CN117078209A - Method, system and device for managing supervision project and computer storage medium - Google Patents

Method, system and device for managing supervision project and computer storage medium Download PDF

Info

Publication number
CN117078209A
CN117078209A CN202311115638.5A CN202311115638A CN117078209A CN 117078209 A CN117078209 A CN 117078209A CN 202311115638 A CN202311115638 A CN 202311115638A CN 117078209 A CN117078209 A CN 117078209A
Authority
CN
China
Prior art keywords
supervision
project
construction
sub
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202311115638.5A
Other languages
Chinese (zh)
Inventor
李新科
邓焕通
张翠平
罗德才
杨柳清
张国榕
张俊杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Kerui Engineering Management Co ltd
Original Assignee
Guangdong Kerui Engineering Management Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Kerui Engineering Management Co ltd filed Critical Guangdong Kerui Engineering Management Co ltd
Priority to CN202311115638.5A priority Critical patent/CN117078209A/en
Publication of CN117078209A publication Critical patent/CN117078209A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the technical field of engineering supervision, in particular to a supervision project management method, a system, a device and a computer storage medium.

Description

Method, system and device for managing supervision project and computer storage medium
Technical Field
The invention relates to a supervision project management method, in particular to a supervision project management method, a supervision project management system, a supervision project management device and a supervision project management computer storage medium.
Background
The construction project supervision refers to that a project supervision unit with legal qualification conditions performs supervision specific activities on the engineering construction process on behalf of a contractor in terms of construction quality, construction period, construction fund use and the like according to laws, administrative regulations and related construction engineering technical standards, design files and construction engineering contracts according to the entrustment of a contractor. As a contractor of a construction project, necessary supervision is required to be implemented on the engineering construction activities of contractors in order to obtain good investment benefits, ensure the project quality and reasonably control the construction period. Most of the contractors do not have good attention to the organization management and technical supervision of engineering construction, specialized engineering supervision units consisting of personnel with professional knowledge and practical experience in engineering construction are accepted by the contractors, the contractors are represented to supervise the quality, construction period and investment use condition of the engineering, and the maintenance of the benefits of the contractors, the coordination of the relationship between the contractors and the contractors, the assurance of the engineering quality and the standardization of the market order of construction are all of great superiority.
In the prior art, in the supervision process of the project, although each supervision has a professional supervision range, the scale of one project is large, the supervision of the project is not in place, the condition of unqualified construction quality is easy to occur because the supervision is not in place, the supervision operation of the project is unfavorable, and generally, the supervision operation of the whole process tracking of the appointed supervision is adopted by one project in the professional field, the supervision operation mode can facilitate the supervision to better know the construction condition, but along with the progress of project construction, after the supervision is continuously contacted with an engineering constructor, the supervision of the project is easy to be communicated with a contractor, the illegal benefit is taken for the contractor, the condition of loss is caused for a contractor, and the supervision operation of the engineering construction is unfavorable.
Based on the above reasons, the present invention provides a method, a system, a device and a computer storage medium for managing projects to solve the problems in the prior art.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a supervision project management method, a supervision project management system, a supervision project management device and a supervision project management computer storage medium.
In order to solve the technical problems, the invention provides the following technical scheme:
a method of managing a proctorial project, comprising the steps of:
s1: acquiring basic information of each item and information of each supervision in the item;
s2: determining and grouping the construction project sequence, and numbering and archiving each grouped construction project;
s3: the general supervision checks each construction sub-project, and issues each construction sub-project to each professional supervision engineer according to the sequence requirement of construction, and the professional supervision engineer distributes the construction supervision project and the requirement to each supervision operator;
s4: the supervisor is responsible for supervising the construction site, recording and reporting the construction condition to a professional supervision engineer, managing each supervisor in the construction process, performing regular and irregular inspection of the site construction condition, checking the actual inspection condition and the condition reported by the supervisor, and collating and reporting the checked information to the total supervision;
s5: the general supervision performs regular and irregular field check and inspection on each sub-project according to the reported information, supervises the construction progress and quality, gathers and archives the specific sub-project construction progress, constructor, construction quality and supervision personnel information, and completes the first-round sub-project construction supervision operation;
s6: then, carrying out second-round construction supervision operation again according to the construction project information in the step 2;
s7: when the second round of general supervision is used for issuing construction sub-projects, the supervision operators under each professional supervision engineer are randomly recombined and arranged under the corresponding professional supervision engineers to manage, and sub-project areas supervised by each professional supervision engineer are divided again;
s8: repeating the project sub-supervision operation steps in the step 5 and the step 6 to finish project sub-construction supervision operation of the second round;
s9: repeating the establishing operation steps from the step 3 to the step 8, and finishing the supervision and management of the whole project;
s10: and uniformly analyzing and archiving all the related data in the supervision project management construction process for later inquiry.
As a preferred technical solution of the present invention, each item of basic information of the item in the step 1 includes an item name, an item category, an item address, an item description, an item target, an item expiration date, an item budget, an item risk management, an item progress plan, and an item work plan, and the information of each supervision includes information of a project supervision organization structure and a general supervision, personal basic information of each professional supervision engineer, a supervision person, a practitioner qualification, and a background investigation of a practitioner experience, and a social relationship.
As a preferred technical scheme of the invention, the basis of dividing the project into different sub-projects in the step 2 is determined by a single construction building module, for example, one factory building in the whole project is a sub-project, and the number of the sub-project is formed by the upper case of Arabic numerals and English letters, for example, 1A, which means the first construction building module in the first round of sub-projects.
As a preferable technical scheme of the invention, the steps 3, 6 and 7 are all completed by grouping in a random mode for issuing the sub-items and determining the supervision operators, and the special supervision engineers in the step 3 comprise civil engineering supervision engineers, installation supervision engineers, hydropower supervision engineers, safety supervision engineers and cost supervision engineers, wherein at least two of each special supervision engineer are arranged, and at least two of the supervision operators under each special supervision engineer are arranged.
As a preferable technical scheme of the invention, the general supervision in the step 4 and the step 5 is at least once every five days for the regular inspection and check operation of the field construction, the professional supervision engineer is at least once every three days for the regular inspection and check operation of the field construction, at least once every four days for the irregular inspection and check operation of the field construction, and the regular and irregular inspection time is completely randomly determined, and the supervision engineer needs to perform the on-site construction condition supervision operation every day to the post.
The supervision project management system comprises a project information module, a supervision information module, a project distribution module, a project management module and a project data collection module;
the project information module is used for collecting and summarizing information of project names, project categories, project addresses, project descriptions, project targets, project expiration dates, project budgets, project risk management, project progress plans and project work plans, and dividing the whole project installation building module into each supervision sub-project according to the collected project information;
the supervision information module is used for collecting and summarizing personal basic information, practitioner qualification and information of background investigation of practitioner experience and social relations of each professional supervision engineer and each supervision person, and can also add, delete, upgrade and blacklist information according to the supervision construction requirement;
the project distribution module randomly distributes each sub-project to each professional supervision engineer according to the construction professional requirements of each round of sub-projects, randomly distributes the supervision workers meeting the appointed professional requirements for each professional supervision engineer, and then performs random supervision personnel and sub-project distribution operation again after each round of supervision sub-projects are completed.
The project management module is used for recording construction quality problems in the project construction process, recording violations and rule violations of the supervision personnel and constructors, recording on-duty conditions and supervision operation conditions of the supervision personnel, reassigning the supervision personnel and recording project construction progress;
the project data collection module is used for collecting data obtained by the on-site supervision of the supervision staff, collecting on-site condition information checked by the professional supervision engineer and collecting each item of information checked and allocated by the total supervision engineer, and collecting the collected project data information.
A supervision project management apparatus comprising
A memory for storing a computer program;
and the processor is used for realizing the steps of a supervision project management method when executing the computer program.
A computer storage medium in which is stored a computer program which, when executed by a processor, implements the steps of a method of managing items.
The embodiment of the invention provides a supervision project management method, a supervision project management system, a supervision project management device and a computer storage medium, which have the following beneficial effects:
1. according to the invention, by forming the architecture of the general supervision engineer, the professional supervision engineer and the supervision engineer, different professional supervision engineers are utilized to lead a plurality of supervision engineers to carry out construction supervision on a single sub-project, the supervision engineer is adopted to carry out real-time on-site supervision on the site and the supervision engineers, the general supervision can carry out supervision operation on the professional supervision engineer, the supervision engineer and the site, each sub-project can be comprehensively and accurately subjected to supervision operation, the whole project is divided into a plurality of sub-projects, the project quantity required to be supervised by the supervision engineer, the professional supervision engineer and the general supervision are further reduced, the situation of insufficient supervision is effectively avoided, and the project management is convenient;
2. according to the invention, the whole project is divided into a plurality of sub-projects according to the construction sequence to perform random sub-management construction operation, and after each round of sub-project construction is completed, sub-project construction areas of professional supervision engineers are randomly allocated to each round of sub-projects, and the supervision workers of each professional supervision engineer are randomly recombined, so that excessive contact between the professional supervision engineers and the supervision workers and single constructors in the project construction process is effectively avoided, cross talk between supervision and sub-division constructors is avoided, and project construction quality and project stability are ensured.
Drawings
The accompanying drawings are included to provide a further understanding of the invention and are incorporated in and constitute a part of this specification, illustrate the invention and together with the embodiments of the invention, serve to explain the invention. In the drawings:
FIG. 1 is a flow chart of a method of managing items in accordance with the present invention;
fig. 2 is a diagram showing a supervision architecture of a supervision project management method according to the present invention.
Detailed Description
The preferred embodiments of the present invention will be described below with reference to the accompanying drawings, it being understood that the preferred embodiments described herein are for illustration and explanation of the present invention only, and are not intended to limit the present invention.
Examples: as shown in fig. 1-2, a method for managing a supervision item includes the following steps:
s1: acquiring basic information of a project and information of each supervision in the project, wherein the basic information of the project comprises project names, project categories, project addresses, project descriptions, project targets, project expiration dates, project budgets, project risk management, project progress plans and project work plans, and the information of each supervision comprises information of project supervision organization architecture and general supervision, personal basic information of each professional supervision engineer and supervision manager, practitioner qualification and information of background investigation of practitioner experience and social relationship;
s2: determining and grouping the sequence of construction projects, numbering and archiving each grouped construction sub-project, wherein the project is divided into different sub-projects and is determined by a single construction building module according to the basis, for example, one factory building in the whole project is a sub-project, and the number of the sub-project is formed by Arabic numerals and English letters in capitalization, for example, 1A, which means the first construction building module in the first round of sub-project;
s3: the method comprises the steps that a master supervision checks construction sub-projects, the construction sub-projects are issued to professional supervision engineers according to construction sequence requirements, the construction sub-projects are issued and the supervision workers are determined in a random mode, the professional supervision engineers distribute the construction supervision projects and the requirements to the supervision workers, each professional supervision engineer comprises a civil engineering supervision engineer, an installation supervision engineer, a hydropower supervision engineer, a safety supervision engineer and a construction cost supervision engineer, at least two professional supervision engineers are arranged, and at least two supervision workers under each professional supervision engineer are arranged;
s4: the supervision engineer is responsible for supervising the construction site, recording and reporting the construction condition, and the professional supervision engineer needs to manage each supervision engineer in the construction process and make regular and irregular inspection of the site construction condition, checks the actual inspection condition with the condition reported by the supervision engineer, and reports the checked information to the total supervision, wherein the professional supervision engineer makes regular inspection and check operation for the site construction at least once every three days, makes irregular inspection and check operation for the site construction at least once every four days, and makes regular and irregular inspection time completely random, and the supervision engineer needs to make site construction condition supervision operation every day;
s5: the general supervision carries out regular and irregular field check and inspection on each sub-project according to the reported information, supervises the progress and quality of construction, gathers and archives the specific sub-project construction progress, constructors, construction quality and supervision personnel information, completes the first round of sub-project construction supervision operation, the general supervision carries out regular inspection and check operation on the field construction at least once every five days, carries out irregular inspection and check operation on the field construction at least once every four days, and the regular and irregular inspection time is completely and randomly determined;
s6: then, carrying out second-round construction supervision operation again according to the construction project information in the step 2;
s7: when the second round of general supervision is used for issuing construction sub-projects, the sub-projects are issued and the supervision operators are determined in a random manner, the supervision operators under each professional supervision engineer are randomly recombined and arranged under the corresponding professional supervision engineers to manage, and sub-project areas supervised by each professional supervision engineer are divided again;
s8: repeating the project sub-supervision operation steps in the step 5 and the step 6 to finish project sub-construction supervision operation of the second round;
s9: repeating the establishing operation steps from the step 3 to the step 8, and finishing the supervision and management of the whole project;
s10: and uniformly analyzing and archiving all the related data in the supervision project management construction process for later inquiry.
The supervision project management system comprises a project information module, a supervision information module, a project distribution module, a project management module and a project data collection module;
the project information module is used for collecting and summarizing information of project names, project categories, project addresses, project descriptions, project targets, project expiration dates, project budgets, project risk management, project progress plans and project work plans, and dividing the whole project installation building module into each supervision sub-project according to the collected project information;
the supervision information module is used for collecting and summarizing personal basic information, practitioner qualification and information of background investigation of practitioner experience and social relations of each professional supervision engineer and each supervision person, and can also add, delete, upgrade and blacklist information according to the supervision construction requirement;
the project distribution module randomly distributes each sub-project to each professional supervision engineer according to the construction professional requirements of each round of sub-projects, randomly distributes the supervision workers meeting the appointed professional requirements for each professional supervision engineer, and then performs random supervision personnel and sub-project distribution operation again after each round of supervision sub-projects are completed.
The project management module is used for recording construction quality problems in the project construction process, recording violations and rule violations of the supervision personnel and constructors, recording on-duty conditions and supervision operation conditions of the supervision personnel, reassigning the supervision personnel and recording project construction progress;
the project data collection module is used for collecting data obtained by the on-site supervision of the supervision staff, collecting on-site condition information checked by the professional supervision engineer and collecting each item of information checked and allocated by the total supervision engineer, and collecting the collected project data information.
A supervision project management apparatus comprising
A memory for storing a computer program;
and the processor is used for realizing the steps of a supervision project management method when executing the computer program.
A computer storage medium in which is stored a computer program which, when executed by a processor, implements the steps of a method of managing items.
The foregoing description is only a preferred embodiment of the present invention, and the present invention is not limited thereto, but it is to be understood that modifications and equivalents of some of the technical features described in the foregoing embodiments may be made by those skilled in the art, although the present invention has been described in detail with reference to the foregoing embodiments. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (8)

1. The supervision project management method is characterized by comprising the following steps of:
s1: acquiring basic information of each item and information of each supervision in the item;
s2: determining and grouping the construction project sequence, and numbering and archiving each grouped construction project;
s3: the general supervision checks each construction sub-project, and issues each construction sub-project to each professional supervision engineer according to the sequence requirement of construction, and the professional supervision engineer distributes the construction supervision project and the requirement to each supervision operator;
s4: the supervisor is responsible for supervising the construction site, recording and reporting the construction condition to a professional supervision engineer, managing each supervisor in the construction process, performing regular and irregular inspection of the site construction condition, checking the actual inspection condition and the condition reported by the supervisor, and collating and reporting the checked information to the total supervision;
s5: the general supervision performs regular and irregular field check and inspection on each sub-project according to the reported information, supervises the construction progress and quality, gathers and archives the specific sub-project construction progress, constructor, construction quality and supervision personnel information, and completes the first-round sub-project construction supervision operation;
s6: then, carrying out second-round construction supervision operation again according to the construction project information in the step 2;
s7: when the second round of general supervision is used for issuing construction sub-projects, the supervision operators under each professional supervision engineer are randomly recombined and arranged under the corresponding professional supervision engineers to manage, and sub-project areas supervised by each professional supervision engineer are divided again;
s8: repeating the project sub-supervision operation steps in the step 5 and the step 6 to finish project sub-construction supervision operation of the second round;
s9: repeating the establishing operation steps from the step 3 to the step 8, and finishing the supervision and management of the whole project;
s10: and uniformly analyzing and archiving all the related data in the supervision project management construction process for later inquiry.
2. The method according to claim 1, wherein the basic information of the project in the step 1 includes project name, project category, project address, project description, project goal, project expiration date, project budget, project risk management, project schedule, and project work schedule, and the information of each supervision includes information of project supervision organization structure and general supervision, personal basic information of each professional supervision engineer, practitioner qualification, and, practitioner experience, and background investigation of social relationship.
3. The method according to claim 1, wherein the step 2 is determined for dividing the project into different sub-projects based on a single construction building module, such as one of the plants in the whole project is a sub-project, and the number of the sub-project is formed by using the form of the upper case of the arabic numerals and the english letters, such as 1A, which means the first construction building module in the first sub-project.
4. The supervision project management method according to claim 1, wherein the issuing of the sub-projects and the determination of the supervision engineers in step 3, step 6 and step 7 are all accomplished by grouping in a random manner, and the special supervision engineers in step 3 comprise civil engineering supervision engineers, installation supervision engineers, hydropower supervision engineers, safety supervision engineers and construction cost supervision engineers, wherein at least two of each special supervision engineer are provided, and at least two of the supervision engineers under each special supervision engineer are provided.
5. The supervision project management method according to claim 1, wherein the general supervision in step 4 and step 5 is performed at least once every five days for the regular patrol and check operation of the site construction, the professional supervision engineer is performed at least once every three days for the regular patrol and check operation of the site construction, at least once every four days for the irregular patrol and check operation of the site construction, and the time of the regular and irregular patrol is completely randomly determined, and the supervision engineer is required to perform the supervision operation of the site construction condition every day.
6. The supervision project management system is characterized by comprising a project information module, a supervision information module, a project distribution module, a project management module and a project data collection module;
the project information module is used for collecting and summarizing information of project names, project categories, project addresses, project descriptions, project targets, project expiration dates, project budgets, project risk management, project progress plans and project work plans, and dividing the whole project installation building module into each supervision sub-project according to the collected project information;
the supervision information module is used for collecting and summarizing personal basic information, practitioner qualification and information of background investigation of practitioner experience and social relations of each professional supervision engineer and each supervision person, and can also add, delete, upgrade and blacklist information according to the supervision construction requirement;
the project distribution module randomly distributes each sub-project to each professional supervision engineer according to the construction professional requirements of each round of sub-projects, randomly distributes the supervision workers meeting the appointed professional requirements for each professional supervision engineer, and then performs random supervision personnel and sub-project distribution operation again after each round of supervision sub-projects are completed.
The project management module is used for recording construction quality problems in the project construction process, recording violations and rule violations of the supervision personnel and constructors, recording on-duty conditions and supervision operation conditions of the supervision personnel, reassigning the supervision personnel and recording project construction progress;
the project data collection module is used for collecting data obtained by the on-site supervision of the supervision staff, collecting on-site condition information checked by the professional supervision engineer and collecting each item of information checked and allocated by the total supervision engineer, and collecting the collected project data information.
7. A supervision project management apparatus, comprising
A memory for storing a computer program;
a processor for implementing the steps of a method of managing items according to any one of claims 1 to 6 when executing said computer program.
8. A computer storage medium for supervision of item management, characterized in that the readable storage medium has stored therein a computer program which, when executed by a processor, implements the steps of a supervision item management method according to any one of claims 1 to 6.
CN202311115638.5A 2023-08-31 2023-08-31 Method, system and device for managing supervision project and computer storage medium Pending CN117078209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202311115638.5A CN117078209A (en) 2023-08-31 2023-08-31 Method, system and device for managing supervision project and computer storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202311115638.5A CN117078209A (en) 2023-08-31 2023-08-31 Method, system and device for managing supervision project and computer storage medium

Publications (1)

Publication Number Publication Date
CN117078209A true CN117078209A (en) 2023-11-17

Family

ID=88702216

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202311115638.5A Pending CN117078209A (en) 2023-08-31 2023-08-31 Method, system and device for managing supervision project and computer storage medium

Country Status (1)

Country Link
CN (1) CN117078209A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117634736A (en) * 2023-11-27 2024-03-01 成致项目管理有限公司 Engineering supervision monitoring system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117634736A (en) * 2023-11-27 2024-03-01 成致项目管理有限公司 Engineering supervision monitoring system

Similar Documents

Publication Publication Date Title
CN104951905A (en) Equipment dynamic ledger management system
CN104871182A (en) System for inspection and maintenance of a plant or other facility
Loera et al. Productivity in construction and industrial maintenance
CN107798479B (en) Knowledge management system based on full life cycle integrated knowledge experience information
CN111461517A (en) Intelligent information system for planning laboratory workflow
Gurmu et al. Survey of management practices enhancing labor productivity in multi-storey building construction projects
CN113112233A (en) BIM-based intelligent management method and platform for full life cycle of wind power project
CN117078209A (en) Method, system and device for managing supervision project and computer storage medium
Topchiy et al. Risk management in monolithic construction
CN110930025A (en) Project management system for engineering construction
Safapour et al. Investigation and analysis of human, organizational, and project based rework indicators in construction projects
Setiawan et al. Recruitment analysis on employee performance with variable control as moderating on manufacturing company
CN116523258A (en) Heating system operation and maintenance plan management and control method and device based on advanced plan scheduling
CN113592611A (en) Integrated management system for centralized acquisition and supervision of garbage incineration enterprises
CN113987015A (en) Equipment asset state management method, system, equipment and storage medium
Al‐Muhaisen et al. Auditing of the maintenance system of Fuhais plant/Jordan Cement Factories Co.
RU2676030C1 (en) Automated self-service device network management system
CN110175814A (en) A kind of strong event lifecycle management model
Laryea et al. The price of risk in construction projects
CN109034422A (en) Equipment detection management method and apparatus
Zheleznov et al. Automation of the estimation of production preparation at an aircraft manufacturing
Ling et al. Study on The Cost Attribution Method of Power Grid Equipment Maintenance under Multi-dimensional Lean Management Model
Dharmayanti et al. Analysis of the Covid-19 Pandemic Impact on the Performance of Construction Projects in Denpasar City
Alherian et al. Integrated risk management model implementation's contextual dependence on company size
Qureshi et al. Qualitative study on construction project risk

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination