Summary of the invention
Technical problem to be solved by the invention is to provide a kind of processing of efficient and convenient 110kV line fault tripping
Method.
In order to solve the above technical problems, the present invention adopts the following technical scheme:
A kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
Further, step 1 accident information collects simultaneously preliminary analysis, i.e., carries out according to basic parameter and accident situation
Classification.
Further, the basic parameter includes line length, wire type, relay protection scheme and protection scope.
Further, the accident situation include accident occur time, monitoring-controlling system signal, relay protection and safety from
Dynamic device action situation and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation.
Further, O&M site inspection result includes the time of accident generation, separate and relay protection in the step 3
Automatic safety device action situation, protection ranging situation and failure wave-recording ranging situation.
Further, the step 4 is made to determine whether that for livewire work route, judgment basis is such as according to accident information
Under:
When faulty line is livewire work route, then principle is disposed according to livewire work line fault, information is transmitted to transmission of electricity
Fortune inspection room carries out the electrification line inspection;
When faulty line is not livewire work route, then carry out accident treatment, summarize O&M site inspection result be transmitted to it is defeated
Electricity fortune inspection room carries out the electrification line inspection.
Further, the livewire work line fault disposition principle is live feelings after the tripping of livewire work line fault
Condition summarizes to system platform, and still regards equipment live.
Further, obvious fault includes strand breakage of circuit, damage and/or flashover burn in the step 5.
Beneficial effects of the present invention are as follows:
The present invention uses the processing method of 110kV line fault tripping, solves 110kV line fault tripping in the prior art
Afterwards, existing recovery normal efficiency is low, and fault location accuracy rate is low, leads to line fault tripping processing time longer problem,
The processing time for shortening line fault tripping optimizes electric network fault recovery, realizes and close to 110kV line tripping repairing
Endless tube control improves first-aid repair efficiency and service level, strengthens the control ability to the repairing of 110kV line tripping, improves
The stability of power distribution network operation level fundamentally improves the electricity consumption reliability level of 110kV route.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, with reference to the accompanying drawing 1 and specific embodiment to hair
It is bright to carry out clear, complete description.
As shown in Figure 1, the present embodiment 1 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 2 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 3 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 4 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
The accident situation includes time, monitoring-controlling system signal, relay protection and the automatic safety device movement feelings that accident occurs
Condition and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 5 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
The accident situation includes time, monitoring-controlling system signal, relay protection and the automatic safety device movement feelings that accident occurs
Condition and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;The O&M site inspection knot
Fruit includes time, separate and automatic equipment of relay protection action situation, protection ranging situation and the failure that accident occurs
Recording ranging situation;
Step 4 is made to determine whether according to accident information as livewire work route;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 6 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
The accident situation includes time, monitoring-controlling system signal, relay protection and the automatic safety device movement feelings that accident occurs
Condition and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;The O&M site inspection knot
Fruit includes time, separate and automatic equipment of relay protection action situation, protection ranging situation and the failure that accident occurs
Recording ranging situation;
Step 4 is made to determine whether as livewire work route that judgment basis is as follows according to accident information:
When faulty line is livewire work route, then principle is disposed according to livewire work line fault, information is transmitted to transmission of electricity
Fortune inspection room carries out the electrification line inspection;
When faulty line is not livewire work route, then carry out accident treatment, summarize O&M site inspection result be transmitted to it is defeated
Electricity fortune inspection room carries out the electrification line inspection;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 7 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
The accident situation includes time, monitoring-controlling system signal, relay protection and the automatic safety device movement feelings that accident occurs
Condition and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;The O&M site inspection knot
Fruit includes time, separate and automatic equipment of relay protection action situation, protection ranging situation and the failure that accident occurs
Recording ranging situation;
Step 4 is made to determine whether as livewire work route that judgment basis is as follows according to accident information:
When faulty line is livewire work route, then principle is disposed according to livewire work line fault, information is transmitted to transmission of electricity
Fortune inspection room carries out the electrification line inspection;The livewire work line fault disposition principle is scene after the tripping of livewire work line fault
Situation summarizes to system platform, and still regards equipment live;
When faulty line is not livewire work route, then carry out accident treatment, summarize O&M site inspection result be transmitted to it is defeated
Electricity fortune inspection room carries out the electrification line inspection;
Step 5 determines that line inspection result whether there is obvious fault, when there are the eliminations that when obvious fault, ascertains the reason for line inspection result
After failure, carries out examination and send once;When line inspection result is without obvious fault, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
The present embodiment 8 is related to a kind of processing method of 110kV line fault tripping comprising:
Step 1, accident information is collected and preliminary analysis, i.e., classifies according to basic parameter and accident situation;
The basic parameter includes line length, wire type, relay protection scheme and protection scope;
The accident situation includes time, monitoring-controlling system signal, relay protection and the automatic safety device movement feelings that accident occurs
Condition and switch changed position, equipment state, loss load and dispatching terminal failure wave-recording situation;
Whether step 2, judgement accident are major event, simultaneous transmission Preliminary Analysis Results to O&M scene;
When accident is determined as major event, then a hierarchical system is uploaded to;When accident is determined as insignificant event, then will
Accident situation is transmitted to SMS platform system;
Step 3 summarizes the upload of O&M site inspection result to downstream progress accident treatment;The O&M site inspection knot
Fruit includes time, separate and automatic equipment of relay protection action situation, protection ranging situation and the failure that accident occurs
Recording ranging situation;
Step 4 is made to determine whether as livewire work route that judgment basis is as follows according to accident information:
When faulty line is livewire work route, then principle is disposed according to livewire work line fault, information is transmitted to transmission of electricity
Fortune inspection room carries out the electrification line inspection;The livewire work line fault disposition principle is scene after the tripping of livewire work line fault
Situation summarizes to system platform, and still regards equipment live;
When faulty line is not livewire work route, then carry out accident treatment, summarize O&M site inspection result be transmitted to it is defeated
Electricity fortune inspection room carries out the electrification line inspection;
Step 5 determines that line inspection result whether there is obvious fault, hence it is evident that failure includes that strand breakage of circuit, damage and/or flashover are burnt
Wound;When line inspection result is there are when obvious fault, ascertaining the reason after eliminating the fault, carry out examination send it is primary;When line inspection result is without obvious
When failure, carries out examination and send once;
Whether step 6 determines to try to send to succeed, and when examination is sent successfully, accident treatment situation should be transmitted to SMS platform system;When
Examination is when sending failed, should be transmitted to ascertain the reason accident treatment situation and eliminate failsafe link and analyze.
After above-described embodiment solves 110kV line fault tripping in the prior art, existing recovery normal efficiency is low, therefore
It is low to hinder locating accuracy, leads to line fault tripping processing time longer problem, when shortening the processing of line fault tripping
Between, optimize electric network fault recovery, realize to 110kV line tripping repairing closed loop control, improve first-aid repair efficiency and
Service level strengthens the control ability to the repairing of 110kV line tripping, improves the stability of power distribution network operation level, from
Fundamentally improve the electricity consumption reliability level of 110kV route.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root
According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular
Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet
Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used
To modify to technical solution documented by previous embodiment or equivalent replacement of some of the technical features;And
These are modified or replaceed, the spirit and model of technical solution of the embodiment of the present invention that it does not separate the essence of the corresponding technical solution
It encloses.