CN110219216A - A kind of construction method of town road and abutment backfill based on foam concrete - Google Patents

A kind of construction method of town road and abutment backfill based on foam concrete Download PDF

Info

Publication number
CN110219216A
CN110219216A CN201910470707.1A CN201910470707A CN110219216A CN 110219216 A CN110219216 A CN 110219216A CN 201910470707 A CN201910470707 A CN 201910470707A CN 110219216 A CN110219216 A CN 110219216A
Authority
CN
China
Prior art keywords
foam concrete
foam
concrete
town road
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910470707.1A
Other languages
Chinese (zh)
Other versions
CN110219216B (en
Inventor
马栋
朱卫东
孙成龙
丁传峰
赵永亮
李慧
刘彬
肖春雷
高志
朱开荣
张志勇
李明
刘向楠
陈亚强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Original Assignee
China Railway 16th Bureau Group Co Ltd
Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Fifth Engineering Co Ltd of China Railway 16th Bureau Group Co Ltd filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201910470707.1A priority Critical patent/CN110219216B/en
Publication of CN110219216A publication Critical patent/CN110219216A/en
Application granted granted Critical
Publication of CN110219216B publication Critical patent/CN110219216B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B38/00Porous mortars, concrete, artificial stone or ceramic ware; Preparation thereof
    • C04B38/10Porous mortars, concrete, artificial stone or ceramic ware; Preparation thereof by using foaming agents or by using mechanical means, e.g. adding preformed foam
    • C04B38/106Porous mortars, concrete, artificial stone or ceramic ware; Preparation thereof by using foaming agents or by using mechanical means, e.g. adding preformed foam by adding preformed foams
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00034Physico-chemical characteristics of the mixtures
    • C04B2111/00146Sprayable or pumpable mixtures
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/0075Uses not provided for elsewhere in C04B2111/00 for road construction
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/20Resistance against chemical, physical or biological attack
    • C04B2111/2038Resistance against physical degradation
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/20Resistance against chemical, physical or biological attack
    • C04B2111/27Water resistance, i.e. waterproof or water-repellent materials
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/20Resistance against chemical, physical or biological attack
    • C04B2111/28Fire resistance, i.e. materials resistant to accidental fires or high temperatures
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/40Porous or lightweight materials
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/52Sound-insulating materials

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Structural Engineering (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses the construction methods that a kind of town road based on foam concrete and abutment backfill, and include the following steps: to obtain cement slurry after being mixed and stirred for cement, light-weight aggregate and water;Foaming agent is sufficiently foamed using foaming machine and obtains foam;Obtained foam is mixed with cement slurry, obtains foam concrete;Obtained foam concrete is directly pumped, is poured using merogenesis segmented mode;After pouring foam concrete in 3~12h, foam concrete is conserved using covering straw pulp, reed pad, gunnysack, sawdust, wet soil or damp sand soil and by the way of watering, the curing time of foam concrete is no less than 7 days.The construction method improves the uneven subsidence of roadbed and bridge by the way that foam concrete is applied to town road and abutment backfill;The globality that single layer of wires net improves foam concrete is installed in foam concrete.

Description

A kind of construction method of town road and abutment backfill based on foam concrete
Technical field
The present invention relates to technical field of road engineering, it particularly relates to a kind of town road based on foam concrete And the construction method of abutment backfill.
Background technique
Foam cohesion is a kind of mechanical means that bubble solution is added in bubble, and foam is injected cement, is gathered materials, outside Add in slurry made of agent, water and various additives, is then mixed, forms and keeps light porous material.Foam cohesion Body has good heat-proof quality due to its unique pore structure, compared with traditional materials, with light-weight, body is hard, fire resisting The features such as.
Due to traditional concrete exist from great, tensile strength is low, crack resistance is poor, the feature of environmental protection is poor, contraction distortion greatly , often there is differential settlement in problem between roadbed and bridge, road pavement quality impacts.
Summary of the invention
For above-mentioned technical problem in the related technology, the present invention propose a kind of town road based on foam concrete and The construction method of abutment backfill, can overcome the above-mentioned deficiency of the prior art.
To realize the above-mentioned technical purpose, the technical scheme of the present invention is realized as follows:
A kind of construction method of town road and abutment backfill based on foam concrete, includes the following steps:
(1) production of cement slurry obtains cement slurry after being mixed and stirred for cement, light-weight aggregate and water in blender, will obtain Cement slurry be stored in the tank with agitating function, to avoid cement slurry precipitating;
(2) foam is produced, and foaming agent is sufficiently foamed using foaming machine and obtains foam, and the density of the foam is 40-60 kilograms/ Cubic meter, foam dilution rate are 40-60, and foam rate is greater than 20 times;
(3) foam that step (2) obtains is mixed with the cement slurry that step (1) obtains, obtains foam by the production of foam concrete Concrete;
(4) foam concrete that step (3) obtains directly is pumped, is poured using merogenesis segmented mode, 10~15m by pouring construction For a segment, foam concrete single layer is poured with a thickness of 0.3~0.8m, sets subsiding crack between segment, subsiding crack uses with a thickness of 1 The plank sheathing of~2cm is poured and is a little expanded by center around or poured using multiple spot;
(5) foam concrete conserves, after pouring foam concrete in 3~12h, using covering straw pulp, reed pad, gunnysack, saw End, wet soil or damp sand soil and water mode conserve foam concrete, the curing time of foam concrete is no less than 7 days.
Further, the strength grade of cement described in step (1) is 42.5 or 42.5 or more.
Further, storage time of the cement slurry in tank described in step (1) is no more than 2 hours.
Further, the retention time of foam described in step (2) is no more than 20 minutes.
Further, in step (4) foam concrete bottom installation single layer steel wire, the steel wire is arranged in 50cm Hereinafter, the steel wire netting wire spacing is 5cm, steel wire diameter is 3.2mm in the steel wire, and the steel wire overlap length is 20cm。
Further, in the step (5), when temperature is at 15 DEG C or more, in three days after foam concrete pours, It answers at least every three hours of daily daytime to pour a water, pours water twice at night, at least pour water three times daily in subsequent maintenance.
Beneficial effects of the present invention: mixed using foam by the way that foam concrete is applied to town road and abutment backfill Solidifying soil lightweight, heat preservation, sound insulation, fire resisting, integrality is good, elasticity is low, damping, waterproof, durable, environmentally friendly, easy for construction etc. many excellent Benign energy, improves the uneven subsidence of roadbed and bridge;Single layer of wires net is installed in foam concrete and improves foam The globality of concrete.
Detailed description of the invention
It in order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only some implementations of the invention Example, for those of ordinary skill in the art, without creative efforts, can also obtain according to these attached drawings Obtain other attached drawings.
Fig. 1 is the construction method using town road and abutment backfill described in the embodiment of the present invention based on foam concrete Soft Roadbed light foam concrete earthing change and fill out schematic cross-sectional view;
Fig. 2 is the schematic diagram using the abutment backfill of conventional backfill;
Fig. 3 is the schematic diagram backfilled using the abutment of foam concrete;
In figure: 1, foam concrete, 2, banket, 3, road surface structare layer, 4, road surface, 5, steel wire, 6, bridge floor, 7, abutment, 8, road Base.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, those of ordinary skill in the art's every other embodiment obtained belong to what the present invention protected Range.
The town road based on foam concrete and the construction method of abutment backfill are applied according to embodiments of the present invention Preparation before work includes:
The requirement of field condition, design drawing is familiar with, according to construction drawing and project manager's organization material, equipment, construction personnel; According to construction plan and technical stipulation, operating personnel should submit technical data and job instruction, and work out by site requirement;The palm The performance and technical indicator of foam concrete used in this engineering are held, and carries out crucial control;Complete foam concrete construction technology Inspection record in the inspection and work progress of data;Construction site must solve the warehouse of material, equipment storage;Check construction Whether basal plane Equipment Foundations, line pipe etc. are installed in place;Check whether the absolute altitude of formation level is correct;Foam concrete construction is opened Before beginning, changes and fill out basic Ying Wuming water.
Base treatment: it by sundries, barrier cleaning, cleans up.
The town road based on foam concrete and the construction method packet of abutment backfill according to embodiments of the present invention Include following steps:
(1) production of cement slurry obtains cement slurry after being mixed and stirred for cement, light-weight aggregate and water in blender, will obtain Cement slurry be stored in the tank with agitating function, to avoid cement slurry precipitating.Wherein, the strength grade of cement is 42.5MPa;Cement slurry chinese raw materials proportion is mainly determined according to the bulk density of the requirement of detailed programs, intensity.
Foam concrete filling main raw material(s) be exactly cement, because filling construction usually be all carry out at normal temperature, Gu The gelatification mainly by cement is steeped, so cement slurry chinese raw materials match ratio must be matched based on cement using high cement Proportion.700kg/m3The foam concrete packing material of following bulk density, the proportional quantity of cement cannot be below material in cement slurry The 70% of total amount.When bulk density is in 500kg/m3When following, the room temperature proportional quantity of cement should account for about the 90% of material total amount in cement slurry More than.
Light-weight aggregate should not be designed or designed less in cement-slurry method, because it will affect the initial set of slurry, when dosage is larger When, in some instances it may even be possible to it will cause the mould that collapses.The maximum following foam concrete of additive amount A07 of light-weight aggregate is not to be exceeded the 20% of cement amount; The 40% of cement amount is not to be exceeded in A09 or less;A12 or less no more than cement amount 50%.
Ratio of water to material is the ratio of water and various dry material total values, and ratio of water to material will not only meet the needs of hydrated reaction of cement, Also to meet the needs of stirring and moulding by casting.Ideal ratio of water to material should be that cement slurry can easily be mixed into foam, be mixed into Slurry is only dilute after foam, that is, is easy casting, and will not influence the stability of casting.
The stirring of cement slurry should be carried out according to building adjustment report and the technological parameter determined, to ensure stirring for each ingredient It mixes uniformly;Storage time of the cement slurry in tank is no more than 2 hours.
(2) foam is produced, and foaming agent is sufficiently foamed using foaming machine and obtains foam, and the density of the foam is 40-60 Kilograms per cubic meter, foam dilution rate is 40-60, and foam rate is greater than 20 times, and foam diameter should control within 1mm, and elasticity is good, It is not easy to break.Foaming agent is used for the physical property of the test foaming agent before foam concrete is constructed.Foam should be combined with production It uses, the retention time of foam is no more than 20 minutes.By compressed air by foam compression at foaming agent solution, it is adjusted and steady Determine coefficient of foaming.The defoamed ratio and sedimentation rate of light-weight soils can be used before meeting design requirement.
(3) foam that step (2) obtains is mixed with the cement slurry that step (1) obtains, is obtained by the production of foam concrete Foam concrete;
(4) pouring construction directly pumps the foam concrete that step (3) obtains, because this engineering actual conditions and special want It asks, needs layering, excavation section by section and backfill, segmented to pour to adapt to longitudinal slope, 10~15m is a segment, foam concrete list Layer pours with a thickness of 0.3~0.8m, and subsiding crack is set between segment, and the plank sheathing that subsiding crack uses with a thickness of 1~2cm pours a little Expanded around by center or is poured using multiple spot;In the construction of level of ground water, interim dewatering measure should be taken, guarantees ground Not ponding.In the case where foam concrete curing period being no less than 3 days, when construction, which reaches anti-floating, to be required, interim drop should be cancelled Water measure.
The engineering of water supply must use pipeline pump.Before conveying pump, tightly whether, sealing joint is or not confirmation pipe joint It divulges.The pressure of pump feed trumpet should meet the needs of superior and distance.It's 30 minutes or more dead time has past main shaft process, and Shi Qingli pipeline.When cleaning pipeline, on the basis of pipeline output.When overstocking lifebuoy when upper end is watered, need absorbing people When work cleans, upper layer is accumulated at once.
During assisting in, foam concrete, mobile foam concrete or transportable concrete not can be reduced.The single area Fu Zhou Construction time to be controlled within the cement end time.When pouring foam concrete, shareholder wants on your toes and vigilance, Bu Nengcong It gets off above.Nozzle should be not less than 10cm, in foam concrete to reduce the antifoam performance of foam concrete.It pours a little Panel and templates for expansion joints should not be directly hit, in order to avoid panel bottom and seam crossing leakage.
When casting, outlet should be embedded in foam concrete.When requiring cannot meet the requirements, the height of outlet and pour point Difference should control within 1m, and the duration of pouring in the area Dan Jiao should be controlled in cement slurry initial set.When pouring layer initial set, upper layer can be carried out Construction.In the construction process, during heavy rain or heavy rain, non-hardened foam concrete surface should take interim rain-proof measure.
50cm single layer of wires net is installed in 1 bottom of foam concrete, and single layer of wires net is arranged in 50cm or less.Steel wire spacing For 5 cm*5 cm, diameter is 3.2 mm, and steel wire overlap length is 20 cm.
The intensity of foam concrete reaches design strength and is directly accessed.
(5) foam concrete conserves, according to environment temperature, after pouring foam concrete in 3~12h, using covering grass Slurry, reed pad, gunnysack, sawdust, wet soil or damp sand soil and water mode conserve foam concrete, portland cement, ordinary silicon Acid salt cement is mixed with concrete, cement with water, and the curing time of foam concrete is no less than 7 round the clock.There is retarder or impervious It is required that concrete, round the clock must not be less than 14 days;When using bauxite cement, it must not be less than 3 days round the clock.When temperature 15 DEG C with When upper, in three days three nights after concreting, a water should be poured at least every three hours daily, and water twice be poured at night, rear Water (certainly, when temperature is dry, can suitably increase irrigation times) three times is at least poured in continuous maintenance daily.For large area (or Large volume) concrete, Ying Caiyong " water storing conservation ".For a kind of reservoir, internal model is removed, it, can be with after reaching some strength Maintain water.For underground structure or basis, asphalt emulsion can be sprayed again on surface or be filled with soil, rather than be spilt Water curing.
Plastic film maintenance refers to that concrete is not evaporated by plastic film covering and air separation, moisture, in concrete The aquation of moisture is the condensation and hardening of cement.This method can directly use plastics drawing-off oversite concrete surface, or mixed Solidifying soil component surface painted plastic lotion, until lotion is evaporated, in concrete surface formation plastic foil, thus by concrete component With air separation, thus make condense soil in moisture will not change.The shortcomings that plastics spray film maintenance is coagulation in 28 days Native intensity has dropped 8% or so, and due to the formation of plastics spray film, the effect for keeping the temperature and freezing cannot be fully achieved.Therefore, in the summer It in season, needs to add solar protection installation (no less than for 24 hours) in the method, otherwise can cause the Filamentous crack of foam concrete.
Fig. 1 is the construction method using town road and abutment backfill described in the embodiment of the present invention based on foam concrete Soft Roadbed light foam concrete earthing change and fill out schematic cross-sectional view, 1 lower section of foam concrete and two sides are to banket 2, bubble The top of foam concrete 1 is road surface structare layer 3, and the top of road surface structare layer 3 is road surface 4, the top and bottom of foam concrete 1 Provided with steel wire 5.
Fig. 2 is using the schematic diagram of the abutment backfill of conventional backfill, and the lower section of bridge floor 6 is provided with abutment 7, under road surface 4 Side is conventional backfill roadbed 8, and the differential settlement phenomenon between the abutment of the structure is more serious.
Fig. 3 is the schematic diagram backfilled using the abutment of foam concrete;It is segmented using foam concrete 1 below road surface 4 It is poured, relative settlement is obviously improved between abutment.
In conclusion by means of above-mentioned technical proposal of the invention, by by foam concrete be applied to town road and Abutment backfill, using foam concrete lightweight, heat preservation, sound insulation, fire resisting, integrality is good, elasticity is low, damping, waterproof, durable, ring Many excellent performances such as guarantor, easy for construction, improve the uneven subsidence of roadbed and bridge;It is installed in foam concrete single Layer steel wire improves the globality of foam concrete.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (6)

1. a kind of construction method of town road and abutment backfill based on foam concrete, which is characterized in that including walking as follows It is rapid:
(1) production of cement slurry obtains cement slurry after being mixed and stirred for cement, light-weight aggregate and water in blender, will obtain Cement slurry be stored in the tank with agitating function, to avoid cement slurry precipitating;
(2) foam is produced, and foaming agent is sufficiently foamed using foaming machine and obtains foam, and the density of the foam is 40-60 kilograms/ Cubic meter, foam dilution rate are 40-60, and foam rate is greater than 20 times;
(3) foam that step (2) obtains is mixed with the cement slurry that step (1) obtains, obtains foam by the production of foam concrete Concrete;
(4) foam concrete that step (3) obtains directly is pumped, is poured using merogenesis segmented mode, 10~15m by pouring construction For a segment, foam concrete single layer is poured with a thickness of 0.3~0.8m, sets subsiding crack between segment, subsiding crack uses with a thickness of 1 The plank sheathing of~2cm is poured and is a little expanded by center around or poured using multiple spot;
(5) foam concrete conserves, after pouring foam concrete in 3~12h, using covering straw pulp, reed pad, gunnysack, saw End, wet soil or damp sand soil and water mode conserve foam concrete, the curing time of foam concrete is no less than 7 days.
2. the construction method of the town road and abutment backfill according to claim 1 based on foam concrete, feature It is, the strength grade of cement described in step (1) is 42.5MPa or 42.5MPa or more.
3. the construction method of the town road and abutment backfill according to claim 1 based on foam concrete, feature It is, storage time of the cement slurry in tank described in step (1) is no more than 2 hours.
4. the construction method of the town road and abutment backfill according to claim 1 based on foam concrete, feature It is, the retention time of foam described in step (2) is no more than 20 minutes.
5. the construction method of the town road and abutment backfill according to claim 1 based on foam concrete, feature It is, the steel wire of foam concrete bottom installation single layer, the steel wire are arranged in 50cm hereinafter, the steel in step (4) Silk screen steel wire spacing is 5cm, and steel wire diameter is 3.2mm in the steel wire, and the steel wire overlap length is 20cm.
6. the construction method of the town road and abutment backfill according to claim 1 based on foam concrete, feature It is, in the step (5), when temperature is at 15 DEG C or more, in three days after foam concrete pours, answers daily daytime extremely It pours a water within few every three hours, pours water twice at night, at least pour water three times daily in subsequent maintenance.
CN201910470707.1A 2019-05-31 2019-05-31 Construction method for municipal road and abutment backfilling based on foam concrete Active CN110219216B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910470707.1A CN110219216B (en) 2019-05-31 2019-05-31 Construction method for municipal road and abutment backfilling based on foam concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910470707.1A CN110219216B (en) 2019-05-31 2019-05-31 Construction method for municipal road and abutment backfilling based on foam concrete

Publications (2)

Publication Number Publication Date
CN110219216A true CN110219216A (en) 2019-09-10
CN110219216B CN110219216B (en) 2021-06-29

Family

ID=67819242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910470707.1A Active CN110219216B (en) 2019-05-31 2019-05-31 Construction method for municipal road and abutment backfilling based on foam concrete

Country Status (1)

Country Link
CN (1) CN110219216B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112010669A (en) * 2020-07-30 2020-12-01 中铁十四局集团隧道工程有限公司 Underground cavity filling method and system
CN112627166A (en) * 2020-12-10 2021-04-09 广东佛山地质工程勘察院 Foam concrete backfill operation method and system for civil air defense engineering
CN112811855A (en) * 2020-07-03 2021-05-18 苏州望意阳环保科技有限公司 High-strength multifunctional light foam concrete
CN112900175A (en) * 2021-01-19 2021-06-04 华振贵 Road widening structure and construction method thereof
CN112900174A (en) * 2021-01-19 2021-06-04 华振贵 Soft foundation replacement structure and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268043A (en) * 1996-04-02 1997-10-14 Toutetsu Kogyo Kk Lightweight bubbled grout material and its application
CN104119101A (en) * 2014-07-29 2014-10-29 中冶建工集团有限公司 Cast-in-place light-weight foamed concrete construction technique
CN105000845A (en) * 2015-06-29 2015-10-28 河南华泰建材开发有限公司 Light foamed soil for abutment back backfilling and construction method
CN105019326A (en) * 2015-06-29 2015-11-04 河南华泰建材开发有限公司 Roadbed structure applied to road widening and construction method
CN105155383A (en) * 2015-07-31 2015-12-16 中交二公局第三工程有限公司 Construction process of bubble light soil
CN105481325A (en) * 2015-12-17 2016-04-13 东南大学 Rapid hardening early strength type foam concrete and preparation method thereof
CN108797249A (en) * 2018-04-28 2018-11-13 广西驰胜农业科技有限公司 The construction method of soft soil roadbed high roadbed steep slope road section Foam lightweight soil
CN109653049A (en) * 2018-12-18 2019-04-19 中铁十五局集团第工程有限公司 The construction method in approach fill section in a kind of soft ground treatment

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268043A (en) * 1996-04-02 1997-10-14 Toutetsu Kogyo Kk Lightweight bubbled grout material and its application
CN104119101A (en) * 2014-07-29 2014-10-29 中冶建工集团有限公司 Cast-in-place light-weight foamed concrete construction technique
CN105000845A (en) * 2015-06-29 2015-10-28 河南华泰建材开发有限公司 Light foamed soil for abutment back backfilling and construction method
CN105019326A (en) * 2015-06-29 2015-11-04 河南华泰建材开发有限公司 Roadbed structure applied to road widening and construction method
CN105155383A (en) * 2015-07-31 2015-12-16 中交二公局第三工程有限公司 Construction process of bubble light soil
CN105481325A (en) * 2015-12-17 2016-04-13 东南大学 Rapid hardening early strength type foam concrete and preparation method thereof
CN108797249A (en) * 2018-04-28 2018-11-13 广西驰胜农业科技有限公司 The construction method of soft soil roadbed high roadbed steep slope road section Foam lightweight soil
CN109653049A (en) * 2018-12-18 2019-04-19 中铁十五局集团第工程有限公司 The construction method in approach fill section in a kind of soft ground treatment

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
罗旋: "轻质泡沫混凝土施工", 《轻质泡沫混凝土在软基路基处理中应用研究》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112811855A (en) * 2020-07-03 2021-05-18 苏州望意阳环保科技有限公司 High-strength multifunctional light foam concrete
CN112010669A (en) * 2020-07-30 2020-12-01 中铁十四局集团隧道工程有限公司 Underground cavity filling method and system
CN112627166A (en) * 2020-12-10 2021-04-09 广东佛山地质工程勘察院 Foam concrete backfill operation method and system for civil air defense engineering
CN112627166B (en) * 2020-12-10 2022-06-24 广东佛山地质工程勘察院 Foam concrete backfill operation method and system for civil air defense engineering
CN112900175A (en) * 2021-01-19 2021-06-04 华振贵 Road widening structure and construction method thereof
CN112900174A (en) * 2021-01-19 2021-06-04 华振贵 Soft foundation replacement structure and construction method thereof

Also Published As

Publication number Publication date
CN110219216B (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN110219216A (en) A kind of construction method of town road and abutment backfill based on foam concrete
CN101985882B (en) Construction method of rigid primary support of mould-building concrete of plateau permafrost tunnel
CN102776897B (en) Wash apron anti-settling anti-cracking construction method and structure
CN103321257A (en) Anti-cracking seepage-proof construction method for ultra-long mass concrete structure basement
CN102926398B (en) A kind of for Salt Lake Area iron tower of power transmission line bolts of inclined column type anti-corrosion foundation construction method
CN106759126B (en) Construction method of side slope support drainage channel
CN106988164A (en) Platy ballastless track structure and its construction method
CN103556830A (en) Controllable cast-in-place foam concrete roof construction method
CN104472254A (en) Root-blocking waterproof roof planting system and construction method thereof
CN105271916B (en) Waterproof reinforcing agent, water proofing property foam concrete and roof waterproof system
CN103302919B (en) Light reinforced composite floating plate for preventing water level from evaporating
CN100410470C (en) Permanently waterproof and green roofing
CN103615076B (en) The oblique roofing concrete construction method of a kind of heavy grade
CN108059476A (en) A kind of permeable concrete and preparation method thereof
CN109424054A (en) The technique constructed in construction to storm sewer
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN106555371B (en) Garden large area pervious concrete road construction technique
CN109594449A (en) Snow-ice melting system system and its construction method
CN107586068A (en) A kind of construction method of column concrete and concrete column
CN113417310A (en) Construction method for foundation of column cap type elevator
CN207794117U (en) A kind of foundation base configuration
CN203174899U (en) Slope finding and heat preservation integrated roof building construction
CN207452913U (en) A kind of light-weight foamed concrete backfill bridge pier structure
CN207265620U (en) A kind of cable installation support of armored concrete electric power pipe trench
CN205475308U (en) Adopt quick set to build in precast concrete rigidity stub basis of material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Ma Dong

Inventor after: Zhu Kairong

Inventor after: Zhang Zhiyong

Inventor after: Li Ming

Inventor after: Liu Xiangnan

Inventor after: Chen Yaqiang

Inventor after: Zhu Weidong

Inventor after: Sun Chenglong

Inventor after: Ding Chuanfeng

Inventor after: Zhao Yongliang

Inventor after: Li Hui

Inventor after: Liu Bin

Inventor after: Xiao Chunlei

Inventor after: Gao Zhi

Inventor before: Ma Dong

Inventor before: Zhu Kairong

Inventor before: Zhang Zhiyong

Inventor before: Li Ming

Inventor before: Liu Xiangnan

Inventor before: Chen Yaqiang

Inventor before: Zhu Weidong

Inventor before: Sun Chenglong

Inventor before: Ding Chuanfeng

Inventor before: Zhao Yongliang

Inventor before: Li Hui

Inventor before: Liu Bin

Inventor before: Xiao Chunlei

Inventor before: Gao Zhi

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant