CN110397249A CN201910733865.1A CN201910733865A CN110397249A CN 110397249 A CN110397249 A CN 110397249A CN 201910733865 A CN201910733865 A CN 201910733865A CN 110397249 A CN110397249 A CN 110397249A
Authority
CN
China
Prior art keywords
fixed
cavity
gear
shaft
chamber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910733865.1A
Other languages
Chinese (zh)
Other versions
CN110397249B (en
Inventor
俞淼松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong zhuchao decoration design Engineering Co.,Ltd.
Original Assignee
Zhuji Ouyi Automation Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuji Ouyi Automation Equipment Co Ltd filed Critical Zhuji Ouyi Automation Equipment Co Ltd
Priority to CN201910733865.1A priority Critical patent/CN110397249B/en
Publication of CN110397249A publication Critical patent/CN110397249A/en
Application granted granted Critical
Publication of CN110397249B publication Critical patent/CN110397249B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Spray Control Apparatus (AREA)
  • Nozzles (AREA)

Abstract

A kind of integral type wall plaster equipment of the invention, including the first fuselage, discharging chamber is equipped in first fuselage, being equipped in the feed cavity makes to paint the discharging mechanism risen in pipeline by piston press, the first sliding groove being equipped in the discharging chamber, the first sliding block is equipped in the first sliding groove, the first drive cavity is equipped in first sliding block, equipment of the invention reduces the operating time of finishing work by quickly painting wall, it is intracavitary that paint is squeezed into coating by way of extruding by equipment, it will be in paint application to brush wheel by coating chamber, brush wheel is disposably by whole face wall plastering, working efficiency is higher, equipment makes paint accelerate to dry out by way of air draught, the unusual odor of paint can be also absorbed simultaneously, reduce air pollution, protect the health of environment and resident, equipment energy utilization rate with higher, it grasps simultaneously It is safety quick to make simple procedure.

Description

A kind of integral type wall plaster equipment
Technical field
The present invention relates to quick decoration field, specially a kind of integral type wall plaster equipment.
Background technique
It is well known that with the development of economy, people become the demand in shelter house on the head of modern society people It pursues, buys house, fits up the family for possessing a warm beauty, become the target of many people struggles, society shows situation now, People be also to the standard of finishing it is higher and higher, living in the room that one is admired can allow people to feel more happiness, in fitment process Most important is exactly wall plaster, and the plasterer of metope makees mainly have decoration worker to complete at present, working efficiency it is relatively slow and And quality not can guarantee yet, and the taste painted is also harmful to the body of people, if can disposably be unified to metope Painting efficiency will greatly promote, while quality also can be higher, it is therefore desirable to design a kind of integral type wall plaster equipment to solve The certainly above problem.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of integral type wall plaster equipment, to metope can unite One painting, disposably carries out paint covering for entire metope, while can also absorb the effective integrated equipment of the peculiar smell of paint, The equipment reaction is sensitive, feature-rich.
The present invention is achieved through the following technical solutions.
A kind of integral type wall plaster equipment of the invention, including the first fuselage, first fuselage is interior to be equipped with discharging chamber;
Being equipped in the feed cavity makes to paint the discharging mechanism risen in pipeline by piston press, is equipped in the discharging chamber First sliding groove, the first sliding block is equipped in the first sliding groove, the first drive cavity is equipped in first sliding block, described first passes It is located in first fuselage on the downside of dynamic chamber and is equipped with storage cavity, is fixed with belt chamber on the right side of the storage cavity;
The second fuselage is equipped on the left of first fuselage, second fuselage is interior to be equipped with painting chamber, and the painting is intracavitary to be equipped with clearly Painting mechanism that is clean and painting metope progress groundwork, intracavitary left and right of painting, which extends, to be rotated equipped with first rotating shaft, described It is fixed with rotating wheel in first rotating shaft, track groove is fixed on the rotating wheel, is fixed on rear side of the first rotating shaft First connecting rod, sliding is equipped with the cleaning block extending into the track groove on the first connecting rod;
It is fixed with third fuselage on the left of second fuselage, is equipped in the third fuselage and moves strong chamber, in the mobile cavity Equipped with the mobile mechanism for driving the painting mechanism to move up and down, second sliding slot, the second sliding slot are equipped in the mobile cavity It is inside equipped with the second sliding block, is equipped with power cavity in second sliding block, it is fixed in the first rotating shaft in the power cavity Equipped with first gear.
Further, the discharging mechanism includes the discharging chamber, the first sliding groove being equipped in the discharging chamber, institute It states and is equipped with first sliding block in first sliding groove, be equipped with first drive cavity, first drive cavity in first sliding block Interior left and right extends rotation and is equipped with the second shaft, is fixed with first bevel gear in second shaft, in first drive cavity Extend up and down and be equipped with third shaft, the third shaft is equipped with the second bevel gear engaged with the first bevel gear, described Sliding is equipped with third sliding block in first drive cavity, and the third sliding block is contacted with the second bevel gear, the third sliding block and Spring is connected between the first drive cavity base end wall.
Further, it is located in first fuselage on the downside of first drive cavity and is equipped with storage cavity described in the storage cavity Front bulkhead is fixed with equipped with feed inlet, and rotation is equipped with thread bush in the storage cavity, is equipped with third sliding slot in the thread bush, The third shaft can be slided in the third sliding slot and the thread bush is driven to rotate, and the thread bush is equipped with piston, Internal screw thread is equipped in the piston, the internal screw thread is engaged with the thread bush.
Further, be fixed with the belt chamber on the right side of the storage cavity, the belt is intracavitary be fixed with it is described The pipeline of storage cavity bottom connection, the intracavitary rotation of belt are equipped with the second connecting rod, second connecting rod and the pipeline Between rotation be equipped with belt pulley, torsional spring, the skin are connected between the belt pulley aft bulkhead and the belt cavity rear end wall Tep reel chamber is equipped in belt wheel, the tep reel is intracavitary to be equipped with flexible rubber hose, and the pipeline and described flexible rubber hose one end are rotatablely connected, described The conveyance conduit that left and right extends is fixed on the upside of first sliding block, described conveyance conduit one end is fixedly connected with the flexible rubber hose.
Further, the painting mechanism includes the painting chamber, extends to the delivery pipe in second fuselage On road rotation be equipped with gear bush, gear bush left end wall be located at it is described painting it is intracavitary be fixedly connected equipped with the 4th shaft, Paint chamber is equipped in 4th shaft, the paint chamber outer end wall is equipped with liquid drain hole, is fixed in the 4th shaft Painting wheel.
Further, the intracavitary left and right of the painting, which extends to rotate, is equipped with the first rotating shaft, fixed in the first rotating shaft Equipped with the rotating wheel, it is fixed with the track groove on the rotating wheel, described the is fixed on rear side of the first rotating shaft One connecting rod, sliding is equipped with the cleaning block extending into the track groove on the first connecting rod, under the cleaning block End face fixed-link has hairbrush.
Further, it is fixed with motor on the right side of the painting chamber, the motor left side is rotatably connected to described first Shaft, the motor right side are rotatably connected to second shaft, are located on the right side of the motor fixed in second fuselage Equipped with the second drive cavity, it is fixed with second gear in second shaft in second drive cavity, described second Gear is engaged with the gear bush, and the second gear left side is fixedly connected equipped with third hand tap gear.
Further, extend rotation in second drive cavity up and down and be equipped with the 5th shaft, be located at second drive cavity The 4th bevel gear is fixed in interior the 5th shaft, the 4th bevel gear engages with the third hand tap gear, described It is fixed with ventilation lumen on the downside of painting chamber, spacing block is equipped in the ventilation lumen, is fixed with suction on the right side of the ventilation lumen upper layer Air pump, the asepwirator pump are connect with the 5th shaft, are located in the ventilation lumen on the left of the asepwirator pump and are fixed with filtering Block, ventilation lumen middle layer front bulkhead are equipped with venthole, and ventilation lumen lower layer aft bulkhead is equipped with air inlet.
Further, the mobile mechanism includes the mobile cavity, and the second sliding slot is equipped in the mobile cavity, described It is equipped with second sliding block in second sliding slot, is equipped with the power cavity, the institute in the power cavity in second sliding block It states and is fixed with the first gear in first rotating shaft, end wall is symmetrically fixed with gear grooved, the tooth before and after the mobile cavity Race is engaged with the first gear.
Beneficial effects of the present invention: when equipment of the invention reduces the work of finishing work by quickly painting wall Long, it is intracavitary that paint is squeezed into coating by way of extruding by equipment, by coating chamber by paint application to brush wheel, brush wheel Disposably by whole face wall plastering, working efficiency is higher, and equipment makes paint accelerate to dry out by way of air draught, while can also inhale The unusual odor of receipts paint, reduction air pollution, the health of protection environment and resident, equipment energy utilization rate with higher, Process safety easy to operate is rapid simultaneously.
Detailed description of the invention
It, below will be to embodiment or existing in order to illustrate more clearly of inventive embodiments or technical solution in the prior art Attached drawing needed in technical description is briefly described, it should be apparent that, the accompanying drawings in the following description is only to invent Some embodiments for those of ordinary skill in the art without creative efforts, can also basis These attached drawings obtain other attached drawings.
Fig. 1 is the mechanical structure schematic diagram of the embodiment of the present invention;
Fig. 2 is the structural schematic diagram of A-A in Fig. 1;
Fig. 3 is the structural schematic diagram of B-B in Fig. 1;
Fig. 4 is the structural schematic diagram of C-C in Fig. 1;
Fig. 5 is the structural schematic diagram of D-D in Fig. 1;
Fig. 6 is the structural schematic diagram of E-E in Fig. 1.
Specific embodiment
Below with reference to Fig. 1-6, the present invention is described in detail, for sake of convenience, now such as to hereafter described orientation regulation Under: hereafter described front-rear direction up and down is consistent with the front-rear direction up and down of Fig. 1 projection relation itself.
A kind of integral type wall plaster equipment in conjunction with described in attached drawing 1-6, including the first fuselage 34, first fuselage 34 Interior to be equipped with discharging chamber 35, being equipped in the feed cavity 35 makes to paint the discharging mechanism 90 risen in pipeline by piston press, The first sliding groove 36 being equipped in the discharging chamber 35, the first sliding groove 36 is interior to be equipped with the first sliding block 37, first sliding block 37 It is inside equipped with the first drive cavity 66, is located in first fuselage 34 on the downside of first drive cavity 66 and is equipped with storage cavity 49, it is described Belt chamber 48 is fixed on the right side of storage cavity 49;
It is equipped with the second fuselage 17 on the left of first fuselage 34, painting chamber 23, the painting chamber are equipped in second fuselage 17 It is equipped in 23 and cleans and paint the painting mechanism 91 that metope carries out groundwork, left and right extends rotation and is equipped in the painting chamber 23 First rotating shaft 24 is fixed with rotating wheel 25 in the first rotating shaft 24, track groove 18, institute is fixed on the rotating wheel 25 It states and is fixed with first connecting rod 63 on rear side of first rotating shaft 24, sliding is equipped with and extend into the track on the first connecting rod 63 Cleaning block 62 in slot 18;
It is fixed with third fuselage 10 on the left of second fuselage 17, mobile strong chamber 11 is equipped in the third fuselage 10, it is described The mobile mechanism 92 for driving the painting mechanism 91 to move up and down is equipped in mobile cavity 11, it is sliding to be equipped with second in the mobile cavity 11 Slot 12, the second sliding slot 12 is interior to be equipped with the second sliding block 13, is equipped with power cavity 15 in second sliding block 13, is located at the power First gear 14 is fixed in the first rotating shaft 24 in chamber 15.
The discharging mechanism 90 includes the discharging chamber 35, the first sliding groove 36 being equipped in the discharging chamber 35, institute It states and is equipped with first sliding block 37 in first sliding groove 36, be equipped with first drive cavity 66 in first sliding block 37, described the Left and right, which extends to rotate, in one drive cavity 66 is equipped with the second shaft 50, is fixed with first bevel gear 31 in second shaft 50, Extend up and down in first drive cavity 66 and be equipped with third shaft 32, the third shaft 32 is equipped with and the first bevel gear The second bevel gears 33 of 31 engagements, sliding is equipped with 38 third sliding blocks 38 in first drive cavity 66, the third sliding block 38 with The second bevel gear 33 contacts, and is connected with spring between the third sliding block 38 and 66 base end wall of the first drive cavity 39, it is located on the downside of first drive cavity 66 in first fuselage 34 and is equipped with 49 front bulkhead of storage cavity described in the storage cavity 49 It is fixed with and is equipped with feed inlet 65, rotation is equipped with thread bush 40 in the storage cavity 49, and it is sliding to be equipped with third in the thread bush 40 Slot 43, the third shaft 32 can be slided in the third sliding slot 43 and the thread bush 40 driven to rotate, the thread bush 40 are equipped with piston 41, are equipped with internal screw thread 42 in the piston 41, the internal screw thread 42 is engaged with the thread bush 40, the storage It is fixed with the belt chamber 48 on the right side of material chamber 49, is fixed in the belt chamber 48 and is connected to 49 bottom of storage cavity Pipeline 47, the interior rotation of the belt chamber 48 are equipped with the second connecting rod 58, turn between second connecting rod 58 and the pipeline 47 It is dynamic to be equipped with belt pulley 45, it is connected with torsional spring 59 between 45 aft bulkhead of belt pulley and 48 aft bulkhead of belt chamber, it is described It is equipped with tep reel chamber 60 in belt pulley 45, flexible rubber hose 44, the pipeline 47 and the flexible rubber hose 44 1 are equipped in the tep reel chamber 60 End is rotatablely connected, and the conveyance conduit 30 that left and right extends, described 30 one end of conveyance conduit are fixed on the upside of first sliding block 37 It is fixedly connected, paint is poured into the storage cavity 49 by the feed inlet 65, when described second turn with the flexible rubber hose 44 When axis 50 rotates, second shaft 50 drives the first bevel gear 31 to rotate, and the rotation of first bevel gear 31 passes through tooth Wheel engagement drives the second bevel gear 33 to rotate, and the rotation of second bevel gear 33 drives the thread bush 40 to rotate, described Thread bush 40, which is rotated, drives 41 slide downward of piston by the screw thread engagement of the internal screw thread 42, and 41 countryside of piston is sliding The dynamic paint squeezed in the storage cavity 49 enters the pipeline 47, when 37 upward sliding of the first sliding block, described first The flexible rubber hose 44 is pulled out the belt pulley 45 by the conveyance conduit 30 by sliding block 37, and the belt pulley 45 is because described soft Sebific duct 44 stretches out rotation, and the rotation of belt pulley 45 rotates the torsional spring 59, and the third sliding block 38 is in the spring 39 It is moved up under effect, the third sliding block 38, which moves up, contacts the first bevel gear 31 with the second bevel gear 33 Engagement, when the sliding of described ground body sliding block countryside, the belt pulley 45 is received the flexible rubber hose 44 by the torsional spring 59 rotation Get up.
The painting mechanism 91 includes the painting chamber 23, extends to the conveyance conduit 30 in second fuselage 17 Upper rotation is equipped with gear bush 29, and the 29 left end wall of gear bush, which is located in the painting chamber 23, to be fixedly connected equipped with the 4th turn Axis 28, is equipped with paint chamber 19 in the 4th shaft 28, and 19 outer end wall of paint chamber is equipped with liquid drain hole 27, and described 4th turn It being fixed on axis 28 and paints wheel 26, left and right, which extends to rotate, in the painting chamber 23 is equipped with the first rotating shaft 24, and described first It is fixed with the rotating wheel 25 in shaft 24, the track groove 18, the first rotating shaft are fixed on the rotating wheel 25 24 rear sides are fixed with the first connecting rod 63, and sliding, which is equipped with, on the first connecting rod 63 extend into the track groove 18 The cleaning block 62, the 62 lower end surface fixed-link of cleaning block has hairbrush 64, is fixed with horse on the right side of the painting chamber 23 Up to 56,56 left side of motor is rotatably connected to the first rotating shaft 24, and 56 right side of motor is rotatably connected to described Second shaft 50 is located in second fuselage 17 on the right side of the motor 56 and is fixed with the second drive cavity 67, is located at described the Second gear 51, the second gear 51 and the gear bush are fixed in second shaft 50 in two drive cavities 67 29 engagements, 51 left side of second gear are fixedly connected equipped with third hand tap gear 52, upper downward in second drive cavity 67 It stretches rotation and is equipped with the 5th shaft 54, the 4th cone tooth is fixed in the 5th shaft 54 in second drive cavity 67 Wheel 53, the 4th bevel gear 53 engages with the third hand tap gear 52, is fixed with ventilation lumen 20 on the downside of the painting chamber 23, It is equipped with spacing block 21 in the ventilation lumen 20, is fixed with asepwirator pump 55, the asepwirator pump 55 on the right side of 20 upper layer of ventilation lumen It is connect with the 5th shaft 54, is located in the ventilation lumen 20 on the left of the asepwirator pump 55 and is fixed with filter block 22, it is described 20 middle layer front bulkhead of ventilation lumen is equipped with venthole 61, and 20 lower layer's aft bulkhead of ventilation lumen is equipped with air inlet 57, opens the horse Up to 56, the motor 56 drives the first rotating shaft 24 to rotate, and the rotation of first rotating shaft 24 keeps second fuselage 17 whole It moves up, the rotation of first rotating shaft 24 drives the rotating wheel 25 to rotate, and the rotation of rotating wheel 25 passes through the track Slot 18 makes the cleaning block 62 do bilateral reciprocation, and the cleaning block 62 does bilateral reciprocation and 64 hairbrush 64 is driven to do Bilateral reciprocation cleans raised metope, and the motor 56 drives second shaft 50 to rotate, and second shaft 50 rotates The second gear 51 is driven to rotate, the rotation of second gear 51 drives the gear bush 29 to rotate by gear engagement, The rotation of gear bush 29 drives the 4th shaft 28 rotation, and the 4th shaft 28 rotation drives the painting to take turns 26 turns Dynamic, the paint in the paint chamber 19 is entered painting wheel 26 by the liquid drain hole 27 by the 4th shaft 28 rotation On, for the painting wheel 26 by paint application to metope, the rotation of the second shaft 50 drives the third hand tap gear 52 to rotate, The rotation of third hand tap gear 52 drives the 4th bevel gear 53 to rotate by gear engagement, the 4th bevel gear 53 rotation The 5th shaft 54 is driven to rotate, the 5th shaft 54 rotation makes the asepwirator pump 55 start air-breathing, the asepwirator pump 55 Start air-breathing to suck gas in the ventilation lumen 20 by the air inlet 57, gas is first by the ventilation lumen 20 The filter block 22 removes peculiar smell, is discharged by the venthole 61.
The mobile mechanism 92 includes the mobile cavity 11, and the second sliding slot 12 is equipped in the mobile cavity 11, described It is equipped with second sliding block 13 in second sliding slot 12, is equipped with the power cavity 15 in second sliding block 13, is located at the power The first gear 14 is fixed in the first rotating shaft 24 in chamber 15, symmetrically fixation is set the 11 front and back end wall of mobile cavity There is gear grooved 16, the gear grooved 16 is engaged with the first gear 14, when the first rotating shaft 24 rotation, described first turn The rotation of axis 24 drives first gear 14 to rotate, and the rotation of first gear 14 makes second sliding block 13 by the gear grooved 16 Upward sliding, 13 upward sliding of the second sliding block drive the second fuselage 17 to move up, and second fuselage 17 moves up First fuselage 34 described in earthquake moves up.
The sequence of the mechanical action of whole device:
1. paint is poured into the storage cavity 49 by the feed inlet 65, when second shaft 50 rotation, described the Two shafts 50 drive the first bevel gear 31 to rotate, and the rotation of first bevel gear 31 drives described second by gear engagement Bevel gear 33 rotates, and the rotation of second bevel gear 33 drives the thread bush 40 to rotate, and the rotation of thread bush 40 passes through institute The screw thread engagement for stating internal screw thread 42 drives 41 slide downward of piston, and 41 countryside of the piston sliding squeezes the storage cavity 49 Interior paint enters the pipeline 47;
2. first sliding block 37 passes through the conveyance conduit 30 for the flexible rubber hose when 37 upward sliding of the first sliding block 44 pull out the belt pulley 45, and for the belt pulley 45 because the flexible rubber hose 44 stretches out rotation, the rotation of belt pulley 45 makes institute The rotation of torsional spring 59 is stated, the third sliding block 38 moves up under the action of spring 39, and the third sliding block 38 is to moving up It is dynamic that the first bevel gear 31 is made to contact engagement with the second bevel gear 33, it is described when the sliding of described ground body sliding block countryside Belt pulley 45 is accepted the flexible rubber hose 44 by the torsional spring 59 rotation;
3. opening the motor 56, the motor 56 drives the first rotating shaft 24 to rotate, and the rotation of first rotating shaft 24 makes institute It states 17 entirety of the second fuselage to move up, the rotation of first rotating shaft 24 drives the rotating wheel 25 to rotate, the rotating wheel 25 Rotation makes the cleaning block 62 do bilateral reciprocation by the track groove 18, and the cleaning block 62 makees bilateral reciprocation band It moves 64 hairbrush 64 and does the raised metope of bilateral reciprocation cleaning, the motor 56 drives second shaft 50 to rotate, institute Stating the rotation of the second shaft 50 drives the second gear 51 to rotate;
4. the rotation of second gear 51 drives the gear bush 29 to rotate by gear engagement, the gear bush 29 is rotated The 4th shaft 28 is driven to rotate, the 4th shaft 28 rotation drives 26 rotation of painting wheel, the 4th shaft 28 Rotation enters the paint in the paint chamber 19 on painting wheel 26 by the liquid drain hole 27, and the painting wheel 26 will be oily Paint is applied on metope;
5. the rotation of the second shaft 50 drives the third hand tap gear 52 to rotate, the rotation of third hand tap gear 52 passes through gear Engagement drives the 4th bevel gear 53 rotation, and the 4th bevel gear 53 rotation drives the 5th shaft 54 rotation, described The rotation of 5th shaft 54 makes the asepwirator pump 55 start air-breathing, and the asepwirator pump 55 starts air-breathing and passes through the air inlet 57 for gas Body sucks in the ventilation lumen 20, and gas removes peculiar smell by the filter block 22 in the ventilation lumen 20 first, is passing through The venthole 61 is discharged;
6. the rotation of first rotating shaft 24 drives first gear 14 to rotate, first tooth when the first rotating shaft 24 rotation 14 rotation of wheel makes 13 upward sliding of the second sliding block by the gear grooved 16, and 13 upward sliding of the second sliding block drives the Two fuselages 17 move up, and second fuselage 17 moves up the first fuselage 34 described in earthquake and moves up, equipment automatization Degree is high, and each mechanism driving cooperation is close, and kinetic energy efficiency is high.
The above embodiments merely illustrate the technical concept and features of the present invention, and its object is to allow be familiar with this field technology Personage can understand the content of present invention and be implemented, and it is not intended to limit the scope of the present invention.It is all according to the present invention Equivalent change or modification made by Spirit Essence, should be covered by the scope of protection of the present invention.

Claims (9)

1. a kind of integral type wall plaster equipment of the invention, including the first fuselage, it is characterised in that: set in first fuselage There is discharging chamber;
Being equipped in the feed cavity makes to paint the discharging mechanism risen in pipeline by piston press, is equipped in the discharging chamber First sliding groove, the first sliding block is equipped in the first sliding groove, the first drive cavity is equipped in first sliding block, described first passes It is located in first fuselage on the downside of dynamic chamber and is equipped with storage cavity, is fixed with belt chamber on the right side of the storage cavity;
The second fuselage is equipped on the left of first fuselage, second fuselage is interior to be equipped with painting chamber, and the painting is intracavitary to be equipped with clearly Painting mechanism that is clean and painting metope progress groundwork, intracavitary left and right of painting, which extends, to be rotated equipped with first rotating shaft, described It is fixed with rotating wheel in first rotating shaft, track groove is fixed on the rotating wheel, is fixed on rear side of the first rotating shaft First connecting rod, sliding is equipped with the cleaning block extending into the track groove on the first connecting rod;
It is fixed with third fuselage on the left of second fuselage, is equipped in the third fuselage and moves strong chamber, in the mobile cavity Equipped with the mobile mechanism for driving the painting mechanism to move up and down, second sliding slot, the second sliding slot are equipped in the mobile cavity It is inside equipped with the second sliding block, is equipped with power cavity in second sliding block, it is fixed in the first rotating shaft in the power cavity Equipped with first gear.
2. a kind of integral type wall plaster equipment according to claim 1, it is characterised in that: the discharging mechanism includes institute Discharging chamber is stated, the first sliding groove being equipped in the discharging chamber is equipped with first sliding block in the first sliding groove, and described the One sliding block is interior to be equipped with first drive cavity, and left and right, which extends to rotate, in first drive cavity is equipped with the second shaft, and described second It is fixed with first bevel gear in shaft, extends up and down in first drive cavity and is equipped with third shaft, in the third shaft Equipped with the second bevel gear engaged with the first bevel gear, sliding is equipped with third sliding block in first drive cavity, and described the Three sliding blocks are contacted with the second bevel gear, are connected with bullet between the third sliding block and the first drive cavity base end wall Spring.
3. a kind of integral type wall plaster equipment according to claim 2, it is characterised in that: on the downside of first drive cavity It is equipped with storage cavity front bulkhead described in the storage cavity in first fuselage to be fixed with equipped with feed inlet, the storage cavity Interior rotation is equipped with thread bush, is equipped with third sliding slot in the thread bush, the third shaft can be slided in the third sliding slot And the thread bush is driven to rotate, the thread bush is equipped with piston, is equipped with internal screw thread, the internal screw thread and institute in the piston State thread bush engagement.
4. a kind of integral type wall plaster equipment according to claim 3, it is characterised in that: fixed on the right side of the storage cavity Equipped with the belt chamber, the belt is intracavitary to be fixed with the pipeline being connected to the storage cavity bottom, intracavitary turn of the belt Dynamic to be equipped with the second connecting rod, rotation is equipped with belt pulley, the belt pulley aft bulkhead between second connecting rod and the pipeline It is connected with torsional spring between the belt cavity rear end wall, tep reel chamber is equipped in the belt pulley, the tep reel is intracavitary equipped with soft Sebific duct, the pipeline and described flexible rubber hose one end are rotatablely connected, and the conveying that left and right extends is fixed on the upside of first sliding block Pipeline, described conveyance conduit one end are fixedly connected with the flexible rubber hose.
5. a kind of integral type wall plaster equipment according to claim 1, it is characterised in that: the painting mechanism includes institute Painting chamber is stated, rotation on the conveyance conduit in second fuselage is extended to and is equipped with gear bush, the gear bush is left End wall is located at that the painting is intracavitary to be fixedly connected equipped with the 4th shaft, and paint chamber, the paint chamber are equipped in the 4th shaft Outer end wall is equipped with liquid drain hole, and painting wheel is fixed in the 4th shaft.
6. a kind of integral type wall plaster equipment according to claim 5, it is characterised in that: prolong the intracavitary left and right of painting It stretches rotation and is equipped with the first rotating shaft, be fixed with the rotating wheel in the first rotating shaft, be fixed on the rotating wheel The track groove, the first rotating shaft rear side are fixed with the first connecting rod, and sliding, which is equipped with, on the first connecting rod stretches Enter the cleaning block into the track groove, cleaning block lower end surface fixed-link has hairbrush.
7. a kind of integral type wall plaster equipment according to claim 6, it is characterised in that: fixed on the right side of the painting chamber Equipped with motor, the motor left side is rotatably connected to the first rotating shaft, and the motor right side is rotatably connected to described Two shafts, the motor right side, which is located in second fuselage, is fixed with the second drive cavity, is located in second drive cavity Second shaft on be fixed with second gear, the second gear is engaged with the gear bush, the second gear Left side is fixedly connected equipped with third hand tap gear.
8. a kind of integral type wall plaster equipment according to claim 7, it is characterised in that: in second drive cavity Lower extension rotation is equipped with the 5th shaft, and the 4th cone tooth is fixed in the 5th shaft in second drive cavity Wheel, the 4th bevel gear engage with the third hand tap gear, are fixed with ventilation lumen, the ventilation lumen on the downside of the painting chamber It is interior to be equipped with spacing block, it is fixed with asepwirator pump on the right side of the ventilation lumen upper layer, the asepwirator pump is connect with the 5th shaft, institute It states to be located in the ventilation lumen on the left of asepwirator pump and is fixed with filter block, ventilation lumen middle layer front bulkhead is equipped with venthole, institute Ventilation lumen lower layer aft bulkhead is stated equipped with air inlet.
9. a kind of integral type wall plaster equipment according to claim 1, it is characterised in that: the mobile mechanism includes institute It states mobile cavity, the second sliding slot is equipped in the mobile cavity, be equipped with second sliding block in the second sliding slot, described second It is equipped with the power cavity in sliding block, the first gear, institute are fixed in the first rotating shaft in the power cavity End wall is symmetrically fixed with gear grooved before and after stating mobile cavity, and the gear grooved is engaged with the first gear.
CN201910733865.1A 2019-08-09 2019-08-09 Integral type wall whitewashes equipment Active CN110397249B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910733865.1A CN110397249B (en) 2019-08-09 2019-08-09 Integral type wall whitewashes equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910733865.1A CN110397249B (en) 2019-08-09 2019-08-09 Integral type wall whitewashes equipment

Publications (2)

Publication Number Publication Date
CN110397249A true CN110397249A (en) 2019-11-01
CN110397249B CN110397249B (en) 2020-09-25

Family

ID=68327827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910733865.1A Active CN110397249B (en) 2019-08-09 2019-08-09 Integral type wall whitewashes equipment

Country Status (1)

Country Link
CN (1) CN110397249B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997316A (en) * 2020-09-03 2020-11-27 福州达泰米智能科技有限公司 Wall bottom surface coating equipment is used to fitment
CN112647687A (en) * 2021-01-05 2021-04-13 四川瑞吉洋洋建筑工程有限公司 A scribble machine of brushing for building side wall waterproof layer is paintd

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205804894U (en) * 2016-06-17 2016-12-14 辽宁科技大学 Vertically and horizontally move wall painting machine
CN107630547A (en) * 2017-10-25 2018-01-26 广州公孙策信息科技有限公司 A kind of wall plastering device with liquid self-feeding function
CN206942083U (en) * 2017-07-26 2018-01-30 陈伟 A kind of continuous type building wall paints device
US20180283019A1 (en) * 2017-03-31 2018-10-04 Canvas Construction, Inc. Automated drywalling system and method
CN109025197A (en) * 2018-09-11 2018-12-18 广东宏穗晶科技服务有限公司 A kind of wall rendering robot

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205804894U (en) * 2016-06-17 2016-12-14 辽宁科技大学 Vertically and horizontally move wall painting machine
US20180283019A1 (en) * 2017-03-31 2018-10-04 Canvas Construction, Inc. Automated drywalling system and method
CN206942083U (en) * 2017-07-26 2018-01-30 陈伟 A kind of continuous type building wall paints device
CN107630547A (en) * 2017-10-25 2018-01-26 广州公孙策信息科技有限公司 A kind of wall plastering device with liquid self-feeding function
CN109025197A (en) * 2018-09-11 2018-12-18 广东宏穗晶科技服务有限公司 A kind of wall rendering robot

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111997316A (en) * 2020-09-03 2020-11-27 福州达泰米智能科技有限公司 Wall bottom surface coating equipment is used to fitment
CN112647687A (en) * 2021-01-05 2021-04-13 四川瑞吉洋洋建筑工程有限公司 A scribble machine of brushing for building side wall waterproof layer is paintd

Also Published As

Publication number Publication date
CN110397249B (en) 2020-09-25

Similar Documents

Publication Publication Date Title
CN110575936A (en) Car is to cut to rub and is fallen car touch-up paint equipment of lacquer based on car
CN110397249A (en) A kind of integral type wall plaster equipment
CN108967143A (en) A kind of summer gardens are with from traveling swing type sprinkler
CN109162428A (en) A kind of house decoration wall emulsion paint brush-coating device
CN208961734U (en) A kind of portable type polishing machine with dust-absorbing function
CN109304338A (en) A kind of cleaning apparatus for pipes
CN210753936U (en) Belt cleaning device for cable processing
CN111001637B (en) Cosmetic bottle cleaning equipment
CN109157949A (en) A kind of printing equipment with exhaust-gas treatment function
CN212069251U (en) Automatic surface spraying device for building accessories
CN107440317A (en) Multifunctional cleaning rifle
CN209059029U (en) A kind of curtain cleaning device
CN207934181U (en) A kind of activity balcony
CN114215316A (en) Building decoration construction method
CN108972802A (en) A kind of pre- mothproof, mould processing equipment of bamboo and wood
CN108273813A (en) A kind of cleaning device of paint can
CN210079103U (en) Spray dust-settling device
CN215197844U (en) Valve processing paint spraying apparatus with stoving function
CN107476541B (en) A kind of intelligent painting instrument
CN219898769U (en) Wood floor coating equipment with dust removal function
CN212671777U (en) Dust collector is adopted in coal mining convenient to change operating position
CN216271033U (en) Emulsion paint blowing device
CN216157070U (en) Paint spraying tool for constructional engineering
CN109046864A (en) Door for reducing noise based on ergonomics
CN211069476U (en) Waste gas treatment device of motor spray room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210428

Address after: 423, floor 4, block a, Xinhua future city building, No. 175, Litang Road, Changping District, Beijing 102200

Patentee after: Li Qiannan

Address before: 312000 Xuandian Natural Village 738, Baoan New Village, Zhaojia Town, Zhuji City, Shaoxing City, Zhejiang Province

Patentee before: ZHUJI OUYI AUTOMATION EQUIPMENT Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211228

Address after: 250000 Room 101, floor 34, building 5, zone A3, Hanyu Jingu, Shunhua South Road, high tech Zone, Jinan, Shandong

Patentee after: Shandong zhuchao decoration design Engineering Co.,Ltd.

Address before: 102200 423, 4 / F, block a, Xinhua future city building, 175 Litang Road, Changping District, Beijing

Patentee before: Li Qiannan

TR01 Transfer of patent right