CN106592635A - Integrated inspection shaft and installation method thereof - Google Patents

Integrated inspection shaft and installation method thereof Download PDF

Info

Publication number
CN106592635A
CN106592635A CN201611143784.9A CN201611143784A CN106592635A CN 106592635 A CN106592635 A CN 106592635A CN 201611143784 A CN201611143784 A CN 201611143784A CN 106592635 A CN106592635 A CN 106592635A
Authority
CN
China
Prior art keywords
shaft
integral type
inspection shaft
arm
pit shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611143784.9A
Other languages
Chinese (zh)
Inventor
孔德信
张泽
张继刚
于计俊
刘伟
朱志华
邓嘉伟
尤明旗
张景元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haining Yada Plastic Pipeline System Co Ltd
Original Assignee
Haining Yada Plastic Pipeline System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haining Yada Plastic Pipeline System Co Ltd filed Critical Haining Yada Plastic Pipeline System Co Ltd
Priority to CN201611143784.9A priority Critical patent/CN106592635A/en
Publication of CN106592635A publication Critical patent/CN106592635A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Abstract

The invention provides an integrated inspection shaft and an installation method thereof. The integrated inspection shaft comprises a shaft and a branch pipe, the shaft is a straight-barrel-shaped winding pipe, an installation hole for the branch pipe to penetrate is formed in the lower end of the shaft, two connecting ports of the branch pipe penetrate out of the shaft, an overhauling opening with an upward opening is cut in the portion, located in the shaft, of the branch pipe, and the shaft and the branch pipe are fixedly welded and sealed. Compared with a portland cement pouring inspection shaft, the high modulus polypropylene material inspection shaft is light in dead load and convenient to transport; in addition, the acid-resisting and corrosion-resisting performance is high, the quality is stable, maintenance is easy, and the service life is long; and the inner wall of the shaft is smooth, the water conservancy condition is good, and drainage is easy.

Description

A kind of integral type inspection shaft and its installation method
Technical field
The invention belongs to municipal works technical field, is related to a kind of integral type inspection shaft and its installation method.
Background technology
During at present municipal pipeline is built, traditional brick inspection shaft and armored concrete inspection shaft still plays important work With, but traditional inspection shaft has exposed congenital defect, its mainly have it is following some:
First, traditional brick well uses the construction process of solid brick plus mixed mud, and transport difficult, installation period is long, no Easy care, and if to have caved in also have certain human safety issues to related operating personnel.Construction progress can not be flexibly controlled, Such as weather problems cause scene to construct, and go wrong and are difficult to improve.
2nd, armored concrete inspection shaft itself is heavy, the handling instrument of specialty is needed, so as to increased operating expenses.Steel Though reinforced concrete inspection shaft has certain acid resistance, acid resistance is well below plastic inspection well.
3rd, armored concrete inspection shaft mostly is building block youngster composition or pre-formed, and the steel reinforced concrete well gap of building block composition is more, close Envelope effect is difficult to ensure that.And connected mode is gun iron link, effluent seepage easily occurs, permeate, it is easily secondary to Groundwater formation Pollution, affects the living environment of resident.
4th, armored concrete inspection shaft causes internal resistance larger due to itself rigid and xoncrete structure, needs one Fixed staff goes into the well and draw clearly.
5th, armored concrete inspection shaft cannot be constructed well by high temperature, severe cold and wet rainy day gas.And can not return Receive, pollute environment, waste of resource.
6th, traditional brick well uses solid brick as construction raw material, does not meet the requirement of the sustainable development national conditions of China, Minstry of Housing and Urban-Rural Development of People Republic of China's (218) number file in 2004 has been run counter to, the regulation of clay solid brick has clearly been prohibitted the use of.
There is prefabricated plastic inspection well before more than 10 years in China, was avoided that above-mentioned most of problem, and in cities and towns life In community living, the application succeeded, but due to the prefabricated inspection shaft bore of living community it is little, low intensity, with town road On inspection shaft require there be certain distance, in municipal, application is almost blank.
The content of the invention
The purpose of the present invention is there are the problems referred to above for existing technology, it is proposed that a kind of integral type inspection shaft and its peace Dress method, can apply on town road, using this equipment and technique, can be with the major part of effectively solving tradition inspection shaft Drawback, realizes the purpose that simple, easy care is installed in transport, easy to leak, construction cost be not low, execution conditions restriction is few.
The purpose of the present invention can be realized by following technical proposal:
A kind of integral type inspection shaft, including pit shaft and arm, it is characterised in that pit shaft is the winding pipe in straight-tube shape, Pit shaft lower end is provided with the installing hole passed through for arm, and two connectivity ports of arm pass pit shaft and part of the arm in pit shaft is cut An opening up access hole is cut, is welded and fixed between pit shaft and arm and is sealed.
Further, part of the arm in pit shaft has 90 °~180 ° of bent angle a.Two ends arm is not in same straight line On, make arm adapt to installation requirement, it is adapted to the connection request of two pipelines being not arranged on the same straight line.
Further, the material of the pit shaft and arm is high modulus polypropylene.
Further, the arm has the connectivity port with pipeline, and connectivity port is enclosed within pipeline outside, connectivity port Inner side is provided with annular groove, and the O-ring seal leant with pipeline outside is provided with annular groove.
Further, the bottom of the pit shaft has abducent base.
A kind of installation method of integral type inspection shaft, it is characterised in that comprise the steps:
A. connecting pipe:Integral type inspection shaft is put in installation pit, the two ends of arm are connected with pipeline;
B. banket:Soil is inserted in installation pit, is backfilling and compacted around integral type inspection shaft, pit shaft upper end reserve 3cm~ The space of 5cm;
C., sealing ring is installed:The sealing ring on the set of pit shaft upper end;
D., cement cover board is installed:Cement cover board is placed above pit shaft, around the cement cover board that bankets, cement cover board center is opened There is through hole;
E. the mixed borehole wall of brick is made:Arrange workman that the mixed borehole wall of tubular brick is built above cement cover board, brick mixes borehole wall upper end Reserve the mounting groove of a well seat;
F., well seat is installed:The well seat of matching is put in the mounting groove of the mixed borehole wall upper end of brick;
G., well lid is installed:Well lid is installed on well seat;
H. it is backfilled to road surface:Backfilled with earth and tamp above cement cover board, road surface soil is flushed with well lid.
In above-mentioned step b, the sealing ring cross-section is L-shaped, bears against in pit shaft upper end and side wall.Ensure cement Watertightness is good between cover plate and pit shaft, prevents subsoil water and silt seepage, blocks tubing.
In above-mentioned steps f, the internal diameter of the mixed borehole wall of the well seat, brick is identical with the through-hole diameter of cement cover board.
Compared with prior art, this integral type inspection shaft is adopted and twined twice with blocked high modulus polypropylene as raw material Machine around molding and welding procedure, with advantages below:
1. compared with the inspection shaft that ordinary cement is poured, the inspection shaft of high modulus polypropylene material is from heavy and light, convenient transportation;
2. the acidproof decay resistance of high modulus polypropylene inspection shaft is strong, and steady quality, easy care, usage cycles are long;
3. sealing ring is provided with, and connection is flexible, and watertightness is good, antiseep;
4. shaft in wall is smooth, and water project situation is good, it is easy to draining;
5. integral type inspection shaft can be made in advance, without considering weather conditions, can be under vile weather, geological conditions Construction, flexible for installation, speed of application is fast, and construction cost is low.
This integral type checks many technologies of well installation method Jing and Project Demonstration, possesses feasibility and reliability.And Jing is carried out in Practical Project, complies fully with design requirement and use requirement.Compare with traditional inspection shaft, integral type inspection Look into well to be obviously improved at aspects such as construction and installation, operation maintenance, cost control, environmental conservation.
Description of the drawings
Fig. 1 is the installation profile of integral type inspection shaft.
Fig. 2 is the partial enlarged drawing A in Fig. 1.
The side structure schematic view of Fig. 3 this integral type inspection shafts.
The overlooking the structure diagram of Fig. 4 this integral type inspection shafts
Fig. 5 is the connection sectional view of arm and pipeline.
In figure, 1, pit shaft;2nd, arm;3rd, access hole;4th, base;5th, pipeline;6th, installation pit;7th, through hole;8th, sealing ring;9、 Cement cover board;10th, the mixed borehole wall of brick;11st, well seat;12nd, well lid;13rd, road surface;14th, connectivity port;15th, annular groove;16th, it is O-shaped close Seal.
Specific embodiment
The following is the specific embodiment of the present invention and combine accompanying drawing, technical scheme is further described, But the present invention is not limited to these embodiments.
As shown in Figure 3, Figure 4, this integral type inspection shaft includes pit shaft 1 and arm 2, and pit shaft 1 is the winding pipe in straight-tube shape, The installing hole passed through for arm 2 is provided with the lower end of pit shaft 1, the two ends of arm 2 pass the part of pit shaft 1 and arm 2 in pit shaft 1 With 90 °~180 ° of bent angle a, an opening up access hole 3 is cut with the bent angle a.
The material of pit shaft 1 and arm 2 is high modulus polypropylene, is welded and fixed and seals between pit shaft 1 and arm 2.Such as Fig. 5 Shown, the arm 2 has the connectivity port with the grafting of pipeline 5, and connectivity port 14 is enclosed within the outside of pipeline 5, connectivity port 14 Inner side is provided with annular groove 15, annular groove 15 and is provided with the O-ring seal 16 leant with the outside of pipeline 5.The pit shaft 1 Bottom has abducent base 4.Integral type inspection shaft, is raw material by import high modulus polypropylene, adopts and winds twice Moulding process and welding procedure are made, and are easy to the system of pipeline 5 to make regular check on, clear and coherent and other special examineds and maintenance.
As shown in Figure 1 and Figure 2, also need to miscellaneous part when integral type inspection shaft is installed, all parts illustrate as Under:
Well lid 12, it is daily current to ensure according to correspondence standard application well lid 12 according to integral type inspection shaft installation site Safety.
Well seat 11, supporting carrying well lid 12, is poured in advance by armored concrete and is completed.
Brick mixes the borehole wall 10, for being integrally connected formula inspection shaft upper end to road surface 13, well head is flushed with road surface 13.
Cement cover board 9, carries the load of the top of cement cover board 9, and plays the transition reducing of pit shaft 1 and the mixed borehole wall 10 of brick and make With.
Pipeline 5, for delivering rainwater, sewage etc..
Sealing ring 8, it is ensured that watertightness is good between cement cover board 9 and pit shaft 1, prevents subsoil water and silt seepage, blocks The system of pipeline 5.
The installation method of this integral type inspection shaft, comprises the steps:
A. connecting pipe 5:Integral type inspection shaft is put in installation pit 6, the two ends of arm 2 are connected with pipeline 5;
B. banket:Soil is inserted in installation pit 6, is backfilling and compacted around integral type inspection shaft, 3cm is reserved in the upper end of pit shaft 1 The space of~5cm;
C., sealing ring 8 is installed:The sealing ring 8 on the set of the upper end of pit shaft 1;
D., cement cover board 9 is installed:Cement cover board 9, around the cement cover board 9 that bankets, cement cover board 9 are placed in the top of pit shaft 1 Center is provided with through hole 7;
E. the mixed borehole wall 10 of brick is made:Workman is arranged to build the mixed borehole wall 10 of tubular brick in the top of cement cover board 9, brick mixes the borehole wall Reserve the mounting groove of a well seat 11 in 10 upper ends;
F., well seat 11 is installed:The well seat 11 of matching is put in the mounting groove of the mixed upper end of the borehole wall 10 of brick;
G., well lid 12 is installed:Well lid 12 is installed on well seat 11;
H. it is backfilled to road surface 13:In the top backfilled with earth of cement cover board 9 and tamp, make the soil of road surface 13 neat with well lid 12 It is flat.
In above-mentioned step b, the section of the sealing ring 8 is L-shaped, bears against in the upper end of pit shaft 1 and side wall.Ensure water Watertightness is good between mud capping plate 9 and pit shaft 1, prevents subsoil water and silt seepage, blocks the system of pipeline 5.
In above-mentioned steps f, the internal diameter of the mixed borehole wall 10 of the well seat 11, brick is identical with the diameter of through hole 7 of cement cover board 9.
Make:From high modulus polypropylene material, using secondary winding process be made into one formula inspection shaft pit shaft 1 and Pipe 2, cuts pit shaft 1 and arm 2 after standing, assemble and weld pit shaft 1 and arm 2, and integral type inspection shaft completes.
Install:First integral type inspection shaft is connected with pipeline 5, is backfilling and compacted below the upper port of pit shaft 1.Then Sealing ring 8 is installed in the upper port position of pit shaft 1, and lifts cement cover board 9, it is ensured that sealing is good after installation.It is high according to ground The mixed borehole wall 10 of laying bricks on cement cover board 9 is spent, well seat 11 is installed after the brick firm molding of the mixed borehole wall 10, cover well lid 12, finally Earthing is covered around well lid 12.

Claims (8)

1. a kind of integral type inspection shaft, including pit shaft and arm, it is characterised in that pit shaft is the winding pipe in straight-tube shape, in well Cylinder lower end is provided with the installing hole passed through for arm, and two connectivity ports of arm pass pit shaft and part cutting of the arm in pit shaft There is an opening up access hole, be welded and fixed between pit shaft and arm and seal.
2. integral type inspection shaft according to claim 1, it is characterised in that part of the arm in pit shaft have 90 °~ 180 ° of bent angle a.
3. integral type inspection shaft according to claim 2, it is characterised in that the material of the pit shaft and arm is high-moduluss Polypropylene.
4. integral type inspection shaft according to claim 3, it is characterised in that the arm has the company plugged with pipeline Connect port, connectivity port is enclosed within pipeline outside, and annular groove is provided with the inside of connectivity port, be provided with annular groove with outside pipeline The O-ring seal that side leans.
5. integral type inspection shaft according to claim 4, it is characterised in that the bottom of the pit shaft has abducent Base.
6. a kind of installation method of integral type inspection shaft, it is characterised in that comprise the steps:
A. connecting pipe:Integral type inspection shaft is put in installation pit, the two ends of arm are connected with pipeline;
B. banket:Soil is inserted in installation pit, is backfilling and compacted around integral type inspection shaft, the reserved 3cm~5cm's in pit shaft upper end Space;
C., sealing ring is installed:The sealing ring on the set of pit shaft upper end;
D., cement cover board is installed:Cement cover board is placed above pit shaft, around the cement cover board that bankets, cement cover board center is provided with logical Hole;
E. the mixed borehole wall of brick is made:Arrange workman that the mixed borehole wall of tubular brick is built above cement cover board, the mixed borehole wall upper end of brick is reserved The mounting groove of one well seat;
F., well seat is installed:The well seat of matching is put in the mounting groove of the mixed borehole wall upper end of brick;
G., well lid is installed:Well lid is installed on well seat;
H. it is backfilled to road surface:Backfilled with earth and tamp above cement cover board, road surface soil is flushed with well lid.
7. the installation method of integral type inspection shaft according to claim 6, it is characterised in that in above-mentioned step b, institute State sealing ring cross-section L-shaped, bear against in pit shaft upper end and side wall.
8. the installation method of integral type inspection shaft according to claim 7, it is characterised in that described in above-mentioned steps f The internal diameter of the mixed borehole wall of well seat, brick is identical with the through-hole diameter of cement cover board.
CN201611143784.9A 2016-12-13 2016-12-13 Integrated inspection shaft and installation method thereof Pending CN106592635A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611143784.9A CN106592635A (en) 2016-12-13 2016-12-13 Integrated inspection shaft and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611143784.9A CN106592635A (en) 2016-12-13 2016-12-13 Integrated inspection shaft and installation method thereof

Publications (1)

Publication Number Publication Date
CN106592635A true CN106592635A (en) 2017-04-26

Family

ID=58599177

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611143784.9A Pending CN106592635A (en) 2016-12-13 2016-12-13 Integrated inspection shaft and installation method thereof

Country Status (1)

Country Link
CN (1) CN106592635A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755764A (en) * 2018-06-04 2018-11-06 华煜建设集团有限公司 A kind of inspection shaft and its construction method
CN113863384A (en) * 2021-10-12 2021-12-31 吴明辉 Construction protection supporting device and protection method for medium maintenance bituminous pavement inspection well

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1844593A (en) * 2006-04-30 2006-10-11 广东联塑科技实业有限公司 Manhole with steps
CN2830512Y (en) * 2005-09-22 2006-10-25 上海建威科技有限公司 Plastic inspection shaft
CN101381999A (en) * 2008-10-14 2009-03-11 沈阳骅飞管业有限公司 Glass fibre reinforced plastic sand inclusion well chamber
CN203475473U (en) * 2013-09-27 2014-03-12 河北新大地通讯管网工程有限公司 Communication pipeline combination well
CN203701250U (en) * 2013-12-19 2014-07-09 吉林经济技术开发区城发集塑管业股份有限公司 Enhanced type municipal drainage inspection well
CN203701251U (en) * 2013-12-19 2014-07-09 吉林经济技术开发区城发集塑管业股份有限公司 Bearing type high-strength municipal drainage manhole
CN204435531U (en) * 2015-01-22 2015-07-01 山西二建集团有限公司 Plastic inspection well
CN205296229U (en) * 2016-01-12 2016-06-08 上海市城市建设设计研究总院 Sewer manhole in utility tunnel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2830512Y (en) * 2005-09-22 2006-10-25 上海建威科技有限公司 Plastic inspection shaft
CN1844593A (en) * 2006-04-30 2006-10-11 广东联塑科技实业有限公司 Manhole with steps
CN101381999A (en) * 2008-10-14 2009-03-11 沈阳骅飞管业有限公司 Glass fibre reinforced plastic sand inclusion well chamber
CN203475473U (en) * 2013-09-27 2014-03-12 河北新大地通讯管网工程有限公司 Communication pipeline combination well
CN203701250U (en) * 2013-12-19 2014-07-09 吉林经济技术开发区城发集塑管业股份有限公司 Enhanced type municipal drainage inspection well
CN203701251U (en) * 2013-12-19 2014-07-09 吉林经济技术开发区城发集塑管业股份有限公司 Bearing type high-strength municipal drainage manhole
CN204435531U (en) * 2015-01-22 2015-07-01 山西二建集团有限公司 Plastic inspection well
CN205296229U (en) * 2016-01-12 2016-06-08 上海市城市建设设计研究总院 Sewer manhole in utility tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755764A (en) * 2018-06-04 2018-11-06 华煜建设集团有限公司 A kind of inspection shaft and its construction method
CN113863384A (en) * 2021-10-12 2021-12-31 吴明辉 Construction protection supporting device and protection method for medium maintenance bituminous pavement inspection well

Similar Documents

Publication Publication Date Title
CN205276316U (en) Modular prefabricated piping lane
CN202969415U (en) Multifunctional assembled comprehensive pipe gallery
CN210031914U (en) Assembled inspection shaft
CN107859065A (en) A kind of ultra-high performance concrete precast assembly pipe gallery and construction method
CN105064400A (en) Urban comprehensive pipe rack of steel corrugated plate structure
CN205617426U (en) Cast -in -place bottom plate of utility tunnel and prefabricated outer panel connection structure
CN202131613U (en) Lined prefabricated reinforced concrete inspection well
CN204715426U (en) A kind of water burst drainage system for closed deep foundation ditch exploratory hole
CN202247920U (en) Construction structure for water drainage of blind ditch and water collecting wells in deep foundation pit
CN204401650U (en) Square longitudinally connection prestressed assembly formula underground pipe gallery
CN106592635A (en) Integrated inspection shaft and installation method thereof
CN207268009U (en) A kind of underground pipe gallery drainage system based on existing blowdown canal
CN207121916U (en) Shut-in well structure
CN205617425U (en) Prefabricated structure of assembling of utility tunnel
CN201400679Y (en) Prestressed steel cylinder concrete marsh gas generation tank
CN207392241U (en) A kind of ultra-high performance concrete precast assembly pipe gallery
CN208136954U (en) Precast splice type Pipe rack
CN206752632U (en) Plastic reinforcing steel composite construction municipal drainage inspection shaft
CN206090623U (en) Prefabricated inspection shaft of construction efficient
CN204941552U (en) A kind of subway station of parallel shield method enlarging construction
CN203393828U (en) Rectangular reinforced concrete prefabricated inspection well
CN205677031U (en) A kind of sewage piece well
CN2627065Y (en) Combined glass reinforced plastic well
CN2814074Y (en) Device for sealing up pipe in the wall
CN201180308Y (en) Plastic hydraulic drop inspection shaft

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170426

RJ01 Rejection of invention patent application after publication