CN106836325A - A kind of outdoor construction elevator strengthening of foundation device - Google Patents

A kind of outdoor construction elevator strengthening of foundation device Download PDF

Info

Publication number
CN106836325A
CN106836325A CN201710239568.2A CN201710239568A CN106836325A CN 106836325 A CN106836325 A CN 106836325A CN 201710239568 A CN201710239568 A CN 201710239568A CN 106836325 A CN106836325 A CN 106836325A
Authority
CN
China
Prior art keywords
steel
construction elevator
external wall
concrete cushion
mounting hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710239568.2A
Other languages
Chinese (zh)
Inventor
赵永龙
高燕
郭诚
王辉
孙镇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao No 1 Construction Group Co Ltd
Original Assignee
Qingdao No 1 Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao No 1 Construction Group Co Ltd filed Critical Qingdao No 1 Construction Group Co Ltd
Priority to CN201710239568.2A priority Critical patent/CN106836325A/en
Publication of CN106836325A publication Critical patent/CN106836325A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance

Abstract

The invention discloses a kind of outdoor construction elevator strengthening of foundation device, including external wall, indoor reinforced concrete floor, original soil layer, I-steel and construction elevator basis, it is backfill between the external wall and the original soil layer, the external wall offers mounting hole, concrete cushion has been poured on the original soil layer, if being embedded with arterial highway round steel on the concrete cushion, the upper surface of the root of the mounting hole, the upper surface of the indoor reinforced concrete floor and the concrete cushion is respectively positioned on same level;One end of the I-steel is fixedly mounted on the indoor reinforced concrete floor through the mounting hole, and the other end of the I-steel is fixedly mounted on the concrete cushion by round steel, and the construction elevator basis is placed on the I-steel.The present invention can be prevented effectively from construction elevator basis and differential settlement is occurred using I-steel Construction of Supporting elevator basis, simple to operate, easy construction, and safe effect is good.

Description

A kind of outdoor construction elevator strengthening of foundation device
Technical field
The invention belongs to construction engineering technical field, and in particular to a kind of outdoor construction elevator strengthening of foundation device.
Background technology
Construction elevator has a wide range of applications as a kind of vertical transport instrument in architectural engineering.For deep-foundation pit engineering For, building often occurs the backfill that construction elevator is located between building and foundation ditch outside when construction elevator is set Situation on soil, in this case, it is possible that because backfill rammed earth not enough causes construction elevator basis uneven heavy Drop, with the extension of construction usage time, backfill deformation increase may cause steel pipe scaffold support system unbalance stress, Part does not even have supporting role, so as to influence the normal of construction elevator to use, or even serious safety problem occurs.
The content of the invention
In view of the shortcomings of the prior art, it is existing to solve the invention provides a kind of outdoor construction elevator strengthening of foundation device Have in work progress because backfill soil compactness not enough causes the technical problem of construction elevator foundation uneven settlement.
A kind of outdoor construction elevator strengthening of foundation device, including external wall, indoor reinforced concrete floor, primitive soil Layer, I-steel and construction elevator basis, are backfill between the external wall and the original soil layer, on the external wall Mounting hole is offered, concrete cushion has been poured on the original soil layer, if being embedded with arterial highway round steel on the concrete cushion, The root of the mounting hole, the equal position in the upper surface of upper surface and the concrete cushion of the indoor reinforced concrete floor In same level;One end of the I-steel is fixedly mounted on the indoor reinforced concrete floor through the mounting hole On, the other end of the I-steel is fixedly mounted on the concrete cushion by round steel, and the construction elevator basis is placed On the I-steel.
Preferably, it is embedded with twice round steel on the concrete cushion.
Preferably, the I-steel passes through to be welded together with round steel.
Preferably, one end of the I-steel is fixedly mounted on the indoor reinforced concrete floor by fixed iron block On.
Preferably, the side of the fixed iron block is fixed on the inner surface of the external wall.
Preferably, the I-steel is several.
Preferably, the I-steel is 32# I-steel.
Preferably, the round steel is 20 round steel.
Advantageous Effects of the invention:
1)Outdoor construction elevator strengthening of foundation device of the invention is not constructed directly in backfill, but construction elevator is basic Set up indoors on reinforced concrete floor and original soil layer, it is to avoid because backfill rammed earth not enough causes construction elevator basis Differential settlement so as to influence the normal problem for using of construction elevator, therefore, be not in serious safety problem.
2)In the present invention, the stress surface of I-steel is the concrete mats on indoor reinforced concrete floor and original soil layer Layer, its intensity is high, and bearing capacity is strong, and power transmission effect is good, and bearing capacity will not drop with contact surface because of the extension of use time Low and deformation.
3)In the present invention, the two ends of I-steel carry out reinforcing installation by fixed iron block and round steel respectively, not easily shifted, apply Man-hour is safer.
4)The present invention can after the completion of the usage quantity of I-steel, and construction can be determined according to construction elevator foundation load Dismounting recycling, saves substantial amounts of financial resources, material resources, and construction cost is low, and shortens the duration.
Summary, outdoor construction elevator strengthening of foundation device of the invention employs I-steel Construction of Supporting elevator base Plinth, simple to operate, easy construction can be prevented effectively from construction elevator basis and differential settlement occurs, and safe effect is good.
Brief description of the drawings
Fig. 1 is structural representation of the invention;
Reference:1st, I-steel;2nd, round steel;3rd, concrete cushion;4th, original soil layer;5th, construction elevator basis;6th, build outer Wall;7th, fixed iron block;8th, indoor reinforced concrete floor;9th, mounting hole;10th, backfill.
Specific embodiment
The present invention is further detailed explanation with reference to the accompanying drawings and detailed description.
Embodiment 1
As shown in figure 1, a kind of outdoor construction elevator strengthening of foundation device, including external wall 6, indoor reinforced concrete floor 8, Original soil layer 4, I-steel 1 and construction elevator basis 5, are backfill 10 between the external wall 6 and the original soil layer 4, The external wall 6 offers mounting hole 9, and concrete cushion 3 has been poured on the original soil layer 4, and concrete cushion 3 can be carried Construction elevator basis 5 high by force intensity, be embedded with twice round steel 2 on the concrete cushion 3, the root of the mounting hole 9, The upper surface of the indoor reinforced concrete floor 8 and the upper surface of the concrete cushion 3 are respectively positioned on same level, with Make the stress surface uniform force on carrying construction elevator basis 5.One end of the I-steel 1 fixedly mounts through the mounting hole 9 On the indoor reinforced concrete floor 8, the other end of the I-steel 1 is fixedly mounted on the concrete by round steel 2 On bed course 3, the I-steel 1 passes through to be welded together with round steel 2, to reinforce the fixed installation of I-steel 1.The construction Elevator basis 5 is placed on the I-steel 1, and the load according to construction elevator basis 5 determines the number of I-steel 1 in the present invention Amount, the I-steel 1 can select 32# I-steel, and the round steel 2 can select 20 round steel.
Form of construction work of the invention:Mounting hole 9 first is opened up on the skin 6 of construction elevator to be installed, and is protected The upper surface of the root and the indoor reinforced concrete floor 8 of demonstrate,proving mounting hole 9 is located at same level, then in original soil layer A block concrete bed course 3 is poured on 4, makes the upper surface of concrete cushion 3 and the upper surface of the indoor reinforced concrete floor 8 Positioned at same level, so that the mounting plane for ensureing construction elevator basis 5 is smooth and uniform force;It is pre- on concrete cushion 3 Round steel 2 is buried, I-steel 1 is penetrated from mounting hole 9, one end of I-steel 1 is fixed on reinforced concrete floor 8 indoors, separately One end is fixed on concrete cushion 3, and carries out reinforcement of weld by round steel 2 and I-steel 1, finally by construction elevator basis 5 are placed on the I-steel 1.
Embodiment 2
As different from Example 1, one round steel 2 is embedded with the concrete cushion 3.
Embodiment 3
As different from Example 1, one end of the I-steel 1 is fixedly mounted on the indoor reinforcing bar and mixes by fixed iron block 7 On solidifying Tulou plate 8, the side of the fixed iron block 7 is fixed on the inner surface of the external wall 6, and this setting can reinforce described The fixed installation of the one end of I-steel 1, makes elevator not easily shifted when constructing and avoids causing danger.
Although the present invention is described in detail above to have used general explanation and specific embodiment, at this On the basis of invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Therefore, These modifications or improvements, belong to the scope of protection of present invention without departing from theon the basis of the spirit of the present invention.

Claims (6)

1. a kind of outdoor construction elevator strengthening of foundation device, it is characterised in that:Including external wall, indoor reinforced concrete Tulou Plate, original soil layer, I-steel and construction elevator basis, are backfill between the external wall and the original soil layer, described Mounting hole is offered on external wall, concrete cushion has been poured on the original soil layer, be embedded with the concrete cushion If arterial highway round steel, the root of the mounting hole, the upper surface of the indoor reinforced concrete floor and the concrete cushion Upper surface be respectively positioned on same level;One end of the I-steel is fixedly mounted on the indoor reinforcing bar through the mounting hole On concrete floor, the other end of the I-steel is fixedly mounted on the concrete cushion by round steel, the construction electricity Ladder foundation is placed on the I-steel.
2. outdoor construction elevator strengthening of foundation device according to claim 1, it is characterised in that:On the concrete cushion It is embedded with twice round steel.
3. outdoor construction elevator strengthening of foundation device according to claim 2, it is characterised in that:The I-steel and round steel By being welded together.
4. outdoor construction elevator strengthening of foundation device according to claim 1, it is characterised in that:One end of the I-steel It is fixedly mounted on the indoor reinforced concrete floor by fixed iron block.
5. outdoor construction elevator strengthening of foundation device according to claim 4, it is characterised in that:The side of the fixed iron block Face is fixed on the inner surface of the external wall.
6. the outdoor construction elevator strengthening of foundation device according to claim any one of 1-5, it is characterised in that:The I-shaped Steel is several.
CN201710239568.2A 2017-04-13 2017-04-13 A kind of outdoor construction elevator strengthening of foundation device Pending CN106836325A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710239568.2A CN106836325A (en) 2017-04-13 2017-04-13 A kind of outdoor construction elevator strengthening of foundation device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710239568.2A CN106836325A (en) 2017-04-13 2017-04-13 A kind of outdoor construction elevator strengthening of foundation device

Publications (1)

Publication Number Publication Date
CN106836325A true CN106836325A (en) 2017-06-13

Family

ID=59146874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710239568.2A Pending CN106836325A (en) 2017-04-13 2017-04-13 A kind of outdoor construction elevator strengthening of foundation device

Country Status (1)

Country Link
CN (1) CN106836325A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086346A (en) * 2018-01-26 2018-05-29 广东省建筑工程机械施工有限公司 A kind of tower crane differential settlement bracing means and conquering method
CN109083419A (en) * 2018-08-09 2018-12-25 中国建筑第八工程局有限公司 The installation method of improvement project vertical transport integrated system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285613A (en) * 2003-03-20 2004-10-14 Kamiya Kenchiku Sekkei:Kk Construction method for building foundation
CN202809639U (en) * 2012-09-11 2013-03-20 中国建筑第二工程局有限公司 Steel girder foundation of construction elevator
CN103015432A (en) * 2012-12-07 2013-04-03 天津住宅集团建设工程总承包有限公司 Construction method for changing steel pipe supports of ramp foundation pit
CN202899159U (en) * 2012-11-16 2013-04-24 中建四局第五建筑工程有限公司 Outer hanging type construction elevator foundation
CN203905044U (en) * 2014-05-07 2014-10-29 中启胶建集团有限公司 Overhead deep foundation pit crossing construction elevator beam plate type base structure
CN204982932U (en) * 2015-08-11 2016-01-20 上海建工五建集团有限公司 Lift foundation structure
CN206052767U (en) * 2016-08-31 2017-03-29 云南建工第四建设有限公司 The construction elevator basis that can be used in turn
CN206616602U (en) * 2017-04-13 2017-11-07 青岛一建集团有限公司 A kind of outdoor construction elevator strengthening of foundation device

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004285613A (en) * 2003-03-20 2004-10-14 Kamiya Kenchiku Sekkei:Kk Construction method for building foundation
CN202809639U (en) * 2012-09-11 2013-03-20 中国建筑第二工程局有限公司 Steel girder foundation of construction elevator
CN202899159U (en) * 2012-11-16 2013-04-24 中建四局第五建筑工程有限公司 Outer hanging type construction elevator foundation
CN103015432A (en) * 2012-12-07 2013-04-03 天津住宅集团建设工程总承包有限公司 Construction method for changing steel pipe supports of ramp foundation pit
CN203905044U (en) * 2014-05-07 2014-10-29 中启胶建集团有限公司 Overhead deep foundation pit crossing construction elevator beam plate type base structure
CN204982932U (en) * 2015-08-11 2016-01-20 上海建工五建集团有限公司 Lift foundation structure
CN206052767U (en) * 2016-08-31 2017-03-29 云南建工第四建设有限公司 The construction elevator basis that can be used in turn
CN206616602U (en) * 2017-04-13 2017-11-07 青岛一建集团有限公司 A kind of outdoor construction elevator strengthening of foundation device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086346A (en) * 2018-01-26 2018-05-29 广东省建筑工程机械施工有限公司 A kind of tower crane differential settlement bracing means and conquering method
CN108086346B (en) * 2018-01-26 2023-09-08 广东省建筑工程机械施工有限公司 Uneven settlement reinforcing device and overcoming method for tower crane foundation
CN109083419A (en) * 2018-08-09 2018-12-25 中国建筑第八工程局有限公司 The installation method of improvement project vertical transport integrated system

Similar Documents

Publication Publication Date Title
CN104866659B (en) Steel construction integral hoisting method based on BIM
AU2019452705B2 (en) Foundation reinforcement structure and method for hoisting heavy equipment close to unclosed building
CN102535478B (en) Enclosing purlin comprising square steel pipe and light concrete for supporting foundation pit
CN107975075B (en) Construction process for existing load-bearing engineering foundation pile detection structure measures
CN110485429A (en) A kind of prestressing force fashioned iron assembled combination inner support construction method
CN207017275U (en) Recyclable system of deep foundation pit support can be assembled
CN106567394A (en) Water-stop PC steel pipe pile and inner pre-stressed section steel support combined supporting construction method
CN105863042A (en) All-steel structure building and construction method thereof
CN103469724A (en) Steel bridge with controllably-deposited foundation system and construction method thereof
CN206616602U (en) A kind of outdoor construction elevator strengthening of foundation device
CN209585054U (en) One kind is quickly met an urgent need diagonal brace for salvage of foundation pits
CN106836325A (en) A kind of outdoor construction elevator strengthening of foundation device
CN111576446A (en) In-situ protection device for pressure pipeline in underground foundation pit and construction method
CN215669551U (en) Beam string supporting structure
CN205024712U (en) Modular tower crane basis
CN104931338A (en) Angle-free rebound testing concrete test block fixing device, and manufacturing method and use method thereof
CN110700332A (en) Existing building reinforcing pile foundation static load test counterforce device and test method thereof
CN108221955B (en) Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method
CN206753488U (en) A kind of artificial digging pile reaming auxiliary equipment
CN213508572U (en) Piping lane supporting construction
CN106592599B (en) Device for rapidly controlling foundation pit displacement and construction method
CN213805443U (en) Steel construction, frame beam structure, side slope reinforced structure and reinforcement and support structure
CN113756554A (en) Construction platform and construction method for cast-in-place reinforced concrete support cantilever scaffold
CN212656218U (en) Heavy pile machine load underpinning structure
CN110016919A (en) A kind of aging blocks install the minimally invasive foundation pit structure of elevator and construction method additional

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination