development plan specifically comprises:
importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system;
importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system;
importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system;
importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system;
-importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
4. The method of project supervision according to claim 3, wherein said editing said personal work tasks and creating new personal work tasks specifically comprises:
filling a preset work item template of the work package task at a mobile phone end;
displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task;
according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported;
and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
5. The method of project supervision according to claim 4, wherein said editing said personal work task and creating a new personal work task specifically comprises also specifically for:
and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
6. The method of project supervision according to claim 5, wherein said showing the comparison of actual progress and planned progress specifically comprises:
when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart;
and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
7. The method of project supervision according to claim 6, wherein setting the name and projected time range of the milestone node specifically comprises:
and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
8. The method of project supervision according to any of claims 1-7, further comprising:
performing identity authentication on user account information of the method for logging in the project supervision;
checking a registration application of a user;
setting a performance integral value corresponding to each task;
managing personal data, company data, project data and task data;
binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering;
and automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
9. A computer-readable storage medium, on which a computer program is stored, which program, when executed by a processor, performs the steps of:
configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company at least comprises the following steps: construction side identification information, supervision side identification information, reconnaissance side identification information, design side identification information, the operation authority includes: viewing permissions and modifying permissions;
editing an A-stage main plan and an A-stage personal expansion plan, and pushing personal work tasks at the time points to a mobile phone end at the time points corresponding to the plans according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
showing the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
editing the personal work task and creating a new personal work task; the personal work tasks comprise a work package task and a common task; the work package tasks comprise quality inspection, safe civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without a standard check item;
and editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity and the number of the in-group detection points.
10. A computer device comprising a memory, a processor and a computer program stored on the memory and executable on the processor, wherein the processor when executing the program performs the steps of:
configuring identification information of each participating party company in each stage in the whole process project management and operation authority corresponding to each participating party company, wherein the identification information of each participating party company at least comprises the following steps: construction side identification information, supervision side identification information, reconnaissance side identification information, design side identification information, the operation authority includes: viewing permissions and modifying permissions;
editing an A-stage main plan and an A-stage personal expansion plan, and pushing personal work tasks at the time points to a mobile phone end at the time points corresponding to the plans according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
setting the name and the planning time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
showing the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
editing the personal work task and creating a new personal work task; the personal work tasks comprise a work package task and a common task; the work package tasks comprise quality inspection, safe civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without a standard check item;
and editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity and the number of the in-group detection points.
CN202011092925.5A 2020-10-13 2020-10-13 Project supervision method, equipment and storage medium Active CN112184177B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011092925.5A CN112184177B (en) 2020-10-13 2020-10-13 Project supervision method, equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011092925.5A CN112184177B (en) 2020-10-13 2020-10-13 Project supervision method, equipment and storage medium

Publications (2)

Publication Number Publication Date
CN112184177A true CN112184177A (en) 2021-01-05
CN112184177B CN112184177B (en) 2023-11-24

Family

ID=73949592

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011092925.5A Active CN112184177B (en) 2020-10-13 2020-10-13 Project supervision method, equipment and storage medium

Country Status (1)

Country Link
CN (1) CN112184177B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112766756A (en) * 2021-01-25 2021-05-07 珠海格力电器股份有限公司 Point inspection management method, point inspection management device, storage medium, management terminal and mobile terminal
CN113344540A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project cooperative control system and method, electronic device and storage medium
CN114331349A (en) * 2021-12-27 2022-04-12 南通智大信息技术有限公司 Scientific research project management method and system based on Internet of things technology
CN114548685A (en) * 2022-01-21 2022-05-27 四川省交通建设集团股份有限公司 Building construction project progress management method, system, electronic device and storage medium
CN114676455A (en) * 2022-03-16 2022-06-28 娄底潇湘职业学院 Information security monitoring system based on project management
CN116911778A (en) * 2023-07-03 2023-10-20 广州豆芽信息科技有限公司 Hotel project development management method and system
CN117455123A (en) * 2023-12-25 2024-01-26 中建科工集团有限公司 Cloud-based steel structure assembly type design project progress plan monitoring method and system

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080079713A (en) * 2007-02-02 2008-09-02 주식회사 비씨엠피 System and its method for managing tender information of construction company to accept a bid of construction work
CN104573991A (en) * 2015-01-28 2015-04-29 携程计算机技术(上海)有限公司 Project process management system
CN108229912A (en) * 2017-12-28 2018-06-29 北京地厚云图科技有限公司 Completion of works acceptance method and storage medium
CN108564347A (en) * 2018-04-20 2018-09-21 北京宇时易能科技发展有限公司 Overhaul whole process management system and lean inspection base
CN108932586A (en) * 2018-06-28 2018-12-04 南京绿新能源研究院有限公司 EPC Project cooperation operation management system
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
US20190220936A1 (en) * 2015-08-22 2019-07-18 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN110070343A (en) * 2019-04-24 2019-07-30 广州市城市规划勘测设计研究院 A kind of prospecting project management system and method
CN111383000A (en) * 2020-03-10 2020-07-07 中建八局第二建设有限公司 Method for improving building engineering project management
KR102131946B1 (en) * 2019-11-29 2020-07-09 한다움건설(주) Method for providing construction project management service using smart planner
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium
CN111598419A (en) * 2020-04-30 2020-08-28 国网浙江省电力有限公司台州供电公司 Power grid construction management and control method based on Internet and intelligent infrastructure platform system

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080079713A (en) * 2007-02-02 2008-09-02 주식회사 비씨엠피 System and its method for managing tender information of construction company to accept a bid of construction work
CN104573991A (en) * 2015-01-28 2015-04-29 携程计算机技术(上海)有限公司 Project process management system
US20190220936A1 (en) * 2015-08-22 2019-07-18 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN108229912A (en) * 2017-12-28 2018-06-29 北京地厚云图科技有限公司 Completion of works acceptance method and storage medium
CN108564347A (en) * 2018-04-20 2018-09-21 北京宇时易能科技发展有限公司 Overhaul whole process management system and lean inspection base
CN108932586A (en) * 2018-06-28 2018-12-04 南京绿新能源研究院有限公司 EPC Project cooperation operation management system
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN110070343A (en) * 2019-04-24 2019-07-30 广州市城市规划勘测设计研究院 A kind of prospecting project management system and method
KR102131946B1 (en) * 2019-11-29 2020-07-09 한다움건설(주) Method for providing construction project management service using smart planner
CN111383000A (en) * 2020-03-10 2020-07-07 中建八局第二建设有限公司 Method for improving building engineering project management
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium
CN111598419A (en) * 2020-04-30 2020-08-28 国网浙江省电力有限公司台州供电公司 Power grid construction management and control method based on Internet and intelligent infrastructure platform system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
许娜;李晓萌;李卿煜;李燕燕;: "基于BIM技术的工程监理关键业务研究", 项目管理技术, no. 12 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112766756A (en) * 2021-01-25 2021-05-07 珠海格力电器股份有限公司 Point inspection management method, point inspection management device, storage medium, management terminal and mobile terminal
CN113344540A (en) * 2021-06-22 2021-09-03 上海外高桥造船有限公司 Project cooperative control system and method, electronic device and storage medium
CN114331349A (en) * 2021-12-27 2022-04-12 南通智大信息技术有限公司 Scientific research project management method and system based on Internet of things technology
CN114331349B (en) * 2021-12-27 2023-01-10 南通智大信息技术有限公司 Scientific research project management method and system based on Internet of things technology
CN114548685A (en) * 2022-01-21 2022-05-27 四川省交通建设集团股份有限公司 Building construction project progress management method, system, electronic device and storage medium
CN114676455A (en) * 2022-03-16 2022-06-28 娄底潇湘职业学院 Information security monitoring system based on project management
CN114676455B (en) * 2022-03-16 2023-05-02 娄底潇湘职业学院 Information security monitoring system based on project management
CN116911778A (en) * 2023-07-03 2023-10-20 广州豆芽信息科技有限公司 Hotel project development management method and system
CN117455123A (en) * 2023-12-25 2024-01-26 中建科工集团有限公司 Cloud-based steel structure assembly type design project progress plan monitoring method and system

Also Published As

Publication number Publication date
CN112184177B (en) 2023-11-24

Similar Documents

Publication Publication Date Title
CN112184177B (en) Project supervision method, equipment and storage medium
CN112184175A (en) Whole-process project management platform
KR102255754B1 (en) BIM-based railway infrastructure business information management system and method
US11907709B2 (en) Enhancing DevOps workflows in enterprise information technology organizations
CN110880097B (en) Project progress simulation display method and device
US11507068B2 (en) Method for life cycle management of a complex utility facility and system for its implementation
US20240028991A1 (en) Flexible Work Breakdown Structure
KR102255756B1 (en) R-IFC viewer apparatus for providing BIM-based railway infrastructure business information service
TWI804694B (en) Method, mobile terminal, and storage medium for checking fixed asset
CN114782022B (en) Construction digital monitoring method and equipment based on identity authentication and storage medium
CN115827051A (en) Software integration management system, method and server
KR102355787B1 (en) Methods to gather screen requirements and to manage processes for the software development including web based services and mobile services
EP3916580A1 (en) Method and system for design and engineering led fiber rollout
CN114281312A (en) Software system construction method and device and computer readable storage medium
CN104408568A (en) Method and device for processing task information of owner project department
CN103530232B (en) A kind of software testing management framework establishment method and device
CN111078664B (en) Model-based system engineering data acquisition method and system
Pozin The principles of life cycle supporting system for mission-critical systems
Dixit et al. Integrating facility management functions in building information modeling (BIM): a review of key issues and challenges
CN110826834B (en) Comparison method and device between different responsibility separation rule sets
US20240143809A1 (en) Service and system integration
KR102255755B1 (en) BIM-based result items delivery management apparatus and method
CN116795329B (en) Work report generation method and device for software engineering and readable storage medium
EP3975026A1 (en) Method and system for managing asset data in an industrial network
Khamidov Manufacturing Know-How Management System for Product Development within the framework of Product Lifecycle Management

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant