CN103374926A - Prefabricated assembly-type reinforced concrete inspection well - Google Patents

Prefabricated assembly-type reinforced concrete inspection well Download PDF

Info

Publication number
CN103374926A
CN103374926A CN2012101088487A CN201210108848A CN103374926A CN 103374926 A CN103374926 A CN 103374926A CN 2012101088487 A CN2012101088487 A CN 2012101088487A CN 201210108848 A CN201210108848 A CN 201210108848A CN 103374926 A CN103374926 A CN 103374926A
Authority
CN
China
Prior art keywords
prefabricated
well
chamber
cover plate
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101088487A
Other languages
Chinese (zh)
Inventor
张广涛
王万春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HARBIN QIANJIN CEMENT PIPE FACTORY Co Ltd
Original Assignee
HARBIN QIANJIN CEMENT PIPE FACTORY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HARBIN QIANJIN CEMENT PIPE FACTORY Co Ltd filed Critical HARBIN QIANJIN CEMENT PIPE FACTORY Co Ltd
Priority to CN2012101088487A priority Critical patent/CN103374926A/en
Publication of CN103374926A publication Critical patent/CN103374926A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention provides a prefabricated assembly-type inspection well which can be put into industrial production. The inspection well is flexible to assemble, convenient to construct and simple and easy-to-implement in structure and manufacturing process, a lower well chamber, an upper well chamber and a well barrel are connected into a whole from bottom to top through flexible joints, well chamber cover plates are arranged between the well chambers and the well barrel, and a cover plate and a well cover are arranged on the well barrel. The prefabricated assembly-type reinforced concrete inspection well has the advantages that connecting joints of the lower well chamber, the upper well chamber and the cover plate are flexible tongue-and-grooves, the well chambers are connected with a pipeline through flexible tongue-and-grooves, the flexible joints are sealed by rubber rings, rigid tongue-and-grooves are sealed by cement mortar, the well chambers and the pipeline are connected by both rigid joints and flexible joints, and the well chambers are connected with the pipeline by pipes not larger than 1000mm, so that when the pipeline differentially settles, joint breakaway or pipeline breakage can be effectively avoided; a bottom plate is prefabricated together with the prefabricated lower well chamber during production, so that a construction seam is reduced, integrity of the inspection well is increased, operating safety of the pipeline is improved, and floating resistance of the inspection well is improved.

Description

The prefabricated assembling type reinforced concrete manhole
Technical field
The invention belongs to a kind of underground structure, particularly a kind of underground reinforced concrete pipiline prefabricated assembling type reinforced concrete prefabricated units and manufacture method.
Background technology
Existing various underground pipeline manholes all adopt loam brick to build by laying bricks or stones and finish: 1, its intensity is low, and speed of application is slow, easy to leak, poor durability, and application life is short, is unfavorable for that the Three Eastern Provinces use coldly.2, the loam brick manhole is formed by brick masonry, and is difficult fully non-leakage, adds northeast cold ground freeze injury, and effluent seepage polluted underground water resource does not meet environmental protection policy.3, fired clay brick uses loam brick to cause the clay resource waste in a large number.4, the field operation time long, the wet trade workload is large, curing time is long, the long period can not backfill, the construction period is long, even environment and constructor's life security around threatening.5, only be example take Beijing, more than 200 kilometers in annual about newly-built pipeline need be built more than 10000 of various pipe manholes, uses loam brick more than 2,500,000.Country also prohibites and uses loam brick as building material at present, and it is imperative to carry out in this case the prefabricated assembling type reinforced concrete manhole.
At present, the domestic application concrete inspection well substitutes brick masonry manhole product, mainly contains prefabricated assembling type reinforced concrete manhole and building-brick type concrete masonry units manhole, also has cast in situs steel concrete manhole.The prefabricated assembling type reinforced concrete manhole has intensity height, assemblingization rapid construction and the tight characteristics of seam, can fundamentally solve the shortcoming of loam brick manhole, thereby can make manhole reach the advantages such as bearing capacity is large, non-leakage, speed of application is fast.Building-brick type concrete masonry units manhole, just solution is never used the loam brick problem, and building-brick type concrete masonry units manhole and cast in situs steel concrete manhole fundamentally do not solve other problems.The prefabricated assembling type reinforced concrete manhole is that current application is the most extensive, a kind of urban construction duct products that development prospect is best.
Summary of the invention
Purpose of the present invention is just providing a kind of assembling manhole that can realize suitability for industrialized production, the technical problem of instead of clay brick masonry manhole.Make its assembling flexibly, constructability.Thereby safety and the compliance of various conduit runnings have been improved.
The technical scheme of the prefabricated assembled manhole of the present invention: by the prefabricated chamber of going into the well, prefabricated upper well chamber, prefabricated pit shaft, interface is linked to be integral body from bottom to top, and the well room cover plate is arranged between well chamber and the pit shaft, is equipped with cover plate, well lid on the pit shaft, it is characterized in that:
The shape of above-mentioned prefabricated assembling type reinforced concrete manhole has circle, rectangle.
Above-mentioned circular pit shaft is to connect prefabricated regulating block below the prefabricated cover plate, and prefabricated pit shaft, cover plate connecting interface are the rigidity tongue and groove, cover plate and well lid connection reservation anchor bolt;
Above-mentioned (circle) prefabricated chamber of going into the well, prefabricated upper well chamber, prefabricated cover plate connecting interface are flexible tongue and grooves, and (rectangle) prefabricated well chamber, prefabricated well room cover plate connecting interface are the rigidity tongue and grooves.It is flexible tongue and groove that (rectangle) prefabricated well chamber is connected with pipeline.
Above-mentioned prefabricated upper well chamber, the chamber of going into the well, well room cover plate, pit shaft, cover plate have the lifting hole(eyelet) of reservation.
Above-mentioned interface is sealed with cement mortar by the rigidity tongue and groove, flexible interface wedge-shaped rubber rubber sealing.
Marking time of above-mentioned prefabricated well chamber and shaft in wall is to reserve mark time position, hole or the pre-buried parts of marking time.
The material of the above-mentioned prefabricated chamber of going into the well, upper well chamber, cover plate, pit shaft, walling crib is C30 steel concrete.
Above-mentioned prefabricated well chamber is the connected mode that rigid interface and flexible interface combine with being connected of pipeline, prefabricated well chamber connecting pipe connects with being not more than 1000mm tubing, therefore when pipeline generation differential settlement, can effectively avoid occuring the phenomenon of interface disengaging or pipeline break.Be not failure of pipeline, thereby improve the conduit running safety.
Above-mentioned circle (rectangle) well chamber is formed by connecting by prefabricated upper well chamber, the prefabricated chamber of going into the well, wherein be reserved with wellhole on the prefabricated well room cover plate, have the preformed hole connecting pipe uses in the prefabricated chamber of going into the well, it is prefabricated together base plate when the prefabricated chamber of going into the well produces, reduce constuction joint one, increase the manhole globality, improved manhole anti-floating ability.
Prefabricated assembling type reinforced concrete manhole of the present invention is with advanced Core Vibrated Casting Process production, and production efficiency is high.
Beneficial effect: the prefabricated assembling type reinforced concrete manhole is finished by reinforced concrete prefabricated, and well chamber and pit shaft are regulated by different moduluses and be assembled, and it is supporting with various pipeline, the rapid construction of realization pipeline assemblingization.The prefabricated assembling type reinforced concrete manhole does not use loam brick, is conducive to protection of the environment.Fast than brick masonry manhole speed of application, quality is high, compressive resistance is high, can stand rolling of heavy-duty machinery, is conducive to the problem of subsiding of solving road well chamber.Advantage with intensity height, antiseep, frost resistance, corrosion resistance are all high than loam brick, thereby have prolonged application life, can satisfy design standard and construction requirement.The construction of manhole is become fast, simple, save lay bricks, jointing.Wipe one's face, the precipitation operation, improved greatly labor productivity and operating efficiency, accelerated the cycle of infrastructure construction.The manhole that can be widely used in various coal gas, water, electricity, heating line.
Description of drawings
Fig. 1 is the top view of circular inspection well of the present invention
Fig. 2 is the I-I of Fig. 1
Fig. 3 is the II-II of Fig. 1
Fig. 4 is the top view of rectangle inspection well of the present invention
Fig. 5 is the I-I of Fig. 4
Fig. 6 is the II-II of Fig. 4
Fig. 7 cover plate
Fig. 8 is the I-I of Fig. 7
Fig. 9 pit shaft
Figure 10 is the I-I of Fig. 9
Figure 11 well chamber interface shape
The Interface Shape of Figure 12 pit shaft (walling crib, cover plate)
Among the figure: 1-goes into the well to mark time in chamber, the upper well of 2-chamber, 3-well room cover plate, 4-pit shaft regulating block, 5-cover plate, 6-, 7-preformed hole, 8-bolt, 9-well lid, 10-sealing ring.
The specific embodiment
Shown in Fig. 1-6, the prefabricated assembling type reinforced concrete manhole, by the prefabricated chamber of going into the well of 1-, the prefabricated upper well of 2-chamber, the prefabricated pit shaft of 4-, interface is linked to be integral body from bottom to top, 3-prefabricated well room cover plate is arranged between prefabricated well chamber and the prefabricated pit shaft, be equipped with the prefabricated cover plate of 5-, 9-well lid on the prefabricated pit shaft of 4-, the prefabricated pit shaft of 4-is by the prefabricated reinforced concrete regulating block, regulating block is comprised of seven kinds of different sizes, be respectively 90mm, 140mm, 180mm, 360mm, 720mm, 1440mm.1800mm, internal diameter is 700mm.The prefabricated assembling type reinforced concrete manhole has all been reserved hole for hoist or has been furnished with special hanger at different component, and prefabricated used concrete all is C30.
The shape of prefabricated assembling type reinforced concrete manhole has circle, rectangle.The physical dimension of manhole and suitable conduit.
The circular inspection well diameter range, D1000-D1500, suitable conduit diameter D200-D800.
Rectangle inspection well size 1100 * 1600 * 1800,1100 * 2000 * 2200,1100 * 2480 * 2600, suitable conduit diameter D800-D2000.
The 6-of manhole marks time and is equipped in advance on the member, and the step pitch that 6-marks time is 340mm, and the prefabricated well chamber first step is located at 100mm at the bottom of the well room cover plate, and pit shaft is located at the cover plate 100mm that makes progress to well room cover plate first, and the material of marking time is plastic-steel or ball milling cast steel.

Claims (5)

1. an invention is the prefabricated assembling type reinforced concrete manhole, by the prefabricated chamber of going into the well, prefabricated upper well chamber, prefabricated pit shaft, interface is linked to be integral body from bottom to top, between prefabricated well chamber and the prefabricated pit shaft prefabricated well room cover plate is arranged, is equipped with cover plate, well lid on the prefabricated pit shaft, it is characterized in that:
The shape of a, prefabricated assembling type reinforced concrete manhole has circle, rectangle.
B, circular pit shaft are to connect prefabricated regulating block below the prefabricated cover plate, cover plate and well lid connection reservation anchor bolt;
C, circle (rectangle) well chamber are formed by connecting by prefabricated upper well chamber, the prefabricated chamber of going into the well, wherein be reserved with wellhole on the prefabricated well room cover plate, have preformed hole in the prefabricated chamber of going into the well, it is prefabricated together base plate when the prefabricated chamber of going into the well produces, reduce constuction joint one, increase the manhole globality, improved manhole anti-floating ability.
2. prefabricated assembling type reinforced concrete manhole according to claim 1, it is characterized in that: (circle) prefabricated chamber of going into the well, prefabricated upper well chamber, well room cover plate connecting interface are flexible tongue and grooves, (rectangle) prefabricated well chamber, well room cover plate connecting interface are the rigidity tongue and grooves, and prefabricated pit shaft, well room cover plate connecting interface are the rigidity tongue and groove.
3. prefabricated assembling type reinforced concrete manhole according to claim 1, it is characterized in that: prefabricated upper well chamber, the prefabricated chamber of going into the well, prefabricated well room cover plate, prefabricated pit shaft, prefabricated cover plate have the lifting hole(eyelet) of reservation.
4. prefabricated assembling type reinforced concrete manhole according to claim 1 is characterized in that: circular (rectangle) interface rigidity tongue and groove seals flexible tongue and groove wedge-shaped rubber rubber sealing with cement mortar.
5. prefabricated assembling type reinforced concrete manhole according to claim 1 is characterized in that: marking time of well chamber and shaft in wall is to reserve mark time position, hole or the pre-buried parts of marking time.
CN2012101088487A 2012-04-13 2012-04-13 Prefabricated assembly-type reinforced concrete inspection well Pending CN103374926A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101088487A CN103374926A (en) 2012-04-13 2012-04-13 Prefabricated assembly-type reinforced concrete inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101088487A CN103374926A (en) 2012-04-13 2012-04-13 Prefabricated assembly-type reinforced concrete inspection well

Publications (1)

Publication Number Publication Date
CN103374926A true CN103374926A (en) 2013-10-30

Family

ID=49460728

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101088487A Pending CN103374926A (en) 2012-04-13 2012-04-13 Prefabricated assembly-type reinforced concrete inspection well

Country Status (1)

Country Link
CN (1) CN103374926A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089073A (en) * 2014-05-24 2015-11-25 厦门嘉达环保建造工程有限公司 Precast concrete inspection well module
CN106436872A (en) * 2016-11-11 2017-02-22 江苏工程职业技术学院 Assembly type drainage inspection well
CN107012891A (en) * 2017-06-09 2017-08-04 西安市恒兴市政工程公司 A kind of waterproof method of prefabricated rectangle well room
CN108222223A (en) * 2017-11-20 2018-06-29 杭州市市政工程集团有限公司 A kind of inspection shaft and method for cutting over for having pressure sewage conduct cutover for Large Diameter Pipeline
CN108691320A (en) * 2017-04-05 2018-10-23 扬州市职业大学 A kind of prefabricated assembled regeneration concrete off-load inspection shaft
CN108978717A (en) * 2017-06-05 2018-12-11 陕西晟泰源水泥制品有限公司 Precast assembling concrete manhole and prepackage method
CN109989428A (en) * 2019-03-27 2019-07-09 北京市政路桥股份有限公司 Prefabricated concrete inspection well
CN111074944A (en) * 2020-01-10 2020-04-28 重庆市云鹏水泥制品有限公司 Prefabricated assembled concrete anti-floating inspection well and processing method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
KR100841525B1 (en) * 2007-03-20 2008-06-25 정채영 Drain pipe junction type manhole
DE202009003419U1 (en) * 2009-03-10 2009-07-23 Lammering, Thomas, Dipl.-Ing. Elastomeric manhole liner for the rehabilitation of manholes
KR20100108786A (en) * 2009-03-30 2010-10-08 (주)한성 Manhole with mounting device of cover having height control function
CN201883454U (en) * 2010-12-07 2011-06-29 林刚 Prefabricated reinforced-concrete assembly-type combined inspection well chamber
CN202000463U (en) * 2011-01-31 2011-10-05 日照市东兴城市配套设备有限公司 Prefabricated reinforced concrete drainage inspection well
CN202081434U (en) * 2011-05-25 2011-12-21 姚宝权 Prefabricated pipe shaft
CN202081432U (en) * 2010-12-16 2011-12-21 喻友红 Plastic drainage inspection well device of large-scale combined type

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2546500Y (en) * 2002-04-17 2003-04-23 北京市市政工程研究院 Precast assembling concrete manhole
KR100841525B1 (en) * 2007-03-20 2008-06-25 정채영 Drain pipe junction type manhole
DE202009003419U1 (en) * 2009-03-10 2009-07-23 Lammering, Thomas, Dipl.-Ing. Elastomeric manhole liner for the rehabilitation of manholes
KR20100108786A (en) * 2009-03-30 2010-10-08 (주)한성 Manhole with mounting device of cover having height control function
CN201883454U (en) * 2010-12-07 2011-06-29 林刚 Prefabricated reinforced-concrete assembly-type combined inspection well chamber
CN202081432U (en) * 2010-12-16 2011-12-21 喻友红 Plastic drainage inspection well device of large-scale combined type
CN202000463U (en) * 2011-01-31 2011-10-05 日照市东兴城市配套设备有限公司 Prefabricated reinforced concrete drainage inspection well
CN202081434U (en) * 2011-05-25 2011-12-21 姚宝权 Prefabricated pipe shaft

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089073A (en) * 2014-05-24 2015-11-25 厦门嘉达环保建造工程有限公司 Precast concrete inspection well module
CN106436872A (en) * 2016-11-11 2017-02-22 江苏工程职业技术学院 Assembly type drainage inspection well
CN108691320A (en) * 2017-04-05 2018-10-23 扬州市职业大学 A kind of prefabricated assembled regeneration concrete off-load inspection shaft
CN108978717A (en) * 2017-06-05 2018-12-11 陕西晟泰源水泥制品有限公司 Precast assembling concrete manhole and prepackage method
CN107012891A (en) * 2017-06-09 2017-08-04 西安市恒兴市政工程公司 A kind of waterproof method of prefabricated rectangle well room
CN108222223A (en) * 2017-11-20 2018-06-29 杭州市市政工程集团有限公司 A kind of inspection shaft and method for cutting over for having pressure sewage conduct cutover for Large Diameter Pipeline
CN109989428A (en) * 2019-03-27 2019-07-09 北京市政路桥股份有限公司 Prefabricated concrete inspection well
CN111074944A (en) * 2020-01-10 2020-04-28 重庆市云鹏水泥制品有限公司 Prefabricated assembled concrete anti-floating inspection well and processing method thereof

Similar Documents

Publication Publication Date Title
CN103374926A (en) Prefabricated assembly-type reinforced concrete inspection well
CN202099816U (en) Prefabricated waterproof and soil-blocking plate for later poured band of outer wall of basement
CN201232197Y (en) Combined inspection well
CN104805866A (en) Prefabricated comprehensive pipe gallery and construction method
CN103643966A (en) Prefabricated tunnel lining segment
CN203669880U (en) Assembly type tunnel lining segment
CN209987133U (en) Circular prefabricated inspection shaft steel form of pin-connected panel
CN108978717A (en) Precast assembling concrete manhole and prepackage method
CN202131613U (en) Lined prefabricated reinforced concrete inspection well
CN202466631U (en) Prefabricated reinforced concrete inspection well and die thereof
CN203389471U (en) Ceramic water film dust collector
CN201099864Y (en) Plastic valve manhole
CN107268675A (en) The laying method and structure of a kind of many storehouse underground pipe galleries of combined type
CN203296069U (en) Round precast concrete inspection well
CN210069158U (en) Glass fiber reinforced plastic bell mouth concrete top pipe
CN202247719U (en) Corresponding corrugated pre-stressed anti-sedimentation culvert pipe for bridge
CN201817819U (en) Prefabricated assembled reinforced concrete rectangular inspection well chamber
CN208295326U (en) Full corrosion-proof lining formula Prestressed concrete cylinder pipe
CN107152034B (en) Comprehensive pipe rack and construction method thereof
CN110608052A (en) Tunnel segment based on high-performance cement-based composite material and construction method thereof
CN201883453U (en) Combined pipe jacking working well
CN203546754U (en) Prefabricated reinforced concrete manhole for communication pipeline
CN106592635A (en) Integrated inspection shaft and installation method thereof
CN202672331U (en) Prefabricated reinforced concrete circular grit well
CN202865870U (en) Large-scale plastic inspection well

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131030