CN112184175A CN202011092094.1A CN202011092094A CN112184175A CN 112184175 A CN112184175 A CN 112184175A CN 202011092094 A CN202011092094 A CN 202011092094A CN 112184175 A CN112184175 A CN 112184175A
Authority
CN
China
Prior art keywords
plan
work
stage
project
task
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202011092094.1A
Other languages
Chinese (zh)
Other versions
CN112184175B (en
Inventor
邓荣杰
李勇
周智奇
李长林
祖志甫
欧阳俊
舒光郧
闻正高
朱慧娟
肖进军
祝微
丁欧
刘洋
张�浩
牛犇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Original Assignee
Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Tianheng Engineering Construction Consulting Management Co ltd filed Critical Guangdong Tianheng Engineering Construction Consulting Management Co ltd
Priority to CN202011092094.1A priority Critical patent/CN112184175B/en
Publication of CN112184175A publication Critical patent/CN112184175A/en
Application granted granted Critical
Publication of CN112184175B publication Critical patent/CN112184175B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/30Authentication, i.e. establishing the identity or authorisation of security principals
    • G06F21/31User authentication
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/186Templates
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Geometry (AREA)
  • Computer Hardware Design (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Security & Cryptography (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Operations Research (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Health & Medical Sciences (AREA)
  • Artificial Intelligence (AREA)
  • Audiology, Speech & Language Pathology (AREA)
  • Computational Linguistics (AREA)
  • General Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Business, Economics & Management (AREA)
  • Economics (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • Data Mining & Analysis (AREA)
  • Software Systems (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides an overall process project management platform, which comprises: the information configuration module is used for configuring the identification information of each participating party company and the operation authority corresponding to each participating party company; the plan management module is used for editing the main plan and the individual expansion plan and pushing the individual work tasks at the time point corresponding to the plan; the node setting module is used for setting the name and the planned time range of the milestone node; the progress display module is used for displaying the comparison between the actual progress and the planned progress; the task management module is used for editing the personal work task and creating a new personal work task; and the work package editing module is used for editing the preset work item template. By the project management platform, projects can be supervised from the whole process and multiple stages, project plans can be comprehensively planned by each participating unit conveniently, and the overall progress condition of the projects can be mastered; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.

Description

Whole-process project management platform
Technical Field
The invention relates to the technical field of software, in particular to an overall process project management platform.
Background
In the traditional project management, each participating unit respectively formulates a project plan of each stage of a project and participates in the project management, and each participating unit cannot cooperate and share in time. The progress of the whole project is grasped, and the defect of project management cannot be comprehensively solved.
Disclosure of Invention
The embodiment of the invention provides an overall process project management platform which is used for project management, can supervise projects from the overall process and multiple stages, is convenient for various participating units to overall plan the projects and master the overall progress condition of the projects; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
In a first aspect, the present invention provides a whole process project management platform, where the project management platform includes a display interface, and the project management platform includes:
the information configuration module is used for configuring identification information of each participating party company in a plurality of stages in a project and operation authorities corresponding to each participating party company, and the identification information of each participating party company comprises: the system comprises construction party identification information, supervision party identification information and surveyor identification information, wherein the operation authority comprises checking authority and modifying authority.
The plan management module is used for editing the main plan and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; the A stage is any stage of the plurality of stages; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan includes personal work tasks created based on the A-phase master plan.
The node setting module is used for setting the name and the planned time range of the milestone node; the milestone node is a node or nodes of the plurality of planning nodes in the master plan.
The progress display module is used for displaying the comparison between the actual progress and the planned progress; the actual progress is the actual completion condition of the plurality of plan nodes; the planned schedule is a planned completion of the number of planned nodes.
The task management module is used for editing the personal work task and creating a new personal work task; the personal work task is the minimum execution unit of work and comprises a work package task and a common task; the work package tasks are tasks with preset work items and work item completion standards according to the national building construction quality safety standard, and comprise quality inspection, safety civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without preset work items and work item completion standards, and the work items and the work item standards need to be filled in by self. The system comprises a work packet editing module and a working item editing module, wherein the work packet editing module is used for editing a preset work item template according to the national building construction quality safety standard, and the preset work item template comprises witness content, control key points, sample diagrams, sample video, detection region types, detection region quantity, the number of in-group measurement points and the like.
In one possible design, the plurality of phases includes a decision phase, a survey design phase, a bid and tender phase, a construction phase, and an as-built acceptance phase, wherein the information configuration module is further configured to:
configuring the viewing permission of the identification information of the construction party in the decision stage; configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage; configuring the viewing permission of the constructor identification information in the bidding stage; configuring the viewing authority of the construction party identification information in the construction stage; and configuring the viewing permission of the construction party identification information in the completion acceptance stage.
In one possible design, the information configuration module is further to:
configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage; and configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage.
In one possible design, the information configuration module is further to:
configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage; configuring the viewing authority and the modifying authority of the construction party identification information in the completion acceptance stage; configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage; and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
In one possible design, the plan management module is further to:
importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system; importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system; importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system; importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system; -importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
In one possible design, the task management module is further configured to:
filling a preset work item template of the work package task at a mobile phone end; displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task; according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported; and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
In one possible design, the task management module is further configured to:
and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
In one possible design, the progress display module is further configured to:
when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart; and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
In one possible design, the node setup module is further to:
and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
In one possible design, the project management platform further includes:
the identity authentication module is used for performing identity authentication on the user account information logged in the project management platform; the platform management module is used for auditing the registration application of the user; the integral management module is used for setting a performance integral value corresponding to each task; the file module is used for managing personal data, company data, project data and task data; the drawing model management module is used for binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering; and the report management module is used for automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement actual quantity reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
One or more technical solutions in the embodiments of the present invention at least have one or more of the following technical effects:
in the technical scheme of the embodiment of the invention, the information configuration module is used for configuring the identification information of each participating party company in a plurality of stages in a project and the operation authority corresponding to each participating party company; the plan management module is used for editing the main plan and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; the node setting module is used for setting the name and the planned time range of the milestone node; the progress display module is used for displaying the comparison between the actual progress and the planned progress; the task management module is used for editing the personal work task and creating a new personal work task; and the work package editing module is used for editing the preset work item template according to the national building construction quality safety standard. By adopting the project management platform, the project can be supervised from the whole process and multiple stages, so that each participating unit can conveniently overall plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
Drawings
FIG. 1 is a schematic structural diagram of a project management platform according to an embodiment of the present invention;
fig. 2 is a schematic structural diagram of a project management platform according to an embodiment of the present invention.
Detailed Description
The technical solutions of the present invention are described in detail below with reference to the drawings and specific embodiments, and it should be understood that the specific features in the embodiments and examples of the present invention are described in detail in the technical solutions of the present application, and are not limited to the technical solutions of the present application, and the technical features in the embodiments and examples of the present application may be combined with each other without conflict.
The embodiment of the invention provides an overall process project management platform which can supervise projects from the overall process and multiple stages, is convenient for each participating unit to overall plan the projects and master the overall progress condition of the projects; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management. The examination system can be applied to engineering project management. The project management platform comprises a plurality of project management service terminals and a plurality of project management mobile terminals, wherein the project management service terminals are used for a platform administrator to examine registered enterprise information or the administrator to perform plan management, task management and graph model management on projects. The project management server is also used for the general user to carry out plan management and task management on the project. And the project management mobile terminal is used for adding personal tasks or executing tasks by engineering project personnel and filling according to the work item template.
In the project management platform, the operation roles in the project management server can be divided into a platform administrator, an enterprise administrator and a general user, which are introduced below.
A platform administrator: which has the authority of the platform management module. The platform administrator can perform the following operations in the project management service end: and screening and searching the personnel of the enterprise through or deleting the registered enterprise information.
The administrator: the system has the authority of an information configuration module, a plan management module, a task management module, a work package editing module and a graph model management module. The administrator can perform the following operations in the project management service end: creating a project, inputting information of the project, adding a company of a participating party and configuring authority; assigning tasks to personnel of the participating companies; binding a project two-dimensional design and construction drawing and a three-dimensional BIM model with a unit project; maintaining a main plan of a project and creating individual work tasks; view individual job tasks in question; and editing the preset work item template.
The general user: it has the authority of a plan management module and a task management module. The general user can perform the following operations at the project management service end: maintaining a main plan of a project and creating individual work tasks; to view the individual work tasks in question.
Examples
Referring to fig. 1, a full process project management platform is described, the project management platform including a display interface, the project management platform further including:
an information configuration module 101, configured to configure identification information of each participating party company at a plurality of stages in a project, and an operation authority corresponding to each participating party company, where the identification information of each participating party company includes: the system comprises construction party identification information, supervision party identification information and surveyor identification information, wherein the operation authority comprises checking authority and modifying authority.
The plan management module 102 is used for editing the main plan of the A stage and the personal expansion plan of the A stage, and pushing the personal work task of the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan of the A stage; the A stage is any stage of the plurality of stages; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan includes personal work tasks created based on the A-phase master plan.
The node setting module 103 is used for setting the name and the planned time range of the milestone node; the milestone node is a node or nodes of the plurality of planning nodes in the master plan.
The progress display module 104 is used for displaying the comparison between the actual progress and the planned progress; the actual progress is the actual completion condition of the plurality of plan nodes; the planned schedule is a planned completion of the number of planned nodes.
A task management module 105, configured to edit the personal work task and create a new personal work task; the personal work task is the minimum execution unit of work and comprises a work package task and a common task; the work package tasks are tasks with preset work items and work item completion standards according to the national building construction quality safety standard, and comprise quality inspection, safety civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without preset work items and work item completion standards, and the work items and the work item standards need to be filled in by self. And the work package editing module 106 is used for editing a preset work item template according to the national building construction quality safety standard, wherein the preset work item template comprises witness content, control key points, sample diagrams, sample videos, detection area types, detection area quantity, the number of in-group measurement points and the like.
In the embodiment of the invention, an information configuration module configures identification information of each participating party company in a plurality of stages in a project and operation authorities corresponding to each participating party company; the plan management module is used for editing the main plan and the personal expansion plan at the A stage, and pushing the personal work task at the time point to the mobile phone end at the time point corresponding to the plan according to the main plan and the personal expansion plan at the A stage; the node setting module is used for setting the name and the planned time range of the milestone node; the progress display module is used for displaying the comparison between the actual progress and the planned progress; the task management module is used for editing the personal work task and creating a new personal work task; and the work package editing module is used for editing the preset work item template according to the national building construction quality safety standard. By adopting the project management platform, the project can be supervised from the whole process and multiple stages, so that each participating unit can conveniently overall plan the project and master the overall progress condition of the project; the method can generate a working template according to the national standard and automatically generate various report forms commonly used in project management.
Optionally, in some embodiments of the present invention, the several phases include a decision phase, a survey design phase, a bid and tender phase, a construction phase and an as built acceptance phase, and the information configuration module 101 is configured to:
configuring the viewing permission of the identification information of the construction party in the decision stage; configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage; configuring the viewing permission of the constructor identification information in the bidding stage; configuring the viewing authority of the construction party identification information in the construction stage; and configuring the viewing permission of the construction party identification information in the completion acceptance stage.
Optionally, in some embodiments of the present invention, the information configuring module 101 is further configured to:
configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage; and configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage.
Optionally, in some embodiments of the present invention, the information configuring module 101 is further configured to:
configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage; configuring the viewing authority and the modifying authority of the construction party identification information in the completion acceptance stage; configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage; and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
Optionally, in some embodiments of the present invention, the plan management module 102 is further configured to:
importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system; importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system; importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system; importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system; -importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
Optionally, in some embodiments of the present invention, the task management module 105 is further configured to:
filling a preset work item template of the work package task at a mobile phone end; displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task; according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported; and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
Optionally, in some embodiments of the present invention, the task management module 105 is further configured to:
and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
Optionally, in some embodiments of the present invention, the progress display module 104 is further configured to:
when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart; and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
Optionally, in some embodiments of the present invention, the node setting module 103 is further configured to:
and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
Optionally, in some embodiments of the present invention, as shown in fig. 2, the project management platform further includes:
the identity authentication module 107 is used for performing identity authentication on the user account information logged in the project management platform;
the platform management module 108 is used for auditing the registration application of the user;
the integral management module 109 is used for setting a performance integral value corresponding to each task;
a document module 110 for managing personal data, company data, project data and task data;
the drawing model management module 111 is used for binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering;
and the report management module 112 is used for automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement actual quantity reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
The service end and the mobile end in the embodiment of the present application are introduced from the perspective of the modular functional entity, and the following introduces an overall process project management mobile end from the perspective of hardware, including: a processor, a memory, a display unit and an input-output unit, and a computer program stored in the memory and executable on the processor. The processor implements all or part of the operations implemented by the project management mobile terminal in the embodiment corresponding to any one of fig. 1 to 2 when executing the computer program, or implements the functions of the modules in the project management mobile terminal in the embodiment corresponding to any one of fig. 1 to 2 when executing the computer program.
Illustratively, the computer program may be partitioned into one or more modules/units that are stored in the memory and executed by the processor to implement the invention. The one or more modules/units may be a series of computer program instruction segments capable of performing specific functions, which are used to describe the execution of the computer program in the computer apparatus.
The project management mobile terminal can include, but is not limited to, a processor, a memory. Those skilled in the art will appreciate that the illustrations are merely examples of a computer apparatus and are not meant to be limiting as a server may include more or less components than those shown, or some components may be combined, or different components, e.g., the server may also include input output devices, network access devices, buses, etc.
The Processor may be a Central Processing Unit (CPU), other general purpose Processor, a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), an off-the-shelf Programmable Gate Array (FPGA) or other Programmable logic device, discrete Gate or transistor logic device, discrete hardware component, etc. The general purpose processor may be a microprocessor or the processor may be any conventional processor or the like which is the control center for the computer device and which connects the various parts of the overall computer device using various interfaces and lines.
The memory may be used to store the computer programs and/or modules, and the processor may implement various functions of the computer device by running or executing the computer programs and/or modules stored in the memory and invoking data stored in the memory. The memory may mainly include a storage program area and a storage data area, wherein the storage program area may store an operating system, an application program required by at least one function (such as a sound playing function, an image playing function, etc.), and the like; the storage data area may store data (such as audio data, video data, etc.) created according to the use of the cellular phone, etc. In addition, the memory may include high speed random access memory, and may also include non-volatile memory, such as a hard disk, a memory, a plug-in hard disk, a Smart Media Card (SMC), a Secure Digital (SD) Card, a Flash memory Card (Flash Card), at least one magnetic disk storage device, a Flash memory device, or other volatile solid state storage device.
The transceivers may also be replaced by receivers and transmitters, which may be the same or different physical entities. When the same physical entity, may be collectively referred to as a transceiver. The memory may be integrated in the processor or may be provided separately from the processor. The transceiver may be an input-output unit.
Embodiments of the present invention also provide a computer-readable storage medium on which a computer program is stored, where the computer program can be stored in a computer-readable storage medium when the examination client in the embodiments of the present invention is implemented in the form of a software functional unit and sold or used as a stand-alone product. Based on such understanding, all or part of the processes implemented by the test client in any of the embodiments corresponding to fig. 1-2 may be implemented by a computer program, which may be stored in a computer-readable storage medium and executed by a processor, so as to implement the steps of the above-mentioned method embodiments. Wherein the computer program comprises computer program code, which may be in the form of source code, object code, an executable file or some intermediate form, etc. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, usb disk, removable hard disk, magnetic disk, optical disk, computer Memory, Read-Only Memory (ROM), Random Access Memory (RAM), electrical carrier wave signals, telecommunications signals, software distribution medium, and the like. It should be noted that the computer readable medium may contain content that is subject to appropriate increase or decrease as required by legislation and patent practice in jurisdictions, for example, in some jurisdictions, computer readable media does not include electrical carrier signals and telecommunications signals as is required by legislation and patent practice.
While preferred embodiments of the present invention have been described, additional variations and modifications in those embodiments may occur to those skilled in the art once they learn of the basic inventive concepts. Therefore, it is intended that the appended claims be interpreted as including preferred embodiments and all such alterations and modifications as fall within the scope of the invention.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (10)

1. A full process project management platform, the project management platform comprising a display interface, the project management platform further comprising:
the information configuration module is used for configuring the identification information of each participating party company in a plurality of stages in a project and the operation authority corresponding to each participating party company, and the identification information of each participating party company at least comprises: the system comprises construction party identification information, supervision party identification information, reconnaissance party identification information and design party identification information, wherein the operation authority comprises viewing authority and modifying authority;
the plan management module is used for editing the A-stage main plan and the A-stage personal expansion plan and pushing the personal work task at the time point to the mobile phone end at the time point corresponding to the plan according to the A-stage main plan and the A-stage personal expansion plan; the A phase is any one of the number of phases; the main plan is a project plan progress schedule corresponding to the A stage and comprises a plurality of plan nodes and plan time ranges of the plan nodes; the personal development plan comprises personal work tasks created based on the A-phase main plan;
the node setting module is used for setting the name and the planned time range of the milestone node; the milestone node is a node or nodes of the number of plan nodes in the master plan;
the progress display module is used for displaying the comparison between the actual progress and the planned progress; the actual progress comprises actual completion conditions of the plurality of plan nodes; the plan progress comprises plan completion conditions of the plurality of plan nodes;
the task management module is used for editing the personal work task and creating a new personal work task; the personal work task is the minimum execution unit of work and comprises a work package task and a common task; the work package tasks are tasks with preset work items and work item completion standards according to the national building construction quality safety standard, and comprise quality inspection, safety civilized construction inspection, inspection batch acceptance, safety acceptance, side station, reporting, actual measurement and other tasks; the common task is a task without preset work items and work item completion standards, and the work items and the work item standards need to be filled in by self.
The system comprises a work packet editing module and a working item editing module, wherein the work packet editing module is used for editing a preset work item template according to the national building construction quality safety standard, and the preset work item template comprises witness content, control key points, sample diagrams, sample video, detection region types, detection region quantity, the number of in-group measurement points and the like.
2. The project management platform of claim 1, wherein the number of phases includes a decision phase, a survey design phase, a bid and bid phase, a construction phase, and an as built acceptance phase, wherein the information configuration module is further to:
configuring the viewing permission of the identification information of the construction party in the decision stage;
configuring the viewing permission of the identification information of the construction party in the reconnaissance design stage;
configuring the viewing permission of the constructor identification information in the bidding stage;
configuring the viewing authority of the construction party identification information in the construction stage;
and configuring the viewing permission of the construction party identification information in the completion acceptance stage.
3. The project management platform of claim 2, wherein the information configuration module is further to:
configuring the viewing authority and the modifying authority of the reconnaissance party identification information in the reconnaissance design stage;
and configuring the viewing authority and the modifying authority of the designer identification information in the reconnaissance design stage.
4. The project management platform of claim 3, wherein the information configuration module is further to:
configuring the viewing authority and the modifying authority of the constructor identification information in the construction stage;
configuring the viewing authority and the modifying authority of the construction party identification information in the completion acceptance stage;
configuring the viewing authority and the modifying authority of the proctor identification information in the construction stage;
and configuring the viewing authority and the modifying authority of the proctoring party identification information in the completion acceptance stage.
5. The project management platform of claim 4, wherein the plan management module is further to:
importing an external Project into a Project early-stage work schedule corresponding to the decision stage or directly self-establishing the Project early-stage work schedule corresponding to the decision stage in a system;
importing an external Project into a survey design working schedule corresponding to the survey design stage or directly self-establishing a survey design working schedule corresponding to the survey design stage in the system;
importing an external Project into a bidding work plan corresponding to the bidding stage or directly self-establishing the bidding work plan corresponding to the bidding stage in the system;
importing an external Project to a total construction progress plan corresponding to the construction stage or directly self-establishing the total construction progress plan corresponding to the construction stage in a system;
-importing an as-built acceptance work plan corresponding to the as-built acceptance phase from an external Project or building the as-built acceptance work plan corresponding to the as-built acceptance phase directly within the system.
6. The project management platform of claim 5, wherein the task management module is further to:
filling a preset work item template of the work package task at a mobile phone end;
displaying detailed information and a report of the personal work task, wherein the detailed information comprises witness content, control key points, sample diagrams, sample video, detection area types, detection area quantity, in-group detection points and the like, and the report is data and a conclusion which are filled and stored in a mobile phone terminal by the personal work task;
according to the information such as type, category, state, executant and the like, the personal work task is displayed in a list, and screening and searching according to the information are supported;
and displaying the statistical result of the number of the personal work tasks undertaken by each participating company and the departments thereof.
7. The project management platform of claim 6, wherein the task management module is further to:
and displaying actual measurement data of actual measurement points of the historical task, displaying a two-dimensional DWG drawing and a three-dimensional BIM model, and inputting the actual measurement data of the actual measurement points into the BIM model.
8. The project management platform of claim 7, wherein the progress presentation module is further to:
when a Gantt chart progress mode is selected, performing progress display from the dimension of the Gantt chart;
and when the model progress display mode is selected, displaying the actual model component and the planned model component at the corresponding time point according to a time axis based on the BIM.
9. The project management platform of claim 8, wherein the node setup module is further to:
and updating the state of the node into any one of completion, in-process and completed in real time along with the completion condition of the main plan node.
10. The project management platform of any of claims 1-9, wherein the project management platform further comprises:
the identity authentication module is used for performing identity authentication on the user account information logged in the project management platform;
the platform management module is used for auditing the registration application of the user;
the integral management module is used for setting a performance integral value corresponding to each task;
the file module is used for managing personal data, company data, project data and task data;
the drawing model management module is used for binding a two-dimensional design and construction drawing and a three-dimensional BIM model in the system with unit engineering;
and the report management module is used for automatically generating various daily reports such as supervision logs, daily reports, side station inspection reports, actual measurement actual quantity reports, engineering acceptance and the like according to the personal work tasks and the national building construction quality safety standard.
CN202011092094.1A 2020-10-13 2020-10-13 Whole process project management platform Active CN112184175B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011092094.1A CN112184175B (en) 2020-10-13 2020-10-13 Whole process project management platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011092094.1A CN112184175B (en) 2020-10-13 2020-10-13 Whole process project management platform

Publications (2)

Publication Number Publication Date
CN112184175A true CN112184175A (en) 2021-01-05
CN112184175B CN112184175B (en) 2023-11-24

Family

ID=73949620

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011092094.1A Active CN112184175B (en) 2020-10-13 2020-10-13 Whole process project management platform

Country Status (1)

Country Link
CN (1) CN112184175B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113159724A (en) * 2021-04-29 2021-07-23 王小平 Enterprise management platform organizational framework task management method based on big data
CN113379368A (en) * 2021-05-10 2021-09-10 深圳百胜扬工业电子商务平台发展有限公司 Project matrix management method and device
CN113537955A (en) * 2021-09-17 2021-10-22 天津中新智冠信息技术有限公司 Milestone project management device and method, electronic equipment and storage medium
CN114282897A (en) * 2021-12-24 2022-04-05 深圳市欧瑞博科技股份有限公司 Method and device for managing home service, intelligent equipment and storage medium
CN114971543A (en) * 2022-05-20 2022-08-30 广州市港航工程研究所 BIM-based overall process project management system and method
CN115358596A (en) * 2022-08-24 2022-11-18 国任财产保险股份有限公司 Project management system
CN116258610A (en) * 2023-05-15 2023-06-13 北京清科筑成科技股份公司 Construction project platform management method and system
CN116451986A (en) * 2023-04-14 2023-07-18 重庆信易源智能科技有限公司 Intelligent management system for digital transmitting field

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080079713A (en) * 2007-02-02 2008-09-02 주식회사 비씨엠피 System and its method for managing tender information of construction company to accept a bid of construction work
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem
US8000992B1 (en) * 2007-08-03 2011-08-16 Sprint Communications Company L.P. System and method for project management plan workbook
CN106845923A (en) * 2016-12-20 2017-06-13 柳州顺联科技有限公司 A kind of project management system
CN108229912A (en) * 2017-12-28 2018-06-29 北京地厚云图科技有限公司 Completion of works acceptance method and storage medium
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN110009116A (en) * 2019-03-05 2019-07-12 广州市城市规划勘测设计研究院 Civil air defense constructions and installations lifecycle management system
US20190220936A1 (en) * 2015-08-22 2019-07-18 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN110163509A (en) * 2019-05-23 2019-08-23 重庆渝高科技产业(集团)股份有限公司 A kind of big data platform project management system based on architectural engineering
CN111210199A (en) * 2020-01-03 2020-05-29 广西路桥工程集团有限公司 Bridge prefab BIM information management system
CN111401853A (en) * 2020-03-24 2020-07-10 上海捷规建筑工程咨询有限公司 Intelligent construction project management system based on BIM
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20080079713A (en) * 2007-02-02 2008-09-02 주식회사 비씨엠피 System and its method for managing tender information of construction company to accept a bid of construction work
US8000992B1 (en) * 2007-08-03 2011-08-16 Sprint Communications Company L.P. System and method for project management plan workbook
KR20090062417A (en) * 2007-12-13 2009-06-17 대림산업 주식회사 All working process management system of all working process using e.v.m.s progrem
US20190220936A1 (en) * 2015-08-22 2019-07-18 Salim B. KHALIL Automated, integrated and complete computer program/project management solutions standardizes and optimizes management processes and procedures utilizing customizable and flexible systems and methods
CN106845923A (en) * 2016-12-20 2017-06-13 柳州顺联科技有限公司 A kind of project management system
CN108229912A (en) * 2017-12-28 2018-06-29 北京地厚云图科技有限公司 Completion of works acceptance method and storage medium
CN109886643A (en) * 2019-01-29 2019-06-14 杭州凌望建筑科技有限公司 BIM multidimensional mould based on IOS examines platform
CN110009116A (en) * 2019-03-05 2019-07-12 广州市城市规划勘测设计研究院 Civil air defense constructions and installations lifecycle management system
CN110163509A (en) * 2019-05-23 2019-08-23 重庆渝高科技产业(集团)股份有限公司 A kind of big data platform project management system based on architectural engineering
CN111210199A (en) * 2020-01-03 2020-05-29 广西路桥工程集团有限公司 Bridge prefab BIM information management system
CN111401853A (en) * 2020-03-24 2020-07-10 上海捷规建筑工程咨询有限公司 Intelligent construction project management system based on BIM
CN111598379A (en) * 2020-03-31 2020-08-28 中铁建华南建设有限公司 Project management method, platform, device, computer equipment and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王莉;王金强;王铮辉;: "基于BIM的工程项目管理平台在加油站建设项目中的应用实践", 工程造价管理, no. 05 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113159724A (en) * 2021-04-29 2021-07-23 王小平 Enterprise management platform organizational framework task management method based on big data
CN113379368A (en) * 2021-05-10 2021-09-10 深圳百胜扬工业电子商务平台发展有限公司 Project matrix management method and device
CN113537955A (en) * 2021-09-17 2021-10-22 天津中新智冠信息技术有限公司 Milestone project management device and method, electronic equipment and storage medium
CN114282897A (en) * 2021-12-24 2022-04-05 深圳市欧瑞博科技股份有限公司 Method and device for managing home service, intelligent equipment and storage medium
CN114971543A (en) * 2022-05-20 2022-08-30 广州市港航工程研究所 BIM-based overall process project management system and method
CN115358596A (en) * 2022-08-24 2022-11-18 国任财产保险股份有限公司 Project management system
CN116451986A (en) * 2023-04-14 2023-07-18 重庆信易源智能科技有限公司 Intelligent management system for digital transmitting field
CN116258610A (en) * 2023-05-15 2023-06-13 北京清科筑成科技股份公司 Construction project platform management method and system

Also Published As

Publication number Publication date
CN112184175B (en) 2023-11-24

Similar Documents

Publication Publication Date Title
CN112184175A (en) Whole-process project management platform
CN112184177B (en) Project supervision method, equipment and storage medium
Westerkamp et al. Blockchain-based supply chain traceability: Token recipes model manufacturing processes
CN107516191B (en) Multi-rule-in-one and one-graph project collaborative approval system, method and tool
CN110737584A (en) Service data testing method and device based on block chain and computer equipment
CN113626914A (en) Engineering project management method, device and system based on digital twins
CN109544341B (en) Digital detection method and device based on block chain
CN110716966A (en) Data visualization processing method and system, electronic device and storage medium
US20180365612A1 (en) Systems and methods for strategic maintenance of a production environment utilizing a business rules management system
DE102016103713A1 (en) Detection of virtual machine units based on a catalog
KR20220094389A (en) Method And Apparatus for Managing Design Information for Railway Infrastructure Based On BIM
US20160092801A1 (en) Using complexity probability to plan a physical data center relocation
CN111932200A (en) Remote bidding evaluation system
CN114118047A (en) Report generation method, device, equipment and computer storage medium
US20130197952A1 (en) Product producible number calculation apparatus and computer-readable recording medium
CN111209281B (en) Annuity data processing method, annuity data processing device, medium and electronic equipment
CN112488730A (en) Product recall task processing method, device and equipment
CN114782022B (en) Construction digital monitoring method and equipment based on identity authentication and storage medium
CN116308826A (en) Insurance product online method, apparatus, equipment and storage medium
CN116228153A (en) Engineering project design change price management method, system, equipment and medium
CN112907220B (en) System, method and device for engineering cost
NOVIKOV et al. Improving the enterprise resource planning system based on digital modules of the industry 4.0 concept
CN115827051A (en) Software integration management system, method and server
Mateen et al. Enhancement in the effectiveness of requirement change management model for global software development
CN113657922A (en) Scheme planning method, planning device, terminal equipment and readable storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant