CN113417310A - Construction method for foundation of column cap type elevator - Google Patents

Construction method for foundation of column cap type elevator Download PDF

Info

Publication number
CN113417310A
CN113417310A CN202110613633.XA CN202110613633A CN113417310A CN 113417310 A CN113417310 A CN 113417310A CN 202110613633 A CN202110613633 A CN 202110613633A CN 113417310 A CN113417310 A CN 113417310A
Authority
CN
China
Prior art keywords
column
pouring
concrete
cap
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110613633.XA
Other languages
Chinese (zh)
Inventor
刘帅
毕海超
杨念昆
徐苏苏
李智渊
姚立超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd, Fourth Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltc filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202110613633.XA priority Critical patent/CN113417310A/en
Publication of CN113417310A publication Critical patent/CN113417310A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Abstract

The invention discloses a construction method of a column cap type elevator foundation, which comprises the following steps: and (5) cleaning the original soil surface at the bottom of the foundation pit. Raft construction, the reinforcement of raft is carried out on foundation ditch bottom surface, template installation is carried out after the ligature finishes, concrete placement is carried out after template installation finishes, it is closely knit to ensure to vibrate during pouring, in time cover the maintenance after pouring the completion. The post construction, the ligature of post reinforcing bar is carried out at raft board top, carries out the template mounting after the ligature finishes, carries out concrete placement after the template mounting finishes, and it is closely knit to guarantee to vibrate during pouring, in time covers the maintenance after pouring the completion. And backfilling earthwork in the foundation pit until the earthwork is above the column, and compacting the backfilled soil above the column within the range of 500 mm. And excavating the position of the column cap, excavating a column cap groove for placing the column cap at the top of the column, and timely erecting a template after the excavation is finished. And (5) constructing the column cap, and constructing the column cap at the top of the column. Installing a lifter; the construction safety is improved, and the economic benefit is improved.

Description

Construction method for foundation of column cap type elevator
Technical Field
The invention belongs to the technical field of construction methods, and particularly relates to a construction method of a column cap type elevator foundation.
Background
The arrangement of the construction elevator is to be close to the main building, the construction elevator is inevitably located in the range of the fertilizer tank, and if the foundation of the construction elevator is settled or inclined due to poor backfilling quality of earthwork units which are not controlled by the main package, the safety of the elevator is greatly reduced. In order to solve the problem, graded sandstone is often adopted during backfilling, but the backfilling volume of the graded sandstone is large, and the manufacturing cost is often higher.
Disclosure of Invention
Therefore, the invention provides a construction method of a column cap type elevator foundation, which aims to solve the problem of dangerous construction of an elevator caused by settlement or collapse of an elevator foundation supporting point in the prior art.
In order to achieve the above purpose, the invention provides the following technical scheme: a construction method of a column cap type elevator foundation comprises the following steps:
and (5) cleaning the original soil surface at the bottom of the foundation pit.
Raft construction, the reinforcement of raft is carried out on foundation ditch bottom surface, template installation is carried out after the ligature finishes, concrete placement is carried out after template installation finishes, it is closely knit to ensure to vibrate during pouring, in time cover the maintenance after pouring the completion.
The post construction, the ligature of post reinforcing bar is carried out at raft board top, carries out the template mounting after the ligature finishes, carries out concrete placement after the template mounting finishes, and it is closely knit to guarantee to vibrate during pouring, in time covers the maintenance after pouring the completion.
And backfilling earthwork in the foundation pit until the earthwork is above the column, and compacting the backfilled soil above the column within the range of 500 mm.
And excavating the position of the column cap, excavating a column cap groove for placing the column cap at the top of the column, and timely erecting a template after the excavation is finished.
And (5) constructing the column cap, and constructing the column cap at the top of the column.
And (5) installing a lifter.
Furthermore, the position of the column rib joint is staggered by a distance of more than 500mm in the column construction, and the upper part of the column rib joint is provided with a 12d bend.
Furthermore, the column hoop in the column construction adopts double steel pipes.
Furthermore, the side edge of the column is tightly supported by an inclined strut.
Further, the concrete is cast by using C30 concrete.
Furthermore, the strength of the concrete poured during the form removal is not lower than 1.2 MPa.
Furthermore, the earth is uniformly backfilled around the column during backfilling, so that the column is prevented from being affected by horizontal load.
Furthermore, should establish the full-time staff of seeing the mould at the in-process of pouring, the template appears leaking thick liquid, the slope scheduling problem should in time be corrected, pours the in-process and pays attention to the concrete and vibrates, ensures that the concrete shaping is closely knit.
The invention has the following advantages:
1. because the main stress position of the elevator is the standard knot position, a concrete structure column is arranged below the standard knot position to be matched with the bottom raft plate so as to bear the main load of the elevator. The upper part is provided with a column cap which is mainly used for bearing the dead weight of the plate and the corresponding live load. The structure of the elevator is stable and does not settle or incline, and the operation safety of the elevator is ensured.
2. Traditional graded gravel backfilling is poor in structural stability and high in uncertainty, is limited by the quality of backfilling, can be settled in rainy seasons and the like, and cannot guarantee safe and stable operation of the elevator. By adopting the construction method, the quality of the backfill soil does not need to be considered, and the safety of the lifter is ensured.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
The structures, ratios, sizes, and the like shown in the present specification are only used for matching with the contents disclosed in the specification, so as to be understood and read by those skilled in the art, and are not used to limit the conditions that the present invention can be implemented, so that the present invention has no technical significance, and any structural modifications, changes in the ratio relationship, or adjustments of the sizes, without affecting the effects and the achievable by the present invention, should still fall within the range that the technical contents disclosed in the present invention can cover.
FIG. 1 is a flow chart of the construction method of the present invention.
Fig. 2 is a schematic view of the frame structure of the present invention.
Detailed Description
The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings and the detailed description, but those skilled in the art will understand that the following described embodiments are some, not all, of the embodiments of the present invention, and are only used for illustrating the present invention, and should not be construed as limiting the scope of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Examples
The present embodiment provides a method for constructing a foundation of a cap-type elevator, as shown in fig. 1, including:
s101, cleaning the original soil surface at the bottom of the foundation pit.
S102, raft construction, namely binding reinforcing steel bars of the raft on the surface of the bottom of the foundation pit, installing a template after binding is finished, pouring concrete after template installation is finished, ensuring that the concrete is compacted during pouring, and timely covering and maintaining after pouring is finished. Should guarantee during raft construction that the reinforcement interval is accurate, upper and lower floor's reinforcement interval guarantees to meet the requirements, and the template is erected and is supposed to guarantee the straightness that hangs down to should guarantee not to leak thick liquid, collapse when pouring. C30 concrete is adopted, so that the vibration is ensured to be compact during pouring, and the concrete is covered and maintained in time after pouring is finished.
S103, column construction, namely binding column reinforcing steel bars at the top of the raft, installing templates after binding, pouring concrete after template installation, ensuring that the concrete is compacted during pouring, and timely covering and maintaining after pouring.
The column reinforcement joint is guaranteed to be staggered by a distance of more than 500mm, the upper portion is provided with 12d bending, and the stirrup interval meets the requirement. The column template should guarantee that the straightness that hangs down accords with standard requirement, and the column hoop should adopt two steel pipes. The interval is 500mm, and the side adopts the bracing top tight, guarantees the stability of template. The post adopts C30 concrete placement, and post concrete placement should establish the full-time staff of seeing the mould to cap bottom elevation position, pours the in-process, and the template appears leaking thick liquid, the slope scheduling problem should in time be corrected, pours the in-process and notices the concrete and vibrates, ensures that the concrete shaping is closely knit. And (3) removing the column template when the concrete strength of the column is not lower than 1.2MPa after pouring is finished, and timely maintaining the column after removal.
And S104, backfilling earthwork in the foundation pit until the earthwork is above the column, and compacting the backfilled soil above the column within the range of 500 mm.
When the earthwork is backfilled, the periphery of the column is backfilled uniformly to ensure that the column is not influenced by horizontal load, the column is backfilled to the top to design the elevation of the bottom of the column cap, and the top is compacted within the range of 500 mm.
And S105, excavating the position of the column cap, excavating a column cap groove for placing the column cap at the top of the column, and timely erecting a template after the excavation is finished. Adopting manual excavation operation at the top beam position, and excavating the column cap position to a designed bottom elevation (reserved template thickness); the size of the column cap is ensured, and the template is erected in time after the excavation is finished.
S106, constructing a column cap, and constructing the column cap at the top of the column, wherein the construction method is to adopt a common construction method, the column cap steel bars pay attention to that the anchoring length needs to meet the on-site requirement, and the arrangement position and the spacing of the split heads are paid attention to when the plate steel bars are bound, so that the spacing of the double-layer steel bars is ensured;
and S107, installing a lifter.
Specifically, the construction quality control process is as follows: the strength grade, functionality (anti-permeability, anti-freezing, etc.), durability (chloride ion, alkali content, etc.), and workability (consistency, pumping, early strength, delayed coagulation, etc.) of the concrete all meet the design requirements and specification standards, and meet the requirements of construction operation.
The concrete is transported to a pouring place, and the consistency (slump and expansion) of the concrete meets the construction and design requirements, and is not layered or isolated. And should have sun-proof and rain-proof properties in summer and heat-insulating and wind-snow-preventing measures in winter.
Before concrete is poured, the inspection and acceptance of hidden projects are required to be completed. Checking the tight and flatness of the joints of the template, removing impurities in the template, and checking the positions of the embedded parts, the box and the holes, the thickness of the protective layer and the reliability of the positioning measures. The steel bar framework is strictly prevented from being poured, vibrated and stepped, and the steel bar framework of the plate type is provided with an iron split heads bracket for paving and lapping the springboard.
Pouring a vertical structure, paving cement mortar (without stones during stirring) with proper thickness and the same components as the concrete at the construction joint according to the measures of the construction technical scheme or paving the concrete at the joint position of the construction joint according to the following steps of 1: 2, the cement mortar is fused with the concrete, and a mortar layer cannot be exposed at the construction joint after the form is removed.
Pouring concrete into the mold, and preventing the concrete from intensively dumping to impact the formwork or the steel reinforcement framework. And uniformly distributing the materials in layers according to a pouring procedure. When the filling height of the column and the wall plate is more than 2m, a string cylinder and a chute are adopted for blanking.
The concrete is vibrated, the dense holes, the reserved holes, the box, the embedded parts, the positions of the steel bars and the thickness of the protective layer are ensured to be accurate, and the surface layer is smooth. And leakage vibration, under vibration or over vibration are strictly prevented.
After concrete pouring, covering, moisturizing and curing measures should be taken within 12 hours in time to strictly prevent dehydration and cracks. The maintenance agent is adopted, so that the water-retaining property is good, the spraying is uniform, and the surface layer is not polluted; maintaining with plastic film, tightly covering, preventing wind from blowing open, and keeping the film moist; adopts watering maintenance, temperature control and temperature measurement measures. In winter, heat preservation and antifreezing measures should be taken. The curing time of the concrete and the strength of the upper mounting template thereof should meet the current specifications.
The concrete of the whole structure is compact and neat, the surface layer is smooth, the edges and corners are neat and straight, the beam column nodes, the intersection angles of the wall boards, the lines and the surfaces are straight and clear, and the arching lines and the surfaces are smooth. No honeycomb, pitted surface, peeling and holes; no leakage, die running, die expansion, slab staggering, root rot and cracks. The construction joint is tightly and smoothly combined, has no inclusion, cold joint and mortar interlayer.
The protective layer is accurate, no exposed ribs and no rust penetration exist, and the reserved holes are neat to the edges of post-cast strips and construction joint holes. The bottom of the embedded part is dense, the surface is smooth, the exposed screw thread of the embedded bolt is qualified, and protective measures are taken.
Traditional graded gravel backfilling is poor in structural stability and high in uncertainty, is limited by the quality of backfilling, can be settled in rainy seasons and the like, and cannot guarantee safe and stable operation of the elevator. By adopting the construction method, the quality of the backfill soil does not need to be considered, and the safety of the lifter is ensured.
The method is economical and specifically comprises the following steps:
backfilling graded sandstone: carrying out heavy planting with backfill amount of about 5 × 8 × 5m =200m, and manufacturing cost of 200 × 230=46000 Yuan
Frame-type elevator basis: the cost is about 15000 yuan after accounting, and the cost is saved by 3.1 ten thousand yuan.
The construction method for the frame foundation of the construction elevator in a certain project has the advantages that the practical application effect proves that the construction method obviously reduces the backfill quality requirement of the backfill part and can ensure the operation safety of the elevator. The construction completion effect is highly recognized by owners, a good social image is established for enterprises, and the reputation of the enterprises is enhanced.
Specific use examples: the method is adopted for the elevator foundation, the effect is good, the construction is safe, the elevator foundation does not settle when experiencing typhoon, rainstorm and the like, and the operation safety of the elevator is ensured.
The frame structure of the construction method of the frame type foundation of the construction elevator comprises the following steps: the raft plate a is horizontally arranged at the bottom of the foundation pit; the column b is vertically arranged at the central point of the raft plate and is fixedly connected with the raft plate a; and the column cap c is fixedly arranged at the top of the column b. Referring to fig. 2, in use, the raft a is disposed at the bottom of the foundation pit, the foundation pit is filled with backfill soil, and the top of the cap is used as a support point for the standard section of the elevator.
The invention is not limited to the above alternative embodiments, and any other various forms of products can be obtained by anyone in the light of the present invention, but any changes in shape or structure thereof, which fall within the scope of the present invention as defined in the claims, fall within the scope of the present invention.

Claims (8)

1. A construction method of a column cap type elevator foundation is characterized by comprising the following steps:
cleaning the original soil surface at the bottom of the foundation pit;
performing raft construction, namely binding reinforcing steel bars of the raft on the surface of the bottom of the foundation pit, installing a template after binding is finished, pouring concrete after the template is installed, ensuring dense vibration during pouring, and timely covering and maintaining after pouring is finished;
performing column construction, namely binding column reinforcing steel bars at the top of the raft, installing templates after binding is finished, pouring concrete after the templates are installed, ensuring that the concrete is compacted during pouring, and timely covering and maintaining after pouring is finished;
backfilling earthwork in the foundation pit to the position above the column, and compacting the backfilled soil above the column within the range of 500 mm;
excavating the position of the column cap, excavating a column cap groove for placing the column cap at the top of the column, and timely erecting a template after the excavation is finished;
constructing a column cap, namely constructing the column cap at the top of the column;
and (5) installing a lifter.
2. The method for constructing a foundation of a cap-type lifter according to claim 1, wherein the positions of the column rib joints in the column construction are staggered by a distance of 500mm or more, and the upper part of the column rib joints is provided with a 12d bend.
3. The method of claim 1, wherein the column hoop is a double steel pipe.
4. The method of claim 1, wherein the sides of the column are braced with diagonal braces.
5. The method of constructing a cap elevator foundation of claim 1, wherein the concrete is cast using C30 concrete.
6. The method of claim 1, wherein the strength of the concrete poured during form removal is not less than 1.2 MPa.
7. The method of claim 1, wherein the earth is backfilled uniformly around the column to ensure that the column is not subjected to horizontal loading.
8. The method for constructing the foundation of the cap-type lifter according to the claim 1, wherein a dedicated worker is required to watch the formwork during the pouring process, the problems of slurry leakage, inclination and the like of the formwork are corrected in time, and the concrete is vibrated during the pouring process to ensure the compact formation of the concrete.
CN202110613633.XA 2021-06-02 2021-06-02 Construction method for foundation of column cap type elevator Pending CN113417310A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110613633.XA CN113417310A (en) 2021-06-02 2021-06-02 Construction method for foundation of column cap type elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110613633.XA CN113417310A (en) 2021-06-02 2021-06-02 Construction method for foundation of column cap type elevator

Publications (1)

Publication Number Publication Date
CN113417310A true CN113417310A (en) 2021-09-21

Family

ID=77713610

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110613633.XA Pending CN113417310A (en) 2021-06-02 2021-06-02 Construction method for foundation of column cap type elevator

Country Status (1)

Country Link
CN (1) CN113417310A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115075263A (en) * 2022-05-22 2022-09-20 北京金港场道工程建设有限公司 Airport runway section device, construction method and backfill reverse construction method mold device

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2726303A1 (en) * 1994-10-27 1996-05-03 Harnois Georges Method of forming subterranean dwelling
CN201891128U (en) * 2010-11-03 2011-07-06 中建三局第二建设工程有限责任公司 Single-pile elevated bearing-platform tower-crane foundation structure
CN202969406U (en) * 2012-10-30 2013-06-05 广东明阳风电产业集团有限公司 Wind power generation tower foundation combining reverse frustum with free-standing column
CN204982932U (en) * 2015-08-11 2016-01-20 上海建工五建集团有限公司 Lift foundation structure
CN206245338U (en) * 2016-10-27 2017-06-13 中国建筑第二工程局有限公司 The basic structure of construction elevator of double-deck raft plate
CN107620301A (en) * 2017-09-12 2018-01-23 中国矿业大学(北京) A kind of geology bracing means
CN207974142U (en) * 2018-03-08 2018-10-16 中国建筑第七工程局有限公司 A kind of building hoist basis
CN207974140U (en) * 2017-12-27 2018-10-16 中建三局第二建设工程有限责任公司 A kind of limited high-order double bearing platform construction elevators basis of engineering specifications
CN108867684A (en) * 2018-07-18 2018-11-23 上海勘测设计研究院有限公司 Offshore wind turbine gravity caisson basis and its installation method
CN209873846U (en) * 2019-03-04 2019-12-31 中建三局第三建设工程有限责任公司 Can have enough to meet need construction elevator basis and return reinforcing apparatus
CN210031898U (en) * 2019-05-24 2020-02-07 潍坊学院 Wind power generation tower foundation
CN211447000U (en) * 2019-10-28 2020-09-08 中国建筑第八工程局有限公司 Foundation pit backfill area construction elevator foundation
JP2020159131A (en) * 2019-03-27 2020-10-01 鹿島建設株式会社 Manufacturing method for precast concrete member and manufacturing device for precast concrete member
CN111794267A (en) * 2020-07-10 2020-10-20 广州协安建设工程有限公司 Construction method for foundation of construction elevator
CN112211181A (en) * 2020-11-11 2021-01-12 贵州建工集团第一建筑工程有限责任公司 Construction method for foundation bearing platform of elevator

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2726303A1 (en) * 1994-10-27 1996-05-03 Harnois Georges Method of forming subterranean dwelling
CN201891128U (en) * 2010-11-03 2011-07-06 中建三局第二建设工程有限责任公司 Single-pile elevated bearing-platform tower-crane foundation structure
CN202969406U (en) * 2012-10-30 2013-06-05 广东明阳风电产业集团有限公司 Wind power generation tower foundation combining reverse frustum with free-standing column
CN204982932U (en) * 2015-08-11 2016-01-20 上海建工五建集团有限公司 Lift foundation structure
CN206245338U (en) * 2016-10-27 2017-06-13 中国建筑第二工程局有限公司 The basic structure of construction elevator of double-deck raft plate
CN107620301A (en) * 2017-09-12 2018-01-23 中国矿业大学(北京) A kind of geology bracing means
CN207974140U (en) * 2017-12-27 2018-10-16 中建三局第二建设工程有限责任公司 A kind of limited high-order double bearing platform construction elevators basis of engineering specifications
CN207974142U (en) * 2018-03-08 2018-10-16 中国建筑第七工程局有限公司 A kind of building hoist basis
CN108867684A (en) * 2018-07-18 2018-11-23 上海勘测设计研究院有限公司 Offshore wind turbine gravity caisson basis and its installation method
CN209873846U (en) * 2019-03-04 2019-12-31 中建三局第三建设工程有限责任公司 Can have enough to meet need construction elevator basis and return reinforcing apparatus
JP2020159131A (en) * 2019-03-27 2020-10-01 鹿島建設株式会社 Manufacturing method for precast concrete member and manufacturing device for precast concrete member
CN210031898U (en) * 2019-05-24 2020-02-07 潍坊学院 Wind power generation tower foundation
CN211447000U (en) * 2019-10-28 2020-09-08 中国建筑第八工程局有限公司 Foundation pit backfill area construction elevator foundation
CN111794267A (en) * 2020-07-10 2020-10-20 广州协安建设工程有限公司 Construction method for foundation of construction elevator
CN112211181A (en) * 2020-11-11 2021-01-12 贵州建工集团第一建筑工程有限责任公司 Construction method for foundation bearing platform of elevator

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
全国造价工程师职业资格考试培训教材编审委员会: "《建设工程技术与计量》", 30 June 2019, 中国计划出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115075263A (en) * 2022-05-22 2022-09-20 北京金港场道工程建设有限公司 Airport runway section device, construction method and backfill reverse construction method mold device
CN115075263B (en) * 2022-05-22 2023-09-26 北京金港场道工程建设有限公司 Airport pavement section device, construction method and backfill reverse construction method die device for airport

Similar Documents

Publication Publication Date Title
US11384501B2 (en) Method for sealing post-cast strip in foundation with no gap
CN102392549B (en) Construction working method for seamless prestressed-concrete self-waterproof clean water reservoir
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN206971270U (en) Exterior wall formwork system in underground pipe gallery cast-in-place construction
CN110872869A (en) Waterproof construction method for joints of external wall panels
CN108265623A (en) A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN110682433A (en) Prefabricated stand column construction scheme
CN203729322U (en) Precast concrete pipeline foundation
CN112832079A (en) Construction method of foamed light soil spliced wide-height highway embankment
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN110106915A (en) One kind exempts from that support is inverse to make underground engineering construction method and underground construction structure
CN113417310A (en) Construction method for foundation of column cap type elevator
CN110528524A (en) Volume of concrete foundation unit cellular-type construction method
CN206052778U (en) A kind of steel and Combined concrete piping lane
CN111456085A (en) Cast-in-place concrete construction method for pipe gallery segment
CN110939152A (en) Raft foundation construction method
CN204139369U (en) Assembling fire wall
CN206859370U (en) Plastic rectangular straight line municipal drainage inspection shaft
CN113585317B (en) Construction method for mucky soil support beam cushion layer
CN111535339B (en) Construction process of concrete dam body of refuse landfill
CN113266035A (en) Construction method for upper structure of steam turbine base
CN209942380U (en) Windproof dust suppression net structure system for bulk cargo storage yard
CN209722630U (en) Prefabricated bituminous block and its paving structure
CN112195975A (en) Novel inspection well reinforcing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210921