一种大跨度钢梁安装精度控制施工方法 Download PDFInfo
- Publication number
- CN110781543A CN110781543A CN201910975563.5A CN201910975563A CN110781543A CN 110781543 A CN110781543 A CN 110781543A CN 201910975563 A CN201910975563 A CN 201910975563A CN 110781543 A CN110781543 A CN 110781543A
- Authority
- CN
- China
- Prior art keywords
- steel beam
- span
- welding
- span steel
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 98
- 239000010959 steel Substances 0.000 title claims abstract description 98
- 238000010276 construction Methods 0.000 title claims abstract description 25
- 238000009434 installation Methods 0.000 title claims abstract description 21
- 238000003466 welding Methods 0.000 claims abstract description 35
- 238000013461 design Methods 0.000 claims abstract description 9
- 238000004519 manufacturing process Methods 0.000 claims abstract description 5
- 238000012545 processing Methods 0.000 claims abstract description 5
- 239000000463 material Substances 0.000 claims description 6
- 238000000034 method Methods 0.000 claims description 6
- 238000004088 simulation Methods 0.000 claims description 5
- 238000001514 detection method Methods 0.000 claims description 4
- 238000004364 calculation method Methods 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- 230000007547 defect Effects 0.000 abstract description 2
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
Abstract
本发明公开了一种大跨度钢梁安装精度控制施工方法,本发明严格控制深化设计图纸质量、钢梁加工制作质量,并采用合理的安装顺序、焊接顺序能有有效保证大跨度钢梁的安装精度;有效防止了大跨度钢梁极易产生下挠,造成次梁无法安装的缺陷。
Description
技术领域:
本发明属于建筑领域,尤其涉及一种大跨度钢梁安装精度控制施工方 法。
背景技术:
在纪念馆、博物馆等修建时,由于需要单个厅的面积大,且支柱尽量少, 因此经常需要进行大跨度钢梁(如27米)的修建,但是现有的大跨度钢梁 通常采用多种形式的钢材连接,无法做到精确施工,容易导致建筑质量难 以达标。
发明内容:
本发明的目的在于提供一种大跨度钢梁安装精度控制施工方法,本发明 严格控制深化设计图纸质量、钢梁加工制作质量,并采用合理的安装顺序、 焊接顺序能有有效保证大跨度钢梁的安装精度;有效防止了大跨度钢梁极 易产生下挠,造成次梁无法安装的缺陷。
为解决上述问题,本发明的技术方案是:
一种大跨度钢梁安装精度控制施工方法,包括如下步骤:
步骤一、使用tekla软件对大跨度钢梁进行建模建立tekla模型,通过 模型生成设计详图;所述tekla模型包括钢结构的构件编号、位置、标高、 截面、材质;基于tekla模型统计材料、加工和安装定位方法、工程量统计;
步骤二、所述tekla模型信息导入BIM软件进行总体进度控制、物流 控制和检查;
步骤三、制作所需要的钢梁,所需要的钢梁包括有H型截面钢梁和箱 型截面钢梁;
步骤四、首先建造大跨度钢梁建造区域的核心筒区,然后将核心筒内钢骨 柱和钢骨梁安装完成行成稳定的钢框架作为大跨度钢梁支座,然后通过大 跨度钢梁支座进行大跨度钢梁的安装,然后大跨度钢梁再与次梁相连完成 安装。
进一步的改进,所述钢梁之间通过焊接连接,所述焊接的方法为CO2气 体保护焊,由于其能量密度相对较高,焊接变形也相应小一些。
进一步的改进,钢梁之间焊接时进行结构标高、水平度、垂直度的监 控并且相对节点对称焊接;tekla模型对焊接变形量进行排序,先焊接对构 件整体变形影响较小的焊缝。
进一步的改进,所述步骤四中,先焊接大跨度钢梁的中部然后向两侧 对称焊接,降低焊接应力。
进一步的改进,H型钢梁焊接时的焊接顺序为先焊立焊,再焊下翼缘, 最后焊接上翼缘,同一个钢梁,先完全焊接完一端后再焊接另一端,使得 焊接的收缩变形始终可以自由释放。
进一步的改进,在施工前,施工模拟计算钢梁起拱值,根据施工模拟 计算结果,对于需起拱的钢梁,当计算下挠度大于设计起拱值时根据计算 下挠值进行起拱;当计算下挠度小于设计起拱值是,现场安装按照设计起 拱值进行安装。
进一步的改进,制作所需要的钢梁时,对钢梁进行焊缝探伤和检测, 并进行矫正,保证钢梁符合设计要求。
具体实施方式:
为使本发明的上述目的、特征和优点能够更加明显易懂,下面将对 本发明实施例中的技术方案进行清楚、完整地描述。
实施例1
一种大跨度钢梁安装精度控制施工方法,包括如下步骤:
步骤一、使用tekla软件对大跨度钢梁进行建模建立tekla模型,通过 模型生成设计详图;所述tekla模型包括钢结构的构件编号、位置、标高、 截面、材质;基于tekla模型统计材料、加工和安装定位方法、工程量统计;
步骤二、所述tekla模型信息导入BIM软件进行总体进度控制、物流 控制和检查;
步骤三、制作所需要的钢梁,所需要的钢梁包括有H型截面钢梁和箱 型截面钢梁;
步骤四、首先建造大跨度钢梁建造区域的核心筒区,然后将核心筒内钢骨 柱和钢骨梁安装完成行成稳定的钢框架作为大跨度钢梁支座,然后通过大 跨度钢梁支座进行大跨度钢梁的安装,然后大跨度钢梁再与次梁相连完成 安装。
所述钢梁之间通过焊接连接,所述焊接的方法为CO2气体保护焊,由 于其能量密度相对较高,焊接变形也相应小一些。
钢梁之间焊接时进行结构标高、水平度、垂直度的监控并且相对节点 对称焊接;tekla模型对焊接变形量进行排序,先焊接对构件整体变形影响 较小的焊缝。
所述步骤四中,先焊接大跨度钢梁的中部然后向两侧对称焊接,降低 焊接应力。
H型钢梁焊接时的焊接顺序为先焊立焊,再焊下翼缘,最后焊接上翼 缘,同一个钢梁,先完全焊接完一端后再焊接另一端,使得焊接的收缩变 形始终可以自由释放。
在施工前,施工模拟计算钢梁起拱值,根据施工模拟计算结果,对于 需起拱的钢梁,当计算下挠度大于设计起拱值时根据计算下挠值进行起拱; 当计算下挠度小于设计起拱值是,现场安装按照设计起拱值进行安装。
制作所需要的钢梁时,对钢梁进行焊缝探伤和检测,并进行矫正,保证 钢梁符合设计要求。
以上所述仅为本发明的一个实施例,并不用以限制本发明,凡在本发明 的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发 明的保护范围之内。
Claims (7)
1.一种大跨度钢梁安装精度控制施工方法,其特征在于,包括如下步骤:
步骤一、使用tekla软件对大跨度钢梁进行建模建立tekla模型,通过模型生成设计详图;所述tekla模型包括钢结构的构件编号、位置、标高、截面、材质;基于tekla模型统计材料、加工和安装定位方法、工程量统计;
步骤二、所述tekla模型信息导入BIM软件进行总体进度控制、物流控制和检查;
步骤三、制作所需要的钢梁,所需要的钢梁包括有H型截面钢梁和箱型截面钢梁;
步骤四、首先建造大跨度钢梁建造区域的核心筒区,然后将核心筒内钢骨柱和钢骨梁安装完成行成稳定的钢框架作为大跨度钢梁支座,然后通过大跨度钢梁支座进行大跨度钢梁的安装,然后大跨度钢梁再与次梁相连完成安装。
2.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,所述钢梁之间通过焊接连接,所述焊接的方法为CO2气体保护焊,由于其能量密度相对较高,焊接变形也相应小一些。
3.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,钢梁之间焊接时进行结构标高、水平度、垂直度的监控并且相对节点对称焊接;tekla模型对焊接变形量进行排序,先焊接对构件整体变形影响较小的焊缝。
4.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,所述步骤四中,先焊接大跨度钢梁的中部然后向两侧对称焊接,降低焊接应力。
5.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,H型钢梁焊接时的焊接顺序为先焊立焊,再焊下翼缘,最后焊接上翼缘,同一个钢梁,先完全焊接完一端后再焊接另一端,使得焊接的收缩变形始终可以自由释放。
6.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,在施工前,施工模拟计算钢梁起拱值,根据施工模拟计算结果,对于需起拱的钢梁,当计算下挠度大于设计起拱值时根据计算下挠值进行起拱;当计算下挠度小于设计起拱值是,现场安装按照设计起拱值进行安装。
7.如权利要求1所述的大跨度钢梁安装精度控制施工方法,其特征在于,制作所需要的钢梁时,对钢梁进行焊缝探伤和检测,并进行矫正,保证钢梁符合设计要求。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910975563.5A CN110781543A (zh) | 2019-10-15 | 2019-10-15 | 一种大跨度钢梁安装精度控制施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910975563.5A CN110781543A (zh) | 2019-10-15 | 2019-10-15 | 一种大跨度钢梁安装精度控制施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110781543A true CN110781543A (zh) | 2020-02-11 |
Family
ID=69385327
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910975563.5A Pending CN110781543A (zh) | 2019-10-15 | 2019-10-15 | 一种大跨度钢梁安装精度控制施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110781543A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113210910A (zh) * | 2021-04-27 | 2021-08-06 | 中国一冶集团有限公司 | 一种大跨度钢结构的防变形焊接方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1161994A (ja) * | 1997-08-26 | 1999-03-05 | Takenaka Komuten Co Ltd | 鉄骨柱梁接合部及び鉄骨柱梁接合構法 |
CN105019665A (zh) * | 2015-07-20 | 2015-11-04 | 中国二十二冶集团有限公司 | 基于全站仪的大跨度结构梁安装方法 |
WO2017121315A1 (zh) * | 2016-01-12 | 2017-07-20 | 广州机施建设集团有限公司 | 一种建筑桁架及楼板的施工方法 |
CN108277882A (zh) * | 2017-12-21 | 2018-07-13 | 中交第三航务工程局有限公司 | 恶劣条件下特大型钢结构雨棚施工工艺 |
CN108959725A (zh) * | 2018-06-11 | 2018-12-07 | 东南大学 | 钢箱梁焊接残余应力和结构应力耦合计算模型的建立方法 |
CN109441127A (zh) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | 一种大跨悬挑钢结构虚拟仿真现场安装施工方法 |
CN110258803A (zh) * | 2019-06-21 | 2019-09-20 | 南通大学 | 一种基于bim技术的穹顶钢结构安装施工方法 |
CN110259145A (zh) * | 2019-06-28 | 2019-09-20 | 中冶建工集团有限公司 | 一种拱形管桁架快速施工方法 |
-
2019
- 2019-10-15 CN CN201910975563.5A patent/CN110781543A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1161994A (ja) * | 1997-08-26 | 1999-03-05 | Takenaka Komuten Co Ltd | 鉄骨柱梁接合部及び鉄骨柱梁接合構法 |
CN105019665A (zh) * | 2015-07-20 | 2015-11-04 | 中国二十二冶集团有限公司 | 基于全站仪的大跨度结构梁安装方法 |
WO2017121315A1 (zh) * | 2016-01-12 | 2017-07-20 | 广州机施建设集团有限公司 | 一种建筑桁架及楼板的施工方法 |
CN108277882A (zh) * | 2017-12-21 | 2018-07-13 | 中交第三航务工程局有限公司 | 恶劣条件下特大型钢结构雨棚施工工艺 |
CN108959725A (zh) * | 2018-06-11 | 2018-12-07 | 东南大学 | 钢箱梁焊接残余应力和结构应力耦合计算模型的建立方法 |
CN109441127A (zh) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | 一种大跨悬挑钢结构虚拟仿真现场安装施工方法 |
CN110258803A (zh) * | 2019-06-21 | 2019-09-20 | 南通大学 | 一种基于bim技术的穹顶钢结构安装施工方法 |
CN110259145A (zh) * | 2019-06-28 | 2019-09-20 | 中冶建工集团有限公司 | 一种拱形管桁架快速施工方法 |
Non-Patent Citations (8)
Title |
---|
张毓成等: "BIM技术在大跨度钢结构桁架施工中的应用", 《建筑施工》 * |
张毓成等: "BIM技术在大跨度钢结构桁架施工中的应用", 《建筑施工》, no. 05, 25 May 2017 (2017-05-25) * |
徐永选等: "重庆万达城展示中心快速施工部署", 《施工技术》 * |
徐永选等: "重庆万达城展示中心快速施工部署", 《施工技术》, no. 11, 10 June 2018 (2018-06-10) * |
本书编委会: "《钢结构工程质量检查验收一本通》", 中国建材工业出版社, pages: 49 - 53 * |
苏铠等: "某商业中心高空屋盖大跨度重型钢桁架施工技术", 《施工技术》 * |
苏铠等: "某商业中心高空屋盖大跨度重型钢桁架施工技术", 《施工技术》, no. 08, 25 April 2017 (2017-04-25) * |
陈文龙: "利用BIM仿真技术实现大跨度钢梁现场安装", 《山西建筑》, no. 11, 10 April 2017 (2017-04-10) * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113210910A (zh) * | 2021-04-27 | 2021-08-06 | 中国一冶集团有限公司 | 一种大跨度钢结构的防变形焊接方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103806660B (zh) | 劲性混凝土结构梁-柱节点施工方法 | |
CN104763156B (zh) | 一种核电站钢制安全壳底封头的组装方法 | |
CN111364615A (zh) | 一种异形、曲面悬挂式钢结构体系的安装方法 | |
CN101011781A (zh) | 桥梁钢塔柱制造过程中焊接变形控制方法 | |
CN105019665A (zh) | 基于全站仪的大跨度结构梁安装方法 | |
CN101347703B (zh) | 冶金烟气脱硫吸收塔安装方法 | |
CN111104709A (zh) | 基于bim的大型制冷机房数字化装配方法及系统 | |
CN103015537A (zh) | 一种装配式钢结构体系的梁柱节点连接装置 | |
CN103711066B (zh) | 新型钢箱梁顶板单元结构及制作方法 | |
CN111691681A (zh) | 斜交钢管网格柱外框筒体结构安装方法 | |
CN114033051A (zh) | 一种基于钢结构球幕影院工程大跨度双曲桁架施工工艺 | |
CN110781543A (zh) | 一种大跨度钢梁安装精度控制施工方法 | |
CN111691554A (zh) | 一种地下箱型混凝土灌注钢柱偏位转换结构及其制作方法 | |
CN102587656B (zh) | 超高层建筑矩形钢管弯折柱或倾斜柱施工工法 | |
CN110909399A (zh) | 一种钢结构虚拟预拼装方法 | |
CN110096719A (zh) | 一种大面积焊接球网架结构的变形预控制方法 | |
WO2020259469A1 (zh) | 一种焊接连接的接触网硬横梁及其施工方法 | |
CN110820942A (zh) | 一种屋顶超长悬挑莲花造型钢结构施工方法 | |
CN216379955U (zh) | 一种钢结构建筑箱形梁柱连接节点 | |
CN109252526A (zh) | 基于预应力鱼腹梁支撑技术的装配式支护结构施工工艺 | |
CN104196153A (zh) | 一种厚板l形钢板剪力墙柱及其制作方法 | |
CN112580135B (zh) | 一种基于bim应用的钢柱分节吊装方法 | |
CN217438712U (zh) | 异形曲线结构钢混组合塔节段 | |
Guo et al. | Research and prospect on column-column connection of assembled multi-layer steel structure | |
CN105537811A (zh) | 异形多腔体巨型柱焊接变形控制方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200211 |