CN110334833A - A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system - Google Patents

A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system Download PDF

Info

Publication number
CN110334833A
CN110334833A CN201910231908.6A CN201910231908A CN110334833A CN 110334833 A CN110334833 A CN 110334833A CN 201910231908 A CN201910231908 A CN 201910231908A CN 110334833 A CN110334833 A CN 110334833A
Authority
CN
China
Prior art keywords
target control
organization
administration
item
sub
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910231908.6A
Other languages
Chinese (zh)
Inventor
吴茜龄
吴开平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinan Senkun Enterprise Management Consulting Co Ltd
Original Assignee
Jinan Senkun Enterprise Management Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinan Senkun Enterprise Management Consulting Co Ltd filed Critical Jinan Senkun Enterprise Management Consulting Co Ltd
Priority to CN201910231908.6A priority Critical patent/CN110334833A/en
Publication of CN110334833A publication Critical patent/CN110334833A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention provides a kind of each intermediate item using decomposing step by step, at different levels formulate organization and administration and target control plan respectively, optimization method is controlled using the qualitative duration that reversely project organic management and the target control multistage system of planning are established in duration control step by step, the step of this method: (1) directly judging critical circuits with the target control multistage system of planning by organization and administration;(2) Time-cost optimization of level-one organization and administration and target control plan is carried out;(3) according to level-one organization and administration and the target control requirement that crucial " work " deadline optimizes in the works, the Time-cost optimization of second level linked groups management and target control plan is carried out;(4) according to second level organization and administration and the target control requirement that crucial " work " deadline optimizes in the works, the Time-cost optimization of three-level linked groups management and target control plan is carried out.

Description

A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system
Technical field
The invention belongs to critical path method technical fields, are the masters of critical path method project or taskings management and target control technology Want one of component part, specifically, be it is a kind of use qualitative Time-cost optimization method, by each intermediate item or task use by Grade is decomposed, formulation respectively at different levels organizes and target control plan, by the project or task that reversely duration control is established step by step Organization and administration and duration of the target control multistage system of planning, be optimized to shorter than or equal to the target duration method.
Background technique
Eighties of last century early fifties, in order to be applicable in the development of production and the scientific research and technological development of relationship complexity The managerial needs of job engineering, each advanced industrial country has all successively carried out the research of planning management new technology in the world, wherein Successfully CPM (critical path method) and PERT (programme evaluation and review technique) is studied in the U.S. first, is established due to such methods and is closed in work It is the formulation of plan, coordination, optimization and control organically to be combined, on the basis of network model so being referred to as in foreign countries For network planning technique.
The U.S. is applied to the development of establishment Polaris missile in the PERT (programme evaluation and review technique) of invention in 1956 at that time Plan, has coordinated 3,000 many enterprises, and making plan, two years ahead completes on schedule;It is applied to cost more than 400 again later Hundred million dollars, mobilize manpower more than 40 ten thousand Apollo space program management and control, obtain good result.
It is counted according to kremlin, the construction and erection enterprises of application network planning technique, the duration can shorten 20%, engineering Cost can reduce by 10% or so.
In March, 1978, civil engineering association, U.S. proceedings comment on that this method is current only planning management newly side Method, and in foreseeable future, it is not in the new method of one kind to substitute it, therefore, we should enjoy it, use It, improve it.
Currently, each advanced industrial country, such as the United States, Russia, English, day, method, moral in the world, is all promoting and applying network planning skill Art.
The famous mathematician Hua Luogeng professor in China, from the national conditions in China, absorbing, external network planning technique is theoretical On the basis of, " critical path method " scientific system is established, and since eighties of last century early sixties, promotes answer in production practice With achieving huge economic benefit.
Since network planning technique is there are following many defects and deficiency, influences and restrict pushing away for network planning technique Row is promoted, popularization and application:
(1) restriction and planar network of project or taskings management and target control plannet model rule are established The restriction of model tormulation mode manages most projects or taskings and is unable to complete with target control person, especially compared with Big or more complex project;
(2) it is unfavorable for the restriction of computer technology application, the application of such technology depends on the support of computer technology, net Foundation, modification, the calculating of time parameter, the optimal control of constructing aims and optimal control of resource object of network model etc., only It is difficult to complete by manpower;
(3) restriction of application range, CPM are only applicable to type project or task certainly and are directly decomposed into a series of specific works Organization and administration and target control;PERT is only applicable to the evaluation of non-type project or task milestone target certainly;And with section Comprehensive fast development of technology, not only most projects or task have the feature of mixed type, and method for organizing also has There is the feature of mixed type;
(4) lack necessary function technology, major function technology only has: time-cost trade-off technology;Duration is constant, money Source demand balance optimizing technology;Resource is limited, duration most short optimisation technique;It is commented with non-type project or task milestone target certainly The technology of examining;
(5) all there is apparent defect and deficiency in major function technology, such as:
1) it time-cost trade-off technology: needs to carry out time parameter meter by the route that key job forms to each respectively After calculation, critical circuits can be just judged, need to calculate the rate of each single item key job, just can be carried out the optimization of duration-cost, This be in practical work it is highly difficult, it is even impossible;
2) duration is constant, resources balance optimisation technique: its optimization method does not consider non-key work in part (or motor-driven) Resource requirement current intelligence in time difference range, hence it is evident that unreasonable;
3) resource is limited, duration shortest optimisation technique: the work started before the period will be optimized and come most important first place, Do not consider influence size of the optimization of the non-key work started before the optimization period to the duration;
4) Evaluation technology of non-type project or task milestone target certainly, when not considering non-key milestone target interval Between Lagi-jInfluence etc. to estimate variance.
Network planning technique belongs to critical path method, is one of application technology of critical path method;It may be said that network planning technique is system Method is raised, not vice versa.
The optimization and control of target duration is the target control of critical path method project or taskings management and target control technology One of system, embodiment is that Hua Luogeng professor is pointed: using critical path method, wanting the time to key job.
Since the time-cost trade-off method of traditional network planning technique haves the defects that following many and deficiency, influence And restrict the application of time-cost trade-off method:
(1) type project or task certainly are only applicable to and is directly decomposed into a series of specific work, the organization and administration of formulation Target Time Optimization and control with target control plan, and it is not suitable for overlap joint project or taskings' management and target control The target Time Optimization of plan and control;
(2) method for judging project or taskings management and the critical circuits of target control in the works, it is right respectively to need Each carries out time parameter calculating by the route that key job forms;
(3) need to calculate the rate of each single item key job;
(4) it does not identify project or taskings manage and the method for target control planned target duration;
Do not have each intermediate item or task using decompose step by step, it is at different levels formulate respectively organization and administration and target control plan, by The Time Optimization method of project or taskings management and the target control multistage system of planning that reversely duration control is established step by step Deng.
Summary of the invention
Present invention direct basis project first or taskings' management and the target control multistage system of planning judge key lines Road, then by the qualitative Time-cost optimization method away from, " work " deadline when critical circuits, overlap joint, by project or times The Time Optimization of business organization and administration and the target control multistage system of planning is to shorter than or equal to the target duration.
For the present invention by project or task by organization and administration and target control requirement, " work " decomposed is divided into type certainly " work " and non-type " work " two types certainly:
(1) certainly type " work ": completing time t required for " work "i(or Ti) it is affirmative;
(2) non-affirmative type " work ": the time needed for completing " work " is non-affirmative, need to be carried out using three point estimations Complete the estimation of " work " time:
1)aT、mT、bT, DT=(aT+4mT+bT) ÷ 6, σT 2=[(bT-aT)÷6]2
2)at、mt、bt, Dt=(at+4mt+bt) ÷ 6, σt 2=[(bt-at)÷6]2
aT、atOptimistic completion " work " time;
mT、mtPossible completion " work " time;
bT、btPessimistic completion " work " time;
DT、DtThe weighted average of " work " time is completed in estimation;
σT 2、σt 2Complete the estimated bias of " work " time.
The present invention is decomposed the type of " work " by project, and project is divided into type, non-type certainly and three kinds of mixed type certainly Type:
(1) affirmative type project: by organization and administration and target control requirement, " work " decomposed all is affirmative type " work Make ";
(2) non-type project certainly: by organization and administration and target control requirement, " work " decomposed all is non-type certainly " work ";
(3) mixed type project: by organization and administration and target control requirement, " the work of the existing type certainly of " work " decomposed Make ", and have the work of non-type certainly.
Project of the present invention decomposes organizational form and organizer between " work " by organization and administration and target control requirement Method has following seven kinds:
Project is by organization and administration and target control requirement, the organizational form and method for organizing between " work " decomposed, By taking i " work " and j " work " as an example, i " work " be j " work " it is tight before " work " or j " work " be the next of i " work " " work ", organizational form and method for organizing between i " work " and j " work ":
(1) FYS (LT): i " work " terminates LT days, and j " work " starts;
(2)STS(LTi): i " work " starts LTiIt, j " work " starts;
(3)FTF(LTj): i " work " terminates LTjIt, j " work " terminates;
(4)STF(LTi, LTj): i " work " starts LTiIt, use LT againjIt, j " work " terminates, i.e. j " work " will be in i " work " starts LTiAfter it, LT is usedjIt terminates;
(5) STS and FTF (LTi, LTj): i " work " starts LTiIt, j " work " start, i " work " end LTjIt, j " work " terminates;
(6) STS and STF (LTi, LTi’, LTj): i " work " starts LTi days, j " work " beginning, and i " work " starts LTi It, use LT againjIt, j " work " terminates, i.e. j " work " will start LT in i " work "i’After it, LT is usedjIt terminates;
(7) FTS and STF (LT, LTi, LTj): i " work " terminates LT days, j " work " beginning, and i " work " starts LTiIt, LT is used againjIt, j " work " terminates, i.e. j " work " will start LT in i " work "iAfter it, LT is usedjIt terminates.
Organization and administration between " work " are divided into type certainly and non-two type of type certainly with target control mode by the present invention Type:
(1) type organizes and target control mode certainly: away from the organization and administration for being all affirmative when bonding relation and overlap joint With target control mode;
(2) the non-organization and administration of type certainly are with target control mode: bonding relation is affirmative;But away from being non-affirmative when overlapping , need to using three point estimations be overlapped when away from estimation:
a.LTa、LTm、LTb, DLT=(LTa+4LTm+LTb) ÷ 6, σLT 2=[(LTb-LTa)÷6]2
b.LTia、LTim、LTib, DiLT=(LTia+4LTim+LTib) ÷ 6, σiLT 2=[(LTib-LTia)÷6]2
c.LTja、LTjm、LTjb, DjLT=(LTja+4LTjm+LTjb) ÷ 6, σjLT 2=[(LTjb-LTja)÷6]2
d.LTI ' a、LTI ' m、LTI ' b, DI ' LT=(LTI ' a+4LTI ' m+LTI ' b) ÷ 6, σI ' LT 2=[(LTI ' b-LTI ' a)÷6]2
The present invention presses the difference of project organic management and target control mode, by project organic management and target control mode It is divided into type, non-type and mixed type three types certainly certainly with method:
(1) type project organic management and target control mode certainly: project decompose organization and administration between " work " and Target control mode is all the organization and administration and target control mode of type certainly;
(2) non-type project organic management and target control mode certainly: project decomposes the organization and administration between " work " It is all the organization and administration and target control mode of non-type certainly with target control mode;
(3) mixed type project organic management and target control mode: project decompose organization and administration between " work " with Target control mode, existing type certainly, also there are the organization and administration and target control mode of non-type certainly.
Project organic management of the present invention is divided into three classes with target control plan:
(1) type project organic management and target control plan certainly: type project certainly, using type organization and administration and mesh certainly Mark project organic management and the target control plan of control mode;
(2) non-type project organic management and target control plan certainly, include the following three types:
1) affirmative type project, project organic management and target control using the non-organization and administration of type certainly with target control mode System plan;
2) non-type project certainly, project organic management and target control using type organization and administration certainly with target control mode System plan;
3) non-type project certainly, using the project organic management and target of non-type certainly organization and administration and target control mode Control plan;
(3) mix mode project organic management and target control plan, including following five kinds:
1) mix mode project, project organic management and target control using type organization and administration certainly with target control mode Plan;
2) mixed type project, project organic management and target control using the non-organization and administration of type certainly with target control mode System plan;
3) mixed type project, project organic management and target control using mixed type organization and administration with target control mode Plan;
4) non-type project certainly, project organic management and target control using mixed type organization and administration with target control mode System plan;
5) affirmative type project, project organic management and target control using mixed type organization and administration with target control mode Plan.
Sub-item, individual event mesh, work three-level is pressed step by step with project below to decompose, it is at different levels to formulate organization and administration and target respectively Control plan, by the project organic management and the duration cost of the target control multistage system of planning that reversely duration control is established step by step For optimization method, the present invention will be described:
The method for building up of project organic management and the target control multistage system of planning, as shown in the table:
The present invention by organization and administration with target control requirements, using duration control method step by step formulate organizations at different levels management and Target control plan, by reversely step by step the duration control establish project organic management and the target control multistage system of planning, it is as follows Shown in table:
(1) organization and administration of project level-one and target control plan, as shown in the table:
Wherein:
A. type sub-item is affirmed:
aT=mT=bT=DT=T;σT 2=0;
B. affirm type overlap joint when away from:
a.LTa=LTm=LTb=DLT=LT, σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi, σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj, σjLT 2=0;
d.LTI ' a=LTI ' m=LTI ' b=DI ' LT=LTI ', σI ' LT 2=0.
The target duration of project level-one organization and administration and target control plan, the requirement of Yao Fuhe contract or predetermined duration.
(2) organization and administration of one of project second level and target control plan, as shown in the table:
Wherein:
A. type individual event mesh is affirmed:
aT=mT=bT=DT=T;σT 2=0;
B. affirm type overlap joint when away from:
a.LTa=LTm=LTb=DLT=LT, σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi, σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj, σjLT 2=0;
d.LTI ' a=LTI ' m=LTI ' b=DI ' LT=LTI ', σI ' LT 2=0.
The target duration of project second level each sub-item organization and administration and target control plan, as level-one organization and administration and mesh Mark the duration of corresponding sub-item in control plan.
(3) organization and administration of one of project three-level and target control plan, as shown in the table:
Wherein:
A. type work is affirmed:
at=mt=bt=Dt=t;σt 2=0;
B. affirm type overlap joint when away from:
a.LTa=LTm=LTb=DLT=LT, σLT 2=0;
b.LTia=LTim=LTib=DiLT=LTi, σiLT 2=0;
c.LTja=LTjm=LTjb=DjLT=LTj, σjLT 2=0;
d.LTI ' a=LTI ' m=LTI ' b=DI ' LT=LTI ', σI ' LT 2=0.
The target duration of project three-level each single project organic management and target control plan, as second level organization and administration and mesh It marks in control plan, the corresponding individual event purpose duration.
According in the above project organic management and the target control multistage system of planning, at different levels, each organization and administration and target control Following steps are passed through in system plan, complete formulation and project organic management and target control of organizations at different levels' management with target control plan Make the foundation of the multistage system of planning:
(1) conversion for carrying out organizational logical relationship between " work ", such as by project organic management and target control plan system What the person of determining determined: B " work " it is tight before " work " be A " work ", be converted into next " work " of A " work " as B " work ";Or Next " work " of A " work " be B " work ", be converted into B " work " it is tight before " work " be A " work ";
(2) arrangement of organizational logical relationship is carried out
(4) in main " work " list " work " tissue sequence sequence: by ST successively are as follows: with ST for before tightly " work " of " work ";With ordering " work " be it is tight before " work " " work ";……;Until FIN;By FIN according to It is secondary are as follows: to take FIN as " work " of next " work ";It take ordering " work " as " work " of next " work ";……;Until ST。
The present invention is at different levels, each organization and administration are as follows with the time parameter calculation method of target control plan:
(1) time that " work " may start earliest
(2) time that " work " may terminate earliest
(3) interval time between " work "
(4) motor-driven (part) time difference of " work ": FFi=min (Lagi-j);
(5) total time difference of " work ": TFi=min (TFj+Lagi-j);
(6) time that " work " must start at the latest: LSi=ESi+TFi
(7) time that " work " must terminate at the latest: LFi=EFi+TFi
Project organic management and the target control multistage system of planning time parameter that reversely duration control is established step by step with estimate Count the calculation method of variance:
(1) three-level respectively organize with target control plan, the calculating of time parameter and estimate variance:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、 υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, really Determine FFi, then calculate TFi、LSiAnd LFi
(2) second level respectively organizes and target control plan, the calculating of time parameter and estimate variance: each with three-level respectively The organization and administration of individual event purpose and the duration of target control plan and the estimate variance of duration, as second level organization and administration and target control Make the estimate variance of each individual event purpose duration and duration in the works:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、 υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, really Determine FFi, then calculate TFi、LSiAnd LFi
(3) level-one organization and administration are with target control plan, the calculating of time parameter and estimate variance: respectively with each point of second level The organization and administration of project and the duration of target control plan and the estimate variance of duration, as level-one organization and administration and target control The estimate variance of the duration and duration of each sub-item in the works:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、 υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, really Determine FFi, then calculate TFi、LSiAnd LFi
The estimate variance of organizations at different levels management and target control plan:
(1) sub-item is in level-one organization and administration and target control ES in the worksiEstimate variance, for second level organization and administration with Target control is in the works, sub-item organizes and the estimate variance of target control planned start time;
(2) individual event mesh is in second level organization and administration and target control ES in the worksiEstimate variance, for three levels of organization management with Target control in the works, the estimate variance of single project organic management and target control planned start time;
(3) three levels of organization manage with target control in the works, when the organization and administration of individual event purpose are completed with target control plan Between estimate variance, for second level organization and administration with target control in the works, the estimate variance of single project's finish time;
(4) second level is organized with target control in the works, when the organization and administration and target control plan of sub-item are completed Between estimate variance, for level-one organization and administration with target control in the works, the estimate variance of sub-item deadline.
The resource requirement of " work " unit time, is the main resource considered when a kind of optimization of selection, for being not required to " work " of this resource is wanted, resource requirement is set as zero;
The present invention is at different levels, each organization and administration are as follows with the estimate variance calculation method of target control plan:
The present invention is after the completion of at different levels, each organization and administration are calculated with target control planned time parameter, by every main " work Make " influence of the deadline estimated bias to next " work " implementation process, carry out deviations2Adjustment after, carry out its estimation side The calculating of difference.
For " work " (i.e. the discontinuous " work ") of discontinuous completion, the time Estimate deviation that " works " is completed Adjustment;
The method of adjustment of every main " work " estimation " work " deadline deviation:
Note:
(1)*σi 2- it is σ adjustedi 2
(2)σi 2The variance of-estimated time to completion the deviation for being main " work " i: σi 2=[(bit-ait)÷6]2, in which:
1)bitPessimism (longest) value of-estimated time to completion for being main " work " i;
2)aitOptimism (most short) value of-estimated time to completion for being main " work " i;
(3)DitThe weighted average of-the estimated time to completion for being main " work " i: Dit=(ait+4mit+bit) ÷ 6, in which:
1)mitMost probable (time) value of-estimated time to completion for being main " work " i;
(4)DitThe limit value of the estimated time to completion of main " work " i of '-be,
By Parameters of Normal DistributionWork as λiWhen >=3.5, P (Dit') ≈ 100%;So
It is organizing with target control in the works, the estimated bias of main " work " deadline, to next " work " Influence, away from (EF when considering actually to overlapi-ESj) influence, i.e., by when practical overlap joint away from adjustment to the shadow of next " work " It rings;
Between mainly " working ", temporal duration estimate variance is overlapped, to next " work " influence value υ2 j(LT)Calculation method, by Shown in following table:
Project organic management in the works, every " work " organization arrangement (when overlap joint away from) estimate variance (υ2 j(LT)Take following calculating As a result maximum value)
" work " will consider in organization and administration and the estimate variance of target control in the works, influence to next " work " Interval time (ES between " work "j-EFi) influence factor, be as follows:
Every main " work " adds up estimated time to completion deviation variance υ2 j(t)Calculation method:
Note:
(1)EFi'-for main " work " i is because estimation work deadline estimated bias influences, the time that can be completed at the latest, By Parameters of Normal Distribution λiWhen >=3.5, P(iEF’)≈ 100%, so
(2) it is organizing with target control in the works, the variance of every main " work " estimated time to completion deviation is by two It is grouped as: i.e. υ2 j(t)(do not include*σj 2) and*σj 2;υ2 i(t)It also include two parts, i.e. υ2 i(t)With*σi 2Influence for j " work "; υ2 j(t)(do not include*σj 2The estimate variance of)-be j attack time;υ2 i(t)(do not include*σi 2)-be i attack time Estimate variance.
The judgment method of key of the invention " work " and crucial " work " route:
(1) level-one of project organic management and the target control multistage system of planning is organized with target control in the works, Total time difference is equal to zero, i.e. TFi=0 sub-item is crucial sub-item;Interval time between crucial sub-item is equal to zero, i.e. Lagi-j=0 route is the critical circuits of level-one organization and administration and target control plan;
(2) organization and administration of the second level of project organic management and the target control multistage system of planning and target control plan, pass Total time difference is equal to zero, i.e. TF in the works for the organization and administration and target control of key sub-itemi=0 individual event mesh is project organization pipe Reason and the crucial individual event mesh in the target control multistage system of planning;Interval time between crucial individual event mesh is equal to zero, i.e. Lagi-j =0 route is the critical circuits of second level organization and administration and target control plan;
(3) management of the three levels of organization of project organic management and the target control multistage system of planning and target control plan, are closed Total time difference is equal to zero, i.e. TF to the organization and administration of key individual event purpose in the works with target controli=0 work is project organic management With the key job in the target control multistage system of planning;Interval time between key job is equal to zero, i.e. Lagi-j=0 Route is the critical circuits of three levels of organization's management and target control plan.
The method and sequence of Time Optimization of the present invention: by the level-one of project organic management and the target control multistage system of planning It organizes and starts with the Time Optimization of target control plan, optimization sequence is as follows with method:
The optimization of bonding relation is carried out first: taking technology and organiztion measure, the sub-item that will successively carry out as much as possible (bonding relation FTS, and the sub-item of LT=0) is optimized for overlap joint organizational form, optional STS (LTi)、FTF(LTj)、STF (LTi, LTj), STS and FTF (LTi, LTj), STS and STF (LTi, LTi', LTj), FTS and STF (LT, LTi, LTjOne of); LTi、LTI 'Desirable Ti50%~70%;LTjDesirable Tj50%~70%;
When the sub-item successively carried out has multiple groups, after sorting by the following method, to coming group between last sub-item Relationship (bonding relation) is knitted to optimize:
(1) the tight preceding sub-item duration (Ti) long;
(2)TiIt is identical, σi 2Small;
(3)σi 2Also identical, RiFew;
(4)RiAlso identical, then next sub-item duration (Tj) long;
(5)TjAlso identical, σj 2Small;
(6)σj 2Also identical, RjFew;
(7)RjAlso identical, then tight preceding sub-item earliest may the time started (ESi) early;
(8)ESiAlso when identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding.
Note: when the formulation of project organic management and target control plan, do not consider that every " work " unit time mainly provides The requirement in source, by Ri=0 carries out the optimization of duration.
When being overlapped away from optimization: in the case where no optimizable bonding relation, take technology and organiztion measure, Away from, optimization sequence when shortening overlap joint as much as possible are as follows: FTS (LT ≠ 0) → STS → FTF → STF → STS and FTF → STS with STF → FTS and STF;When can be overlapped by original away from 60%~80% optimize;
When the sub-item that identical overlapping mode carries out is by multiple groups, after sorting by the following method, to coming last subitem Away from optimizing when overlap joint between mesh:
(1) (LT ≠ 0) FTS:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, TiLong;
4)TiAlso identical, tight preceding sub-item duration estimated bias (σi 2) small;
5)σi 2Also identical, RiFew;
6)RiAlso identical, next sub-item duration TjLong;
7)TjAlso identical, estimated bias (σj 2) small;
8)σj 2It is identical, RjFew;
9)RjAlso identical, tight preceding sub-item earliest may the time started (ESi) early;
10)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding.
(2) STS:
1) the tight preceding sub-item duration (Ti) long;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, next sub-item duration (Tj) long;
7)TjAlso identical, TjEstimated bias (σj 2) small;
8)σj 2Also identical, RjFew;
9)RjAlso identical, the ES of tight preceding sub-itemiEarly;
10)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding.
(3) FTF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, LTjLong;
5)LTjAlso identical, LTjEstimated bias (σjLT 2) small;
6)σjLT 2Also identical, TjLong;
7)TjAlso identical, TiEstimated bias (σj 2) small;
8)σj 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding.
(4) STF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, TjLong;
7)TjAlso identical, TjEstimated bias (σjt 2) small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding.
(5) STS and FTF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, TjLong;
7)TjAlso identical, TjEstimated bias (σjt 2) small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding;But (Ti-LTi+ LTj)-Tj>=0, it otherwise needs to TjIt optimizes.
(6) STS and STF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σit 2) small;
3)σit 2Also identical, RiFew;
4)RiAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, (LTi'+LTj) long;
7)(LTi'+LTj) also identical, LTi' estimated bias (σI ' LT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
8)(σI ' LT 2jLT 2) also identical, TjLong;
9)TjAlso identical, TjEstimated bias (σjt 2) small;
10)σjt 2Also identical, RjFew;
11)RjAlso identical, ESiEarly;
12)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding;But (LTi'+ LTj)-LTi≥Tj, otherwise need to TjIt optimizes.
(7) FTS and STF:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, TiLong;
4)TiAlso identical, TiEstimated bias (σit 2) small;
5)σit 2Also identical, RiFew;
6)RiAlso identical, TjLong;
7)TjAlso identical, σjt 2Small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, (LTi+LTj) long;
10)(LTi+LTj) also identical, (σiLT 2jLT 2) small;
11)(σiLT 2jLT 2) also identical, ESiEarly;
12)ESiAlso identical, it is tight before sub-item sort in the works in organization and administration with target control it is preceding;But (LTi+LTj)- (Ti+LT)≥Tj, otherwise need to TjIt optimizes.
Note: when the formulation of project organic management and target control plan, do not consider that every " work " unit time mainly provides The requirement in source, by Ri=0 carries out the optimization of duration.
Complete the optimization of " work " time: in no optimizable bonding relation, also without optimizable overlap joint when away from In the case of, to it is tight before sub-item organizational form be FTS or STS;The subitem for being FTS or FTF with next sub-item organizational form Mesh takes technology and organiztion measure, shortens complete subitem object time as much as possible.
Using reversely step by step the duration control, by with it is tight before sub-item organizational form be FTS or STS;With next subitem Sub-item of the mesh organizational form for FTS or FTF, the Time Optimization in second level organization and administration and target control plan, which are realized, to be shortened The purpose of its deadline;
It when optimizable sub-item has multinomial, sorts by the following method, carries out its second level to last sub-item is come The Time Optimization of organization and administration and target control plan:
(1) sub-item time TiLong;
(2)TiIt is identical, σi 2Small;
(3)σi 2Also identical, RiFew;
(4)RiAlso identical, with it is tight before sub-item overlap joint when away from LT or LTqLong;
(5) LT or LTqAlso identical, estimate variance σLT 2Or σqLT 2Small;
(6)σLT 2Or σqLT 2Also identical, RqFew;
(7)RqAlso identical, away from LT or LT when overlap joint with next sub-itemjLong;
(8) LT or LTjAlso identical, estimated bias σLT 2Or σjLT 2Small;
(9)σLT 2Or σjLT 2Also identical, RjFew;
(10)RjAlso identical, time started ESiEarly;
(11)ESiAlso identical, it sorts in the works in project organic management with target control preceding.
The Time Optimization method and sequence of organization and administration Yu the target control plan of second level sub-item:
The optimization of bonding relation is carried out first: taking technology and organiztion measure, the individual event mesh that will successively carry out as much as possible (bonding relation FTS, and the individual event mesh of LT=0) is optimized for overlap joint organizational form, optional STS (LTi)、FTF(LTj)、STF (LTi, LTj), STS and FTF (LTi, LTj), STS and STF (LTi, LTi', LTj), FTS and STF (LT, LTi, LTjOne of); LTi、LTI 'Desirable Ti50%~70%;LTjDesirable Tj50%~70%;
When the individual event mesh successively carried out there are multiple groups, organized between last individual event mesh after sorting by the following method to coming Relationship (bonding relation) optimizes:
(1) tight preceding single Item duration (Ti) long;
(2)TiIt is identical, σi 2Small;
(3)σi 2Also identical, RiFew;
(4)RiAlso identical, then next single Item duration (Tj) long;
(5)TjAlso identical, σj 2Small;
(6)σj 2Also identical, RjFew;
(7)RjAlso identical, then tight preceding individual event mesh earliest may the time started (ESi) early;
(8)ESiAlso when identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding.
Note: when the formulation of project organic management and target control plan, do not consider that every " work " unit time mainly provides The requirement in source, by Ri=0 carries out the optimization of duration.
When being overlapped away from optimization: in the case where no optimizable bonding relation, take technology and organiztion measure, Away from, optimization sequence when shortening overlap joint as much as possible are as follows: FTS (LT ≠ 0) → STS → FTF → STF → STS and FTF → STS with STF → FTS and STF;When can be overlapped by original away from 60%~80% optimize;
When the individual event mesh that identical overlapping mode carries out is by multiple groups, after sorting by the following method, to coming last individual event Away from optimizing when overlap joint between mesh:
(1) (LT ≠ 0) FTS:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, TiLong;
4)TiAlso identical, single Item duration estimated bias (σ before tighti 2) small;
5)σi 2Also identical, RiFew;
6)RiAlso identical, next individual event mesh duration TjLong;
7)TjAlso identical, estimated bias (σj 2) small;
8)σj 2It is identical, RjFew;
9)RjAlso identical, tight preceding individual event mesh earliest may the time started (ESi) early;
10)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding.
(2) STS:
1) tight preceding single Item duration (Ti) long;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, next list Item duration (Tj) long;
7)TjAlso identical, TjEstimated bias (σj 2) small;
8)σj 2Also identical, RjFew;
9)RjAlso identical, tight preceding individual event purpose ESiEarly;
10)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding.
(3) FTF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, LTjLong;
5)LTjAlso identical, LTjEstimated bias (σjLT 2) small;
6)σjLT 2Also identical, TjLong;
7)TjAlso identical, TiEstimated bias (σj 2) small;
8)σj 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding.
(4) STF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, TjLong;
7)TjAlso identical, TjEstimated bias (σjt 2) small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding.
(5) STS and FTF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σi 2) small;
3)σi 2Also identical, RiFew;
4)RiAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, TjLong;
7)TjAlso identical, TjEstimated bias (σjt 2) small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, ESiEarly;
10)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding;But (Ti-LTi+ LTj)-Tj>=0, it otherwise needs to TjIt optimizes.
(6) STS and STF:
1)TiLong;
2)TiIt is identical, TiEstimated bias (σit 2) small;
3)σit 2Also identical, RiFew;
4)RiAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, (LTi'+LTj) long;
7)(LTi'+LTj) also identical, LTi' estimated bias (σI ' LT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
8)(σI ' LT 2jLT 2) also identical, TjLong;
9)TjAlso identical, TjEstimated bias (σjt 2) small;
10)σjt 2Also identical, RjFew;
11)RjAlso identical, ESiEarly;
12)ESiAlso identical, it is tight before individual event mesh sort in the works in organization and administration with target control it is preceding;But (LTi'+ LTj)-LTi≥Tj, otherwise need to TjIt optimizes.
(7) FTS and STF:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, TiLong;
4)TiAlso identical, TiEstimated bias (σit 2) small;
5)σit 2Also identical, RiFew;
6)RiAlso identical, TjLong;
7)TjAlso identical, σjt 2Small;
8)σjt 2Also identical, RjFew;
9)RjAlso identical, (LTi+LTj) long;
10)(LTi+LTj) also identical, (σiLT 2jLT 2) small;
11)(σiLT 2jLT 2) also identical, ESiEarly;12)ESiAlso identical, tight preceding individual event mesh is in organization and administration and target control System sorts preceding in the works.But (LTi+LTj)-(Ti+LT)≥Tj, otherwise need to TjIt optimizes.
Note: when the formulation of project organic management and target control plan, do not consider that every " work " unit time mainly provides The requirement in source, by Ri=0 carries out the optimization of duration.
Complete the optimization of " work " time: in no optimizable bonding relation, also without optimizable overlap joint when away from In the case of, to it is tight before individual event mesh organizational form be FTS or STS;The individual event for being FTS or FTF with next individual event mesh organizational form Mesh takes technology and organiztion measure, shortens complete individual event object time as much as possible;
Use reversely that the duration controls step by step: by with tight preceding individual event mesh organizational form for FTS or STS;With next individual event Mesh organizational form is the individual event mesh of FTS or FTF, in the Time Optimization of three levels of organization's management and target control plan, realizes and shortens The purpose of its deadline;
When optimizable individual event mesh has multinomial, by the following method sequence, carry out its three-level to coming last individual event mesh The Time Optimization of organization and administration and target control plan:
(1) single PROJECT TIME TiLong;
(2)TiIt is identical, σi 2Small;
(3)σi 2Also identical, RiFew;
(4)RiAlso identical, away from LT or LT when being overlapped with tight preceding individual event purposeqLong;
(5) LT or LTqAlso identical, estimate variance σLT 2Or σqLT 2Small;
(6)σLT 2Or σqLT 2Also identical, RqFew;
(7)RqAlso identical, away from LT or LT when being overlapped with next individual event purposejLong;
(8) LT or LTjAlso identical, estimated bias σLT 2Or σjLT 2Small;
(9)σLT 2Or σjLT 2Also identical, RjFew;
(10)RjAlso identical, time started ESiEarly;
(11)ESiAlso identical, it sorts in the works in project organic management with target control preceding.
The Time Optimization method and sequence of the organization and administration of three-level individual event purpose and target control plan:
The optimization of bonding relation is carried out first: being taken technology and organiztion measure, as much as possible (is taken the work successively carried out Relationship is connect as FTS, and the work of LT=0), it is optimized for overlap joint organizational form, optional STS (LTi)、FTF(LTj)、STF(LTi, LTj), STS and FTF (LTi, LTj), STS and STF (LTi, LTi', LTj), FTS and STF (LT, LTi, LTjOne of);LTi、LTI ' Desirable Ti50%~70%; LTjDesirable Tj50%~70%;
When the work successively carried out has multiple groups, by the following method sort after, to come between last work organize close System's (bonding relation) optimizes:
(1) preceding activity duration (ti) long;
(2)tiIt is identical, σi 2Small;
(3)σi 2Also identical, riFew;
(4)riAlso identical, then next run duration (tj) long;
(5)tjAlso identical, σj 2Small;
(6)σj 2Also identical, rjFew;
(7)rjAlso identical, then preceding activity earliest may the time started (ESi) early;
(8)ESiAlso when identical, preceding activity sorts in organization and administration with target control preceding in the works.
Note: when the formulation of project organic management and target control plan, work in every unit time main resource is not considered Requirement, by ri=0 carries out the optimization of duration.
When being overlapped away from optimization: in the case where no optimizable bonding relation, take technology and organiztion measure, Away from, optimization sequence when shortening overlap joint as much as possible are as follows: FTS (LT ≠ 0) → STS → FTF → STF → STS and FTF → STS with STF → FTS and STF;When can be overlapped by original away from 60%~80% optimize;
When identical overlapping mode carry out work have multiple groups when, by the following method sort after, to come last work it Between overlap joint when away from optimizing:
(1) (LT ≠ 0) FTS:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, tiLong;
4)tiAlso identical, preceding activity duration estimated bias (σi 2) small;
5)σi 2Also identical, riFew;
6)riAlso identical, next run duration tjLong;
7)tjAlso identical, estimated bias (σj 2) small;
8)σj 2It is identical, rjFew;
9)rjAlso identical, preceding activity earliest may the time started (ESi) early;
10)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works.
(2) STS:
1) preceding activity duration (ti) long;
2)tiIt is identical, tiEstimated bias (σi 2) small;
3)σi 2Also identical, riFew;
4)riAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, next run duration (tj) long;
7)tjAlso identical, tjEstimated bias (σj 2) small;
8)σj 2Also identical, rjFew;
9)rjAlso identical, the ES of preceding activityiEarly;
10)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works.
(3) FTF:
1)tiLong;
2)tiIt is identical, tiEstimated bias (σi 2) small;
3)σi 2Also identical, riFew;
4)riAlso identical, LTjLong;
5)LTjAlso identical, LTjEstimated bias (σjLT 2) small;
6)σjLT 2Also identical, tjLong;
7)tjAlso identical, tjEstimated bias (σj 2) small;
8)σj 2Also identical, rjFew;
9)rjAlso identical, ESiEarly;
10)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works.
(4) STF:
1)tiLong;
2)tiIt is identical, tiEstimated bias (σi 2) small;
3)σi 2Also identical, riFew;
4)riAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, tjLong;
7)tjAlso identical, tjEstimated bias (σjt 2) small;
8)σjt 2Also identical, rjFew;
9)rjAlso identical, ESiEarly;
10)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works.
(5) STS and FTF:
1)tiLong;
2)tiIt is identical, tiEstimated bias (σi 2) small;
3)σi 2Also identical, riFew;
4)riAlso identical, (LTi+LTj) long;
5)(LTi+LTj) also identical, LTiEstimated bias (σiLT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
6)(σiLT 2jLT 2) also identical, tjLong;
7)tjAlso identical, tjEstimated bias (σjt 2) small;
8)σjt 2Also identical, rjFew;
9)rjAlso identical, ESiEarly;
10)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works;But (ti-LTi+ LTj)-tj>=0, it otherwise needs to tjIt optimizes.
(6) STS and STF:
1)tiLong;
2)tiIt is identical, tiEstimated bias (σit 2) small;
3)σit 2Also identical, riFew;
4)riAlso identical, LTiLong;
5)LTiAlso identical, LTiEstimated bias (σiLT 2) small;
6)σiLT 2Also identical, (LTi'+LTj) long;
7)(LTi'+LTj) also identical, LTi' estimated bias (σI ' LT 2) and LTjEstimated bias (σjLT 2) the sum of it is small;
8)(σI ' LT 2jLT 2) also identical, tjLong;
9)tjAlso identical, tjEstimated bias (σjt 2) small;
10)σjt 2Also identical, rjFew,
11)rjAlso identical, ESiEarly;
12)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works;But (LTi'+LTj)- LTi≥tj, otherwise need to tjIt optimizes.
(7) FTS and STF:
1) LT long;
2) LT is identical, LT estimated bias (σLT 2) small;
3)σLT 2Also identical, tiLong;
4)tiAlso identical, tiEstimated bias (σit 2) small;
5)σit 2Also identical, riFew;
6)riAlso identical, tjLong;
7)tjAlso identical, σjt 2Small;
8)σjt 2Also identical, rjFew;
9)rjAlso identical, (LTi+LTj) long;
10)(LTi+LTj) also identical, (σiLT 2jLT 2) small;
11)(σiLT 2jLT 2) also identical, ESiEarly;
12)ESiAlso identical, preceding activity sorts in organization and administration with target control preceding in the works;But (LTi+LTj)- (ti+LT)≥tj, otherwise need to tjIt optimizes.
Note: when the formulation of project organic management and target control plan, work in every unit time main resource is not considered Requirement, by ri=0 carries out the optimization of duration.
Complete the optimization of working time: in no optimizable bonding relation, also without optimizable overlap joint when away from feelings Under condition, to preceding activity organizational form be FTS or STS;The work for being FTS or FTF with next job engineering mode, takes skill Art and organiztion measure shorten the time for completing work as much as possible;It is optimized by complete the working time 20%~40%;
It when optimizable work has multinomial, sorts by the following method, the work for coming last is optimized:
(1) working time tiLong;
(2)tiIt is identical, σi 2Small;
(3)σi 2Also identical, riFew;
(4)riAlso identical, away from LT or LT when overlap joint with preceding activityqLong;
(5) LT or LTqAlso identical, estimate variance σLT 2Or σqLT 2Small;
(6)σLT 2Or σqLT 2Also identical, rqFew;
(7)rqAlso identical, away from LT or LT when overlap joint with next workjLong;
(8) LT or LTjAlso identical, estimated bias σLT 2Or σjLT 2Small;
(9)σLT 2Or σjLT 2Also identical, rjFew;
(10)rjAlso identical, time started ESiEarly;
(11)ESiAlso identical, it sorts in the works in project organic management with target control preceding.
Note:
(1) when the formulation of project organic management and target control plan, the need of work in every unit time main resource are not considered It measures, by ri=0 carries out the optimization of duration;
(2) in the case where having two or more critical circuits, optimize common line part first;There is no common line part When, critical circuits optimization is carried out one by one in any order;
(3) one step of every optimization, re-starts the calculating of project organic management Yu target control planned time parameter and estimate variance Afterwards, continue to optimize.

Claims (10)

1. a kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system, it is characterised in that: realize an energy Enough abundant Applied Computer Techniques carry out each intermediate item or task using decomposition step by step, the organization and administration of formulation respectively at different levels and target Control plan, using the project organic management and the qualitative work of the target control multistage system of planning that reversely duration control is established step by step The complete scheme of period cost optimization, is realized by following steps:
Below by taking project is decomposed using sub-item step by step, individual event mesh and specific works three-level as an example, by formulating at different levels, each tissue Management and target control plan, using reversely project organic management and the target control multistage system of planning are established in duration control step by step Qualitative Time-cost optimization, specific method of the invention is illustrated:
(1) level of decomposition formulates the level-one organization and administration and target control plan, i.e. project organic management and target control of project Plan;
(2) second level is decomposed, and formulates the second level organization and administration and target control plan, i.e., the organization and administration of each sub-item of project respectively With target control plan;
(3) three-level is decomposed, and formulates the three levels of organization's management and target control plan of project, i.e., each individual event purpose organization and administration respectively With target control plan;
At different levels, each organization and administration and target control plan are formulated by the above process, and the project organization is established using the control of duration step by step Management and the target control multistage system of planning:
Step (1) is equal to zero according to level-one organization and administration and target control plan, with the interval time between crucial sub-item (Lagi-j=0) route is the judgment method of critical circuits, judges level-one organization and administration and the key lines of target control in the works Road;
Step (2) carries out the optimization that membership credentials are FTS and the critical path of LT=0 first;
For step (3) in the case where no membership credentials are FTS and the critical path optimization of LT=0, progress membership credentials are FTS (LT ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS and STF(LT, LTi, LTj) critical path optimization;
Step (4) in the critical path optimization that no membership credentials are FTS and LT=0, also without membership credentials be FTS (LT ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS with STF(LT, LTi, LTj) critical path optimization in the case where, by with it is tight before crucial sub-item bonding relation be FTS or STS, the work with organization and administration Yu target control plan that next crucial sub-item bonding relation is FTS or FTF key sub-item Period cost optimization, reaches the optimization of its sub-item deadline;
Requirement of the step (5) according to the optimization of sub-item deadline, carries out the organization and administration and target control of the second level sub-item The Time-cost optimization of plan:
Step (5-1) is equal to zero (Lag with the interval time between crucial individual event meshi-j=0) route is the judgement of critical circuits Method judges organization and administration and the critical circuits of target control in the works;
Step (5-2) carries out the optimization that membership credentials are FTS and the critical path of LT=0 first;
In the case where no membership credentials are FTS and the critical path optimization of LT=0, carry out membership credentials is step (5-3) FTS (LT ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS and STF(LT, LTi, LTj) critical path optimization;
Step (5-4) is FTS and the critical path optimization of LT=0 in no membership credentials, is also FTS (LT without membership credentials ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS With STF(LT, LTi, LTj) critical path optimization in the case where, by with it is tight before crucial individual event mesh bonding relation be FTS or STS, the organization and administration of crucial individual event purpose and target control plan that are FTS or FTF with next crucial individual event mesh bonding relation Time-cost optimization reaches the optimization of its single project's finish time;
Requirement of the step (6) according to single project's finish time optimization, carries out the organization and administration of the three-level individual event purpose and target control The Time-cost optimization of plan:
Step (6-1) is equal to zero (Lag with the interval time between key jobi-j=0) route is the judgement side of critical circuits Method judges organization and administration and the critical circuits of target control in the works;
Step (6-2) carries out the optimization that membership credentials are FTS and the critical path of LT=0 first;
In the case where no membership credentials are FTS and the critical path optimization of LT=0, carry out membership credentials is step (6-3) FTS (LT ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS and STF(LT, LTi, LTj) critical path optimization;
Step (6-4) is FTS and the critical path optimization of LT=0 in no membership credentials, is also FTS (LT without membership credentials ≠ 0), STS(LTi), FTF(LTj), STF(LTi, LTj), STS and FTF(LTi, LTj), STS and STF(LTi, LTi', LTj), FTS With STF(LT, LTi, LTj) critical path optimization in the case where, carry out with it is tight before key job bonding relation be FTS or STS, With the optimization for the key job deadline that next key job bonding relation is FTS or FTF.
2. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is, the project organization multistage system of planning:
(1) according to project or the type of the decomposed sub-item of task (individual event mesh, specific works), project (sub-item, individual event mesh) It is divided into type, non-type certainly and three kinds of mixed type certainly;
(2) according to when being overlapped between project or the decomposed sub-item of task (individual event mesh, specific works) away from type, project (divides Project, individual event mesh) method for organizing is divided into type, non-type and three kinds of mixed type certainly certainly;
(3) all kinds of project organization multistage system of planning, in the project organization multistage system of planning, at different levels, each organization and administration and target Control plan, comprising:
1) certainly type project (sub-item, individual event mesh), using the organization and administration and target control meter that type method for organizing is formulated certainly It draws;
2) certainly type project (sub-item, individual event mesh), using the non-organization and administration and target control that type method for organizing is formulated certainly Plan;
3) organization and administration and target control certainly type project (sub-item, individual event mesh), formulated using mixing sizing method for organizing Plan;
4) non-affirmative type project (sub-item, individual event mesh), using the organization and administration and target control that type method for organizing is formulated certainly Plan;
5) non-affirmative type project (sub-item, individual event mesh), the organization and administration and target control formulated using non-type method for organizing certainly System plan;
6) non-affirmative type project (sub-item, individual event mesh), the organization and administration and target control formulated using mixing sizing method for organizing System plan;
7) mixed type project (sub-item, individual event mesh), using the organization and administration and target control meter that type method for organizing is formulated certainly It draws;
8) mixed type project (sub-item, individual event mesh), using the non-organization and administration and target control that type method for organizing is formulated certainly Plan;
9) mixed type project (sub-item, individual event mesh), the organization and administration formulated using mixed type method for organizing and target control meter It draws.
3. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is qualitative duration control, refer to by between crucial sub-item (individual event mesh, specific works) bonding relation, take Time, unit time resource requirement, estimate variance needed for being completed when connecing away from, crucial sub-item (individual event mesh, specific works), When estimated bias, overlap joint away from estimated bias, the sequencing of beginning etc., compare selection optimization critical path or crucial subitem The method of mesh (individual event mesh, specific works).
4. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is that step (1), (5-1), (6-1) are described: the interval time between crucial sub-item is equal to zero (Lagi-j=0) route is The judgment method of critical circuits, not only directly by organization and administration and target control plan, judge critical circuits, and can be direct By organize with target control plan, judge critical circuits in day part;Critical circuits be not only by start and ending, The longest continuous line of elapsed time.
5. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is that step (1), (5-1), (6-1) are described: the interval time between crucial sub-item (individual event mesh, work) is equal to zero (Lagi-j=0) route is the judgment method of critical circuits, second level organization and administration with target control in the works, crucial sub-item Organization and administration and the crucial individual event mesh of target control in the works, be the key that second level organization and administration with target control in the works singly Crucial individual event mesh in project and project organic management and the target control multistage system of planning;In three levels of organization's management and mesh Mark in control plan, the organization and administration of crucial individual event purpose and the key job of target control in the works, be three levels of organization's management with Key job in the key job and project organic management and the target control multistage system of planning of target control in the works.
6. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is:
(1) the resource requirement of level-one organization and administration and target control sub-item unit time in the works, is equal to second level tub of tissue Reason and the resource of target control organization and administration Yu the target control plan of sub-item in the works need total amount, divided by the work of sub-item Phase;
(2) the resource requirement of second level organization and administration and target control individual event mesh unit time in the works is equal to three levels of organization and manages The organization and administration of individual event purpose and the resource of target control plan need total amount to reason in the works with target control, divided by individual event purpose work Phase.
7. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is: the project organic management and target control multistage system of planning time parameter and estimation that reversely duration control is established step by step The calculation method of variance:
(1) three-level respectively organizes and the calculating of target control planned time parameter and estimate variance:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, it determines FFi, then calculate TFi、LSiAnd LFi
Note: each individual event purpose organization and administration of three-level and the target duration of target control plan and the estimate variance of target duration;Make The estimate variance with target control individual event purpose duration and duration in the works is respectively organized for second level;
(2) second level respectively organizes and the calculating of target control planned time parameter and estimate variance:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, it determines FFi, then calculate TFi、LSiAnd LFi
Note: the target duration of organization and administration Yu the target control plan of each sub-item of second level and the estimate variance of target duration;Make The estimate variance with the target control duration and duration of sub-item in the works is respectively organized for level-one;
(3) level-one respectively organizes and the calculating of target control planned time parameter and estimate variance:
1) project organic management to tight preceding organizational logical relationship expression and target control plan, calculate ESi、EFi、υi 2
2) to the project organic management of next organizational logical relationship expression and target control plan, Lag is calculatedi-jAfterwards, it determines FFi, then calculate TFi、LSiAnd LFi
8. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is:
(1) sub-item is in level-one organization and administration and target control ES in the worksiEstimate variance, for second level organization and administration and target The estimate variance of the organization and administration of sub-item and target control planned start time in control plan;
(2) individual event mesh is in second level organization and administration and target control ES in the worksiEstimate variance, for three levels of organization management and target The estimate variance of individual event purpose organization and administration and target control planned start time in control plan;
(3) individual event purpose organizes and estimates with target control Projected completion time in the works for three levels of organization's management and target control Variance is counted, for the estimate variance of second level organization and administration and target control single project's finish time in the works;
(4) second level is organized with target control in the works, organization and administration and the target control Projected completion time of sub-item Estimate variance, for the estimate variance of level-one organization and administration and target control sub-item deadline in the works.
9. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is that estimate variance calculates, comprising:
(1) estimated bias of non-(the individual event mesh, work) deadline of type sub-item certainly, the non-type certainly of discontinuous progress are itemized The adjustment of mesh (individual event mesh, work) deadline estimated bias;
(2) it is non-certainly type overlap joint when away from estimated bias;
(3) interval time ES between sub-item (individual event mesh, work)j-EFiFactor etc..
10. the qualitative Time Optimization method of a kind of reversed gradual control multistage organization planning system according to claim 1, special Sign is:
(1) the resource requirement of level-one organization and administration and target control sub-item unit time in the works, is equal to second level tub of tissue Reason and the resource of target control organization and administration Yu the target control plan of sub-item in the works need total amount, divided by the work of sub-item Phase;
(2) the resource requirement of second level organization and administration and target control individual event mesh unit time in the works is equal to three levels of organization and manages The organization and administration of individual event purpose and the resource of target control plan need total amount to reason in the works with target control, divided by individual event purpose work Phase.
CN201910231908.6A 2019-03-26 2019-03-26 A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system Pending CN110334833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910231908.6A CN110334833A (en) 2019-03-26 2019-03-26 A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910231908.6A CN110334833A (en) 2019-03-26 2019-03-26 A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system

Publications (1)

Publication Number Publication Date
CN110334833A true CN110334833A (en) 2019-10-15

Family

ID=68139087

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910231908.6A Pending CN110334833A (en) 2019-03-26 2019-03-26 A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system

Country Status (1)

Country Link
CN (1) CN110334833A (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴开平: "《替代、且显著领先于具有国际先进水平的网络计划技术的统筹法—JQ、JH、(JQ-JH)》", 《"企业创新与知识管理成果征集及评选活动"优秀成果论文集》 *

Similar Documents

Publication Publication Date Title
CN100573576C (en) Real-time analysis of large underground hole group construction speed and control system and method under the network environment
CN110232466A (en) A kind of all kinds of project organization plan resources balance optimization methods of critical path method
CN110232469A (en) A kind of all kinds of minimum optimization methods of project organization plan resource of critical path method
CN111810144B (en) Shale gas well engineering intelligent scheduling method and system
CN110232465A (en) A kind of all kinds of project organization multistage plans of critical path method resources balance optimization method step by step
CN110334833A (en) A kind of qualitative Time Optimization method of reversed gradual control multistage organization planning system
CN110309942A (en) A kind of all kinds of project organization multistage plan main resource plan management methods of critical path method
CN110334831A (en) A kind of qualitative Time Optimization method of the gradual control project organization multistage system of planning
CN110334888A (en) A kind of positive and negative qualitative Time Optimization method of gradual control project organization multistage plan
CN110334830A (en) A kind of qualitative Time-cost optimization application method of all kinds of project organization plans of critical path method
CN110309998A (en) A kind of all kinds of project organization multistage system of planning reviewing methods of critical path method
CN110322043A (en) A kind of critical path method projects combo by project resource at least with relatively minimal optimization method
CN110334834A (en) A kind of qualitative Time-cost optimization method of all kinds of project organization plans of critical path method
CN110232491A (en) A kind of critical path method project organization multistage plan afterbody resources balance optimization method
CN110322041A (en) A kind of any project combined resource limited optimization method of critical path method
CN110232468A (en) A kind of critical path method combination project, which is fallen into a trap, draws a system most rear class resources balance optimization method
CN110334832A (en) A kind of qualitative Time Optimization application method of all kinds of project organization multistage plans of critical path method
CN110335002A (en) A kind of critical path method forms mode project gradual control multistage system of planning method for building up
CN110363324A (en) A kind of any projects combo multistage plan of the critical path method minimum optimization method of resource step by step
CN110322042A (en) A kind of critical path method project organization multistage system of planning duration resource dynamic reviewing method
CN110309941A (en) A kind of each intermediate item any combination resource comprehensive optimization method of critical path method
CN110309999A (en) A kind of each intermediate item any combination main resource plan management method of critical path method
CN110334836A (en) A kind of critical path method combination project is fallen into a trap the system of drawing resources balance optimization method step by step
CN110334889A (en) Organization planning's resources balance optimization method in a kind of critical path method combination project
CN110322101A (en) A kind of all kinds of project organization multistage system of planning resource limited optimization methods of critical path method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant after: Jinan senkun Technology Co.,Ltd.

Address before: 250014 11-2-501, No.7 Zhuanshan West Road, Lixia District, Jinan City, Shandong Province

Applicant before: Jinan Senkun Enterprise Management Consulting Co.,Ltd.

CB02 Change of applicant information