CN204982932U - Lift foundation structure - Google Patents
Lift foundation structure Download PDFInfo
- Publication number
- CN204982932U CN204982932U CN201520600898.6U CN201520600898U CN204982932U CN 204982932 U CN204982932 U CN 204982932U CN 201520600898 U CN201520600898 U CN 201520600898U CN 204982932 U CN204982932 U CN 204982932U
- Authority
- CN
- China
- Prior art keywords
- wall
- basement
- lifter
- foundation
- bar planting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Abstract
The utility model discloses a fall quick -witted foundation structure, lift basis raft board includes reinforced concrete bottom plate and basic reinforced concrete roof beam, and the pre -buried base of lift is pre -buried in basic reinforced concrete roof beam, one side of lift basis raft board is taken and is put on the wall outdoorly underground, passes through basement outer wall bar planting rigid coupling between lift basis raft board and the basement outer wall, the opposite side of lift basis raft board through the reinforced concrete wall take put excavation slope department strut the dowel crown roof beam on, be equipped with the bar planting of hat roof beam in the reinforced concrete wall, in the basic reinforced concrete roof beam of the upper portion anchor income lift basis raft board of hat roof beam bar planting, implant in strutting the dowel crown roof beam lower part of hat roof beam bar planting, be filled with the back filling in strutting the basic deep basal pit between dowel crown roof beam and the basement outer wall, there is the bed course on the back filling upper berth. The utility model provides a lift in the engineering construction can't directly arrange the technical problem of suitable position.
Description
Technical field
The utility model relates to hoist field, particularly a kind of lifter foundation structure.
Background technology
In engineering construction, build by laying bricks or stones start to construct time, need to install hoist, due to narrow field, lifter foundation cannot be seated on basement roof, can only be seated in backfill, in this construction environment, can only directly be arranged on the limit soil body of hole.When main body construction unit needs to arrange hoist, for above-mentioned reasons, existing way is played lifter foundation stake outward at excavation slope or on excavation slope, plays lifter foundation stake, then in lifter foundation stake, installs lifter foundation and hoist.Cause in engineering construction, a lot of hoist cannot be deployed directly into suitable position.
Utility model content
The utility model provides a kind of lifter foundation structure, to solve the technical problem existed in prior art.
For solving the problems of the technologies described above, the utility model provides a kind of lifter foundation structure, comprise: lifter foundation raft plate, the pre-buried pedestal of hoist is embedded with in this lifter foundation raft plate, wherein, described lifter foundation raft plate comprise reinforced concrete floor and be positioned at described reinforced concrete floor both sides and with the reinforcement foundation concrete beam of described reinforced concrete floor integral molding, the pre-buried pedestal of described hoist is embedded in reinforcement foundation concrete beam; The side described lifter foundation raft plate being provided with reinforcement foundation concrete beam is taken and is placed on outer wall of basement, and affixed by outer wall of basement bar planting between lifter foundation raft plate and outer wall of basement; Opposite side lifter foundation raft plate being provided with reinforcement foundation concrete beam is taken by reinforced concrete wall and is placed on the supporting dowel crown beam at excavation slope place, the bar planting of hat beam is provided with in described reinforced concrete wall, the top of described hat beam bar planting anchors in the reinforcement foundation concrete beam of lifter foundation raft plate, and the bottom of hat beam bar planting is implanted in supporting dowel crown beam; Be filled with backfill in basic deep foundation ditch between described supporting dowel crown beam and outer wall of basement, backfill is covered with bed course, described bed course is folded between lifter foundation raft plate and supporting dowel crown beam near the side of described supporting dowel crown beam.
As preferably, described reinforcement foundation concrete beam comprises two longerons, and take for one in described two longerons and be placed on outer wall of basement, another root in two longerons is taken by reinforced concrete wall and is placed on the supporting dowel crown beam at excavation slope place.
As preferably, described outer wall of basement bar planting anchors in the longeron above outer wall of basement, and the bar planting of described hat beam anchors in the longeron above supporting dowel crown beam.
As preferably, described bed course adopts plain concrete or steel concrete to make.
As preferably, the thickness of described bed course is 80mm ~ 120mm, and intensity is CI5, and bed course is by the side side of outer wall of basement to the wall face of outer wall of basement, and other side of bed course all protrudes from the edge of lifter foundation raft plate.
As preferably, described bed course protrudes from the edge 400mm ~ 600mm of lifter foundation raft plate.
As preferably, the coefficient of consolidation of described backfill is not less than 0.94.
As preferably, it is 35d that described outer wall of basement bar planting and the bar planting of hat beam all anchor in lifter foundation raft plate.
As preferably, described outer wall of basement bar planting and the bar planting of hat beam are 2 φ 32150 reinforcing bars, HRB400 level reinforcing bar.
Compared with prior art, lifter foundation structure of the present utility model make use of the existing outer wall of basement of job site and the supporting dowel crown beam at excavation slope place, both hoist basement process link had been decreased, do not increase equipment leasing expense again, so the secondary decreasing lifter foundation construction drops into, save construction cost, reduce difficulty of construction.The utility model not only can not affect the normal construction of engineering completely, and can meet the construction of Foundation Design.The installation and removal safe ready of lifter foundation structure and can once completing, thus peace to tear the time open short.In addition, the reinforcement foundation concrete beam of lifter foundation raft plate is stressed, reinforced concrete floor as counterweight, overturning or slip resistance analysis, stressed clear, reasonable.
Accompanying drawing explanation
Fig. 1 is the schematic top plan view of lifter foundation mechanism in the utility model;
Fig. 2 is the A-A face sectional view of Fig. 1;
Fig. 3 is the schematic diagram being provided with reinforcement foundation concrete beam in the utility model in lifter foundation raft plate;
Fig. 4 is the B-B face sectional view of Fig. 3.
Shown in figure: 10-lifter foundation raft plate, the pre-buried pedestal of 101-hoist, 102-reinforced concrete floor, 103-reinforcement foundation concrete beam, 20-outer wall of basement, the bar planting of 30-outer wall of basement, 40-reinforced concrete wall, 50-supporting dowel crown beam, 60-are preced with beam bar planting, 70-backfill, 80-bed course, 90-concrete floor.
Detailed description of the invention
For enabling above-mentioned purpose of the present utility model, feature and advantage become apparent more, are described in detail detailed description of the invention of the present utility model below in conjunction with accompanying drawing.It should be noted that, the utility model accompanying drawing all adopts the form of simplification and all uses non-ratio accurately, only in order to object that is convenient, aid illustration the utility model embodiment lucidly.
Shown in Fig. 1 ~ 4, lifter foundation mechanism of the present utility model, includes lifter foundation raft plate l0, is embedded with the pre-buried pedestal 101 of hoist in this lifter foundation raft plate 10.
Particularly, described lifter foundation raft plate 10 comprise reinforced concrete floor 102 and be positioned at described reinforced concrete floor 102 both sides and with the reinforcement foundation concrete beam 103 of described reinforced concrete floor 102 integral molding, the pre-buried pedestal 101 of described hoist is embedded in reinforcement foundation concrete beam 103;
The side that lifter foundation raft plate 10 is provided with reinforcement foundation concrete beam 103 is taken and is placed on outer wall of basement 20, and be provided with outer wall of basement bar planting 30 between lifter foundation raft plate 10 and outer wall of basement 20, the top of this outer wall of basement bar planting 30 anchors in lifter foundation raft plate 10, and the bottom of this outer wall of basement bar planting 30 is implanted in outer wall of basement 20;
The opposite side that lifter foundation raft plate 10 is provided with reinforcement foundation concrete beam 103 is taken by reinforced concrete wall 40 and is placed on the supporting dowel crown beam 50 at excavation slope place, hat beam bar planting 60 is provided with in described reinforced concrete wall 40, and the top being preced with beam bar planting 60 anchors in lifter foundation raft plate 10, the bottom of hat beam bar planting 60 is implanted in supporting dowel crown beam 50; The topping of described supporting dowel crown beam 50 upper surface will be rejected, pouring reinforcement concrete wall 40 again after hat beam bar planting 60 requires to reach.
Backfill 70 is filled with in basic deep foundation ditch between supporting dowel crown beam 50 and outer wall of basement 20, backfill 70 is covered with the bed course 80 be made up of plain concrete or steel concrete, and bed course 80 leans on the side of supporting dowel crown beam 50 to be also clipped between lifter foundation raft plate l0 and supporting dowel crown beam 50;
Described backfill 70 is tamped, and the coefficient of consolidation of backfill 70 is not less than 0.94, and backfill 70 does not participate in stressed, only plays bed course basis and template.
Described reinforcement foundation concrete beam 103 comprises two longerons, taking for one in described two longerons is placed on outer wall of basement 20, another root in two longerons is taken by reinforced concrete wall 40 and is placed on the supporting dowel crown beam 50 at excavation slope place, described outer wall of basement bar planting 30 anchors in the longeron above outer wall of basement 20, and described hat beam bar planting 60 anchors in the longeron above supporting dowel crown beam 50.
Beam level in longeron is indulged muscle and is directly arrived the disconnection of outer wall of basement 20 limit, and the waist muscle in longeron is 6 diameters is the reinforcing bar of 14mm.Reinforcement in longeron is not connected with outer wall of basement 20, to limit, shear wall hole disconnection on the ground, only often hold 6 diameters to be that the reinforcing bar of 14mm is connected with outer wall of basement 20, the termination outer wall of basement 20 of two longerons need not pick cutter, can reduce the impact on building like this.
Described outer wall of basement bar planting 30 and hat beam bar planting 60 all anchor in lifter foundation raft plate 10 and also anchor in longeron according to 40d at the lifter foundation plate muscle of supporting dowel crown beam 50 side for 35d.
The thickness of described bed course 80 is 80mm ~ 120mm, intensity is C15, bed course 80 leans on the side side of outer wall of basement 20 to the wall face of outer wall of basement 20, other side of bed course 80 all protrudes from the edge 400mm ~ 600mm of lifter foundation raft plate 10, wherein side is arranged on concrete floor 90, can prevent rain penetration from entering lifter foundation.
Described outer wall of basement bar planting 30 and hat beam bar planting 60 are 2 φ 32150 reinforcing bars (two diameters are the reinforcing bar of 32 millimeters, spacing 150 millimeters), HRB400 level reinforcing bar.It is 35d that outer wall of basement bar planting 30 and hat beam bar planting 60 all anchor in lifter foundation raft plate 10.Outer wall of basement bar planting 30 is qualified with the necessary pull-out test of hat beam bar planting 60.
If also have exterior wall in the outside of outer wall of basement 20; then the vertical muscle bar planting of reinforcement foundation concrete beam 103 anchors into outward within the walls; the strength grade of concrete of lifter foundation raft plate 10 is C35; reinforcement cover on lifter foundation raft plate 10 is 50mm; Reinforcement in lifter foundation raft plate 10 and waist muscle are grade III steel muscle, and stirrup is secondary reinforcing bar.
Because the load of hoist is born by reinforcement foundation concrete beam 103, then power passed on outer wall of basement 20 and supporting dowel crown beam 50 by outer wall of basement bar planting 30 and hat beam bar planting 60, other parts of lifter foundation raft plate 10 do not participate in stressed.
The pre-buried pedestal of hoist 101 and reinforcement foundation concrete beam 103 are same center line.
Construction method of the present utility model is: after basic engineering construction, utilizes the supporting dowel crown beam 50 at the outer wall of basement 20 and excavation slope place built as the stress point of lifter foundation, outside the building installs lifter foundation structure of the present utility model.When the earthen backfill in basic deep foundation ditch is complete, after construction plant also increases, hoist erection equipment is directly installed on the utility model.
The utility model utilizes existing structure as the strong point of hoist, the strong point is constructed the utility model, install hoist, namely utilize the supporting dowel crown beam 50 at excavation slope place as a strong point, utilize outer wall of basement 20 as another strong point, carry out hoist installation according to beam foundation design lifter foundation.Hoist installs and each jacking, all should carry out foundation settlement survey, and the ground around routine observation the utility model, prevent rainwater from infiltrating.The utility model make use of the existing structure of job site, namely decreases hoist basement process link, does not increase equipment leasing expense again, so the secondary decreasing lifter foundation construction drops into, has saved construction cost, has reduced difficulty of construction.The utility model not only can not affect the normal construction of engineering completely, and can meet the construction of Foundation Design.The installation and removal safe ready of lifter foundation structure and can once completing, thus peace to tear the time open short.In addition, the reinforcement foundation concrete beam 103 of lifter foundation raft plate 10 is stressed, reinforced concrete floor 102 as counterweight, overturning or slip resistance analysis, stressed clear, reasonable.
Obviously, those skilled in the art can carry out various change and modification to utility model and not depart from spirit and scope of the present utility model.Like this, if these amendments of the present utility model and modification belong within the scope of the utility model claim and equivalent technologies thereof, then the utility model is also intended to comprise these change and modification.
Claims (9)
1. a lifter foundation structure, is characterized in that: comprise lifter foundation raft plate, is embedded with the pre-buried pedestal of hoist in this lifter foundation raft plate, wherein,
Described lifter foundation raft plate comprise reinforced concrete floor and be positioned at described reinforced concrete floor both sides and with the reinforcement foundation concrete beam of described reinforced concrete floor integral molding, the pre-buried pedestal of described hoist is embedded in reinforcement foundation concrete beam;
The side described lifter foundation raft plate being provided with reinforcement foundation concrete beam is taken and is placed on outer wall of basement, and affixed by outer wall of basement bar planting between lifter foundation raft plate and outer wall of basement;
Opposite side lifter foundation raft plate being provided with reinforcement foundation concrete beam is taken by reinforced concrete wall and is placed on the supporting dowel crown beam at excavation slope place, the bar planting of hat beam is provided with in described reinforced concrete wall, the top of described hat beam bar planting anchors in the reinforcement foundation concrete beam of lifter foundation raft plate, and the bottom of hat beam bar planting is implanted in supporting dowel crown beam;
Be filled with backfill in basic deep foundation ditch between described supporting dowel crown beam and outer wall of basement, backfill is covered with bed course, described bed course is folded between lifter foundation raft plate and supporting dowel crown beam near the side of described supporting dowel crown beam.
2. lifter foundation structure as claimed in claim 1, it is characterized in that, described reinforcement foundation concrete beam comprises two longerons, taking for one in described two longerons is placed on outer wall of basement, and another root in two longerons is taken by reinforced concrete wall and is placed on the supporting dowel crown beam at excavation slope place.
3. lifter foundation structure as claimed in claim 2, it is characterized in that, described outer wall of basement bar planting anchors in the longeron above outer wall of basement, and the bar planting of described hat beam anchors in the longeron above supporting dowel crown beam.
4. lifter foundation structure as claimed in claim 1, is characterized in that, described bed course adopts plain concrete or steel concrete to make.
5. lifter foundation structure as claimed in claim 1, it is characterized in that, the thickness of described bed course is 80mm ~ 120mm, and intensity is CI5, bed course leans on the side side of outer wall of basement to the wall face of outer wall of basement, and other side of bed course all protrudes from the edge of lifter foundation raft plate.
6. lifter foundation structure as claimed in claim 5, it is characterized in that, described bed course protrudes from the edge 400mm ~ 600mm of lifter foundation raft plate.
7. lifter foundation structure as claimed in claim 1, it is characterized in that, the coefficient of consolidation of described backfill is not less than 0.94.
8. lifter foundation structure as claimed in claim 1, is characterized in that, it is 35d that described outer wall of basement bar planting and the bar planting of hat beam all anchor in lifter foundation raft plate.
9. lifter foundation structure as claimed in claim 1, is characterized in that, described outer wall of basement bar planting and the bar planting of hat beam are 2 φ 32150 reinforcing bars, HRB400 level reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520600898.6U CN204982932U (en) | 2015-08-11 | 2015-08-11 | Lift foundation structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201520600898.6U CN204982932U (en) | 2015-08-11 | 2015-08-11 | Lift foundation structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204982932U true CN204982932U (en) | 2016-01-20 |
Family
ID=55117314
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201520600898.6U Expired - Fee Related CN204982932U (en) | 2015-08-11 | 2015-08-11 | Lift foundation structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204982932U (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105672471A (en) * | 2016-03-17 | 2016-06-15 | 中国建筑第八工程局有限公司 | Construction lifting machine foundation and construction method thereof |
CN106592624A (en) * | 2016-12-22 | 2017-04-26 | 中建四局第三建筑工程有限公司 | Construction method for pouring construction elevator foundation in advance |
CN106703073A (en) * | 2016-12-30 | 2017-05-24 | 中国建筑第八工程局有限公司 | Supporting-free steel beam foundation of super-high-rise construction elevator and construction method of supporting-free steel beam foundation |
CN106836325A (en) * | 2017-04-13 | 2017-06-13 | 青岛建集团有限公司 | A kind of outdoor construction elevator strengthening of foundation device |
CN111794267A (en) * | 2020-07-10 | 2020-10-20 | 广州协安建设工程有限公司 | Construction method for foundation of construction elevator |
CN112962659A (en) * | 2021-02-07 | 2021-06-15 | 上海建工二建集团有限公司 | Construction elevator foundation and construction method of construction elevator |
CN113417310A (en) * | 2021-06-02 | 2021-09-21 | 中建二局第四建筑工程有限公司 | Construction method for foundation of column cap type elevator |
-
2015
- 2015-08-11 CN CN201520600898.6U patent/CN204982932U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105672471A (en) * | 2016-03-17 | 2016-06-15 | 中国建筑第八工程局有限公司 | Construction lifting machine foundation and construction method thereof |
CN106592624A (en) * | 2016-12-22 | 2017-04-26 | 中建四局第三建筑工程有限公司 | Construction method for pouring construction elevator foundation in advance |
CN106592624B (en) * | 2016-12-22 | 2018-12-18 | 中建四局第三建筑工程有限公司 | A kind of construction on pouring construction elevator basis in advance |
CN106703073A (en) * | 2016-12-30 | 2017-05-24 | 中国建筑第八工程局有限公司 | Supporting-free steel beam foundation of super-high-rise construction elevator and construction method of supporting-free steel beam foundation |
CN106836325A (en) * | 2017-04-13 | 2017-06-13 | 青岛建集团有限公司 | A kind of outdoor construction elevator strengthening of foundation device |
CN111794267A (en) * | 2020-07-10 | 2020-10-20 | 广州协安建设工程有限公司 | Construction method for foundation of construction elevator |
CN112962659A (en) * | 2021-02-07 | 2021-06-15 | 上海建工二建集团有限公司 | Construction elevator foundation and construction method of construction elevator |
CN113417310A (en) * | 2021-06-02 | 2021-09-21 | 中建二局第四建筑工程有限公司 | Construction method for foundation of column cap type elevator |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204982932U (en) | Lift foundation structure | |
CN103452147B (en) | Self-balancing anchor counterweight broken pile forced-landing tilt correcting method | |
CN101446088B (en) | Construction method for pole and tower foundation in Gobi Desert gravelly soil area | |
CN204456167U (en) | Prestress anchoraging blower foundation | |
CN101509261B (en) | Method for pile plate base for ultra-high voltage electric power line steel tower on soft foundation | |
CN102864781A (en) | Foundation pit supporting method utilizing inclined piles | |
CN205776273U (en) | Tall earth fill balance weight retaining wall and prestress anchorage cable combined support structure | |
CN108277819B (en) | A kind of retaining wall structure | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN207512752U (en) | A kind of tall earth fill supporting construction | |
CN101787701B (en) | Construction method for supporting pine pile in elevator shaft foundation pit | |
CN104404979B (en) | H type stake panel wall construction method | |
CN108385715A (en) | A kind of assembled stake arch combination retaining wall and its construction method | |
CN204825928U (en) | Excavation supporting | |
CN206408630U (en) | Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body | |
CN201232193Y (en) | Wind motor tower foundation anchor pile structure on rock foundation | |
CN101215840B (en) | Airplane type foundation reinforcing and prestressing method | |
CN102535505A (en) | Tower crane foundation made of basement outer wall and foundation pit supporting piles | |
CN208088311U (en) | Back-pressure de-bowed type pile slab supporting structure after stake | |
CN107165173A (en) | A kind of foundation pit supporting system and its construction method | |
CN106759471A (en) | Arched retaining wall structure formed by waste tires and construction method thereof | |
CN211547803U (en) | Prestressing force monitoring adjustable weighing type combination retaining wall | |
CN111945657A (en) | Wharf upgrading and reconstruction structure and wharf upgrading and reconstruction construction method | |
CN112456353A (en) | Movable arm tower crane fixed foundation construction method and movable arm tower crane structure | |
CN109555129A (en) | Rapid emergency diagonal bracing for foundation pit emergency and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |