CN110685692A - Frame mining method - Google Patents

Frame mining method Download PDF

Info

Publication number
CN110685692A
CN110685692A CN201911077387.XA CN201911077387A CN110685692A CN 110685692 A CN110685692 A CN 110685692A CN 201911077387 A CN201911077387 A CN 201911077387A CN 110685692 A CN110685692 A CN 110685692A
Authority
CN
China
Prior art keywords
concrete
ore
roof
layer
mining method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911077387.XA
Other languages
Chinese (zh)
Other versions
CN110685692B (en
Inventor
张长征
李达
高延龙
王成龙
王军
张孝
章邦琼
张建华
马学社
张洪廷
陈万龙
杨秀森
董连福
王寿刚
刘凤君
王士强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Inner Mongolia Jintao Ltd By Share Ltd
Original Assignee
Inner Mongolia Jintao Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Inner Mongolia Jintao Ltd By Share Ltd filed Critical Inner Mongolia Jintao Ltd By Share Ltd
Priority to CN201911077387.XA priority Critical patent/CN110685692B/en
Publication of CN110685692A publication Critical patent/CN110685692A/en
Application granted granted Critical
Publication of CN110685692B publication Critical patent/CN110685692B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/22Methods of underground mining; Layouts therefor for ores, e.g. mining placers
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • E21D15/005Props; Chocks, e.g. made of flexible containers filled with backfilling material characterised by the material
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/04Transport of mined material in gravity inclines; in staple or inclined shafts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Remote Sensing (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The disclosure relates to a frame mining method, comprising the following steps: a. arranging a concrete bottom in a bottom roadway below the ore block, and arranging a chute in the concrete bottom; b. blasting layer by layer from the bottom of the ore block; b1. conveying out ores through a chute port after each explosion; b2. after the ore is transported out, arranging a middle concrete roof in a stope space; b3. concrete chutes communicated with the chute openings are arranged between the middle concrete tops and the concrete bottom and between the two adjacent middle concrete tops; c. after each blasting, the surrounding rock is caved from the bottoms of the two sides of the ore block; d. after the ore is completely transported out, arranging an upper concrete roof above the middle concrete roof at the uppermost layer; e. pouring the pedestrian to form a concrete column along the road. Through the technical scheme, the ore blocks are blasted layer by layer, and after the ore is blasted and conveyed out each time, the stope space is supported by the multiple layers of middle concrete tops, so that the operation safety can be improved. After the blasting is finished, the concrete column is arranged, so that the whole stope space is supported by the rectangular frame formed by the concrete column, the concrete bottom and the upper concrete top, and the ground pressure is effectively stabilized.

Description

Frame mining method
Technical Field
The disclosure relates to the technical field of mining, in particular to a frame-type mining method.
Background
Depending on the geological conditions in which the vein is located and the nature of the vein itself, different mining methods are used in the prior art. For thin seams, such as gold ores with a width of 0.5 m to 1 m, the mining is usually performed by a cut-wall filling method. In the related art, the cut wall filling method generally collapses ore vein once, recovers the ore, collapses surrounding rock once, fills the stope space where the raw ore is located with the surrounding rock, and circulates the steps until the stope is finished.
However, in the mining process, the ore vein is too narrow, so that the ore falling amount is small, surrounding rocks are easy to mix into an ore heap after the surrounding rocks are collapsed, the loss of high-grade fine ores is large, and the mining cost is increased. Meanwhile, with the increase of the mining amount, the mining depth is gradually increased, the ground pressure at the mining part is gradually increased, the simple filling cannot meet the requirement of a stope after stable filling, and the difficulty is brought to normal stope safety management and effective recovery of ores.
Disclosure of Invention
The purpose of the disclosure is to provide a frame mining method, so as to solve the problems of mineral powder depletion, large loss and large safety risk in mining in the related technology.
In order to achieve the above object, the present disclosure provides a frame mining method, characterized in that the mining method comprises the steps of:
a. arranging a concrete bottom in a bottom roadway below the ore block, arranging a chute in the concrete bottom, forming an ore drawing space below the concrete bottom, and forming a first operation space between the concrete bottom and the ore block;
b. blasting layer by layer from the bottom of the ore block;
b1. conveying out ores through the chute after each explosion;
b2. after the ore is transported out, arranging a middle concrete roof in a stope space for bearing the ore during ore falling, wherein a second operation space is formed between the middle concrete roof and an ore block which is not subjected to ore falling;
b3. concrete chutes communicated with the chute openings are arranged between the middle concrete tops and the concrete bottom and between two adjacent middle concrete tops;
c. after each blasting, caving the surrounding rock from the bottoms of the two sides of the ore block to form a pedestrian direct path;
d. after the ore is completely transported out, arranging an upper concrete roof above the middle concrete roof at the uppermost layer;
e. and pouring the pedestrian to form concrete columns along the road, so that the concrete bottom, the upper concrete top and the two concrete columns form a closed frame in an enclosing manner.
Optionally, in step b, the top of the concrete chute is flush with the top of the middle concrete roof, and the top of the concrete chute is covered by a shed before each ore falling.
Optionally, in step b, before each blast, a rubber mat for carrying ore is laid at the bottom of the stope space.
Optionally, in step b, the surrounding rock and the roof of the stope are supported after the ore break.
Optionally, at step b1, the surrounding rock is supported while the ore is being hauled out.
Optionally, in step b2, a framework of the middle concrete roof is formed by the steel bars which are staggered transversely and longitudinally, concrete is filled in the framework, and the middle concrete roof is supported in the surrounding rock through anchor rods; and d, forming a framework of the upper concrete top through the transversely and longitudinally staggered reinforcing steel bars, filling concrete, and supporting the upper concrete top to the surrounding rock through an anchor rod.
Optionally, in step c, the caving surrounding rock is recovered through the concrete chute for standby.
Optionally, in step c, the pedestrian is supported layer by layer, and in step e, before the pedestrian is poured to form the concrete column along the road, the support material is recovered for standby.
Through the technical scheme, when mining is carried out on the thin veins, the ore blocks are blasted layer by layer, the ore is caved layer by layer, and after the ore is blasted and transported out at each time, the stope space is supported through the middle concrete top in multiple layers, so that the ground pressure is stabilized, and the operation safety can be improved. After blasting is finished, the concrete columns are arranged, so that the whole stope space is supported by a rectangular frame formed by the concrete columns, the concrete bottom and the upper concrete top, and a plurality of layers of middle concrete tops are arranged in the frame, so that ground pressure is effectively and stably pressed. In addition, when the ore blocks are blasted, the ore falls to the bottom of the concrete or the top of the middle concrete without mixing with surrounding rocks, so that the dilution loss of the ore powder can be reduced.
Additional features and advantages of the disclosure will be set forth in the detailed description which follows.
Drawings
The accompanying drawings, which are included to provide a further understanding of the disclosure and are incorporated in and constitute a part of this specification, illustrate embodiments of the disclosure and together with the description serve to explain the disclosure without limiting the disclosure. In the drawings:
fig. 1 is a frame mining method according to one embodiment of the present disclosure;
FIG. 2 is a schematic illustration of a stope space prior to mining in a mining method provided in accordance with an embodiment of the present disclosure;
FIG. 3 is a schematic illustration of a stope space during mining in a mining method provided in accordance with an embodiment of the present disclosure;
FIG. 4 is a schematic illustration of a stope space after ore is completely removed in a mining method provided in accordance with an embodiment of the present disclosure;
fig. 5 is a schematic view of a stope space after mining is completed in a method of mining provided in accordance with an embodiment of the present disclosure;
fig. 6 is a schematic view of an intermediate concrete roof in a mining method provided in accordance with an embodiment of the present disclosure.
Description of the reference numerals
10-lumps; 21-concrete bottom; 22-loading a concrete roof; 23-central concrete top; 24-concrete column; 201-reinforcing steel bars; 202-concrete; 203-anchor rod; 31-ore drawing space; 32-a first operating space; 33-a second operating space; 41-concrete draw shaft; 42-raise; 50-surrounding rock; 60-the pedestrian is on the way.
Detailed Description
The following detailed description of specific embodiments of the present disclosure is provided in connection with the accompanying drawings. It should be understood that the detailed description and specific examples, while indicating the present disclosure, are given by way of illustration and explanation only, not limitation.
In the present disclosure, when not stated to the contrary, the use of the directional words such as "upper" and "lower" refers to the position above and below the actual position of the stope, and specifically, the direction of the drawing of fig. 2 to 5 can be referred to.
In mining, referring to fig. 2, a vertical raise 42 is firstly opened from the middle of the ore block 10 for ventilation and serving as a transportation channel, and a bottom roadway is opened at the bottom of the ore block 10 for transporting the collapsed ore after mining. The method provided by the disclosure is applied to the open of the patio 42 on the ore block 10, and after a bottom roadway is formed at the bottom of the ore block 10, namely after the preparation work for mining is finished. The stope space described below refers to the entire space in which the ore block 10 before caving and the ore block 11 after caving are located, that is, the area between the concrete bottom 21 and the upper concrete roof 22, and includes a first operating space 32, a second operating space 33, and the like described below.
Referring to fig. 1, the frame mining method provided by the present disclosure includes the steps of:
a. a concrete bottom 21 is arranged in a bottom roadway below the ore block 10, a chute is arranged in the concrete bottom 21, an ore drawing space 31 is formed below the concrete bottom 21, and a first operation space 32 is formed between the concrete bottom 21 and the ore block 10, as shown in figure 2. Wherein, the concrete bottom 21 can be pressed stably, the ore drawing space 31 is used as a channel for transporting ores after mining, and the first operation space 32 is used as an active area of constructors before primary blasting. A plurality of chutes can be arranged at intervals according to the length of the ore block, for example, one chute can be arranged at intervals of 10 meters for the ore block with the length of 100 meters.
b. Blasting layer by layer from the bottom of the block 10 until the blasting of the entire block 10 is complete, see fig. 3. In step b, the following substeps are also included: b1. conveying out ores through a chute port after each explosion; c2. after the ores are conveyed out, the middle concrete roof 23 is arranged in the stope space and used for bearing the ores during ore falling, a second operation space 33 is formed between the middle concrete roof 23 and the ore blocks 10 which are not subjected to ore falling, the second operation space 33 is used as an activity area of constructors before blasting each time, and the middle concrete roof 23 can ensure the safety of the constructors while stabilizing the ground pressure; b3. a concrete chute 41 is provided. In the sub-step b3, specifically, after the first blasting, a concrete chute 41 communicated with the chute is arranged between the middle concrete roof 23 and the concrete bottom 21, after the subsequent blasting, a concrete chute 41 is arranged between two adjacent middle concrete roofs 23, and the concrete chutes 41 of each layer are communicated with each other and the chute of the concrete bottom 21. The concrete chute 41 can ensure ventilation of the stope space on one hand, and on the other hand, can be used as a channel for transporting out ores and can also be used as a material for transporting in concrete, reinforcing steel bars and the like for constructing the middle concrete roof 23. In addition, the concrete chute 41 is supported between the concrete bottom 21 and the middle concrete roof 23 or between two layers of middle concrete roofs 23, so that the ground pressure can be further stabilized, and the safety of constructors can be ensured particularly when the concrete chute is applied to a deeper mining depth.
c. After each blast, the surrounding rock 50 is broken down from the bottom on either side of the block 10 to form a pedestrian walkway 60, see fig. 4. As the mining height increases from layer to layer, the constructor needs to support the pedestrian crosswalk 60 layer by layer upwards until the mining is finished. It should be noted here that the sequence of steps c and b2, b3 may be adapted to the actual production, for example, according to one embodiment, the construction may be performed in the sequence of b2-c-b3, that is, after the ore is transported out, the surrounding rock 50 is firstly collapsed, and then the concrete chute 41 is arranged. Furthermore, according to one embodiment, in step c, the caving surrounding rock 50 may be recovered through the concrete chute 41 for use, for example, as backfill material for other stopes, and this portion of surrounding rock 50 may be carried out through the same path as the ore. According to another embodiment, the caving surrounding rock 50 can be retained between the concrete bottom 21 and the middle concrete top 23 or between two adjacent middle concrete tops 23.
d. After the ore has been completely removed, an upper concrete roof 22 is arranged above the uppermost intermediate concrete roof 23, see fig. 4. The upper concrete roof 22 is located at the uppermost part of the stope space and is used as a protective cover of the stope space, so that the safety of constructors is ensured while the ground pressure is stabilized.
e. And pouring the pedestrian along the road 60 to form the concrete columns 24, so that the concrete bottom 21, the upper concrete top 22 and the two concrete columns 24 form a closed frame, which is shown in figure 5.
Through the technical scheme, when mining is carried out on a thin ore vein, the ore blocks 10 are blasted layer by layer, the ore is collapsed layer by layer, after the ore is blasted and transported out each time, the stope space is supported through the multiple layers of middle concrete roofs 23, the earth pressure is stabilized, and the operation safety can be improved. After blasting is finished, the concrete column 24 is arranged, so that the whole stope space is supported by a rectangular frame formed by the concrete column 24, the concrete bottom 21 and the upper concrete top 22, and a plurality of layers of middle concrete tops 23 and concrete chutes 41 are further arranged in the frame, so that ground pressure is effectively stabilized. In addition, when the ore block 10 is blasted, the ore falls to the concrete bottom 21 or the middle concrete top 23 and is not mixed with the surrounding rock, so that the dilution loss of the ore powder can be reduced.
According to some embodiments, in step b, the top of the concrete chute 41 may be flush with the top of the middle concrete roof 23 and the top of the shed concrete chute 41 is open before each ore drop. Therefore, the ore can not directly impact the concrete chute 41 during each ore caving, and the ore is prevented from directly falling into the concrete chute 41 during the ore caving. Specifically, a rubber mat can be covered on the top of the concrete chute 41, that is, the rubber mat blocks the chute mouth, so that an effective buffering effect is achieved. Similarly, a shed may be placed above the concrete bottom 21 prior to the first blast.
According to some embodiments, at step b, before each blast, a rubber mat for carrying ore may be laid at the bottom of the stope space. Specifically, before the first blasting of the block 10, a rubber mat is laid on the concrete bottom 21, and during the subsequent blasting, a rubber mat is laid on the corresponding middle concrete top 23. The cushion can be provided with the polylith, the overlap joint between the adjacent cushion, and cushion edge hem is in order to form and accomodate the effect. By arranging the rubber mat, on one hand, the buffer effect can be realized during ore falling, and the loss of ore powder is reduced; on the other hand, when the ore is transported out, the rubber mat can be extracted to transport the whole ore out, and the efficiency is improved.
According to some embodiments, at step b, the surrounding rock 50 and the stope roof may be supported after each ore break. Here, the stope roof refers to the lower surface of the unblasted lump 10, for example, the portion indicated by the line a in fig. 3. Because the surrounding rocks around can be influenced by the impact generated during blasting, the stope roof is also loose, and after each blasting, the surrounding rocks 50 beside and the stope roof can be supported to stabilize the surrounding rocks 50 and the ore blocks 10 and ensure the safety of the stope. The supporting mode can be any appropriate mode such as a cross brace supporting mode, a column supporting mode, a concrete supporting mode and the like.
According to some embodiments, referring to fig. 6, in step b2, a framework of the middle concrete roof 22 may be formed by the reinforcing bars 201 staggered in the horizontal and vertical directions, concrete 202 is filled in, and the middle concrete roof 23 is supported into the surrounding rock 50 by the anchor rods 203; in step d, a framework of the upper concrete roof 22 can be formed by the reinforcing steel bars 201 which are staggered transversely and longitudinally, the concrete 202 is filled, and the upper concrete roof 22 is supported in the surrounding rock 50 through the anchor rods 203, so that the upper concrete roof 22 and the middle concrete roof 23 which can be stably supported are formed.
According to some embodiments, at step b2, the surrounding rock 50 is supported while the ore is being hauled out, i.e., run out while supporting. Thus, the surrounding rock 50 is supported after each construction to stabilize the surrounding rock 50.
According to some embodiments, at step e, the shoring material may first be recovered to be kept ready for use before pouring the pedestrian walkway 60 to form the concrete column 24.
The preferred embodiments of the present disclosure are described in detail with reference to the accompanying drawings, however, the present disclosure is not limited to the specific details of the above embodiments, and various simple modifications may be made to the technical solution of the present disclosure within the technical idea of the present disclosure, and these simple modifications all belong to the protection scope of the present disclosure.
It should be noted that, in the foregoing embodiments, various features described in the above embodiments may be combined in any suitable manner, and in order to avoid unnecessary repetition, various combinations that are possible in the present disclosure are not described again.
In addition, any combination of various embodiments of the present disclosure may be made, and the same should be considered as the disclosure of the present disclosure, as long as it does not depart from the spirit of the present disclosure.

Claims (8)

1. A frame mining method, characterized in that the mining method comprises the steps of:
a. arranging a concrete bottom (21) in a bottom roadway below the ore block (10), arranging a chute in the concrete bottom (21), forming an ore drawing space (31) below the concrete bottom (21), and forming a first operation space (32) between the concrete bottom (21) and the ore block (10);
b. blasting layer by layer from the bottom of the ore block (10);
b1. conveying out ores through the chute after each explosion;
b2. after the ore is conveyed out, arranging an intermediate concrete roof (23) in the stope space for bearing the ore during ore falling, wherein a second operation space (33) is formed between the intermediate concrete roof (23) and the ore block (10) without ore falling;
b3. concrete chutes (41) communicated with the chute openings are arranged between the middle concrete tops (23) and the concrete bottom (21) and between two adjacent middle concrete tops (23);
c. after each blasting, the surrounding rocks (50) are caved from the bottoms of the two sides of the ore block (10) to form a pedestrian direct path (60);
d. after the ore is completely transported out, an upper concrete roof (22) is arranged above a middle concrete roof (23) at the uppermost layer;
e. and pouring the pedestrian along the road (60) to form concrete columns (24), so that the concrete bottom (21), the upper concrete top (22) and the two concrete columns (24) enclose a closed frame.
2. Mining method according to claim 1, characterised in that in step b the top of the concrete shaft (41) is flush with the top of the intermediate concrete roof (23) and the top of the concrete shaft (41) is covered before each ore drop.
3. A mining method according to claim 1, characterised in that in step b, before each blast, a rubber mat for carrying ore is laid at the bottom of the stope space.
4. A mining method according to claim 1, characterised in that in step b the surrounding rock (50) and the roof of the stope are supported after the ore has been dropped.
5. A mining method according to claim 1, characterised in that in step b1 the surrounding rock (50) is supported while the ore is being hauled out.
6. Mining method according to claim 1, characterized in that in step b2 the skeleton of the middle concrete roof (22) is formed by cross and longitudinal staggered steel bars (201), filled with concrete (202) and the middle concrete roof (23) is braced into the surrounding rock (50) by anchor rods (203); in the step d, a framework of the upper concrete roof (22) is formed through the steel bars (201) which are staggered transversely and longitudinally, concrete (202) is filled, and the upper concrete roof (22) is supported into the surrounding rock (50) through anchor rods (203).
7. Mining method according to claim 1, characterized in that in step c, the caving surrounding rock (50) is recovered through the concrete chute (41) for standby.
8. Mining method according to claim 1, characterised in that at step c the pedestrian walkway (60) is braced layer by layer and at step e the bracing material is recovered for use before the pedestrian walkway (60) is poured to form the concrete column (24).
CN201911077387.XA 2019-11-06 2019-11-06 Frame mining method Active CN110685692B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911077387.XA CN110685692B (en) 2019-11-06 2019-11-06 Frame mining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911077387.XA CN110685692B (en) 2019-11-06 2019-11-06 Frame mining method

Publications (2)

Publication Number Publication Date
CN110685692A true CN110685692A (en) 2020-01-14
CN110685692B CN110685692B (en) 2021-05-04

Family

ID=69115573

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911077387.XA Active CN110685692B (en) 2019-11-06 2019-11-06 Frame mining method

Country Status (1)

Country Link
CN (1) CN110685692B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065402A (en) * 2020-08-28 2020-12-11 内蒙古金陶股份有限公司 Construction method of pedestrian conveying channel in mining stope

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU877015A1 (en) * 1980-01-24 1981-10-30 Сибирский Государственный Институт По Проектированию Шахт,Разрезов И Обогатительных Фабрик Method of mining thick sloping coal beds
SU1188324A1 (en) * 1984-05-14 1985-10-30 Vni P K I Gornogo Dela Tsvetno Ore overflow method
SU1314060A1 (en) * 1986-01-28 1987-05-30 Московский Геологоразведочный Институт Им.Серго Орджоникидзе Method of combination mining of mineral deposits
CN1424489A (en) * 2003-01-08 2003-06-18 广东高要河台金矿 Method for constructing reinforced concrete artificial bottom pillar by medium-thickness ore body open stope mining method
CN104632223A (en) * 2015-02-04 2015-05-20 中南大学 Mining environment-reconstructing mobile pumping filling artificial pillar shrinkage mining method
CN104847356A (en) * 2015-05-15 2015-08-19 西北矿冶研究院 Mining method of thin and small ore body
CN207470183U (en) * 2018-02-09 2018-06-08 内蒙古金陶股份有限公司 A kind of ro om -character
CN207538855U (en) * 2018-02-09 2018-06-26 内蒙古金陶股份有限公司 The mining drop shaft that rubber cushion is arranged
CN108278114A (en) * 2018-02-09 2018-07-13 内蒙古金陶股份有限公司 Frame-type mining methods
CN108678745A (en) * 2018-05-11 2018-10-19 长春黄金研究院有限公司 A kind of narrow vein concrete bed course scarps filling mining method
CN209354129U (en) * 2018-11-22 2019-09-06 吕梁学院 A kind of concrete vacation bottom structure of mining with stowing

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU877015A1 (en) * 1980-01-24 1981-10-30 Сибирский Государственный Институт По Проектированию Шахт,Разрезов И Обогатительных Фабрик Method of mining thick sloping coal beds
SU1188324A1 (en) * 1984-05-14 1985-10-30 Vni P K I Gornogo Dela Tsvetno Ore overflow method
SU1314060A1 (en) * 1986-01-28 1987-05-30 Московский Геологоразведочный Институт Им.Серго Орджоникидзе Method of combination mining of mineral deposits
CN1424489A (en) * 2003-01-08 2003-06-18 广东高要河台金矿 Method for constructing reinforced concrete artificial bottom pillar by medium-thickness ore body open stope mining method
CN104632223A (en) * 2015-02-04 2015-05-20 中南大学 Mining environment-reconstructing mobile pumping filling artificial pillar shrinkage mining method
CN104847356A (en) * 2015-05-15 2015-08-19 西北矿冶研究院 Mining method of thin and small ore body
CN207470183U (en) * 2018-02-09 2018-06-08 内蒙古金陶股份有限公司 A kind of ro om -character
CN207538855U (en) * 2018-02-09 2018-06-26 内蒙古金陶股份有限公司 The mining drop shaft that rubber cushion is arranged
CN108278114A (en) * 2018-02-09 2018-07-13 内蒙古金陶股份有限公司 Frame-type mining methods
CN108678745A (en) * 2018-05-11 2018-10-19 长春黄金研究院有限公司 A kind of narrow vein concrete bed course scarps filling mining method
CN209354129U (en) * 2018-11-22 2019-09-06 吕梁学院 A kind of concrete vacation bottom structure of mining with stowing

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
梁春贵等: "削壁充填采场回采工艺设计与施工", 《黄金》 *
贾洪杰等: "削壁充填采矿法在金厂沟梁金矿的应用实践", 《黄金》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112065402A (en) * 2020-08-28 2020-12-11 内蒙古金陶股份有限公司 Construction method of pedestrian conveying channel in mining stope

Also Published As

Publication number Publication date
CN110685692B (en) 2021-05-04

Similar Documents

Publication Publication Date Title
CN108756885B (en) downward or upward cemented filling mechanized mining method for steeply-inclined ore body with extremely-broken ore rock
CN110331978B (en) Environment reconstruction segmented medium-length hole subsequent filling mining method
CN105804748B (en) A kind of method of block mining Wall ore under open air transport system
CN107725052B (en) One kind, which is adopted, stays integration exploitation gob side entry top plate constant-resistance anchor body beam method for protecting support
CN110359914B (en) Safe and low-cost combined sublevel mining method for gently inclined medium-thickness ore body
CN105507947B (en) A kind of networking waste filling method
CN113738367B (en) Sublevel caving downward filling mining method for complex broken and steeply inclined thin vein
CN113914860B (en) Roof-cutting gob-side entry retaining method for non-compact solid filling working face
CN111691885A (en) Efficient filling mining method for ultra-thick coal seam
CN109026005B (en) Comprehensive mechanized ore-breaking layered caving mining method
CN111456729A (en) Mining method of steeply inclined thin ore body
CN107387083A (en) A kind of medium-thickness seam gob side entry retaining roadside support body construction method supported using spoil
CN110700834B (en) Mining method of thin vein
CN110685692B (en) Frame mining method
CN112012744A (en) Comprehensive mechanized ore breaking layered filling mining method
CN113494292B (en) High and large point column in-situ collapse recovery method
CN108952725B (en) Low dilution mining method suitable for gentle dip thin ore body
CN110388210B (en) Stope structure arrangement mode suitable for combined sectional mining of slowly-inclined medium-thickness ore body
CN111852473B (en) Mining method of thin vein
CN216866688U (en) Ore mining structure under extremely broken ore body condition
CN114592868B (en) Ore exploitation structure under condition of extremely crushing ore body and method thereof
CN109882172A (en) A kind of cut falls the gob-side entry retaining method that roadside support wall is done on directly top
CN113187481A (en) Filling mining method for overburden rock concentrated grouting caving stoping
CN109025996B (en) Underground mine layer-by-layer extrusion and smooth blasting mining method
CN111456736A (en) Method for maintaining stability of downward single-access filling false roof and recovering studs

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant