CN109989428A - Prefabricated concrete inspection well - Google Patents

Prefabricated concrete inspection well Download PDF

Info

Publication number
CN109989428A
CN109989428A CN201910236460.7A CN201910236460A CN109989428A CN 109989428 A CN109989428 A CN 109989428A CN 201910236460 A CN201910236460 A CN 201910236460A CN 109989428 A CN109989428 A CN 109989428A
Authority
CN
China
Prior art keywords
concrete component
concrete
lock connector
adjacent
inspection well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910236460.7A
Other languages
Chinese (zh)
Inventor
李明
陈军民
钱峰
李宁
张永强
张岩
李砚辉
朱春雨
纪献维
陈林
冉召
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Administration Road And Bridge Ltd Co
Beijing Municipal Road and Bridge Co Ltd
Original Assignee
Beijing Municipal Administration Road And Bridge Ltd Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Administration Road And Bridge Ltd Co filed Critical Beijing Municipal Administration Road And Bridge Ltd Co
Priority to CN201910236460.7A priority Critical patent/CN109989428A/en
Publication of CN109989428A publication Critical patent/CN109989428A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/125Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the lining of the shaft
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F5/027The bottom made of prefabricated segments
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F5/00Sewerage structures
    • E03F5/02Manhole shafts or other inspection chambers; Snow-filling openings; accessories
    • E03F2005/028Sealing joints between manhole segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention relates to technical field of construction, more particularly to a kind of prefabricated concrete inspection well, including several concrete components, the concrete component successively includes pedestal, lower well room, upper well room, closing in cover board and walling crib from bottom to top, in corresponding end surface between any two adjacent concrete component, it is connected and fixed using several groups lock connector, is provided with rubber seal between the two adjacent concrete component.The present invention using several groups lock connector by being connected and fixed, construction only need to be by each concrete component on-site hoisting in the corresponding end surface between any two-phase neighbour concrete component, it is locked using the lock connector, process operations are simple, and mechanization degree is high, and construction speed can be effectively ensured.In addition, being provided with injected hole at the pipe joint that the lower well room is connect with pipeline, waterproof cement mortar or cement slurry and other waterproof materials can be applied by injected hole scene after pipeline puts in well room, facilitate site operation, reduce the construction period.

Description

Prefabricated concrete inspection well
Technical field
The present invention relates to technical field of construction, and in particular to a kind of prefabricated concrete inspection well.
Background technique
In the infrastructure construction in town and country, need in multinomial pipes such as provided underground power supply, water supply, combustion gas, communication, blowdowns Road route constructs a large amount of concrete inspection well with maintenance for the construction convenient for every facility.
Traditional concrete inspection well is in practice of construction to build or poured using mold mixed after excavation pit Solidifying soil, therefore construction period length, complex process, and quality is influenced by construction personnel's technical level, performance is unstable.
Then in recent years, some prefabricated concrete inspection wells come into being, but existing some precast inspection wells, each pre- It mostly uses groove and tognue type to connect greatly between molding block, at the construction field (site) after lifting combination, is still at connection tongue and groove with waterproof mortar seat Slurry seals and fixes construction, there are also precast inspection well, needs in job location installation mold again, and each module is further Pour fixed-type, therefore complex process, construction speed are slow.
Summary of the invention
The present invention overcomes disadvantages mentioned above, provide a kind of prefabricated concrete inspection easy to operate, quality is stable Cha Jing.
The technical scheme adopted by the invention to solve the technical problem is that: a kind of prefabricated concrete inspection well, packet Include several concrete components, the concrete component successively include from bottom to top pedestal, lower well room, upper well room, closing in cover board and Walling crib in the corresponding end surface between any two adjacent concrete component, is connected and fixed, the two-phase using several groups lock connector Rubber seal is provided between adjacent concrete component.
Lock connector between any two adjacent concrete component can be at least three groups, and corresponding can be evenly distributed In on the circumference of the concrete component end face.
The lock connector between any two adjacent concrete component can be six groups.
Rubber seal between the two adjacent concrete component can be two, be located at where the lock connector In concentric circumferences within circumference and in addition.
The lock connector may include the claw being arranged on the concrete component end face of side and the other side adjacent thereto Card on concrete component end face refers to that the claw top has claw hook, and the card refers to that top has for the claw hook that is loaded Platform or hook groove, after described two adjacent concrete components docking, the claw hook on the claw top hooks the card and refers to top Platform or hook groove, so that claw and card is referred to mutually to fasten and is locked.
The lock connector may include the grab being arranged on the concrete component end face of side and adjacent thereto another mixed Card slot on solidifying soil component end face, after described two adjacent concrete component docking, the grab is inserted into card slot, hooks grab The card slot is fixed.
A variety of height specifications are also provided between the closing in cover board and walling crib for the pit shaft regulating block of selection, for adjusting Save the height of inspection shaft.
The lower well room both ends are provided with pipe joint, and the top of the pipe joint may be provided with injected hole, the note Slurry bore dia is 100mm-200mm.
There is several reinforcing bars being axially arranged, the lock connector on each concrete component in each concrete component It is securable to the reinforcing bar end.
The present invention using several groups lock connector by being connected in the corresponding end surface between any two-phase neighbour concrete component Fixation is connect, each concrete component on-site hoisting need to be only locked by construction using the lock connector, and process operations are simple, Mechanization degree is high, and construction speed can be effectively ensured.In addition, being provided at the pipe joint that the lower well room is connect with pipeline Injected hole can apply waterproof cement mortar or cement slurry and other waterproof materials after pipeline puts in well room by injected hole scene Material facilitates site operation, reduces the construction period.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is the structural schematic diagram of the end face of heretofore described upper well room;
Fig. 3 is the partial enlarged view in Fig. 1 at A;
Fig. 4 is the top view of heretofore described lower well room.
Specific embodiment
It as shown in fig. 1, is a kind of preferred embodiment of the prefabricated concrete inspection well of the present invention, if including dry-mixed Solidifying soil component, successively includes pedestal 1, lower well room 2, upper well room 3, closing in cover board 4, pit shaft regulating block 5 and walling crib 6 from bottom to top, Well lid 7 is covered at 6 upper opening of walling crib.Wherein, the pedestal 1 is mainly used for the bottom support of inspection shaft, lower well room 2 It is mainly used for the introducing of main split's pipe, upper well room 3 is mainly used for well room height adjustment, and pit shaft is installed on 4 top of closing in cover board Adjusting block 5, in addition, the pit shaft regulating block 5 can in advance prefabricated a variety of different height specifications, configured in above-mentioned standard well room It is complete that there is also when difference in height, select the pit shaft regulating block 5 of appropriate height to adjust inspection shaft height.Any two adjacent concrete It in corresponding end surface between component, is connected and fixed using at least three groups of lock connectors, and between the two adjacent concrete component It is provided with rubber seal.
Fig. 2 is to guarantee grafting in figure for the above well room 3, to illustrate the structural schematic diagram of any concrete component end face It is steady secured, corresponding six groups of setting can be set on the end face of upper well room 3 and lower well room adjacent thereto (not indicating in figure) Connector 8 is latched, and the lock connector 8 is evenly distributed on the circumference of the upper well room 3 and lower well room corresponding end surface.On described Rubber seal 9 between well room 3 and lower well room is two, is located within the 8 place circumference of lock connector and in addition Concentric circumferences on.
Fig. 3 is the partial enlarged view at the place A in Fig. 1, in the present embodiment, corresponding to six between any two adjacent concrete component The group lock connector, all as marked structure at A there are six tool, but Fig. 1 is only marked at one, and elsewhere is omitted and do not indicated.Such as Fig. 3 Shown in, the lock connector includes that the card on the claw 81 being arranged on upper 3 end face of well room and lower 2 end face of well room refers to 82, institute 81 top of claw is stated with claw hook 811, the card refers to that 82 tops have platform 821 or the hook groove (figure for the claw hook that is loaded In do not indicate), after described two adjacent concrete components (i.e. upper well room 3 and lower well room 2) docking, the pawl on 81 top of claw Hook 811 hooks the platform 821 or hook groove for blocking and referring to 82 tops, and claw 81 is made to refer to that 82 mutually fastenings are locked with card.It is described Two sealing rings 9 are located within the lock 8 place circumference of connector and in concentric circumferences in addition.To guarantee concrete structure The intensity of part itself, each concrete component is interior to have several reinforcing bars 10 being axially arranged, each lock connector, i.e. claw 81 refer to 82 10 ends of reinforcing bar being individually fixed in inside the upper well room 3 and lower well room 2 with card, ensure that each adjacent concrete structure Fixing intensity after being connected between part.
It is as shown in Figure 4 the top view of heretofore described lower well room, lower 2 both ends of well room are provided with for being connected to The pipe joint 21 of main split's pipeline, the top of the pipe joint 21 are provided with injected hole 22, and the slip casting bore dia is 100mm-200mm, preferably 200mm.
Using prefabricated concrete inspection well of the invention, site operation mainly uses following workflow: applying Working drawing is standby → excavation of foundation pit and crater wall supporting → basement process, cushion construction → well room is assembled, connecting pipe → cover board lifting → Chute construction → fertilizer slot backfill → well head processing → closed-water test (if needed) → backfill → well lid installation.
By the above-mentioned description as described in structure of the invention and the course of work it is found that being pressed first by each concrete component of prefabrication Design standard is produced, and well room quality is stable, sturdy and durable, impervious good, and it is good to conserve simple and environmentally-friendly property, and not It can occur well room breakage erosion, when construction, directly each concrete component be transported to construction site, is carried out at the construction field (site) Excavation of foundation pit and supporting, basement process, cushion construction are carried out after preparation of construction;Then using crane to each coagulation of precast inspection well Native component is lifted, and the lock connector 8 is directed in hoisting process, is self-possessed using Prefabricated block and is completed inserting for lock connector 8 Enter connection and fixation, when self weight is not enough to complete the lock connection of connector 8, the mode that outer weighting material or pressure can be used is completed to connect It connects, therefore work progress facilitates, without live slip casting, protects environment, operational sequence is simple, and mechanization degree is high, can have Effect saves the duration, guarantees construction speed;And rubber seal rings for seal waterproof is used between adjacent concrete component, it improves simultaneously Construction quality and construction efficiency.
Under lifting after well room 2, pipeline (not indicating in figure) is put in the pipe joint 21 of the lower well room 2, described 120 degree of pipeline lower part range inner seat waterproof mortar, squeezing the pipeline, to connect waterproof mortar with pipeline closely knit, excessive with mortar It is advisable;Slurry is sat by the reserved injected hole 22 scene of carrying out, pipeline two sides and top are filled up respectively with waterproof mortar, are inserted Waterproof mortar is smash, until it is completely full, triangular shape waterproof mortar is finally smeared out, width is maintained at 5-6cm, continues thereafter in lifting Well room 3 and closing in cover board 4;According to live buried depth and inspection shaft height, it may be selected and the pit shaft for lifting appropriate height specification is adjusted Block 5 carries out detection well whole height and adjusts, and is also beneficial to accelerate site operation progress, saves construction cost;Finally complete walling crib 6 And the installation of well lid 7.
As another preferred embodiment of the invention, the lock connector 8 can be using in side concrete component Grab is set on end face, card slot is set on another concrete component end face adjacent thereto, shape is similar to remote controller battery The buckle of warehouse lid, after described two adjacent concrete component docking, the grab is inserted into card slot, so that grab is hooked the card slot real Now it is locked.Therefore, the lock connector can take many forms, as long as can be realized the side between adjacent concrete component Just simultaneously close installation is fixed for locking.
Prefabricated concrete inspection well provided by the present invention is described in detail above, it is used herein A specific example illustrates the principle and implementation of the invention, and the above embodiments are only used to help understand originally The method and its core concept of invention;At the same time, for those skilled in the art, according to the thought of the present invention, specific There will be changes in embodiment and application range, in conclusion the content of the present specification should not be construed as to of the invention Limitation.

Claims (9)

1. a kind of prefabricated concrete inspection well, including several concrete components, the concrete component from bottom to top according to Secondary includes pedestal, lower well room, upper well room, closing in cover board and walling crib, it is characterised in that: between any two adjacent concrete component In corresponding end surface, it is connected and fixed using several groups lock connector, is provided with rubber seal between the two adjacent concrete component Circle.
2. prefabricated concrete inspection well according to claim 1, it is characterised in that: any two adjacent coagulation Lock connector between native component is at least three groups, and on the corresponding circumference for being evenly distributed in the concrete component end face.
3. prefabricated concrete inspection well according to claim 2, it is characterised in that: the two adjacent concretes structure Rubber seal between part is two, within circumference where being located at the lock connector and in concentric circumferences in addition.
4. prefabricated concrete inspection well according to claim 1, it is characterised in that: the lower well room both ends setting There is pipe joint, the top of the pipe joint is provided with injected hole, and the slip casting bore dia is 100mm-200mm.
5. prefabricated concrete inspection well according to claim 2, it is characterised in that: any two adjacent coagulation The lock connector between native component is six groups.
6. prefabricated concrete inspection well according to claim 1, it is characterised in that: in each concrete component With several reinforcing bars being axially arranged, the lock connector on each concrete component is fixed on the reinforcing bar end.
7. prefabricated concrete inspection well described according to claim 1 ~ any one of 6, it is characterised in that: the lock Connector includes on the claw being arranged on the concrete component end face of side and other side concrete component end face adjacent thereto Card refers to that the claw top has claw hook, and the card refers to that top has the platform or hook groove for the claw hook that is loaded, described After two adjacent concrete component docking, the claw hook on the claw top hooks the platform or hook groove for blocking and referring to top, makes claw Refer to mutually to fasten with card and be locked.
8. prefabricated concrete inspection well described according to claim 1 ~ any one of 6, it is characterised in that: the lock Connector includes the card on the grab being arranged on the concrete component end face of side and another concrete component end face adjacent thereto Slot, after described two adjacent concrete component docking, the grab is inserted into card slot, so that grab is hooked the card slot and fixes.
9. prefabricated concrete inspection well described according to claim 1 ~ any one of 6, it is characterised in that: the closing in A variety of height specifications are additionally provided between cover board and walling crib for the pit shaft regulating block of selection, for adjusting the height of inspection shaft.
CN201910236460.7A 2019-03-27 2019-03-27 Prefabricated concrete inspection well Pending CN109989428A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910236460.7A CN109989428A (en) 2019-03-27 2019-03-27 Prefabricated concrete inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910236460.7A CN109989428A (en) 2019-03-27 2019-03-27 Prefabricated concrete inspection well

Publications (1)

Publication Number Publication Date
CN109989428A true CN109989428A (en) 2019-07-09

Family

ID=67131516

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910236460.7A Pending CN109989428A (en) 2019-03-27 2019-03-27 Prefabricated concrete inspection well

Country Status (1)

Country Link
CN (1) CN109989428A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110792148A (en) * 2019-11-06 2020-02-14 上海建工七建集团有限公司 Prefabricated reinforced concrete drainage ditch and construction method
CN112282023A (en) * 2020-11-03 2021-01-29 长春市城建维护集团股份有限公司 Combined assembly type inspection well and installation method thereof
CN112431289A (en) * 2019-08-24 2021-03-02 无锡交通建设工程集团有限公司 Municipal sewage well wall prefabrication and assembly process and concrete well wall component
CN114108392A (en) * 2021-11-29 2022-03-01 成都蜀禹通途新材料科技有限公司 Fully-assembled underground seepage and drainage system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200337105Y1 (en) * 2003-09-30 2003-12-31 주식회사 씨앤앤건설 The concrete manhole where transportation and Union construction are easy
CN103374926A (en) * 2012-04-13 2013-10-30 哈尔滨市前进水泥管厂有限责任公司 Prefabricated assembly-type reinforced concrete inspection well
CN109440903A (en) * 2018-11-28 2019-03-08 福建建中建设科技股份有限公司 A kind of prefabricated concrete inspection well and its construction method
CN209975581U (en) * 2019-03-27 2020-01-21 北京市政路桥股份有限公司 Assembled precast concrete inspection shaft

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200337105Y1 (en) * 2003-09-30 2003-12-31 주식회사 씨앤앤건설 The concrete manhole where transportation and Union construction are easy
CN103374926A (en) * 2012-04-13 2013-10-30 哈尔滨市前进水泥管厂有限责任公司 Prefabricated assembly-type reinforced concrete inspection well
CN109440903A (en) * 2018-11-28 2019-03-08 福建建中建设科技股份有限公司 A kind of prefabricated concrete inspection well and its construction method
CN209975581U (en) * 2019-03-27 2020-01-21 北京市政路桥股份有限公司 Assembled precast concrete inspection shaft

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112431289A (en) * 2019-08-24 2021-03-02 无锡交通建设工程集团有限公司 Municipal sewage well wall prefabrication and assembly process and concrete well wall component
CN110792148A (en) * 2019-11-06 2020-02-14 上海建工七建集团有限公司 Prefabricated reinforced concrete drainage ditch and construction method
CN112282023A (en) * 2020-11-03 2021-01-29 长春市城建维护集团股份有限公司 Combined assembly type inspection well and installation method thereof
CN112282023B (en) * 2020-11-03 2022-03-25 长春市城建维护集团股份有限公司 Combined assembly type inspection well and installation method thereof
CN114108392A (en) * 2021-11-29 2022-03-01 成都蜀禹通途新材料科技有限公司 Fully-assembled underground seepage and drainage system

Similar Documents

Publication Publication Date Title
CN109989428A (en) Prefabricated concrete inspection well
CN103898831B (en) Prefabricated assembled arch rib of ultrahigh-performance concrete and manufacturing and mounting method thereof
CN104947709A (en) Pre-assembled single-compartment municipal tunnel and construction method thereof
CN108914931A (en) A kind of ring-like foundation pile of the vertical shield of assembled and construction method
CN204690783U (en) A kind of prefabricated assembled single cabin municipal administration synthesis pipe gallery
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN112323823B (en) Filling device and method for waste air-raid shelter of pile foundation construction site
CN106555408A (en) The structure and construction method of underground pipe gallery
CN108716189A (en) Large span T-steel structure beam sections for joining island bridge install closure method
CN208251372U (en) A kind of assembled steel reinforced concrete shear force wall
CN108914945A (en) A kind of deep basal pit pile for prestressed pipe, prestress anchorage cable combined supporting construction method
CN209975581U (en) Assembled precast concrete inspection shaft
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN102927364A (en) Reinforced concrete pipe installation method and clamp special for reinforced concrete pipe
CN208792483U (en) Combined-type sewage well prefabricated component
CN110094206A (en) A kind of vertical shaft tunnel concrete liner structure and method
CN207315379U (en) A kind of precast assembly vertical shaft
CN106906125B (en) A kind of construction method of prefabricated board assembly fermentor
CN207392241U (en) A kind of ultra-high performance concrete precast assembly pipe gallery
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN109706970A (en) A kind of prefabricated square cable active well
CN108457191A (en) Large span T-steel structure beam sections for joining island bridge install closure method
CN211113774U (en) Assembled PC basement lateral wall post-cast strip structure
CN212641364U (en) Underwater leakage blocking structure system for concrete faced rockfill dam
CN210341975U (en) Major diameter single pile steel-pipe pile interpolation changeover portion grouting construction system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination