CN110439036A - A kind of poured band of outer wall of basement advance water stop construction method - Google Patents

A kind of poured band of outer wall of basement advance water stop construction method Download PDF

Info

Publication number
CN110439036A
CN110439036A CN201910653826.0A CN201910653826A CN110439036A CN 110439036 A CN110439036 A CN 110439036A CN 201910653826 A CN201910653826 A CN 201910653826A CN 110439036 A CN110439036 A CN 110439036A
Authority
CN
China
Prior art keywords
basement
wall
seal plate
construction
cast strip
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910653826.0A
Other languages
Chinese (zh)
Inventor
陶金福
袁宗慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201910653826.0A priority Critical patent/CN110439036A/en
Publication of CN110439036A publication Critical patent/CN110439036A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Building Environments (AREA)

Abstract

The present invention relates to the realm of building construction, specifically design a kind of poured band of outer wall of basement advance water stop construction method, comprising the following steps: Step 1: the construction of outer wall of basement concrete;Step 2: assembled post-cast strip seal plate is prefabricated;Step 3: SBS extra play is handled between outer wall of basement and assembled post-cast strip seal plate;Step 4: base's water-proofing treatment between outer wall of basement and assembled post-cast strip seal plate;Step 5: the installation of assembled post-cast strip seal plate;Step 6: the construction of outer wall of basement SBS waterproof layer;Step 7: the construction of outer wall of basement protective layer and backfilling of earthwork;The invention has the following advantages that basement post-pouring zone part leakage problem, shorten the deep foundation pit precipitation duration, save the cost, it creates conditions for processes such as basement waterproofing, pit earthwork backfills, the advantages of eliminating deep foundation pit construction stage bring security risk, providing place to construction plane management and create favorable conditions for site safety civilized construction.

Description

A kind of poured band of outer wall of basement advance water stop construction method
Technical field
The present invention relates to the realm of building construction, specifically design a kind of poured band of outer wall of basement advance water stop construction method.
Background technique
Currently, in the construction of post-pouring belt of outer wall in basement construction, often because of post-cast strip conventional construction technique shadow Outer wall of basement side backfilling of earthwork and adjacent structures construction speed are rung, construction requirement, post-cast strip conventional construction side are not able to satisfy The method construction period is long, and rapid construction cannot be achieved, and can not meet economic serviceability.
Summary of the invention
For the technical problems in the prior art, the purpose of the present invention is to provide a kind of poured band of outer wall of basement Advance water stop construction method, to achieve the goals above, the technical scheme adopted by the invention is as follows:
A kind of poured band of outer wall of basement advance water stop construction method, comprising the following steps:
Step 1: the construction of outer wall of basement concrete: first successively installing outer wall of basement reinforcing bar and outer wall of basement mould Plate, then fast-easy closing-up net is constructed, install pre-embedded bolt and Screw arbor with nut at both-ends, and then outer wall of basement concrete pours, later Outer wall formwork of basement is removed, finally outer wall of basement concrete is carried out to carry out lid maintenance;
Step 2: assembled post-cast strip seal plate is prefabricated: matching coagulation using basement bottom board or outer wall of basement are same Soil is processed, and the sealing board width adds 400mm depending on the every side of post-cast strip width, two-way 60 ° of bevel edges, using double steel bar, Upper and lower plates interface uses ribbet;
Step 3: SBS extra play is handled between outer wall of basement and assembled post-cast strip seal plate: the seal plate installation Before, one layer of SBS extra play is done in joint on the inside of outer wall of basement and seal plate;
Step 4: base's water-proofing treatment between outer wall of basement and assembled post-cast strip seal plate: before the seal plate installation, It is laminated at macromolecule waterproof coating that on the inside of seal plate and upper and lower interface position is uniformly coated with one;
Step 5: the installation of assembled post-cast strip seal plate: successively installing outer wall of basement seal plate, installation from bottom to top The pre-embedded bolt of seal plate is fastened when outer wall of basement seal plate, it is closely knit with the filling of organic waterproof putty at bolt, to sealing Plate seam and seal plate and wall joints carry out the processing of organic waterproof putty waterproof reinforced;
Step 6: the construction of outer wall of basement SBS waterproof layer: after installing seal plate, entirety SBS waterproof layer of constructing is prevented Water layer and waterproof slab overlap;
Step 7: the construction of outer wall of basement protective layer and backfilling of earthwork: carrying out entirety XPS extruded polystyrene to outer wall of basement The construction of plate protective layer, carries out the protection to SBS waterproof layer using protective layer, then carries out outdoor backfilling of earthwork.
Preferably, the plate thickness of the seal plate is 150mm, length 1500mm, the thickness of the steel bar stress protective layer For 15mm.
Preferably, it is that height every side in post-cast strip adds 200mm that the SBS, which adds layer height, and it is every that width regards post-cast strip width Bian Gejia 600mm, with a thickness of 3mm.
Preferably, the waterproof coating with a thickness of 2mm.
Preferably, the SBS waterproof layer with a thickness of 3mm.
Preferably, the XPS extruded polystyrene board protective layer thickness is 50mm.
A kind of poured band of outer wall of basement advance water stop construction method provided by the invention, has the advantage that (1) underground The deep foundation pit precipitation duration is shortened in room post-cast strip part leakage problem, (2), save the cost, and (3) are basement waterproofing, pit earthwork The processes such as backfill create conditions, and (4) eliminate deep foundation pit construction stage bring security risk, and (5) are provided to construction plane management Place and for site safety civilized construction create favorable conditions the advantages of.
Detailed description of the invention
Fig. 1 is a kind of poured band of outer wall of basement advanced water-stopping construction schematic front view;
Fig. 2 is a kind of poured band of outer wall of basement advanced water-stopping construction schematic side view;
1, basement bottom board 2, outer wall of basement 3, pre-embedded bolt 4, Screw arbor with nut at both-ends 5, seal plate 6, SBS are attached in figure Add layer 7, organic waterproof putty 8, SBS waterproof layer 9, XPS extruded polystyrene board protective layer
Specific embodiment
A kind of poured band of outer wall of basement advance water stop construction method to further describe the present invention, with reference to the accompanying drawing It is described further.
In Fig. 1-2: a kind of poured band of outer wall of basement advance water stop construction method, comprising the following steps:
Step 1: the construction of 2 concrete of outer wall of basement: first successively installing 2 reinforcing bar of outer wall of basement and outer wall of basement 2 Template, then fast-easy closing-up net is constructed, install pre-embedded bolt 3 and Screw arbor with nut at both-ends 4, and then 2 concrete of outer wall of basement pours, 2 template of outer wall of basement is removed later, finally 2 concrete of outer wall of basement is carried out to carry out lid maintenance;
Step 2: assembled post-cast strip seal plate 5 is prefabricated: mixed with proportion using basement bottom board 1 or outer wall of basement 2 Solidifying soil is processed, and 5 width of seal plate adds 400mm, two-way 60 ° of bevel edges, using clad steel depending on the every side of post-cast strip width Muscle, upper and lower plates interface use ribbet;
Step 3: SBS extra play 6 is handled between outer wall of basement 2 and assembled post-cast strip seal plate 5: the seal plate 5 is pacified Before dress, one layer of SBS extra play 6 is done in outer wall of basement 2 and 5 inside joint of seal plate;
Step 4: base's water-proofing treatment between outer wall of basement 2 and assembled post-cast strip seal plate 5: the post-cast strip assembly Before formula seal plate 5 is installed, it is laminated at macromolecule waterproof coating that 5 inside of seal plate and up and down interface position are uniformly coated with one;
Step 5: the installation of assembled post-cast strip seal plate 5: successively installing the seal plate of outer wall of basement 2 from bottom to top 5, the pre-embedded bolt 3 of seal plate 5 is fastened when the seal plate 5 of outer wall of basement 2 is installed, is filled out at bolt with organic waterproof putty 7 It fills closely knit, the processing of 7 waterproof reinforced of organic waterproof putty is carried out to 5 seam of seal plate and seal plate 5 and wall joints;
Step 6: the construction of the SBS waterproof layer 8 of outer wall of basement 2: after installing seal plate 5, entirety SBS waterproof of constructing Layer 8, waterproof layer and waterproof slab overlap;
Step 7: the construction of 2 protective layer of outer wall of basement and backfilling of earthwork: it is poly- to carry out whole XPS extrusion molding to outer wall of basement 2 Benzene plate protective layer 9 is constructed, and carries out the protection to SBS waterproof layer 8 using protective layer, then carries out outdoor backfilling of earthwork.
The plate thickness of the seal plate be 150mm, length 1500mm, the steel bar stress protective layer with a thickness of 15mm.
6 height of SBS extra play is that height every side in post-cast strip adds 200mm, and width regards the every Bian Gejia of post-cast strip width 600mm, with a thickness of 3mm.
The waterproof coating with a thickness of 2mm.
The SBS waterproof layer 8 with a thickness of 3mm.
The XPS extruded polystyrene board protective layer 9 is with a thickness of 50mm.
Method of the invention for engineer application, is applied in basement post-pouring zone environment in basement post-pouring zone backfilling of earthwork Working hour carries out outer wall of basement SBS waterproof layer, entirety XPS using assembled post-cast strip seal plate using the method for the present invention in advance The construction of extruded polystyrene board protective layer is completed interface and is separated, post-cast strip construction in later period difficulty in process is eliminated, carries out basement in advance Exterior wall side backfilling of earthwork.Method and process of the invention is structurally reasonable, easy to operate, effectively improves basement post-pouring zone position infiltration Leakage control, shortens the deep foundation pit precipitation duration, and save the cost eliminates deep foundation pit construction stage bring security risk, is basement The processes such as waterproof, pit earthwork backfill create conditions, and provide place to construction plane management and create for site safety civilized construction The advantages of making advantage.
The above content is just an example and description of the concept of the present invention, not detailed place, is the art Well-known technique, affiliated those skilled in the art make various modifications or additions to the described embodiments or It is substituted in a similar manner, it as long as it does not deviate from the concept of invention or beyond the scope defined by this claim, should all It belongs to the scope of protection of the present invention.

Claims (6)

1. a kind of poured band of outer wall of basement advance water stop construction method, which comprises the following steps:
Step 1: the construction of outer wall of basement (2) concrete: first successively installing outer wall of basement (2) reinforcing bar and outer wall of basement (2) template, then fast-easy closing-up net is constructed, and installs pre-embedded bolt (3) and Screw arbor with nut at both-ends (4), then outer wall of basement (2) coagulation Pouring for soil, later removes outer wall of basement (2) template, finally carry out covering to outer wall of basement (2) concrete and support Shield;
Step 2: assembled post-cast strip seal plate (5) is prefabricated: using basement bottom board (1) or outer wall of basement (2) with proportion Concrete is processed, and seal plate (5) width adds 400mm, two-way 60 ° of bevel edges, using double depending on the every side of post-cast strip width Layer reinforcing bar, upper and lower plates interface use ribbet;
Step 3: SBS extra play (6) is handled between outer wall of basement (2) and assembled post-cast strip seal plate (5): the seal plate (5) before installing, one layer of SBS extra play (6) is done in joint on the inside of outer wall of basement (2) and seal plate (5);
Step 4: base's water-proofing treatment between outer wall of basement (2) and assembled post-cast strip seal plate (5): the post-cast strip assembly Before formula seal plate (5) installation, it is laminated at the painting of macromolecule waterproof that on the inside of seal plate (5) and upper and lower interface position is uniformly coated with one Film;
Step 5: the installation of assembled post-cast strip seal plate (5): successively installing the seal plate of outer wall of basement (2) from bottom to top (5), the pre-embedded bolt (3) of seal plate (5) is fastened when seal plate (5) of outer wall of basement (2) are installed, with organic anti-at bolt Water blocking material (7) filling is closely knit, carries out organic waterproof putty (7) waterproof to seal plate (5) seam and seal plate (5) and wall joints Reinforcement processing;
Step 6: the construction of the SBS waterproof layer (8) of outer wall of basement (2): after installing seal plate (5), construction entirety SBS is anti- Water layer (8), waterproof layer and waterproof slab overlap;
Step 7: the construction of outer wall of basement (2) protective layer and backfilling of earthwork: it is poly- to carry out entirety XPS extrusion molding to outer wall of basement (2) Benzene plate protective layer (9) construction, carries out the protection to SBS waterproof layer (8) using protective layer, then carries out outdoor backfilling of earthwork.
2. a kind of poured band of outer wall of basement advance water stop construction method according to claim 1, which is characterized in that described The plate thickness of seal plate be 150mm, length 1500mm, the steel bar stress protective layer with a thickness of 15mm.
3. a kind of poured band of outer wall of basement advance water stop construction method according to claim 1, which is characterized in that described SBS extra play (6) highly adds 200mm for the every side of post-cast strip height, and width adds 600mm, thickness depending on the every side of post-cast strip width For 3mm.
4. a kind of poured band of outer wall of basement advance water stop construction method according to claim 1, which is characterized in that described Waterproof coating with a thickness of 2mm.
5. a kind of poured band of outer wall of basement advance water stop construction method according to claim 1, which is characterized in that described SBS waterproof layer (8) with a thickness of 3mm.
6. a kind of poured band of outer wall of basement advance water stop construction method according to claim 1, which is characterized in that described XPS extruded polystyrene board protective layer (9) is with a thickness of 50mm.
CN201910653826.0A 2019-07-19 2019-07-19 A kind of poured band of outer wall of basement advance water stop construction method Pending CN110439036A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910653826.0A CN110439036A (en) 2019-07-19 2019-07-19 A kind of poured band of outer wall of basement advance water stop construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910653826.0A CN110439036A (en) 2019-07-19 2019-07-19 A kind of poured band of outer wall of basement advance water stop construction method

Publications (1)

Publication Number Publication Date
CN110439036A true CN110439036A (en) 2019-11-12

Family

ID=68429742

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910653826.0A Pending CN110439036A (en) 2019-07-19 2019-07-19 A kind of poured band of outer wall of basement advance water stop construction method

Country Status (1)

Country Link
CN (1) CN110439036A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576658A (en) * 2020-05-21 2020-08-25 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN113863389A (en) * 2021-08-28 2021-12-31 安徽朗凯奇建材有限公司 Basement outer wall post-cast strip advanced water stop structure and construction method thereof
CN113944240A (en) * 2021-09-24 2022-01-18 上海宝冶集团有限公司 Fixed prefabricated structure for sealing basement outer wall post-cast strip in advance and construction method thereof
CN114351852A (en) * 2021-12-23 2022-04-15 广东金辉华集团有限公司 Basement outer wall post-cast strip assembly type maintenance water stop structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203625942U (en) * 2013-08-21 2014-06-04 中建二局第二建筑工程有限公司 Basement outer wall post-cast strip ahead water stopping structure
JP2016079686A (en) * 2014-10-17 2016-05-16 東日本高速道路株式会社 Water cut-off member, and water cut-off structure using the same
CN205653820U (en) * 2016-05-13 2016-10-19 歌山建设集团有限公司 Basement post -cast strip advances plugging device
CN108589793A (en) * 2018-01-29 2018-09-28 江苏江中集团有限公司 A kind of poured band of outer wall of basement postposition assembled advance water stop construction method
CN108894256A (en) * 2018-07-10 2018-11-27 天津三建建筑工程有限公司 A kind of advanced plugging construction method of poured band of outer wall of basement

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203625942U (en) * 2013-08-21 2014-06-04 中建二局第二建筑工程有限公司 Basement outer wall post-cast strip ahead water stopping structure
JP2016079686A (en) * 2014-10-17 2016-05-16 東日本高速道路株式会社 Water cut-off member, and water cut-off structure using the same
CN205653820U (en) * 2016-05-13 2016-10-19 歌山建设集团有限公司 Basement post -cast strip advances plugging device
CN108589793A (en) * 2018-01-29 2018-09-28 江苏江中集团有限公司 A kind of poured band of outer wall of basement postposition assembled advance water stop construction method
CN108894256A (en) * 2018-07-10 2018-11-27 天津三建建筑工程有限公司 A kind of advanced plugging construction method of poured band of outer wall of basement

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576658A (en) * 2020-05-21 2020-08-25 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN111576658B (en) * 2020-05-21 2021-08-31 武汉博宏建设有限公司 Construction method of post-cast strip protection wall of assembled basement outer wall
CN113863389A (en) * 2021-08-28 2021-12-31 安徽朗凯奇建材有限公司 Basement outer wall post-cast strip advanced water stop structure and construction method thereof
CN113944240A (en) * 2021-09-24 2022-01-18 上海宝冶集团有限公司 Fixed prefabricated structure for sealing basement outer wall post-cast strip in advance and construction method thereof
CN114351852A (en) * 2021-12-23 2022-04-15 广东金辉华集团有限公司 Basement outer wall post-cast strip assembly type maintenance water stop structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN110439036A (en) A kind of poured band of outer wall of basement advance water stop construction method
CN107326940B (en) basement advanced water stop post-cast strip structure and construction method thereof
CN209723052U (en) The prefabricated plate advanced water-stopping of poured band of outer wall of basement backfills structure
CN109707415B (en) Joint construction method and joint structure of subway shield tunnel and station
CN107190782A (en) A kind of poured band of outer wall of basement structure and its construction method
CN205653820U (en) Basement post -cast strip advances plugging device
CN206706791U (en) Base pit dewatering well plugging structure
CN108060928A (en) Shield tunnel multiple tube piece ring structure, assembling method and the manufacturing method of compound section of jurisdiction
CN110219458A (en) A kind of waterproof integrated equipment room floor construction method of sound insulation and noise reducing
CN106759843A (en) A kind of outer wall of basement waterproof construction and its construction method
CN103410173A (en) Construction method for vertical post pouring belt plugging of underground structural outer wall
CN112376624A (en) Secondary pouring and retaining advanced water stop structure for basement floor post-cast strip and construction method
CN207211188U (en) Outer wall of underground structure HCMW engineering methods overlap wall
KR20140139217A (en) Concrete protection wall with linear drainage functions and construction method thereof
CN206220277U (en) The simple type deformation joint structure of site operation
CN107326924A (en) Outer wall of underground structure HCMW engineering methods overlap wall and its construction method
CN203247838U (en) Fully-buried basement side wall post-pouring belt advance water stop formwork
JPH08269984A (en) Construction of basement in outside waterproofing construction method
CN115387393A (en) Post-cast strip pre-sealing quick construction method
CN102587421A (en) Advanced water-stopping isolation structure of later poured band for basement
CN206768879U (en) A kind of poured band of outer wall of basement structure
CN113187487B (en) Construction method of double-layer full-section frozen underground excavation station structure of subway
CN108589793A (en) A kind of poured band of outer wall of basement postposition assembled advance water stop construction method
CN213625699U (en) Basement outer wall waterproof construction structure for reverse construction
CN111576658B (en) Construction method of post-cast strip protection wall of assembled basement outer wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191112